CN87102786A - Self-reaction testing method for pile with big diameter and deep piling - Google Patents

Self-reaction testing method for pile with big diameter and deep piling

Info

Publication number
CN87102786A
CN87102786A CN198787102786A CN87102786A CN87102786A CN 87102786 A CN87102786 A CN 87102786A CN 198787102786 A CN198787102786 A CN 198787102786A CN 87102786 A CN87102786 A CN 87102786A CN 87102786 A CN87102786 A CN 87102786A
Authority
CN
China
Prior art keywords
pile
test
bearing capacity
stake
big diameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN198787102786A
Other languages
Chinese (zh)
Other versions
CN87102786B (en
Inventor
刘健群
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Inst Of New Technology Heilongjiang Architecture Design Inst
Original Assignee
Inst Of New Technology Heilongjiang Architecture Design Inst
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Inst Of New Technology Heilongjiang Architecture Design Inst filed Critical Inst Of New Technology Heilongjiang Architecture Design Inst
Priority to CN87102786A priority Critical patent/CN87102786B/en
Publication of CN87102786A publication Critical patent/CN87102786A/en
Publication of CN87102786B publication Critical patent/CN87102786B/en
Expired legal-status Critical Current

Links

Images

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The present invention is the method for testing of the vertical quiet lotus bearing capacity of a kind of big diameter and deep stake, is to do test pile with two identical big diameter and deep stakes, at the pile crown of two test piles and the same level height place at pile body handing-over position, one group of loading jack is set respectively.And dig a vertical shaft in addition, the jack place set with horizontal tunnel and these two test piles links, and can carry out the test pile operation.The quiet lotus supporting capacity of utilizing the pile body of the pile crown of a pile and another pile to test its corresponding pile body and pile crown for reaction support respectively, superpose measured pile crown and bearing capacity of pile just draw complete bearing capacity.

