DE1058453B - Method and apparatus for cementing casing in a borehole - Google Patents
Method and apparatus for cementing casing in a boreholeInfo
- Publication number
- DE1058453B DE1058453B DEH16883A DEH0016883A DE1058453B DE 1058453 B DE1058453 B DE 1058453B DE H16883 A DEH16883 A DE H16883A DE H0016883 A DEH0016883 A DE H0016883A DE 1058453 B DE1058453 B DE 1058453B
- Authority
- DE
- Germany
- Prior art keywords
- casing
- rings
- borehole
- pipe
- cement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims description 9
- 239000004568 cement Substances 0.000 claims description 14
- 238000007790 scraping Methods 0.000 claims description 4
- 230000008569 process Effects 0.000 claims description 3
- 239000010802 sludge Substances 0.000 claims description 3
- 230000008878 coupling Effects 0.000 claims description 2
- 238000010168 coupling process Methods 0.000 claims description 2
- 238000005859 coupling reaction Methods 0.000 claims description 2
- 238000009434 installation Methods 0.000 claims description 2
- 238000009966 trimming Methods 0.000 claims description 2
- 238000006748 scratching Methods 0.000 claims 2
- 230000002393 scratching effect Effects 0.000 claims 2
- 230000002411 adverse Effects 0.000 claims 1
- 238000006073 displacement reaction Methods 0.000 claims 1
- 238000005553 drilling Methods 0.000 claims 1
- 230000007935 neutral effect Effects 0.000 description 2
- 230000035508 accumulation Effects 0.000 description 1
- 238000009825 accumulation Methods 0.000 description 1
- 238000004873 anchoring Methods 0.000 description 1
- 238000004140 cleaning Methods 0.000 description 1
- 150000001875 compounds Chemical class 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000002441 reversible effect Effects 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B37/00—Methods or apparatus for cleaning boreholes or wells
- E21B37/02—Scrapers specially adapted therefor
Landscapes
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Physics & Mathematics (AREA)
- Environmental & Geological Engineering (AREA)
- Fluid Mechanics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Earth Drilling (AREA)
Description
BUNDESKEPUBLIK DEUTSCHLANDFEDERAL SKI PUBLIC OF GERMANY
INTERNAT. KL. E 21b INTERNAT. KL. E 21b
DEUTSCHES MjMif&s. PATENTAMTGERMAN MjMif & s. PATENT OFFICE
AUSLEGESCHRIFT 1058 453EXPLAINING EDITORIAL 1058 453
H 16883 VI/5aH 16883 VI / 5a
ANMELDETAG: 2 7. JUNI 1953REGISTRATION DATE: June 2, 1953
BEKANNTMACHUNG
DER ANMELDUNG
UND AUSGABE DES
AUSLEGESCHRIFT: i. J U N I 19 5 9NOTICE
THE REGISTRATION
AND ISSUE OF THE
EDITORIAL: i. JUNE 19 5 9
Verfahren und VorrichtungMethod and device
Die Rrfindung betrifft ein Verfahren zum Kin- τ-,. ^. ~ ^1 ,The Rrfindung relates to a method for Kin- τ- ,. ^. ~ ^ 1 ,
zementieren eines Futterrohres in einem Bohrloch ZUm Einzementieren eines Futterrohres cementing a casing in a borehole for cementing a casing
unter Verwendung von Schrappern und gegebenenfalls ίη βίηΘΓΩ. Bohrloch using scrapers and optionally ίη βίηΘΓΩ. Borehole
Zentriervorrichtungen, die auf dem Futterrohr angeordnet sind. 5 ~~Centering devices placed on the casing. 5 ~~
Bei den bisher bekannten Zementierverfahren ist es
allgemein üblich, nur die Bohrlochwandung vonIn the previously known cementing processes, it is
common practice, only the borehole wall of
Schlammansammlungen zu reinigen, die den ringför- . ,_.To clean accumulations of sludge, which the ring conveying. , _.
migen Schacht verstopfen und ein gutes Abbinden des Anmelder:clog the manhole and ensure that the applicant has set well:
Zementes an der durchbohrten Gesteiniormation ver- 10 Jesse Eimer Hall Cement on the pierced rock improvement 10 Jesse Eimer Hall
hindern. Zu diesem Zweck wurden auf das Futterrohr 'prevent. For this purpose, the casing '
aufgesetzte Schrappvorrichtungen entwickelt, deren Weatherford, Tex. (V. St. A.)developed scraper devices whose Weatherford, Tex. (V. St. A.)
