CS264564B1 - Method of mining of ore deposits of sedimentary type - Google Patents

Method of mining of ore deposits of sedimentary type Download PDF

Info

Publication number
CS264564B1
CS264564B1 CS865596A CS559686A CS264564B1 CS 264564 B1 CS264564 B1 CS 264564B1 CS 865596 A CS865596 A CS 865596A CS 559686 A CS559686 A CS 559686A CS 264564 B1 CS264564 B1 CS 264564B1
Authority
CS
Czechoslovakia
Prior art keywords
chamber
mining
corridor
contouring
mineralization
Prior art date
Application number
CS865596A
Other languages
Czech (cs)
Other versions
CS559686A1 (en
Inventor
Jiri Ing Bruha
Tomas Ing Slovacek
Josef Ing Berka
Pavel Ing Sadilek
Original Assignee
Jiri Ing Bruha
Tomas Ing Slovacek
Josef Ing Berka
Pavel Ing Sadilek
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiri Ing Bruha, Tomas Ing Slovacek, Josef Ing Berka, Pavel Ing Sadilek filed Critical Jiri Ing Bruha
Priority to CS865596A priority Critical patent/CS264564B1/en
Publication of CS559686A1 publication Critical patent/CS559686A1/en
Publication of CS264564B1 publication Critical patent/CS264564B1/en

Links

Landscapes

  • Manufacture And Refinement Of Metals (AREA)

Abstract

Způsob dobývání rudných ložisek sedimentárního typu, zejména uranových při použití metody komora -„pilíř s vyztužováním stropu a zalistováním boků svorníku s následným zakládáním vydobytých komor hydrotuhnoucí zakládkou. Po vyražení vrchní konturační chodby se provádí ražba vrchní nebo spodní části komory při„současném vyztužování stropu a zajištování boků svorníky a pletivem v celé úklonné délce dobýváčího bloku až po dosažení úrovně spodní nebo vrehní konturační chodby. Dále je z úrovně spodní nebo vrchní konturační chodny ražena spodní část komory a to přímo v půdorysném profilu pod vrchní částí komory. Tato spodní část komory je ražena opět až do úrovně vrchní nebo spodní konturační chodby, přičemž je postupně prováděno zajištování boků této spodní části komory v návaznosti na zajištěné již dříve boky vrchní části komory.Method of mining sedimentary ore deposits, especially uranium ores, using the chamber-pillar method with ceiling reinforcement and bolt side lining, followed by backfilling of the extracted chambers with hydro-setting backfill. After the upper contouring passage is excavated, the upper or lower part of the chamber is excavated while simultaneously reinforcing the ceiling and securing the sides with bolts and mesh throughout the entire inclined length of the mining block until the level of the lower or upper contouring passage is reached. Furthermore, the lower part of the chamber is excavated from the level of the lower or upper contouring passage, directly in the plan view profile under the upper part of the chamber. This lower part of the chamber is excavated again up to the level of the upper or lower contouring passage, while the sides of this lower part of the chamber are gradually secured in connection with the previously secured sides of the upper part of the chamber.

Description

Vynález se týká způsobu dobývání rudných ložisek sedimentárního typu,zejména uranových,využitím metody komora - pilíř s následným zakládáním hydrotuhnoucí zakládkou·The invention relates to a method of mining sedimentary-type ore deposits, in particular uranium, by using the chamber-pillar method with subsequent foundation of a water-hardening filler.

Při dobývání rudných ložisek sedimentárního typu, zejména uranových,je používána dobývací metoda komora - pilíř. Tato dobývací metoda vychází ze známé metody komorování, která je využívána při dobývání především mocnějších uhelných ložisek sedimentárního typu. Při této dobývací metodě komorování vyžaduje technologie postupu vedení důlního díla ponechání mezikomorových a stropních ochranných pilířů za účelem udržení celkové stability horninového masívu. Při použití této dobývací metody zůstávají ve ztrátách mezikomorové a stropní pilíře.When mining sedimentary ore deposits, especially uranium, the chamber - pillar mining method is used. This mining method is based on the known method of chambering, which is used in the mining of mainly stronger sedimentary-type coal deposits. In this mining method, mining technology requires the operation of the mine work to maintain the inter-chamber and ceiling protective pillars in order to maintain the overall stability of the rock mass. When using this mining method, the inter-chamber and ceiling pillars remain in losses.

