DE1534598A1 - Process for the mining of underground spaces according to the Berger system - Google Patents

Process for the mining of underground spaces according to the Berger system

Info

Publication number
DE1534598A1
DE1534598A1 DE19651534598 DE1534598A DE1534598A1 DE 1534598 A1 DE1534598 A1 DE 1534598A1 DE 19651534598 DE19651534598 DE 19651534598 DE 1534598 A DE1534598 A DE 1534598A DE 1534598 A1 DE1534598 A1 DE 1534598A1
Authority
DE
Germany
Prior art keywords
underground
mining
tunnels
space
created
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
DE19651534598
Other languages
German (de)
Inventor
Berger Dr-Ing Hermann
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BERGER DR ING HERMANN
Original Assignee
BERGER DR ING HERMANN
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BERGER DR ING HERMANN filed Critical BERGER DR ING HERMANN
Publication of DE1534598A1 publication Critical patent/DE1534598A1/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D13/00Large underground chambers; Methods or apparatus for making them

Description

DR.-ING. HERMANN BERGERDR.-ING. HERMANN BERGER

Lehrbeauftragter für Stollen-, Tunnel- und U-BahntunnelbauLecturer for tunnel, tunnel and subway tunnel construction

an der Technischen Hochschule Stuttgart.
Ingenieurbüro für Tiefbau und unterirdische Bauwerke.
at the Technical University of Stuttgart.
Engineering office for civil engineering and underground structures.

7 STUTTGART W Honoldweg 5 a Fernsprecher 63 41 257 STUTTGART W Honoldweg 5 a Telephone 63 41 25

Verfahren zur bergmännischen. Herstellung unterirdischer Räume nach System B e r g e rProcedure for mining. Creation of underground spaces according to the B e r g e r system

Beschreibungdescription

Die Herstellung unterirdischer Räume wird von Jahr zu Jahr erforderlicher« Hierbei kann es sich um größere Räume oder Speicher oder auch um Straßen oder Schienenwege handeliio Die Förderung nach Herstellung von Ü-Straßenbahnen steht heute in fast allen großen Städten im Vordergrund.The creation of underground spaces is becoming more and more necessary from year to year « This can be about larger rooms or storage or also about roads or railways handeliio The promotion after the production of Ü-trams is in the foreground in almost all large cities today.

Bei der Herstellung solcher unterirdischer Räume in. bebauten Gebieten ist es notwendig, Setzungen infolge der Bauarbeiten und Behinderungen des oberirdischen Verkehrs unbedingt zu vermeiden oder auf ein möglichst geringes Maß einzuschränken. Diese Forderungen werden bei der vorliegenden Erfindung erfüllet.In making such underground spaces in. Built-up In areas it is necessary to avoid subsidence as a result of construction work and obstructions to above-ground traffic or to restrict it to the lowest possible level. These requirements are met in the present invention.

Es ist bekannt, bei dem derzeitigen Stand der Technik zur Erfüllung der o.a. Forderungen den Schildvortrieb anzuwenden. Diese Vortriebsart ist aber mit erheblichen Kosten verbunden und bei kurzen Strecken unrentabel. Außerdem ist man bei dieser Bauart an einen kreisrunden Querschnitt gebunden. Eine weitere Möglichkeit besteht darin, unterirdische Räume mit Hilfe einer offenen Baugrube herzustellen. Diese Bauart ist ebenfalls sehr teuer und erfüllt außerdem nicht die Forderungen, die hinsichtlich der Setzungen und der Behinderung des oberirdischen Verkehrs gestellt werden. Hierbei müssen zum größten Teil unter den Straßen verlegte Versorgungs- und Entwässerungsleitungen beseitigt und später neu verlegt werden. Außerdem erreichen die Setzungen der anliegenden Gebäude bei hohem Grundwasserstand einen besonders großen Wert, da der Absenkungstrichter bei einer offenen Baugrube größer ist als bei einer unterirdischen Wasserhaltung. .It is known to use shield tunneling in the current state of the art in order to meet the above-mentioned requirements. However, this type of tunneling is associated with considerable costs and is unprofitable for short distances. In addition, you are bound to a circular cross-section with this design. Another possibility is to create underground rooms with the help of an open construction pit. This type of construction is also very expensive and also does not meet the requirements that are made with regard to subsidence and the obstruction of above-ground traffic. For the most part, the supply and drainage pipes laid under the streets have to be removed and re-laid later. In addition, when the groundwater level is high, the subsidence of the adjacent buildings is particularly high, as the subsidence funnel is larger in an open excavation than in an underground dewatering. .

909826/074 2909826/074 2

Der Erfindung liegt die Aufgabe zugrunde, bei der Herstellung unterirdischer Räume Setzungen zu vermeiden und den oberirdischen Verkehr in keiner Weise zu stören.The invention is based on the object in the manufacture to avoid subsidence of underground spaces and not to disturb the traffic above ground in any way.

Diese Aufgabe wird erfindungsgemäß dadurch gelöst, daß in bindigen und stark kompressiblen Böden zunächst zwei kleine Seitenstollen vorgetrieben werden, deren Solhbreite sich nach der zulässigen Bodenpressung richtet. Diese Stollen werden durch eine Getriebezimmerung (i) so verbaut, daß beim Vortrieb dieser Stollen alle Setzungen vermieden werden. Mach dem Ausbruch dieser Seitenstollen werden dieselben zum später endgültig zu erstellenden unterirdischen Raum hin glatt abgeschalt (2) und voll als Auf- und Widerlager ausbetoniert. Im Anschluß hieran erfolgt je nach der Höhe des zu erstellenden Rauines im Vollausbruch oder in mehreren Ebenen der Ausbruch des Erdmaterials für den geplanten unterirdischen Raum. Hierbei wird zur Unterfangung des überlagernden Materials und anderer evtl. vorhandener Auflasten der Vortrieb im Schütze eines Teilschildes ausgeführt, das jeweils vor dem Ausbruch auf in den Seitenstollen ausgesparten Gleitlagern (3) vorgeschoben bzw. gepreßt wird. Gleichzeitig werden dem Teilschild folgen dicht auf dicht Stahlträger IPBAccording to the invention, this object is achieved in that, in cohesive and highly compressible soils, first two small Side tunnels are driven, the width of which depends on the permissible soil pressure. These studs will built by a gear box (i) so that during the advance all subsidence is avoided in this tunnel. If these side tunnels break out, they will become final later on The underground space to be created is shut off smoothly (2) and fully concreted as a support and abutment. Following this depending on the height of the rauines to be created, the excavation of the earth material takes place in full or in several levels the planned underground space. This is used to underpin the overlying material and other possibly existing Load the jacking carried out in the contactor of a partial shield, which was cut out in the side tunnels before the excavation Slide bearings (3) is advanced or pressed. At the same time, the partial shield is followed closely by IPB steel girders

in die Aussparungen (3) eingelegt und der geringe Hohlraum (5) zwischen den Stahlträgern und der Firste ausgemörtelt. Nachdem so der obere Teil des zu erstellenden unterirdischen Raumes aufgefahren ist, erfolgt in Abschnitten von 2,50 m bis 3»00 m Tiefe der Ausbruch des weiteren Materials, in der Art, daß Spannbetonfertigteile im statisch erforderlichen Abstand dem Ausbruch unmittelbar folgend in die Aussparung (7) der aus den Seitenstollen gebildeten Widerlager eingeführt und mittels Druckspindeln (8) abgestützt werden. Im Anschluß hieran wird der Zwischenraum zwischen den in den einzelnen Abschnitten versetzt angeordneten Spannbetonfertigteilen mit durch Baustahlgewebe armierten Spritzbeton (9) ausbetoniert. Auf diese Weise wird eine Bewegung des anstehenden Materials verhindert.placed in the recesses (3) and the small cavity (5) between the steel girders and the roof is mortared. After the upper part of the underground space to be created has been excavated, the further material is excavated in sections from 2.50 m to 3 »00 m depth, in such a way that prestressed concrete elements at the statically required distance immediately follow the excavation into the recess (7) of the abutment formed from the side tunnels are introduced and supported by means of pressure spindles (8). Subsequently, the space between the pre-cast pre-fabricated concrete elements, which are offset in the individual sections, is concreted with shotcrete (9) reinforced with structural steel mesh. This prevents the material from moving.

Die mit der Erfindung erzielten Vorteile bestehen hauptsächlichThe advantages achieved by the invention are mainly

909826/0742 "909826/0742 "

darin, daß bei geringeren Kosten als bei der bisher bekannten Bauweise und unter Aufrechterhaltung des oberirdischen Verkehrs Setzungen fast vollkommen ausgeschlossen sind und somit Schaden an verlegten Leitungen und an der Oberfläche stehenden Gebäuden vermieden werden. Außerdem ist es möglich, erforderliche Isolierungen vor dem Einbringen des Auskleidungsbetons auf die Spritzbetonwände aufzubringen.in that at a lower cost than the previously known Construction method and while maintaining the above-ground traffic subsidence are almost completely excluded and thus Damage to installed lines and buildings standing on the surface can be avoided. It is also possible to make required Isolation before placing the lining concrete to apply to the shotcrete walls.

Claims (1)

PatentanspruchClaim Verfahren zur bergmännischen Herstellung unterirdischer Räume nach System Berger dadurch gekennzeichnet, daß unmittelbar seitlich neben dem oberen Teil eines zu erstellenden unterirdischen Raumes je ein Stollen mit oder ohne GetriebeZimmerung vorgetrieben wird, der als Widerlager zur Aufnahme eines Teilschildes und der Firstabfangung voll ausbetoniert werden kann, so daß im Schütze dieser Firstabfangung bei gleichzeitiger Vermörtelung des geringen Zwischenraumes zwischen Firste und Abfangungskönstruktion der Ausbruch des zu erstellenden unterirdischen Raumes unter Vermeidung von Setzungen erfolgen kann.Process for mining underground Rooms according to the Berger system, characterized in that immediately next to the upper part of a to be created underground space, a tunnel with or without a gear box is driven to act as an abutment to accommodate a partial shield and the ridge support can be fully concreted, so that in the shooter this Ridge support with simultaneous grouting of the small one Space between the roof and the supporting structure the excavation of the underground space to be created can take place while avoiding subsidence. 2«) Verfahren zur bergmännischen Herstellung unterirdischer Räume nach System Berger nach Anspruch 1 dadurch gekennzeichnet, daß die beiden seitlichen Stollen als Entwässerungsstollen für das Gelände darüber und darunter benutzt werden können. Im Letzteren Falle können Absenkbrunnen von diesen aus nach unten geführt werden« Die Vorflutleitungen können in diesen Stollen verlegt werden.2 «) Process for the mining of underground Rooms according to the Berger system according to claim 1, characterized in that the two lateral tunnels are used as drainage tunnels can be used for the terrain above and below. In the latter case, sink wells can be used from these downwards «The drainage pipes can be laid in these tunnels. 9098 2 6/07429098 2 6/0742
DE19651534598 1965-12-10 1965-12-10 Process for the mining of underground spaces according to the Berger system Pending DE1534598A1 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
DEB0084915 1965-12-10

Publications (1)

Publication Number Publication Date
DE1534598A1 true DE1534598A1 (en) 1969-06-26

Family

ID=6982662

Family Applications (1)

Application Number Title Priority Date Filing Date
DE19651534598 Pending DE1534598A1 (en) 1965-12-10 1965-12-10 Process for the mining of underground spaces according to the Berger system

Country Status (1)

Country Link
DE (1) DE1534598A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2403448A1 (en) * 1977-09-06 1979-04-13 Banyaszati Kutato Intezet PROCESS FOR THE REALIZATION OF UNDERGROUND CONSTRUCTIONS AND CONSTRUCTIONS SO REALIZED
DE2915231A1 (en) * 1979-04-14 1980-10-23 Gewerk Eisenhuette Westfalia Versatile open trench cutting driving shield - has closable cover shield on top for adjacent underground working

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2403448A1 (en) * 1977-09-06 1979-04-13 Banyaszati Kutato Intezet PROCESS FOR THE REALIZATION OF UNDERGROUND CONSTRUCTIONS AND CONSTRUCTIONS SO REALIZED
DE2915231A1 (en) * 1979-04-14 1980-10-23 Gewerk Eisenhuette Westfalia Versatile open trench cutting driving shield - has closable cover shield on top for adjacent underground working

Similar Documents

Publication Publication Date Title
DE2905688A1 (en) METHOD AND DEVICE FOR THE PRODUCTION OF BUILDINGS IN THE GROUND WITH VERTICAL WALLS EXITING FROM AN UNDERGROUND CANAL
DE4226067A1 (en) Device and method for stabilising highways in sloping locations - involves vertical injection posts fitted in lowermost stage with externally extending sections provided with inclined posts and steel reinforcement of concrete support wall
DE202022104117U1 (en) An underground mine support structure combined with piles and pipes, which can take into account the treatment of voids
DE2142894A1 (en) Sealed continuous wall as a foundation or civil engineering plant and process for their production
US6406220B1 (en) Arched support structure
AT397415B (en) METHOD FOR PRODUCING UNDERGROUND CONSTRUCTIONS BY LID CONSTRUCTION
DE102006000920B4 (en) Method for environmentally friendly production of underground stations of suburban trains and the like
DE4412880A1 (en) Process for digging underground cavity
DE1534598A1 (en) Process for the mining of underground spaces according to the Berger system
DE4119259A1 (en) Method for constructing basements under existing building - uses root piles to underpin existing load-bearing walls for construction of concrete ceiling, foundation blocks, support columns
DE3607499A1 (en) Method of sealing the soil surface area of an old or operating landfill site in a gastight and watertight manner
DE2917994C2 (en) Process for the production of a construction pit sheeting or retaining wall made of reinforced concrete for terrain cuts
EP0648298B1 (en) Process for carrying out civil engineering works
Schönlechner et al. The construction of the Obervermuntwerk II pumped storage power station/Die Bauausführung des Pumpspeicherkraftwerks Obervermuntwerk II
DE3543098C2 (en)
DE3716750A1 (en) Method of constructing and sinking foundation structures
DE1915091A1 (en) Method and device for the production of channels using the diaphragm wall method
Leitner et al. The new line crossing U2/U5 of the Vienna subway: Das neue Linienkreuz U2/U5 der Wiener U‐Bahn
DE19818338C1 (en) Platform construction for providing access to and from trains, trams etc.
Schmeiser et al. Technical and logistical challenges of the construction of the Museumsinsel Station in Berlin
DE2217459A1 (en) PROCEDURES AND EQUIPMENT FOR UNDER CONSTRUCTION OF STRUCTURES AND TRAFFIC ROUTES
DE720617C (en) Procedure for the execution of tunnels and similar civil engineering
DE1658735A1 (en) Process for the production of underground spaces built in concrete
EP0230667A2 (en) Method for the stripe-wise removal of subsoil layers, especially non-rigid ones
AT263845B (en) Method of excavating an underground cavity, e.g. to accommodate a traffic structure to be built later