Schrappelemente nach außen ragen und sich fest anSchrapp elements protrude outwards and are firmly attached
die Bohi lochwandung andrücken. Gewöhnlich sind Vertreter: Dr.-Ing. K. Boehmert, Patentanwalt,press on the wall of the hole. Usually representatives are: Dr.-Ing. K. Boehmert, patent attorney,
diese Schrapper in einem gegenseitigen Abstand von 15 Bremen 1, Feldstr. 24these scrapers at a mutual distance of 15 Bremen 1, Feldstr. 24
zwischen 4,5 und 6 m am Futterrohr starr befestigt.
Einige besondere Ausbildungsformen dieser bekannten
Schrapper sind nun derart auf dem Rohr angebracht,
daß sie zwischen zwei nahe beieinander Hegenden An-between 4.5 and 6 m rigidly attached to the casing pipe.
Some special forms of training of these well-known
Scrapers are now attached to the pipe in such a way that
that they are lying between two
schlagen frei beweglich sind. Diese begrenzte Dewe- *o Jesse r Ha Weatherford Tex (λΛ st A) beat are freely movable. This limited Dewe- * o Jesse r Ha Weatherford Tex (λΛ st A)
gungsmoghchkeit der Schrapper ist vorgesehen, umThe scraper is provided for
den Schrappern auf dem Futterrohr so viel Spiel zu ist als Erfinder genannt wordenTo give so much play to the scrapers on the casing pipe has been named as the inventor
geben, daß das Futterrohr eine kurze Strecke an- that the casing is a short distance
gehoben werden kann, damit es beim Einfuhren in dascan be lifted so that it is imported into the
Bohrloch von den Greifern und dem Drehtisch frei 25 *Drill hole free from grippers and turntable 25 *
gemacht werden kann, ohne dabei eine entsprechende ganze Länge des auszuzementicrenden Bereiches, ins-can be made without a corresponding entire length of the area to be cemented, in particular
Aufwärtsbewegung der Schrapper zu verursachen. besondere während des eigentlichen Zemcntiervor-Causing upward movement of the scraper. especially during the actual ceremony
Weiterhin dient dieser Spielraum dazu. Schrappern ganges, abschaben.This leeway is also used. Scraper ganges, scrape off.
mit umkehrbaren Schrapperelementen bei Richtungs- Dabei wird unter Verwendung von das Futterrohrwith reversible scrapers for directional This is done using the casing
umkehr der hin- und hergehenden Rohrbewegung die 30 mit einem Gleitring umgebenden, zwischen AnschlägenReversal of the reciprocating pipe movement surrounding the 30 with a sliding ring, between stops
notwendige Drehungsfreiheit zu geben. Zwischen be- längsverschiebbaren Schrapp- und Kratzvorrichtungento give the necessary freedom of rotation. Between longitudinally displaceable scraping and scraping devices
nachbarten Schrappern, ob diese nun auf dem Rohr vorzugsweise so vorgegangen, daß das mit jeweilsneighboring scrapers, whether these are now on the pipe, preferably so that that with each
mit etwas Spiel oder fest angeordnet sind, befindet einem gemeinsamen Anschlag zwischen zwei aufein-with a bit of play or are firmly arranged, there is a common stop between two
sich aber bei den bisher üblichen Anordnungen immer anderfolgenden Kratzern ausgerüstete Futterrohr imbut with the previously usual arrangements always differently equipped lining pipe in the scratches
noch eine Rohrlänge von 4 bis 5 m. Dies wurde bisher 35 Bohrloch mit einem Hub auf- und abwärtsbewegta pipe length of 4 to 5 m. So far, this has been moved up and down 35 boreholes with one stroke
nicht als störend angesehen, da man annahm, daß wird, der größer als die Entfernung zwischen benach-not regarded as disturbing, since it was assumed that w i r d, which is greater than the distance between neighboring
Schlamm und insbesondere Zement sich nicht in barten Anschlägen ist.Mud, and especially cement, is not in beard stops.