Předpokladem pro využití dobývací metody komora - pilíř s hydrotuhnoucí základkou je horizontální uložení zrudnění v se dimentech, kdy celková mocnost zrudnění dosahuje hodnoty 3-5 metrů. Při opracování ložiska bývá zpravidla vlastní dolové pole rozděleno na dobývací bloky, ve kterých je následně použita metoda komora - pilíř. Jednotlivé komory jsou raženy z prostoru konturačních chodeb po úklonu ložiska. Pro dodržení opakovatelnosti technologického cyklu je po vydobytí komory provedeno zaplnění volného prostoru hydrotuhnoucí zakládkou z povrchu. Využitím opakovaného,předem stanoveného režimu postupného dobývání jednotlivých komor s následným zakládáním hydrotuhnoucí zakládkou je dosaženo vydobytí celého dobývacího bloku a tím postupně celého ložiska se ztrátami maximálně 5 %· Technologie dobývání metodou komora - pilíř je používána i v případě, že mocnosti zrudnění přesahují výšku 5 metrů. Dobývací metoda umožňuje dobývání tohoto zrudnění pomocí lávek. Prakticky jsou využívány dvě varianty lávkování,a to 3hora dolů nebo zdola nahoru. Při dobývání v lávkách v obou případech musí být vyražena nová zá264 >64A prerequisite for the use of the chamber - pillar method with a hydrothermal foundation is horizontal placement of mineralization in sediments where the total mineralization reaches 3-5 meters. When working the bearing, the actual bottom field is usually divided into mining blocks, in which the chamber - pillar method is subsequently used. Individual chambers are driven from the area of the contour corridors after the bearing inclination. In order to maintain the repeatability of the technological cycle, after the chamber has been extracted, the free space is filled with a water-hardening filler from the surface. By using repeated, predetermined mode of progressive mining of individual chambers followed by hydroturous loading, the extraction of the whole mining block is achieved and consequently the whole bearing with loss of maximum 5% · The technology of chamber-pillar mining is used even if the mineralization thicknesses exceed 5 meters. The quarrying method allows mining of this mineralization by means of footbridges. Practically, there are two variations of pumping, 3 up or down. In the case of quarrying in gangways in both cases, a new base> 64

- 2 kladní chodba ve vrchní části zrudnění, ze které je dobývána při lávkování shora dolů část zrudnění od vrchní hranice do maximální výšky 5 metrů. Před založením komory hydrotuhnoucí zakládkou je na počvu komory položen tzv. umělý strop. Po vydobytí a založení komor ve vrchní lávce je postupně vydobyta zbývající část zrudnění od spodní hranice po umělý strop. Z hlediska zajištění stability stropu komor spodní lávky musí být tyto přesazeny proti půdorysnému profilu komor vrchních lávek minimálně o třetinu šířky. Výztuž komor ražených ve spodní lávce musí být zásadně podpěrná , například neúplná dveřej. Hlavní nevýhodou tohoto způsobu dobývání je nutnost ražby další přípravné základní chodby při dobývání vrchní lávky. Dalšími nevýhodami je časová náročnost jednotlivých pracovních operací technologického cyklu, vysoká pracnost, materiálová a energetická náročnost dobývacích prací, ztráty a objemové znehodnocení.- 2 positive corridor in the upper part of the mineralization, from which the mineralization is extracted from the upper limit up to a maximum height of 5 meters from top to bottom. Before the foundation of the chamber with a solidifying filler, an artificial ceiling is laid at the front of the chamber. After the chambers have been excavated and the upper gangway is established, the remaining part of mineralization is gradually extracted from the lower limit to the artificial ceiling. In order to ensure the stability of the ceiling of the lower gangway chambers, these must be offset by at least a third of the width of the upper gangway chambers. The reinforcement of the chambers embossed in the lower gangway must in principle be supportive, for example an incomplete door. The main disadvantage of this method of mining is the need to excavate another preparatory basic corridor during the mining of the upper gangway. Other disadvantages are the time demands of individual work operations of the technological cycle, high labor intensity, material and energy demands of mining work, losses and volume devaluation.