Description

Self-reaction testing method for pile with big diameter and deep piling
The invention belongs to the method for testing of the vertical quiet lotus supporting capacity of pile foundation of construction work, be specially adapted to the test of the vertical quiet lotus supporting capacity of big diameter and deep stake.
When building is done the basis with stake, all need carry out the test of single-pile static load axial compression supporting capacity in advance, to determine the design supporting capacity of single pile.The stake footpath of stake commonly used on the engineering is all in 30~60 centimetres, about 20~200 tons of single pile design supporting capacity, for this small pile, the method of traditional direct mensuration single-pile static load axial compression supporting capacity has cushion cap loading pile testing method or adopts anchoring pile, crossbeam counterforce device, with jack loading pile testing method.Though these direct static force pile testing method testing expenses height, the cycle is long, and reliable because of resultant data, so some are than important engineering, still essential the employing.In order to improve test pile efficient, reduce the test pile expense, a lot of in recent years pile testing methods indirectly constantly occur, as dynamic measurement of pile, resonance method etc., but the data that these indirect pile testing methods still all need direct pile testing method to be accumulated, set up the dependency relation between the two, could determine the accuracy of these indirect pile testing methods.Therefore, directly the data of pile testing method remains requisite.
Along with the continuous development of Building technology, new big diameter and deep pile foundation is adopted in a large number, and the stake footpath of this stake is at 1~2 meter, and stake is dark to reach 30 meters, single pile design supporting capacity have more than kiloton, these timber piles are used for important engineering more, therefore essential test pile.Adopt above-mentioned jack loading pile testing method commonly used, need four large-scale anchoring piles and three huge crossbeams just can carry out at least, costly, the duration is very long, sometimes even can't test pile, can only estimate, and estimation be inaccurate, causes waste.If adopt indirect pile testing method, because lack relevant direct test pile data, can't be analyzed, again so the single pile design bearing capacity is difficult to determine.Therefore, how direct test pile being carried out in the big diameter and deep stake is a problem extremely to be solved.
Purpose of the present invention, be to make the big diameter and deep stake when direct slow test, do not use costly anchoring pile and crossbeam counterforce device, but when utilizing the big diameter and deep pile driving construction, the stake footpath is bigger, and the constructor can enter a characteristic of inside, hole, the loading jack is put into the gap of pile crown and pile body, test pile crown and another pile body quiet lotus supporting capacity separately in these two test piles respectively, its supporting capacity that superposes is to obtain the quiet lotus supporting capacity of full stake.
Content of the present invention is a kind of pile testing method of big diameter and deep stake, it is characterized in that the big diameter and deep stake (A, B) of two test usefulness when the concrete of pouring stake, pile crown and pile body are watered respectively, all disconnect one section of 60~80 centimeter length at the sustained height place, the pile crown load carrying capacity test is carried out in the A stake, in order to ensure pile body enough counter-forces is arranged, and should expand the lower end of pile body and dig, behind the placing of concrete, be formed on the enlarged footing that the pile body lower end has a concrete rounding platform.If only for test pile, can not water pile concrete, only water a concrete rounding platform.The pile body load carrying capacity test is carried out in the B stake, does reaction support with pile crown, can suitably enlarge the pile crown size in case of necessity.Put into the loading jack at pile crown and pile body gap.Dig a vertical vertical shaft C then in addition, reach with two test piles in its degree of depth and to have put into the fracture absolute altitude degree of depth of loading jack when identical, dig a horizontal tunnel again, the fracture of two test piles of UNICOM, in the tunnel, connect the oil pipe of loading jack and oil pump, can carry out the load carrying capacity test of pile crown and pile body respectively.With the pile crown bearing capacity of A stake and the bearing capacity of pile stack of B stake, be exactly the supporting capacity of a full stake.Test pile by withdrawing from the tunnel, hangs out ground with jack after finishing from vertical shaft C, fill tunnel and vertical shaft C at last.
If what test pile was used is engineering piles, a need be made pile body hollow, 15~20 centimetres of hollow hole hole dias.After the test pile task termination, pour into the pea gravel concreten of high-ductility in the hollow thus hole, fill up the fracture space between pile crown and pile body, just can be unified into an integral body to stake, guarantee the engineering use.This vertical vertical shaft C also can substitute with an engineering piles, continues the pile crown of excavating shaft C stake after the off-test, fills the tunnel with the pile crown earthwork, builds stifled tunnel face with common brick then, forms pile lining, is exactly an engineering piles behind the placing of concrete.
The present invention and the most frequently used anchoring pile, crossbeam counterforce device and the comparison of jack loading pile testing method, can save the concrete and the steel of whole four large-scale anchoring piles, and the making of three huge girder steels, transportation, mounting cost, save test pile material 70~80%, reduce test pile expense 90%, the test pile cycle shortens 50%, and economic benefit is very remarkable.
Further advantage of the present invention is, can utilize engineering piles to do test pile, can obtain test result directly and accurately, helps guaranteeing workmanship.
Fig. 1 is a floor map of the present invention.
Fig. 2 is I-I sectional drawing of Fig. 1 of the present invention.
Fig. 3 is that the present invention tests the pile body structure chart after finishing.
Below in conjunction with drawings and Examples, the present invention is described further.
As shown in the figure, be plastic lam in soil property, it is on the dark 30 meters ground of 18 tons/square metre, soil layer that bearing stratum allows supporting capacity, choose A, B, C three pile types identical, carry out test pile at a distance of nearer and the position engineering piles on same straight line.90 centimetres of pile body diameters, 1.4 meters of pile crown diameters, full stake is long 10 meters.
Excavate A, B stake simultaneously, up to whole pore-formings;
The pile crown concrete of pouring A, B stake reaches same absolute altitude (7 meters) and locates;
After the pile crown concrete curing 24 hours, put into and test with 200 tons of loading jack (1);
On pile crown, put into the cylinder gap dividing plate (2) that is welded into steel plate that is higher than the jack height, be enclosed within on the jack,, make it at a distance of 60 centimetres so that separate the concrete of pile crown and pile body;
Excavating the rounding platform earthwork of pile body lower end in the A stake, is 2 meters rounding platform reaction support (3) with the formation diameter;
Installation A, B stake pile body are taken out the steel pipe (4) in hole;
Pouring A, B stake pile concrete, and rotate and take out the hole steel pipe, before pile concrete final set, take out the hole steel pipe with practicing to extract;
During the maintenance pile concrete, the C stake stake hole (5) that excavation is used as vertical shaft, reach the absolute altitude at A, B pile head and pile body interval after, excavate horizontal tunnel (6) again, the gap location that makes A, B stake put into jack is communicated with the tunnel.
In the tunnel, connect the oil pipe of jack and oil pump, carry out the test of the supporting capacity of stake;
The A stake is made reaction support with the concrete rounding platform of pile body lower end, the end load of test pile crown, and the actual measurement ultimate bearing capacity is 176 tons;
The B stake is made reaction support with the pile crown that enlarges, the frictional resistance of test pile body, and the actual measurement ultimate bearing capacity is 98 tons;
With the pile crown end load of A stake and the pile body frictional resistance stack of B stake, be the ultimate bearing capacity of a full stake, be 274 tons.
After the off-test, use jack by withdrawing from test in the tunnel, the vertical shaft by C stake hole hangs out ground;
Build the breach of stifled A, B stake and tunnel UNICOM with common brick (7);
By the hole of taking out of A, B stake pile body, the bigger pea gravel concreten (8) of pouring plasticity, the gap of filling A, B pile head and pile body gap makes pile crown and pile body all be unified into an integral body, and reaching can be for the condition of the actual use of engineering.
The pile crown earthwork of the C stake that excavation is used as vertical shaft, and come fill level tunnel (9) with this earthwork;
Build stifled tunnel face with common brick, form the pile body wall (10) of C stake;
The concrete of pouring C stake forms a complete engineering stake.
Above-mentioned operation had both been finished the test pile task, constructed simultaneously again A, B, the stake of three engineerings of C, none waste.