einem beträchtlichen Ausmaß auf dem Rohr absetzen Andere Ziele ergeben '-ich aus der Beschreibung ansettle to a considerable extent on the pipe. Other objectives emerge from the description
würde. Hand der Zeichnungen, in denen die in verschiedenenwould. Hand of the drawings in which the in different
Es wurde nun nach einer großen Anzahl von Ver- 40 Figuren befindlichen gleichen Teile mit den gleichenAfter a large number of 40 figures, the same parts were found with the same
suchen gefunden, daß entgegen der bisherigen Ansicht, Bezugszeichen bezeichnet sind. In den Zeichnungen istsearch found that, contrary to the previous view, reference numerals are designated. In the drawings is
daß auf der glatten Oberfläche des Futterrohres der Fig. 1 ein Querschnitt eines Bohrloches mit Zen-that on the smooth surface of the casing of FIG. 1 is a cross-section of a borehole with Zen-
Schlamm uud der Zement nicht zum Absetzen und zur trier- und Schrappgeräten, die auf der AußenwandMud and the cement not for settling and for trimming and scraping devices on the outside wall
Klumpenbildung neigen würden, dies doch der Fall des Futterrohres aufgebiacht sind, das eine nach obenWould tend to form lumps, but if this is the case with the casing, the one at the top
ist und daß, wenn nichts dagegen unternommen wird, 45 gerichtete Bewegung ausführt,is and that if nothing is done about it, it carries out 45 directed movement,
sich immer mehr Zement auf diesen glatten Flächen Fig. 2 eine Stirnansicht des Zentriergerätes mitmore and more cement on these smooth surfaces Fig. 2 shows a front view of the centering device
ansammelt. Dabei entstehen Klumpen von beträcht- einem Teil des nächstliegenden Ringes und zwei ge-accumulates. This creates clumps of a considerable part of the closest ring and two
licher Größe und verengen den ringförmigen Zwischen- brachen dargestellten Drahtstangen,licher size and narrow the annular intermediate breaks shown wire rods,
raum wesentlich, so daß der Umlauf von Schlamm Fig. 3 eine Seitenansicht des Zentriergerätes, wobeispace substantially, so that the circulation of sludge Fig. 3 is a side view of the centering device, wherein
und Zement weitgehend beeinträchtigt wird. 5° Teile der Ringe weggebrochen sind,and cement is largely affected. 5 ° parts of the rings have broken off,
Diese bisher unbekannte Ursache einer häufigen Fig. 4 ein waagerechter Teilschnitt in der MitteThis hitherto unknown cause of a frequent Fig. 4 a horizontal partial section in the middle
Störung des Zementiervorgangs wird erfindungs- durch eine gelochte Kante eines Ringes, wobei dieDisturbance of the cementing process is invented by a perforated edge of a ring, whereby the
gemäß dadurch beseitigt, daß die Schrapper auch die Drahte vor dem Einsetzen des Sperringes nach innenaccordingly eliminated by the fact that the scraper also pulls the wires inwards before inserting the locking ring
Außenwand des Futterrohres über im wesentlichen die geschwenkt sind,Outer wall of the casing is pivoted about essentially
3 43 4
Fig. 5 ein Einzelschnitt nach Linie 5-5 der Fig. 3, 20c oder 20d des Zylinders 20 und gegen die Außen-Fig. 5 is a single section along line 5-5 of Fig. 3, 20c or 20d of the cylinder 20 and against the outer
gesehen in Richtung der Pfeile, und zwar nach dem fläche des Futterrohres, um den Zylinder 20 fest aufseen in the direction of the arrows, namely after the surface of the casing to the cylinder 20 firmly
Einsetzen des Sperringes, (h-m Futterrohr zu halten. Beim Aufschieben desInsertion of the locking ring (hm to hold the casing. When pushing on the
Fig. 6 ein abgeändertes· Zentriergerät, dessen obere Zylinders 20 auf das Rohr wird die SchraubenfederFig. 6 shows a modified centering device, the upper cylinder 20 of which on the tube becomes the helical spring
und untere Ringe einen einzigen zylindrischen Bau- 5 21 in der in Fig. 6 dargestellten Neutralstellung ge-and lower rings form a single cylindrical structure 5 21 in the neutral position shown in FIG.