Výše uvedené nevýhody do značné míry odstraňuje způsob dobývání rudných ložisek sedimentárního typutzejména uranových/ v mocnostech nad 5 metrů/podle vynálezu, využitím dobývací metody komora - pilíř při vyztužování stropu a zajišťování boků svorníky a pletivem s následným zakládáním hydrotuhnoucí zakládkou. Podstata tohoto způsobu spočívá v technologii ražby vrchní části komory od vrchní hranice zrudnění z prostoru vrchní nebo spodní konturační chodby ve výšce maximálně dvou třetin mocnosti zrudnění v celé úklonné délce dobývacího bloku. Postupně s ražbou je prováděno vyztužování stropu a zajišťování boků vrchní části komory svorníky a pletivem. Ražba je ukončena v úrovni spodní nebo horní konturační chodby a dále je postupně vyražena v půdorysném profilu pod vrchní částí komory spodní část komory, která počvou sleduje spodní hranici zrudnění. Tato ražba spodní části komory je dále prováděna až do úrovně vrchní nebo spodní konturační chodby při současném zajišťování boků komory svorníky a pletivem v návaznosti na zajištění boků již dříve provedené ve vrchní části komory.The above disadvantages are substantially eliminated by a method of mining ore deposits in sedimentary t particularly uranium / at a thickness above 5 m / according to the invention, using mining methods chamber - pillar reinforcement at the ceiling and securing bolts and wire sides with subsequent establishment hydrotuhnoucí fill. The essence of this method lies in the technology of driving the upper part of the chamber from the upper limit of mineralization from the area of the upper or lower contour corridor at the height of a maximum of two thirds of the mineralization thickness in the entire inclined length of the mining block. Gradually, the ceiling is reinforced and the sides of the upper part of the chamber are secured by bolts and mesh. The excavation is finished at the level of the lower or upper contour corridor and is subsequently embossed in the ground profile below the upper part of the chamber, the lower part of the chamber, which initially follows the lower limit of mineralization. This embossing of the lower part of the chamber is further carried out up to the level of the upper or lower contouring passage while simultaneously locking the sides of the chamber with bolts and mesh following the securing of the sides previously performed in the upper part of the chamber.

Výhody způsobu dobývání rudných ložisek sedimentárního typu v mocnostech nad 5 metrů/zejména uranových, dle vynálezu,se projevují jednoznačně ve zvýšení produktivity práce při ražbě, snížení materiálové náročnosti při vyztužování, při zakládání, snížení energetické náročnosti a snížení spotřeby trhavin. DáleThe advantages of the method of mining sedimentary ore deposits in thicknesses above 5 meters / especially uranium, according to the invention, are clearly manifested in increased productivity of excavation work, reduction of material intensity during reinforcement, foundation, reduction of energy intensity and reduction of explosives consumption. Further

264 564264 564

- 3 jsou výhody ve snížení ztrát z neúplného vydobytí, snížení procenta objemového znehodnocení a snížení nákladů na jednotku vydobytí rudniny. Související je i zvýšení produktivity vedlejších činností při zakládání vydobytých prostor a celkové zvýšení bezpečnosti práce·- 3 are the benefits of reducing losses from incomplete recovery, reducing the percentage of impairment and reducing the cost per unit of ore recovery. Related is also an increase in the productivity of secondary activities in the establishment of the acquired space and an overall increase in work safety.

Příkladné provedení způsobu dobývání podle vynálezu je znázorněno na přiložených Na obrázcích 1 - 3 je podélný řez dobývanou komorou v těžebním bloku s postupem vedení důlních prací při dobývání z vrchní konturační chodby a na obrázcích 4 - 6 je podélný řez dobývanou komorou v těžebním bloku s postupem vedení důlních prací při dobývání ze spodní konturační chodby· Na obr· 7 je příčný řez komorou·An exemplary embodiment of a method of mining according to the invention is shown in the enclosed figures. Figures 1-3 are a longitudinal section through a quarrying chamber in a mining block with the process of conducting mine work during mining from the upper contouring corridor; guiding mine workings during mining from the lower contour corridor · Fig. 7 shows a cross section of the chamber ·

Způsob dobývání vyšších mocností zrudnění ložisek sedimentárního typu podle vynálezu spočívá v tom, že z prostoru vrchní konturační chodby 11 nebo spodní konturační chodby 12 je od vrchní hranice li zrudnění 30 vyražena vrchní část 51 komory 20 ve výšce maximálně dvou třetin mocnosti zrudnění 30· Tato část komory 20 je vyražena v celé úklonné délce dobývacího bloku 10. Postupně s ražbou vrchní části 21 komory 20 ne prováděno vy z tuž ování stropu 26 komory 20 pomocí svorníků 4.1 a zátahem stropu 26 ocelovým pletivem 42· Pletivo 4.2 je současně použito i k zátahu boků 25 vrchní části 21 komory 20. Po dosažení úrovně spodní konturační chodby 12 nebo vrchní konturační chodby 11 je ražba vrchní části 21 komory 20 ukončena· Z prostoru spodní konturační chodby 12 nebo vrchní konturační chodby 11 jev půdorysném profilu pod vydobytou vrchní částí 21 komory 20 ražena spodní část 22 komory 20 od spodní hranice 32 zrudnění JO,, která sleduje tuto spodní hranici 32 zrudnění 30 komory 20 ^až do úrovně vrchní konturační chodby 12 nebo spodní konturační chodby 11· Při ražbě této spodní části 22 komory 20 pod zajištěným stropem 26 z ražby vrchní části 21 komory 20 je opět prováděno zajištění boků 25 spodní části 22 komory 20, v návaznosti na zajištění boků 25 komory 20 ocelovým pletivem 42 z ražby vrchní části 21 komory 20·The method of mining higher ore mineralization powers according to the invention is characterized in that the upper part 51 of the chamber 20 is punched from the upper contour corridor 11 or the lower contour corridor 12 from the upper limit of the mineralization 30 at a maximum of two thirds of the mineralization thickness 30. chamber 20 is punched in the entire inclined length of the mining block 10. Gradually with the excavation of the top part 21 of chamber 20, no reinforcement of the ceiling 26 of the chamber 20 is carried out by bolts 4.1 and the ceiling 26 is reinforced with steel mesh 42 When the lower contouring passage 12 or upper contouring passage 11 has reached the level of the lower contouring passage 12 or the upper contouring passage 11, the excavation of the upper portion 21 of the chamber 20 is terminated. part 22 of the chamber 20 from the lower limit 32 of mineralization 10 'which follows this lower limit 32 of mineralization 30 of chamber 20' to the level of upper contouring corridor 12 or lower contouring corridor 11. 20, again securing the sides 25 of the lower part 22 of the chamber 20, following the securing of the sides 25 of the chamber 20 with the steel mesh 42 from the stamping of the upper part 21 of the chamber 20 ·

Způsob podle vynálezu je prakticky využitelný při dobývání rudných ložisek sedimentárního ty£u při mocnostech zrudnění nad 5 metrů.The process according to the invention is practically applicable in the extraction of ore deposits of a sedimentary rod at mineralization powers above 5 meters.

Claims (1)

předmEt vynálezuobject of the invention Způsob dobývání rudných ložisek sedimentárního typu, zejména uranových v mocnostech nad 5 metrů využitím metody komora - pilíř při zajišťování stropu svorníky a pletivem s následným zakládáním hydrotuhnoucí zakládkou,vyznačený tím, že se z prostoru vrchní konturační chodby (11) nebo spodní konturační chodby (12) od vrchní hranice (31) zrudnění (30) nejdříve vyrazí vrchní část (21) komory (20) ve výšce maximálně dvou třetin mocnosti zrudnění (30) v celé úklonné délce dobývacího bloku (10), přičemž se současně s ražbou vrchní části (21) komory (20) postupně provádí vyztužování jejího stropu (26) a zajišťování boků (25) svorníky (41) a pletivem (42), načež se po dosažení úrovně spodní konturační chodby (12) nebo vrchní konturační chodby (11) vyrazí v půdorysném profilu pod vrchní částí (21) komory (20) spodní část (22) komory (20), sledující spodní hranici (32) zrudnění (30) až po dosažení úrovně vrchní konturační chodby (11) nebo spodní konturační chodby (12), přičemž se dále postupně provádí zajišťování boků (25) spodní Části (22) komory (20) v návaznosti na zajištění boků vrchní části (21) komory (20).Method of mining sedimentary-type ore deposits, especially uranium in thicknesses over 5 meters using the chamber-pillar method for securing the ceiling with bolts and mesh followed by hydrotracing filler, characterized by the fact that from the upper contour corridor (11) or lower contour corridor (12) ) from the upper limit (31) of the mineralization (30), firstly, the upper portion (21) of the chamber (20) is punched at a maximum of two thirds of the mineralization thickness (30) over the entire inclined length of the mining block (10); 21) of the chamber (20) successively reinforces its ceiling (26) and secures the sides (25) with bolts (41) and mesh (42), after which it reaches the level of the lower contour corridor (12) or the upper contour corridor (11). plan profile below the top (21) of the chamber (20) the bottom (22) of the chamber (20), following the lower limit (32) of the mineralization (30) up to reaching the level of the upper contour corridor (11) or the lower contour corridor (12), further securing the flanks (25) of the lower part (22) of the chamber (20) in succession after securing the flanks of the upper part (21) of the chamber (20).
CS865596A 1986-07-24 1986-07-24 Method of mining of ore deposits of sedimentary type CS264564B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CS865596A CS264564B1 (en) 1986-07-24 1986-07-24 Method of mining of ore deposits of sedimentary type

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CS865596A CS264564B1 (en) 1986-07-24 1986-07-24 Method of mining of ore deposits of sedimentary type

Publications (2)

Publication Number Publication Date
CS559686A1 CS559686A1 (en) 1988-09-16
CS264564B1 true CS264564B1 (en) 1989-08-14

Family

ID=5401133

Family Applications (1)

Application Number Title Priority Date Filing Date
CS865596A CS264564B1 (en) 1986-07-24 1986-07-24 Method of mining of ore deposits of sedimentary type

Country Status (1)

Country Link
CS (1) CS264564B1 (en)

Also Published As

Publication number Publication date
CS559686A1 (en) 1988-09-16

Similar Documents

Publication Publication Date Title
US5522676A (en) Undercut excavation method
CN111828007B (en) Stoping method for residual studs in underground mine goaf
CN108087008B (en) A kind of three-soft seam gob side entry method for protecting support
CN110331978B (en) Environment reconstruction segmented medium-length hole subsequent filling mining method
RU2277171C1 (en) Method of underground solid mineral deposit mining
EA000555B1 (en) Undercut excavation with protection against seismic events or excessive ground movement
CN108756901A (en) Former times lattice reach special formation Shallow Tunnel Construction method
CN106089207A (en) Super high seam work surface gob side entry driving thin coal pillar stays equipment, method
CN113565513A (en) Upper and lower step reserved core soil excavation method for tunnel excavation
Potvin et al. Open stope mining in Canada
US3731976A (en) Mining methods using equipment suspended from roof-mounted rails
CA2295230C (en) Method for the combined exploitation of mining fields
CS264564B1 (en) Method of mining of ore deposits of sedimentary type
RU2164293C2 (en) Process of working of coal seams
CN209443459U (en) Cut-pff wall assembled leads wall
Andrews et al. The geotechnical evolution of deep level mechanised destress mining at South Deep
RU2167299C2 (en) Method of mine working construction (versions)
RU2147683C1 (en) Method of mining blind orebodies under protected objects
CN114673528A (en) Tunnel top cavity supporting method
CN118242089B (en) Accurate and dense filling and repeated mining method for residual coal in small coal mine destroyed area
CN108547615A (en) A method of it is dug up mine using trackless equipment in Varied ore deposit group
CN215632971U (en) Digging and building construction structure of large underground mine chamber
CN116357322B (en) Low-waste arrangement method for off-pulse mining quasi-engineering by downward access filling mining method
SU1219806A1 (en) Method of mining thick gently-sloping ore deposits
CN111456742B (en) High-grade common mining opposite-drawing working face roadway of thin coal seam and forming method thereof