Claims (6)

1, the method for testing of the vertical quiet lotus bearing capacity of a kind of big diameter and deep stake, it is characterized in that doing test pile with two identical big diameter and deep stakes, at the pile crown of two test piles and the same level height place at pile body handing-over position, one group of loading jack respectively is set, with a pile body is reaction support, tests the supporting capacity of its pile crown, is reaction support with another pile crown, test the supporting capacity of its pile body, with pile crown bearing capacity and bearing capacity of pile superimposed be full pile capacity.
2, the method for testing of the vertical quiet lotus bearing capacity of big diameter and deep stake as claimed in claim 1 is characterized in that disconnecting 60~80 centimetres at the same level height place at the handing-over position of the pile crown of two test piles and pile body, and the loading jack is set.
3, the method for testing of the vertical quiet lotus bearing capacity of big diameter and deep stake as claimed in claim 1 is characterized in that expanding in the pile body lower end of the test pile A of test pile crown bearing capacity and digs, and waters into a concrete rounding platform reaction support.
4, the method for testing of the vertical quiet lotus bearing capacity of big diameter and deep stake as claimed in claim 1 is characterized in that the pile crown of test pile B of test bearing capacity of pile is suitably strengthened bearing area.
5, the method for testing of the vertical quiet lotus bearing capacity of big diameter and deep stake as claimed in claim 1, it is characterized in that between two test piles, other digs a vertical vertical shaft C, reach the fracture absolute altitude place that two test pile A, B put into the loading jack in the vertical shaft C degree of depth, excavate the horizontal channel again and communicate, install oil pipe, oil pump and the test instrumentation of connecting the loading jack with test pile A, B.
6, the method for testing of the vertical quiet lotus bearing capacity of big diameter and deep stake as claimed in claim 1 is characterized in that two test pile A, B can be engineering piles with vertical vertical shaft C.
CN87102786A 1987-04-18 1987-04-18 Self-reaction testing method for pile with big diameter and deep piling Expired CN87102786B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN87102786A CN87102786B (en) 1987-04-18 1987-04-18 Self-reaction testing method for pile with big diameter and deep piling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN87102786A CN87102786B (en) 1987-04-18 1987-04-18 Self-reaction testing method for pile with big diameter and deep piling

Publications (2)

Publication Number Publication Date
CN87102786A true CN87102786A (en) 1987-12-16
CN87102786B CN87102786B (en) 1988-12-28