teil bilden, während der Mittelabschnitt eine zum halten. Nach richtigem Aufsetzen wird die Schrauben-form part, while the middle section one to hold. After correct placement, the screw
Befestigen des Gerätes an dem Mantelrohr dienende feder freigegeben, so daß sich der Zylinder in beidenFastening the device to the jacket pipe serving the spring released so that the cylinder is in both
Verankerung hat, Richtungen mit Bezug auf die Schraubenfeder freiAnchoring has free directions with respect to the coil spring
Fig. 7 eine Stirnansicht des in Fig. 6 dargestellten bewegen kann, wobei die Feder gegen eine der Schräg-Zentriergerätes, wobei ein Teil des Zylinders weg- io flächen 20 c oder 2Od des Zylinders geklemmt und ingebrochen ist, um die Schraubenfeder sichtbar zu folgedessen das Zentriergerät fest in seiner Stellung machen, die einen Teil der Keilvcrankerimg bildet, gehalten wird. Das Merkmai, wie die Schraubenfeder7 shows an end view of the one shown in FIG. 6, the spring being able to move against one of the oblique centering devices, with part of the cylinder being clamped away from surfaces 20c or 20d of the cylinder and broken in order to visibly follow the helical spring make the centering device firmly in its position, which forms part of the wedge crankerimg, is held. The feature, like the coil spring
Fig. 8 ein zusammengestapelter Aufbau aus Schrap- beim Aufsetzen des Gerätes auf das Rohr in einer8 shows a stacked structure of scrap when the device is placed on the pipe in a
pern und Zentrierkörpern, fertig zum Aufbringen auf ,Veutralstellung gehalten wird, und das Merkmal, wiepern and centering bodies, ready for application on, neutral position is held, and the feature of how
ein Futterrohr, und 15 die Feder freigegeben wird, damit das Werkzeug sicha liner, and 15 the spring is released to allow the tool to move
Fig. 9 ist ein lotrechter Schnitt durch eine abge- frei bewegen kann, um die Feder zwischen das RohrFig. 9 is a vertical section through an ab- able to move the spring between the tube
änderte Form des Zentriergerätes, bei dem federnde und die Schrägfläche des Zylinders 20 einzuklemmen,changed shape of the centering device, in which the resilient and the inclined surface of the cylinder 20 are clamped,
Doppelkeilc verwendet werden, um das Zentriergerät sind Gegenstand einer besonderen Erfindung,Doppelkeilc used to center the centering device are the subject of a particular invention,
auf dem Rohr zu befestigen, und bei dem der Halte- Bei der in Fig. 9 dargestellten Ausführung ist derto fasten on the pipe, and in which the holding In the embodiment shown in Fig. 9 is the
ring und die Ringe aus einer einzigen zylindrischen 20 Körper des Zylinders auf seinem Umfang oberhalbring and the rings from a single cylindrical 20 body of the cylinder on its circumference above
Büchse bestehen. und unterhalb seines Mittelabschnittes mit dach-Can exist. and below its middle section with roof
Tn dem durch die Erdschicht 12 gebohrten Bohr- förmigen Erhebungen versehen, durch die zwei Gruploch 11 hängt das Futterrohr 10, dessen Abschnitte pen von Schrägflächen 20c und 2Od gebildet werden, mittels Stoßverbindungen "oder Kupplungen 13 mit- innerhalb des Zylinders und zwischen dem Zylinder einander verbunden sind.. Auf dem in Fig. ί dar- 25 and dem Futterrohr unmittelbar unterhalb der Ergestellten Rohrabschnitt sind die in Fig. 8 gestapelt hebungen liegen einzelne Schraubenfedern 21, die als dargestellten Geräte aufgesetzt. Am oberen Ende und zwischen den Schrägflächen und dem Futterrohr lieam unteren Ende sowie zwischen den beiden Zentrier- gende Keile wirken. Bei dieser Ausführung wird kein geräten befinden sich die Schrapper 14 üblicher Aus- Sperring 18 verwendet, der die Enden der Drahtführung aus einem Ιΐ-iiig, aus dessen Lochreiheji die 30 stalle 17 an ihrem Platz in den Ringen hält, sondern die Schrapperdrähte vorstehen. Die in Fig. 8 gestapelt oberen und unteren Kanten des Zylinders sind in dargestellten Zentrierkörper sind einzeln im ver- Form von untergreif enden Felgen 20c auf sich zugrößerten Maßstab in den Fig. 2 und 3 wiedergegeben rückgebogen.Provided in the Bohr-shaped elevations drilled through the earth layer 12, through the two group holes 11 hangs the casing 10, whose sections pen are formed by inclined surfaces 20c and 20d, by means of butt joints "or couplings 13 with- within the cylinder and between the cylinder are connected to each other .. On the one in Fig Pipe section are the lifts stacked in Fig. 8 are individual coil springs 21, which as devices shown. At the upper end and between the inclined surfaces and the casing pipe lower end as well as between the two centering wedges act. There is no Devices are the scrapers 14 conventional locking ring 18 used, which the ends of the wire guide from a Ιΐ-iiig, from whose row of holes ji holds the 30 stalls 17 in their place in the rings, but the Scraper wires protrude. The top and bottom edges of the cylinder stacked in Fig. 8 are in The centering bodies shown are individually enlarged towards themselves in the form of rims 20c reaching under Scale shown in FIGS. 2 and 3 bent back.
und bilden je einen einheitlichen Bauteil 15. Aufbau- Um das in den Fig. 1 bis 3 dargestellte Zentriermäßig besteht jeder Zentrierkorper aus einem oberen 35 gerät auf dem Futterrohr aufzustellen, sitzt auf dem Ring 16 und aus einem unteren Ring 16, die durch Futterrohr zwischen den Ringen ein Anschlagring 21 auswärts gewölbte Drahtstäbe 17 miteinander ver- (Fig. 1 und 8). Die Befestigung des Anschlagringes bunden sind. In den Ringen sind Rippen 16a und 16b an dem Futterrohr mittels einer Schraubenfeder, z. B. vorhanden, you denen die Rippen 16a auf Abstand der Schraubenfeder 21, ist am Mittelabschnitt des stehende Bohrungen aufweisen, um die zurückgebo- 40 Zylinders 20 in Fig. 6 ersichtlich.and each form a unitary component 15. Structure To the centering shown in Figs. 1 to 3, each centering body consists of an upper 35 device to set up on the casing, sits on the ring 16 and a lower ring 16, which is through the casing between the rings a stop ring 21 outwardly curved wire rods 17 with each other (Fig. 1 and 8). The fastening of the stop ring are tied. In the rings, ribs 16a and 16b are attached to the casing by means of a coil spring, e.g. B. present, you which the ribs 16a at a distance from the helical spring 21, is at the central portion of the standing bores to the bent back 40 cylinder 20 in Fig. 6 can be seen.
genen Enden 17a der Stäbe 17 aufzunehmen, die auf Die jetzt allgemein verwendeten ZentriergeräteGenen ends 17a of the rods 17 to receive the centering devices now generally used
diese Weise in den Ringen verankert werden. haben nach außen gebogene Flügel mit einem Gesamt-this way to be anchored in the rings. have outwardly curved wings with a total
Sperrbänder 18 mit einer Ringnut, die sich in die durchmesser, der für gewöhnlich etwas größer ist als gleichartig gebildete Nut 16/» der Ringe 16 von hinten der Durchmesser des Bohrloches. Infolgedessen beeinlegt, werden nach dem Einschieben der Hrahtstab- 45 steht eine Berührung zwischen den Flügeln und dem enden in die Ringe 16 hineingepreßt, um die Draht- Bohrloch, ausgenommen dort, wo der Bohrlochdurchstabenden fest an ihrem Platz zu halten. Die gewölb- messer vergrößert worden ist. Der Durchmesser des ten MittelabschnJtte der Drahtstäbe sind zwecks Ver- erfindungsgemäßen Zentriergerätes entspricht vorsteifung zu S-Kurven 17?; gebogen und bilden bei der zugsweise dem Durchmesser des Bohrloches, um den Auf- und Abwärtsbewegung des Zentrierkörpers im 50 Reibungswiderstand zu vermindern und auch den Bohrloch ein Schneidwerkzeug. Der zusammengesetzte Flüssigkeitsumlauf nicht zu behindern. Der Aufbau Stapel aus Schrappern und Zentriergeräten wird bei der Ringe und des Anschlagringes zu einem einzigen der Ausführung nach Fig. 8 mittels eines Drahtes 19 zylindrischen Bauteil, wie ihn die Abänderung nach zusammengehalten. den Fig. 6 und 7 zeigt, ermöglicht ein Stoßen oderLocking straps 18 with an annular groove extending into the diameter, which is usually slightly larger than similarly formed groove 16 / »of the rings 16 from behind the diameter of the borehole. As a result, After the wire rod has been pushed in, there is contact between the wings and the ends pressed into rings 16 around the wire borehole, except where the borehole rod ends hold firmly in place. The vaulting diameter has been enlarged. The diameter of the The middle sections of the wire rods are pre-stiffened for the purpose of the centering device according to the invention to S-curves 17 ?; bent and form in the preferably the diameter of the borehole to the To reduce up and down movement of the centering body in the 50 frictional resistance and also the Borehole a cutting tool. Not to hinder the compound fluid circulation. The structure The stack of scrapers and centering devices becomes one with the rings and the stop ring the embodiment according to FIG. 8 by means of a wire 19 cylindrical component, as the modification according to held together. 6 and 7 shows, allows a bump or
Bei der in den Fig. 6 und 7 dargestellten abge- 55 Ziehen, ohne Rücksicht auf die BewegungsrichtungIn the case of the pulling shown in FIGS. 6 and 7, regardless of the direction of movement
änderten Ausführung sind die Ringe als ein einziger des Futterrohres.In the modified version, the rings are a single part of the casing.
zylindrischer Bauteil 20 mit Nuten 20a und 20b ge- Das Aufsetzen von Schneidwerkzeugen, und zwarcylindrical component 20 with grooves 20a and 20b- The placement of cutting tools, namely
formt. Die Nuten 20a sind gelocht, um die Enden der Zeutriergeräten oder Schrappern, erfolgt so, daß eineforms. The grooves 20a are perforated around the ends of the Zeutriergeräte or scrapers, so that a
Drahtstäbe 17 aufzunehmen, wie dies bei der Aus- Längsbewegung längs des Futterrohres währendTo receive wire rods 17, as this during the longitudinal movement along the casing pipe
führung nach den Fig. 2 und 3 der Fall ist. An gegen- 60 dessen Auf- und Abwärtsbewegung möglich ist, damitguide according to FIGS. 2 and 3 is the case. At opposite 60 whose upward and downward movement is possible so
überliegenden Enden des Bauteils werden Sperrbänder die Fläche des Futterrohres ständig abgeschabt wyird.opposite ends of the component stop bands, the surface of the casing is constantly scraped w y ird.
18 eingesetzt mit je einer einzigen Vertiefung, die in Der Abstand zwischen den Anschlagringen zur Länge18 used each with a single recess, which in The distance between the stop rings to the length
die Nuten 206 des Zylinders eingreifen, um die ver- des dem Futterrohr gegebenen Hubes bestimmt diethe grooves 206 of the cylinder engage to determine the amount of stroke given to the casing
ankerten Enden der Drahtstangen fest an ihrem Platz Zahl der Schneidwerkzeuge und Anschlagringe, dieanchored ends of the wire rods firmly in place Number of cutting tools and stop rings that
zu halten. Der Mittelabschnitt des zylindrischen Bau- 65 auf jedem Rohrabschnitt notwendig sind, um einto keep. The middle section of the cylindrical construction 65 on each pipe section are necessary to a
teils 20 hat einen etwas größeren Durchmesser, so gleichzeitiges Reinigen des Rohres und der Bohrloch-partly 20 has a slightly larger diameter, so simultaneous cleaning of the pipe and the borehole
daß schräg liegende Keilflächen 20c und 2Od ent- wand zu erhalten. Die Aufstellung des Zentriergerätes,that inclined wedge surfaces 20c and 20d was removed. The installation of the centering device,
stehen. Innerhalb des vergrößerten Mittelabschnittes der Schrapper und der Anschlagringe wird vorzugs-stand. Within the enlarged central section of the scrapers and the stop rings, it is preferred
des Zylinders 20 liegt eine Schraubenfeder 21. Die weise so gewählt, daß die Auf- und Abwärtsbewegungof the cylinder 20 is a coil spring 21. The way chosen so that the up and down movement
Feder drückt gegen eine der schräg liegenden Flächen 70 während der Fertigstellung des Bohrloches nicht nurThe spring not only presses against one of the inclined surfaces 70 during the completion of the borehole
Claims (1)
anfangs das Futterrohr über verhältnismäßig kurze p
Hube auf- und abwärtsbewegt, um die an der Bohr- 5 latent Ansprüche:
lochwand befindliche Schlammschicht nicht zu stören, 1. Verfahren zum Zementieren eines Futterweil der Zusatz dieser Schicht zu dem Schlamm die rohres in einem Bohrloch, wobei von der Bohrloch-Viskosität und das Gewicht des Schlammes nachteilig wand über die ganze Länge des zu zementierenden erhöht. Nachdem ein freier Umlauf des Schlammes Bereiches Schlamm und/oder Zementansätze abvorhanden ist, kann die Hublänge erhöht werden, um io gekratzt werden, dadurch gekennzeichnet, daß auch die innerhalb des Bohrloches liegenden Schrapper die Außenwand des Futterrohres über im wesentdurcli Anstoßen mit den Anschlagriugen so zu be- liehen die ganze Länge des auszuzementierenden wegen, daß ihre über die Wandfläche geführten Bewe- Bereiches, insbesondere während des eigentlichen gungen sich überlappen und ein einwandfreies Ab- Zementiervorganges, abgeschabt wird,
schleifen erfolgt. Die längs des Futterrohres gleitenden 15 2. Verfahren nach Anspruch \ unter Verwen-Ringe des Zentriergerätes und der Schrapper halten dung von das Futterrohr mit einem Gleitring das Futterrohr sauber und verhüten eine Aiisamm- umgebenden, zwischen Anschlägen längsverschieb' lung von Schlamm oder Zement auf dem Rohr. Als baren Kratzvorrichtungen, dadurch gekennzeichein typisches Beispiel für die Aufstellung der Zen- net, daß das mit jeweils einem gemeinsamen trier- und Schrappgeräte sei angegeben, daß bei Rohr- ao Anschlag zwischen zwei aufeinanderfolgenden längen von 13,5 m drei Schrapper vorgesehen werden, Kratzern ausgerüstete Futterrohr im Bohrloch deren Anschlagringe so im Abstand voneinander auf- mit einem Hub auf- und abwärts bewegt wird, der gestellt sind, daß eine annähernd 4,5 m große Bewe- größer als die Entfernung zwischen benachbarten gung der Schrapper auf dem Rohr erfolgt. Um die Anschlägen ist.In order to achieve free movement, the limiting sense must be assessed
initially the casing over a relatively short p
Stroke moved up and down to the 5 latent claims on the drilling:
Not to disturb the hole wall located mud layer, 1. Method of cementing a lining because the addition of this layer to the mud increases the pipes in a borehole, whereby the borehole viscosity and the weight of the mud adversely wall over the entire length of the to be cemented increases. After there is no free circulation of the mud area, mud and / or cement deposits, the stroke length can be increased by 10 scratches, characterized in that the scrapers located inside the borehole also close the outer wall of the casing by essentially abutting with the stop rings lent the entire length of the cement to be cemented, so that their movement areas guided over the wall surface, especially during the actual work, overlap and a perfect cementing process is scraped off,
grinding takes place. The sliding along the liner 15 2. Method according to claim \ under use rings of the centering device and the scraper keep the liner clean with a sliding ring and prevent an Aiisamm- surrounding, between stops longitudinal displacement of mud or cement on the Pipe. As a bar scratching device, a typical example for the installation of the center is indicated that each with a common trimming and scraping device, three scrapers are provided between two successive lengths of 13.5 m, scratches equipped casing in the borehole whose stop rings are moved up and down at a distance from each other with a stroke that is set so that a movement of approximately 4.5 m is greater than the distance between adjacent movement of the scrapers on the pipe. To the attacks is.
als die Anschläge für die Schrapper benutzt, so er- 4. Kratzvorrichtung zur Ausführung des Vergibt sich die in Fig. 1 dargestellte typische Aufstel- fahrens nach den Ansprüchen 1 bis 3, welche mit lung der Zentriergeräte, wobei die Schrapper oberhalb einer gleitbaren Zentriervorrichtung verbunden ist, des oberen Zentriergerätes und unterhalb des unteren dadurch gekennzeichnet, daß die Rohrkupplungen Zentriergerätes Siegen und ein Schrapper in einer 35 (13) als obere und untere Anschläge für die Mittelstellung zwischen den beiden Zentriergeräten Kratzer und Zentrier vorrichtungen vorgesehen vorgesehen ist. sind.To clean the borehole wall, up and down were 25 3. The method according to claim 2, characterized in that movements of 9 m or more marked the desired, that temporarily worked with a stroke result. There will be one or two centering devices, which is slightly less than the distance between two devices for each adjacent stop consisting of three scrapers, so that the scraper set is used on a single pipe section, only the outer wall of the casing pipe will be used, and the centering devices and pipe connections will be used do not fertilize 30 but scrape the borehole wall,
used as the stops for the scrapers, so he 4. Scratching device for executing the. The typical erection shown in FIG is, the upper centering device and below the lower one characterized in that the pipe couplings centering device Siegen and a scraper is provided in a 35 (13) as upper and lower stops for the middle position between the two centering devices, scratchers and centering devices. are.
laß für den Zement geschaffen, so daß der Zement 6. Zentriervorrichtung nach Anspruch 5, dadurch leichter an die VerwendungssteUe gepumpt werden 50 gekennzeichnet, daß die Ringe (16) in Unifangskann und die Möglichkeit begrenzt wird, daß nach dem richtung verlaufende gelochte Rippen (I60) haben, Erhärten der Zemcntsäule nicht verlagerter Zement in welche die gebogenen Enden (17 α) der Stäbe in dem Futterrohr sich befindet. (17) eingeführt und verankert sind.As soon as the cement is poured into the annular space surrounding the casing, the lifting can be slid on the casing pipe, lower length on which the casing moves up and down v 3 and upper rings on which the opposite will be shortened, so that the scrapers stand- ^ n ends of several remain on the circumference of the rings and do not work on the wall of the borehole. spaced resilient elements be-The pipe then slides inside the scraper rings, which are fastened between the rings prevents the cement from accumulating on the stretching middle sections arched outwardly outer wall of the pipe, while a structure of 45 are characterized that the resilient cement layer is possible in the borehole. On these elements are formed from rods (17), which are cut in ways by means of the movement of the tube through their outwardly curved center en the rings are bent through an open annular channel or through-in S-shaped curves,
let created for the cement, so that the cement 6. centering device according to claim 5, characterized more easily 50 to the usage control, characterized in that the rings (16) in the Unifangskann and the possibility is limited that in the direction of perforated ribs (I60 ), hardening of the Zemcntsäule not displaced cement in which the bent ends (17 α) of the rods in the casing is located. (17) are introduced and anchored.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DEH16883A DE1058453B (en) | 1953-06-27 | 1953-06-27 | Method and apparatus for cementing casing in a borehole |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
DEH16883A DE1058453B (en) | 1953-06-27 | 1953-06-27 | Method and apparatus for cementing casing in a borehole |
Publications (1)
Publication Number | Publication Date |
---|---|
DE1058453B true DE1058453B (en) | 1959-06-04 |
Family
ID=7148043
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
DEH16883A Pending DE1058453B (en) | 1953-06-27 | 1953-06-27 | Method and apparatus for cementing casing in a borehole |
Country Status (1)
Country | Link |
---|---|
DE (1) | DE1058453B (en) |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2179812A (en) * | 1938-06-17 | 1939-11-14 | Ralph M Calkins | Plug for use in cementing wells |
DE745658C (en) * | 1941-04-27 | 1944-03-21 | Fuerther Tiefbohranstalt | Guide device for deep drilling rigs |
US2546582A (en) * | 1948-03-01 | 1951-03-27 | Baker Oil Tools Inc | Casing centralizer |
-
1953
- 1953-06-27 DE DEH16883A patent/DE1058453B/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2179812A (en) * | 1938-06-17 | 1939-11-14 | Ralph M Calkins | Plug for use in cementing wells |
DE745658C (en) * | 1941-04-27 | 1944-03-21 | Fuerther Tiefbohranstalt | Guide device for deep drilling rigs |
US2546582A (en) * | 1948-03-01 | 1951-03-27 | Baker Oil Tools Inc | Casing centralizer |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
DE945321C (en) | Hydraulic anchoring and holding tool, in particular for use in oil wells | |
DE2043385C3 (en) | Breakout valve for boreholes | |
DE1962443C3 (en) | Sealing device for an underwater wellhead | |
DE2721279A1 (en) | PROCESS FOR THE STEPPING CEMENTING OF A COMPOSITE PIPE STRING INTO A DRILL HOLE IN THE SEA FLOOR AND DEVICE FOR CARRYING OUT THE PROCESS | |
DE1297043B (en) | Underground diaphragm wall and methods of making it | |
DE2550626A1 (en) | METHOD AND DEVICE FOR CONNECTING PILE SECTIONS | |
DE1302138B (en) | ||
DE2624079C2 (en) | Method and drilling device for producing rock and earth boreholes with a special cross-section | |
DE1058453B (en) | Method and apparatus for cementing casing in a borehole | |
DE1299255B (en) | Method of drilling in the earth and drill bits for practicing the method | |
DE1301286B (en) | Hanging device for string of pipes in underwater boreholes and insertion tools | |
AT393525B (en) | METHOD FOR CUTTING A LOCAL CONCRETE PILE | |
EP2942474B1 (en) | Drill bit having a number of roller bits for drilling a ground surface, and a method for detaching a drill bit with a number of roller bits drilling a ground surface from a pipe shoe in the sunk state | |
CH679881A5 (en) | ||
DE8714200U1 (en) | Kelly bar for an earth drilling machine | |
DE3543295C2 (en) | ||
AT226160B (en) | Method of building secant pillars which have free parts | |
DE2030276C3 (en) | Manhole cover, consisting of a cover and a height-adjustable frame | |
AT205063B (en) | Device for fixing the dowels in the production of concrete road surfaces | |
DE697025C (en) | Device for lowering pipes, in particular concrete pipes | |
DE2303767C2 (en) | Process to be carried out in two phases for the production of a pile consisting essentially of in-situ concrete and a kit for carrying out the process | |
DE7204914U (en) | ROAD CAP FOR WATER GAS PIPES LAYING UNDER THE FLOOR OR DGL. | |
DE1963758C3 (en) | Method and device for releasing a pipe string from a connection lying under the seabed | |
DE4138497A1 (en) | Installation of pipes in bathrooms with concrete floors - by using support pipes attached to shuttering | |
DE2252005C3 (en) | Precast concrete element with connecting devices |