Family

ID=4814118

Family Applications (1)

Application Number Title Priority Date Filing Date
CN87102786A Expired CN87102786B (en) 1987-04-18 1987-04-18 Self-reaction testing method for pile with big diameter and deep piling

Country Status (1)

Country Link
CN (1) CN87102786B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106284441A (en) * 2016-08-26 2017-01-04 杭州西南检测技术股份有限公司 A kind of O cell test pile load conversion is the method for vertical compression pile load
CN109930634A (en) * 2019-03-28 2019-06-25 中交路桥建设有限公司 A method of pile foundation soil layer utmost tip resistance is tested using steel pile casting self-reaction force
CN110542365A (en) * 2019-09-04 2019-12-06 丁正旺 Soil-wood pile foundation construction pile foundation hole fixed-point detection device
CN110565704A (en) * 2019-08-12 2019-12-13 中国能源建设集团江苏省电力设计院有限公司 method for calculating horizontal loading force of single pile in static load test of fan

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106284441A (en) * 2016-08-26 2017-01-04 杭州西南检测技术股份有限公司 A kind of O cell test pile load conversion is the method for vertical compression pile load
CN109930634A (en) * 2019-03-28 2019-06-25 中交路桥建设有限公司 A method of pile foundation soil layer utmost tip resistance is tested using steel pile casting self-reaction force
CN109930634B (en) * 2019-03-28 2021-03-02 中交路桥建设有限公司 Method for testing ultimate lateral friction resistance of pile foundation soil layer by using self-reaction force of steel casing
CN110565704A (en) * 2019-08-12 2019-12-13 中国能源建设集团江苏省电力设计院有限公司 method for calculating horizontal loading force of single pile in static load test of fan
CN110542365A (en) * 2019-09-04 2019-12-06 丁正旺 Soil-wood pile foundation construction pile foundation hole fixed-point detection device

Also Published As

Publication number Publication date
CN87102786B (en) 1988-12-28

Similar Documents

Publication Publication Date Title
CN102535477B (en) Safety construction method for cutting off anchor cables of support of excavating foundation pit
CN1800514A (en) Big section pipe roof- box culvert jacking construction method
CN107724383B (en) Rotary digging cast-in-place pile construction method
CN110331743B (en) Test device and test method for testing bearing performance of enlarged head of pile end of static drilling root planting pile
CN105604065A (en) Foundation fit support and peat-soil deep-foundation-pit-support high-pressure jet grouting anchoring method
CN105926594A (en) Double-pipe construction method for static pressure pipe-sinking carrier cast-in-place pile
CN1163654C (en) Support structure and construction process of foundation pit
CN87102786A (en) Self-reaction testing method for pile with big diameter and deep piling
CN208328968U (en) A kind of upper stake suitable for large-scale cyclic load is casted anchor novel foundation
CN108487226A (en) Multisection type composite bushing punching press sandy pile construction engineering method
CN1128906C (en) Method for constructing club-footed hollow pile
CN210684814U (en) Test device for testing bearing performance of pile end expanding head of static drill root planting pile
CN210031875U (en) Open caisson device for pushing
CN111379254A (en) Basic treatment method for building sediment treatment plant in unfavorable geology
CN105887812B (en) A kind of single casing construction method of static pressure, immersed tube carrier bored concrete pile
CN215052905U (en) Major diameter steel pipe friction pile anticorrosion coating
CN2346837Y (en) Steel pipe wall guard appts. of dry earth grouted pile
CN218204422U (en) Foundation pit supporting structure of PRC tubular pile and prestressed anchorage cable combination
CN218148411U (en) Deep foundation pit narrow road supporting device
CN215669660U (en) But reuse's retaining wall
CN214061557U (en) Backfill miscellaneous soil composite foundation structure
CN114718078B (en) Building envelope for soft soil of ultra-large deep foundation pit and construction method
CN219710338U (en) Deep foundation pit supporting structure
CN210031840U (en) Foundation pit support structure
CN217027192U (en) Marine anchoring barrel basis

Legal Events

Date Code Title Description
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C06 Publication
PB01 Publication
C13 Decision
GR02 Examined patent application
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee