CN105604065A - Foundation fit support and peat-soil deep-foundation-pit-support high-pressure jet grouting anchoring method - Google Patents

Foundation fit support and peat-soil deep-foundation-pit-support high-pressure jet grouting anchoring method Download PDF

Info

Publication number
CN105604065A
CN105604065A CN201510899993.5A CN201510899993A CN105604065A CN 105604065 A CN105604065 A CN 105604065A CN 201510899993 A CN201510899993 A CN 201510899993A CN 105604065 A CN105604065 A CN 105604065A
Authority
CN
China
Prior art keywords
foundation pit
hole
pile
anchor cable
slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510899993.5A
Other languages
Chinese (zh)
Inventor
徐国民
李文平
张庆文
王家权
程承
李世全
常新强
孙亚男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Colored Kunming Survey And Design (institute) Ltd By Share Ltd
Southwest Forestry University
Original Assignee
Southwest Colored Kunming Survey And Design (institute) Ltd By Share Ltd
Southwest Forestry University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Colored Kunming Survey And Design (institute) Ltd By Share Ltd, Southwest Forestry University filed Critical Southwest Colored Kunming Survey And Design (institute) Ltd By Share Ltd
Priority to CN201510899993.5A priority Critical patent/CN105604065A/en
Publication of CN105604065A publication Critical patent/CN105604065A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明提供一种基坑支护,包括坡顶,坡顶一侧倾斜设置有放坡,放坡底部设置有基坑,坡顶上设置有排水沟,放坡上设置有土钉,基坑上设置有竖直相邻的桩孔桩和止水帷幕桩,桩孔桩和止水帷幕桩的底部设置于基坑底部线之下,锚索横穿桩孔桩和止水帷幕桩,通过锚索锚固垫板和锚索锚固锁具固定设置于桩孔桩和止水帷幕桩的一侧,锚索上设置有若干个锚索钻孔和托环,锚索上套设有高压注浆管。本发明还提供一种泥炭土深基坑支护高压旋喷锚固的方法,对锚固段先进行高压旋喷固结土体,保证锚索成孔施工孔道轴线与锚固段高压旋喷固结土体施工轴线保持同心。本基坑支护设计相比内支撑类型的支护形式不仅节约工期、节省造价。

The invention provides a foundation pit support, comprising a slope top, one side of the slope top is obliquely provided with a slope, the bottom of the slope is provided with a foundation pit, the top of the slope is provided with a drainage ditch, the slope is provided with soil nails, the foundation pit There are vertically adjacent pile-hole piles and water-stop curtain piles, the bottom of the pile-hole piles and water-stop curtain piles are set below the bottom line of the foundation pit, and the anchor cables cross the pile hole piles and water-stop curtain piles, passing through The anchor cable anchor plate and the anchor cable anchor lock are fixed on one side of the pile hole pile and the water-stop curtain pile. Several anchor cable drill holes and supporting rings are set on the anchor cable, and high-pressure grouting pipes are set on the anchor cable. . The present invention also provides a peat soil deep foundation pit support high-pressure rotary jet grouting anchorage method, the anchorage section is first subjected to high-pressure rotary jetting to consolidate the soil to ensure that the axis of the anchor cable hole and the high-pressure rotary jetting consolidation soil in the anchorage section The body construction axis remains concentric. Compared with the support form of the internal support type, this foundation pit support design not only saves the construction period and saves the cost.

Description

一种基坑支护及泥炭土深基坑支护高压旋喷锚固的方法A foundation pit support and peat soil deep foundation pit support high-pressure rotary grouting anchoring method

技术领域 technical field

本发明属于建筑工程技术领域,具体涉及一种基坑支护,本发明还涉及一种泥炭土深基坑支护高压旋喷锚固的方法。 The invention belongs to the technical field of construction engineering, and in particular relates to a foundation pit support, and also relates to a peat soil deep foundation pit support high-pressure rotary grouting and anchoring method.

背景技术 Background technique

由于云南高原盆地泥炭土地基土层,泥炭土作为一种特殊土,其孔隙比和含水量都比较大,并且拥有较高的压缩性、灵敏性高、蠕变性强、物理力学性质较差、承载力低的物理特性,其作为构筑物地基会产生长期变形不稳定的特征。在这类地基上修建的建筑物,基坑开挖或受动载荷(城市道路和地铁),发生因不均匀沉降而发生不同功能的破坏事故屡见不鲜。 Due to the base soil layer of peat soil in the Yunnan Plateau Basin, peat soil, as a special soil, has relatively large void ratio and water content, and has high compressibility, high sensitivity, strong creep, and poor physical and mechanical properties. , The physical characteristics of low bearing capacity, as the foundation of the structure, it will have the characteristics of long-term deformation and instability. For buildings built on such foundations, it is not uncommon for foundation pits to be excavated or subjected to dynamic loads (urban roads and subways), and it is not uncommon for damage accidents to occur due to uneven settlement and different functions.

发明内容 Contents of the invention

本发明的目的是提供一种基坑支护。 The purpose of the present invention is to provide a foundation pit support.

本发明的另一目的是提供一种泥炭土深基坑支护高压旋喷锚固的方法,解决了现有技术中存在的高原盆地泥炭土原施工工艺锚固力不足的问题,使周边地面水平和垂直沉降得以缓解,并保持在规范位移许可值内。 Another object of the present invention is to provide a method for peat soil deep foundation pit support high-pressure rotary grouting and anchoring, which solves the problem of insufficient anchoring force in the original construction process of plateau basin peat soil in the prior art, so that the surrounding ground level and The vertical settlement was alleviated and kept within the allowable value of the code displacement.

本发明所采用的第一技术方案是,一种基坑支护,其特征在于,包括坡顶,坡顶一侧倾斜设置有放坡,放坡底部设置有基坑,坡顶上设置有排水沟,放坡上设置有土钉,基坑上设置有竖直相邻的桩孔桩和止水帷幕桩,桩孔桩和止水帷幕桩的底部设置于基坑底部线之下,锚索横穿桩孔桩和止水帷幕桩,通过锚索锚固垫板和锚索锚固锁具固定设置于桩孔桩和止水帷幕桩的一侧,锚索上设置有若干个锚索钻孔和托环,锚索上套设有高压注浆管。 The first technical solution adopted by the present invention is a foundation pit support, which is characterized in that it includes a slope top, one side of the slope top is inclined to be provided with a slope, the bottom of the slope is provided with a foundation pit, and the top of the slope is provided with drainage ditch, soil nails are set on the slope, vertically adjacent pile hole piles and water-stop curtain piles are set on the foundation pit, the bottom of the pile hole piles and water-stop curtain piles are set below the bottom line of the foundation pit, Crossing the pile hole pile and the water stop curtain pile, the anchor cable anchor pad and the anchor cable anchor lock are fixed on one side of the pile hole pile and the water stop curtain pile. The anchor cable is covered with a high-pressure grouting pipe.

在上述技术方案中,锚索至少设置有2个。 In the above technical solution, at least two anchor cables are provided.

本发明的另一目的是提供一种泥炭土深基坑支护高压旋喷锚固的方法,制作上述的基坑支护,包括以下步骤: Another object of the present invention is to provide a method for peat soil deep foundation pit support high-pressure rotary grouting anchorage, making the above-mentioned foundation pit support, comprising the following steps:

步骤1、基坑开挖至设计第一道冠梁下2米后,制作锚索和高压注浆管,采用水钻和跟进套管成孔工艺进行成孔操作; Step 1. After excavating the foundation pit to 2 meters below the designed first crown beam, make anchor cables and high-pressure grouting pipes, and use water drilling and follow-up casing hole forming processes to perform hole forming operations;

步骤2、成孔后,跟进套管暂时放在孔内,把制作的锚索、高压注浆管先后放入孔中,高压注浆管采用2㎝钢管加工而成,高压注浆管喷浆嘴直径1.8㎜,高压注浆管随锚索安装至孔底,进行一次注浆常压5~10MPa压力注满孔,约5~10分钟初凝后进行二次高压注浆; Step 2. After the hole is formed, the follow-up casing is temporarily placed in the hole, and the manufactured anchor cable and high-pressure grouting pipe are put into the hole successively. The high-pressure grouting pipe is made of 2cm steel pipe, and the high-pressure grouting pipe is The diameter of the grout nozzle is 1.8㎜, and the high-pressure grouting pipe is installed to the bottom of the hole along with the anchor cable, and the hole is filled with a normal pressure of 5-10 MPa for one grouting, and the second high-pressure grouting is performed after initial setting for about 5-10 minutes;

步骤3、待一次常压注浆开始凝固时,启动成孔机后退跟进套管,开始启动旋喷管进行锚固段旋喷,注浆压力提升速度每分钟20~25㎝,扩孔直径500~600㎜;水灰比0.40~0.50的纯水泥浆,压浆量≥120kg/m,直至锚固段全部旋喷完。 Step 3. When the normal-pressure grouting begins to solidify, start the hole-forming machine to move back and follow the casing, and start the rotary nozzle to perform rotary spraying at the anchorage section. The grouting pressure increases at a rate of 20-25cm per minute, and the diameter of the hole is 500mm. ~600㎜; pure cement slurry with water-cement ratio 0.40~0.50, grouting volume ≥ 120kg/m, until the anchorage section is completely sprayed.

在上述技术方案中,基坑开挖过程具体为:制作坡顶,坡顶一侧倾斜设置放坡,放坡底部设置基坑,坡顶上设置排水沟,放坡上设置土钉。 In the above technical scheme, the excavation process of the foundation pit is specifically: making a slope top, setting a slope on one side of the slope top, setting a foundation pit at the bottom of the slope, setting a drainage ditch on the top of the slope, and setting soil nails on the slope.

本发明的有益效果是:其一,本方法针对软弱泥炭土先对锚固段进行高压旋喷固结土体,再进行锚索成孔施工,承载力能满足设计要求。其二,对锚固段先进行高压旋喷固结土体,保证锚索成孔施工孔道轴线与锚固段高压旋喷固结土体施工轴线保持同心,是锚索成孔施工的关键工艺。其三,本基坑支护设计相比内支撑类型的支护形式不仅节约工期、节省造价,并且可让后续施工组织更为灵活,是一项适合软弱泥炭土基坑围护工程技术。 The beneficial effects of the present invention are as follows: firstly, the method first performs high-pressure rotary spraying on the anchorage section to consolidate the soil body for soft peat soil, and then carries out anchor cable hole-forming construction, and the bearing capacity can meet the design requirements. Second, the anchorage section is firstly subjected to high-pressure rotary grouting to consolidate the soil to ensure that the axis of the hole-forming construction of the anchor cable is concentric with the construction axis of the high-pressure rotary spraying-consolidated soil in the anchorage section, which is the key process for the construction of the anchor cable hole. Third, compared with the internal support type, this foundation pit support design not only saves the construction period and cost, but also makes the subsequent construction organization more flexible. It is a technology suitable for soft peat soil foundation pit protection engineering.

附图说明 Description of drawings

图1是本发明基坑支护的结构示意图; Fig. 1 is the structural representation of foundation pit support of the present invention;

图2是本发明基坑支护高压旋喷锚固的结构示意图; Fig. 2 is a schematic structural view of foundation pit support high-pressure rotary grouting anchorage of the present invention;

图3是普通锚索试验荷载-位移曲线图; Fig. 3 is a load-displacement curve diagram of an ordinary anchor cable test;

图4是普通锚索试验荷载-弹塑性位移曲线图; Fig. 4 is the load-elastic-plastic displacement curve diagram of common anchor cable test;

图5是高压旋喷锚索试验荷载-位移曲线; Figure 5 is the load-displacement curve of the high-pressure jet grouting anchor cable test;

图6是高压旋喷锚索试验荷载-弹塑性位移曲线。 Figure 6 is the test load-elastic-plastic displacement curve of the high-pressure jet grouting anchor cable.

图中,1.排水沟,2.放坡,3.土钉,4.桩孔桩,5.止水帷幕桩,6.锚索钻孔,7.锚索,8.高压注浆管,9.托环,10.锚索锚固垫板,11.锚索锚固锁具,12.基坑底部线,13.,14.。 In the figure, 1. drainage ditches, 2. grading, 3. soil nails, 4. pile hole piles, 5. water stop curtain piles, 6. anchor cable drilling, 7. anchor cable, 8. high pressure grouting pipe, 9. Support ring, 10. Anchor cable anchor pad, 11. Anchor cable anchor lock, 12. Bottom line of foundation pit, 13., 14.

具体实施方式 detailed description

下面结合具体实施方式对本发明进行详细说明。 The present invention will be described in detail below in combination with specific embodiments.

本发明提供一种基坑支护,其结构如图1和图2所示,包括坡顶13,坡顶13一侧倾斜设置有放坡2,放坡2底部设置有基坑14,坡顶13上设置有排水沟1,放坡2上设置有土钉3,基坑14上设置有竖直相邻的桩孔桩4和止水帷幕桩5,桩孔桩4和止水帷幕桩5的底部设置于基坑底部线12之下,锚索7横穿桩孔桩4和止水帷幕桩5设置,通过锚索锚固垫板10和锚索锚固锁具11固定设置于桩孔桩4和止水帷幕桩5的一侧,锚索7上设置有若干个锚索钻孔6和托环9,锚索7上套设有高压注浆管8;锚索7至少设置有2个。 The present invention provides a kind of foundation pit support, its structure is shown in Figure 1 and Figure 2, comprises slope crest 13, and one side of slope crest 13 is obliquely provided with slope 2, and foundation pit 14 is arranged at the bottom of slope 2, and slope crest 13 is provided with drainage ditches 1, soil nails 3 are provided on the slope 2, vertically adjacent pile hole piles 4 and water stop curtain piles 5 are arranged on the foundation pit 14, pile hole piles 4 and water stop curtain piles 5 The bottom of the foundation pit is arranged below the bottom line 12 of the foundation pit, the anchor cable 7 is set across the pile hole pile 4 and the water-stop curtain pile 5, and the anchor cable anchor pad 10 and the anchor cable anchor lock 11 are fixedly arranged on the pile hole pile 4 and the water-stop curtain pile 5. On one side of the water-stop curtain pile 5, several anchor cable boreholes 6 and supporting rings 9 are arranged on the anchor cable 7, and a high-pressure grouting pipe 8 is set on the anchor cable 7; at least two anchor cables 7 are provided.

本发明提供一种泥炭土深基坑支护高压旋喷锚固的方法,采用上述基坑支护,该方法包括以下步骤: The invention provides a peat soil deep foundation pit supporting method for high-pressure rotary grouting and anchoring. The above-mentioned foundation pit support is adopted, and the method includes the following steps:

步骤1、基坑开挖至设计第一道冠梁下2米(常规技术中的冠梁)后,制作锚索7和高压注浆管8,采用水钻和跟进套管成孔工艺进行成孔操作; Step 1. After the foundation pit is excavated to 2 meters below the designed first crown beam (the crown beam in the conventional technology), the anchor cable 7 and the high-pressure grouting pipe 8 are made, and the drilling process is carried out by using water drilling and following the casing hole forming process. hole operation;

步骤2、成孔后,跟进套管暂时放在孔内,把制作的锚索7、高压注浆管8先后放入孔中,高压注浆管8采用2㎝钢管加工而成,高压注浆管8喷浆嘴直径1.8㎜,高压注浆管8随锚索7安装至孔底,进行一次注浆常压5~10MPa压力注满孔,约5~10分钟初凝后进行二次高压注浆; Step 2. After the hole is formed, the follow-up casing is temporarily placed in the hole, and the manufactured anchor cable 7 and high-pressure grouting pipe 8 are put into the hole successively. The high-pressure grouting pipe 8 is made of 2cm steel pipe. The diameter of the grouting nozzle of the grouting pipe 8 is 1.8㎜, and the high-pressure grouting pipe 8 is installed to the bottom of the hole along with the anchor cable 7, and the hole is filled with a normal pressure of 5 to 10 MPa for one grouting, and the second high pressure is performed after the initial setting for about 5 to 10 minutes grouting;

步骤3、待一次常压注浆开始凝固时,启动成孔机后退跟进套管,开始启动旋喷管进行锚固段旋喷,注浆压力提升速度每分钟20~25㎝,扩孔直径500~600㎜;水灰比0.40~0.50的纯水泥浆,压浆量≥120kg/m,直至锚固段全部旋喷完。 Step 3. When the normal-pressure grouting begins to solidify, start the hole-forming machine to move back and follow the casing, and start the rotary nozzle to perform rotary spraying at the anchorage section. The grouting pressure increases at a rate of 20-25cm per minute, and the diameter of the hole is 500mm. ~600㎜; pure cement slurry with water-cement ratio 0.40~0.50, grouting volume ≥ 120kg/m, until the anchorage section is completely sprayed.

其中,基坑开挖过程具体为:制作坡顶13,坡顶13一侧倾斜设置放坡2,放坡2底部设置基坑14,坡顶13上设置排水沟1,放坡2上设置土钉3。 Among them, the foundation pit excavation process is specifically: making the slope top 13, setting the slope 2 on one side of the slope top 13 obliquely, setting the foundation pit 14 at the bottom of the slope 2, setting the drainage ditch 1 on the slope top 13, and setting the soil on the slope 2. Nail 3.

实施例1 Example 1

1、工程概况 1. Project overview

拟建场地位于昆明市高新区,南靠海源北路,西临商院路(高新一小海源校区),项目规划总用地面积约31933.49m2,总建筑面积202579.98㎡,项目总体规划由4栋塔楼(建筑高度100~130m)和1~4层的裙楼组成。本项目基坑占地面积约27500㎡,2层地下室。基坑开挖支护周长约785m,开挖深度为7.9~9.2m之间。 The proposed site is located in the High-tech Zone of Kunming City, adjacent to Haiyuan North Road in the south and Shangyuan Road in the west (Gaoxin No. 1 Haiyuan Campus). The planned total land area of the project is about 31933.49m 2 , and the total construction area is 202579.98㎡. The overall planning of the project consists of 4 buildings It consists of a tower (building height 100-130m) and a podium of 1-4 floors. The foundation pit of this project covers an area of about 27,500 square meters, with 2 floors of basement. The perimeter of foundation pit excavation and support is about 785m, and the excavation depth is between 7.9m and 9.2m.

2、场地地质条件 2. Geological conditions of the site

场区表层分布第四系人工堆积(Qml)层,其下为第四系冲、洪积(Qal+pl)层,岩性为粉质粘土;第四系冲、湖积(Qal+l)层,岩性为粉质粘土、粘土、淤泥质粘土、泥炭质土、含粘性土砾砂、粉土等。在基坑开挖深度范围内,以填土、淤泥质粘土、泥炭质土为主。 The Quaternary artificial accumulation (Q ml ) layer is distributed on the surface of the field, and the Quaternary alluvial and diluvial (Q al+pl ) layer is located below it, and the lithology is silty clay; the Quaternary alluvial and lacustrine (Q al +l ) layer, the lithology is silty clay, clay, silty clay, peaty soil, cohesive gravel sand, silt, etc. Within the excavation depth of the foundation pit, it is mainly filled with soil, silty clay and peaty soil.

表1基坑土壤力学性质指标 Table 1 The soil mechanical properties of the foundation pit

3、基坑支护设计主要结构形式 3. Main structural forms of foundation pit support design

如图1和图2所示,0~-3.5m放坡开挖部分以土钉墙为主,-3.5以下垂直开挖部分以桩加预应力锚索为主,基坑止水以深层搅拌水泥土桩及高压旋喷桩为主。预应力锚索共设置3排,锚索孔径300mm,采用3Φ15.2(或4Φ15.2)钢绞线进行制作,设计锚固力410kN~720kN,锚固段分别位于淤泥质粘土、泥炭质土、粉质粘土、粘土层中。本基坑支护设计相比内支撑类型的支护形式不仅节约工期、节省造价,并且可让后续施工组织更为灵活,是一项适用基坑围护工程技术。 As shown in Fig. 1 and Fig. 2, soil nailing wall is the main part of grading excavation from 0 to -3.5m, piles and prestressed anchor cables are the main part of vertical excavation below -3.5m, and deep mixing is used for water stop of foundation pit. Cement-soil piles and high-pressure rotary grouting piles are mainly used. There are 3 rows of prestressed anchor cables, the anchor cable aperture is 300mm, and it is made of 3Φ15.2 (or 4Φ15.2) steel strands. The design anchoring force is 410kN~720kN. Clay, clay layer. Compared with the support form of the internal support type, this foundation pit support design not only saves the construction period and cost, but also makes the subsequent construction organization more flexible. It is a technology suitable for foundation pit enclosure engineering.

4、预应力锚索施工思路 4. Construction ideas of prestressed anchor cables

基于该场地地质条件情况,如何确保预应力锚索在淤泥质土及泥炭质土层中能够提供足够的抗拔力,以达到设计要求承载力,保证预应力锚索的有效性和基坑支护结构体系的可靠性,是在基坑支护工程实施前需要解决的关键技术问题。 Based on the geological conditions of the site, how to ensure that the prestressed anchor cable can provide sufficient pullout resistance in the muddy soil and peaty soil layer to achieve the design required bearing capacity, ensure the effectiveness of the prestressed anchor cable and the support of the foundation pit? The reliability of the protection structure system is a key technical problem that needs to be solved before the implementation of the foundation pit support project.

根据设计要求及场地地质条件,把预应力锚索施工分两阶段进行,第一阶段为实验阶段,施工实验锚索;第二阶段为实施阶段,根据实验结果,选择最佳施工工艺,实施工程锚索。 According to the design requirements and geological conditions of the site, the prestressed anchor cable construction is divided into two stages. The first stage is the experimental stage, and the anchor cable is constructed and tested; the second stage is the implementation stage. According to the experimental results, the best construction technology is selected and the project is implemented. Anchor cable.

5、施工锚索试验 5. Construction anchor cable test

通过现场实验,验证在设计锚固土层(主要为泥炭质土、粉质粘土及粘土)中锚索体的粘结锚固强度,从而确定锚索在本地层设计承载力的合理性;确定在该场地地质条件下锚索施工应采用的施工工艺(钻孔工艺、注浆工艺);通过试验结果分析来确定锚索的安全系数及锚索的变形是否在有效的控制范围内。 Through field experiments, verify the bonded anchorage strength of the anchor cable body in the designed anchorage soil layer (mainly peaty soil, silty clay and clay), so as to determine the rationality of the design bearing capacity of the anchor cable in the local layer; The construction technology (drilling technology, grouting technology) that should be adopted for the anchor cable construction under the geological conditions of the site; through the analysis of the test results, it is determined whether the safety factor of the anchor cable and the deformation of the anchor cable are within the effective control range.

5.1、实验工艺及设备 5.1. Experimental process and equipment

试验对成孔工艺采用水钻、全孔道跟管工艺,注浆工艺采用2种不同的工艺进行:常规注浆工艺(2次注浆)和锚固段高压旋喷扩体注浆工艺。设备选用无锡安迈MDL-135D型履带式钻机、天津GPB-90型高压泵及预应力锚索张拉设备。材料(1)钢绞线:采用天津高力生产的高强度、低松驰Φ15.20钢绞线;(2)无粘结压板、P锚:均为定型产品;(3)注浆用水泥:P.O42.5级普通硅酸盐水泥。 In the test, water drilling, full channel and pipe technology were used for the hole forming process, and two different processes were used for the grouting process: the conventional grouting process (2 times grouting) and the high-pressure rotary grouting expansion grouting process in the anchorage section. The equipment used is Wuxi Amman MDL-135D crawler drilling rig, Tianjin GPB-90 high pressure pump and prestressed anchor cable tensioning equipment. Materials (1) Steel strands: high-strength, low-relaxation Φ15.20 steel strands produced by Tianjin Gaoli; (2) Unbonded pressure plates and P anchors: both are shaped products; (3) Cement for grouting : P.O42.5 ordinary Portland cement.

锚索钻孔采用水钻及全套管跟进水冲法1次成孔;锚固段注浆方法采用高压旋喷扩孔注浆工艺,注浆设备采用高压泵及高压旋喷机,注浆管采用2㎝钢管加工而成,喷浆嘴直径1.8㎜,高压注浆管随锚索安装至孔底,待拆除套管后,开始旋喷扩孔,注浆压力25MPa,提升速度每分钟25㎝,扩孔直径500~600㎜(论证值)。水灰比0.40~0.50的纯水泥浆,压浆量≥120kg/m。 The anchor cable drilling adopts water drilling and full casing follow-up water flushing method to form a hole once; the grouting method of the anchorage section adopts the high-pressure rotary jet grouting expansion grouting process, the grouting equipment adopts high-pressure pump and high-pressure rotary jet machine, and the grouting pipe adopts The diameter of the spray nozzle is 1.8mm, and the high-pressure grouting pipe is installed to the bottom of the hole with the anchor cable. After the casing is removed, the hole will be expanded by rotary spraying. The grouting pressure is 25MPa, and the lifting speed is 25cm per minute. Reaming diameter 500 ~ 600 mm (demonstration value). For pure cement slurry with a water-cement ratio of 0.40-0.50, the grouting volume is ≥120kg/m.

对比例 comparative example

本对比例锚索钻孔采用水钻及全套管跟进水冲法1次成孔;本实施例锚固段注浆方法采用常规注浆工艺,注浆管在编制锚索时安装在锚索体中部,注浆方向从孔底向孔口,直到孔口返浓浆为止,以保证浆液饱满,注浆采用2次注浆方法,第一次注浆在锚索安装完成拆除套管前开始注浆,注浆压力为0.5MPa第一次注浆结束,拆除套管,间隔2小时左右,进行二次注浆,压力5MPa水灰比0.40~0.50的纯水泥浆,压浆量≥120kg/m。 In this comparative example, the anchor cable is drilled using water drilling and the full casing follow-up water flushing method to form a hole once; in this embodiment, the anchor section grouting method adopts the conventional grouting process, and the grouting pipe is installed in the middle of the anchor cable body when weaving the anchor cable , the grouting direction is from the bottom of the hole to the orifice until the orifice returns to the thickened grout to ensure that the grout is full. The grouting adopts two grouting methods. The first grouting starts before the anchor cable is installed and the casing is removed. , The grouting pressure is 0.5MPa. After the first grouting, the casing is removed, and the second grouting is performed at an interval of about 2 hours. The pressure is 5MPa and the water-cement ratio is 0.40-0.50. The grouting volume is ≥120kg/m.

结果分析: Result analysis:

1、试验锚索布置: 1. Test anchor cable arrangement:

根据场地地质条件,结合现场实际情况,选取基坑支护设计方案中2剖面、5剖面、6剖面不同位置进行2组对比实验,每组2根锚索,锚索基本实验参数表如下: According to the geological conditions of the site and the actual situation of the site, two sets of comparative experiments were carried out at different positions of the 2nd section, 5th section, and 6th section in the foundation pit support design scheme, with 2 anchor cables in each group. The basic experimental parameters of the anchor cables are as follows:

表2试验锚索参数表 Table 2 Test anchor cable parameter list

2、锚索张拉成果 2. Results of anchor cable tensioning

实验锚索安装完后7天用标定的千斤顶(YCW100G),高压油泵(ZB4500)进行拉拔实验。试验严格按照《建筑基坑支护技术规程》(JGJ120-2012)中有关锚杆验收试验的规定进行。试验时,初始荷载取锚杆轴向受拉承载力设计值Tw的0.1倍,试验采用多循环加载的方法,其加载分级和锚头位移观测时间应按表2确定,加荷等级观测时间内,测读锚头位移3次,达到最大位移是观测10min。终止试验条件为:①位移不收敛,锚固体从岩土层中拔出或锚固件从锚固体中拔出;②满足设计要求的试验荷载值;③)对锚固件在试验中后一级荷载产生的①锚固件端部位移增量超过上一级试验荷载增量的2倍。 7 days after the experimental anchor cable is installed, use the calibrated jack (YCW100G) and high-pressure oil pump (ZB4500) to carry out the pulling test. The test was carried out in strict accordance with the provisions of the bolt acceptance test in the "Technical Regulations for Building Foundation Pit Support" (JGJ120-2012). During the test, the initial load is taken as 0.1 times the design value Tw of the axial tensile bearing capacity of the anchor rod. The test adopts the method of multi-cycle loading. The loading classification and anchor head displacement observation time should be determined according to Table 2. The loading level observation time , measure and read the displacement of the anchor head 3 times, and the maximum displacement is observed for 10 minutes. The termination test conditions are: ① the displacement does not converge, the anchor is pulled out from the rock and soil layer or the anchor is pulled out from the anchor; ② the test load value meets the design requirements; The resulting displacement increment at the end of the ① anchor exceeds 2 times the incremental test load of the previous stage.

表3试验结果汇总表 Table 3 Summary of test results

通过对实测的实验数据进行统计,选取了最有代表性的两组实验数据进行对比分析,从表3和图3至图6可看出,对比例普通锚索满足不了设计要求,实施例高压旋喷扩体锚索,均满足设计要求承载力。应此确定本工程锚索施工工艺采用高压旋喷扩体锚索工艺进行。 Through the statistics of the measured experimental data, the most representative two groups of experimental data were selected for comparative analysis. It can be seen from Table 3 and Figure 3 to Figure 6 that the ordinary anchor cable of the comparative example cannot meet the design requirements, and the high pressure of the embodiment Rotary grouting expanded body anchor cables all meet the design requirements for bearing capacity. Therefore, it is determined that the anchor cable construction process of this project is carried out by the high-pressure rotary grouting expanded body anchor cable process.

根据确定的施工工艺,完成了250根共计约2000米的锚索施工,监测数据表明,基坑水平位移及竖直位移均在设计要求变形控制30mm范围内,且施工中未出现报警现象。由此可见,高压旋喷扩体锚索锚桩支护技术取得了良好的支护效果。 According to the determined construction technology, the construction of 250 anchor cables totaling about 2,000 meters was completed. The monitoring data showed that the horizontal displacement and vertical displacement of the foundation pit were within the 30mm range of deformation control required by the design, and no alarms occurred during construction. It can be seen that the support technology of high-pressure rotary grouting expanded body anchor cable and anchor pile has achieved good support effect.

Claims (4)

1.一种基坑支护,其特征在于,包括坡顶(13),坡顶(13)一侧倾斜设置有放坡(2),放坡(2)底部设置有基坑(14),坡顶(13)上设置有排水沟(1),放坡(2)上设置有土钉(3),基坑(14)上设置有竖直相邻的桩孔桩(4)和止水帷幕桩(5),桩孔桩(4)和止水帷幕桩(5)的底部设置于基坑底部线(12)之下,锚索(7)横穿桩孔桩(4)和止水帷幕桩(5),通过锚索锚固垫板(10)和锚索锚固锁具(11)固定设置于桩孔桩(4)和止水帷幕桩(5)的一侧,锚索(7)上设置有若干个锚索钻孔(6)和托环(9),锚索(7)上套设有高压注浆管(8)。1. A kind of foundation pit support is characterized in that, comprises slope crest (13), and slope crest (13) one side is provided with slope (2), and the bottom of slope (2) is provided with foundation pit (14), Drainage ditches (1) are arranged on the top of the slope (13), soil nails (3) are arranged on the grading (2), and vertically adjacent pile hole piles (4) and water stop are arranged on the foundation pit (14). The bottom of the curtain pile (5), the pile-hole pile (4) and the water-stop curtain pile (5) are arranged below the foundation pit bottom line (12), and the anchor cable (7) traverses the pile-hole pile (4) and the water-stop The curtain pile (5) is fixed on one side of the pile hole pile (4) and the water-stop curtain pile (5) through the anchor cable anchor pad (10) and the anchor cable anchor lock (11), on the anchor cable (7) Several anchor cable boreholes (6) and support rings (9) are provided, and a high-pressure grouting pipe (8) is sheathed on the anchor cable (7). 2.根据权利要求1所述的基坑支护,其特征在于,所述锚索(7)至少设置有2个。2. The foundation pit support according to claim 1, characterized in that there are at least two anchor cables (7). 3.一种泥炭土深基坑支护高压旋喷锚固的方法,其特征在于,制作权利要求1所述的基坑支护,包括以下步骤:3. A method for peat soil deep foundation pit support high-pressure rotary grouting anchorage, is characterized in that, making the foundation pit support described in claim 1 may further comprise the steps: 步骤1、基坑开挖至设计第一道冠梁下2米后,制作锚索(7)和高压注浆管(8),采用水钻和跟进套管成孔工艺进行成孔操作;Step 1. After excavating the foundation pit to 2 meters below the designed first crown beam, make anchor cables (7) and high-pressure grouting pipes (8), and use water drilling and follow-up casing hole forming processes to perform hole forming operations; 步骤2、成孔后,跟进套管暂时放在孔内,把制作的锚索(7)、高压注浆管(8)先后放入孔中,高压注浆管(8)采用2㎝钢管加工而成,高压注浆管(8)喷浆嘴直径1.8㎜,高压注浆管(8)随锚索(7)安装至孔底,进行一次注浆常压5~10MPa压力注满孔,约5~10分钟初凝后进行二次高压注浆;Step 2. After the hole is formed, the follow-up casing is temporarily placed in the hole, and the manufactured anchor cable (7) and high-pressure grouting pipe (8) are put into the hole successively. The high-pressure grouting pipe (8) is made of a 2cm steel pipe Processed, high-pressure grouting pipe (8) nozzle diameter 1.8mm, high-pressure grouting pipe (8) is installed to the bottom of the hole along with the anchor cable (7), and the hole is filled with a normal pressure of 5-10MPa for one grouting. After about 5 to 10 minutes of initial setting, carry out secondary high-pressure grouting; 步骤3、待一次常压注浆开始凝固时,启动成孔机后退跟进套管,开始启动旋喷管进行锚固段旋喷,注浆压力提升速度每分钟20~25㎝,扩孔直径500~600㎜;水灰比0.40~0.50的纯水泥浆,压浆量≥120kg/m,直至锚固段全部旋喷完。Step 3. When the normal-pressure grouting begins to solidify, start the hole-forming machine to move back and follow the casing, and start the rotary nozzle to perform rotary spraying at the anchorage section. The grouting pressure increases at a rate of 20-25cm per minute, and the diameter of the hole is 500mm. ~600㎜; pure cement slurry with water-cement ratio 0.40~0.50, grouting volume ≥ 120kg/m, until the anchorage section is completely sprayed. 4.根据权利要求3所述的泥炭土深基坑支护高压旋喷锚固的方法,其特征在于,所述基坑开挖过程具体为:制作坡顶(13),坡顶(13)一侧倾斜设置放坡(2),放坡(2)底部设置基坑(14),坡顶(13)上设置排水沟(1),放坡(2)上设置土钉(3)。4. the method for peat soil deep foundation pit support high-pressure rotary jet grouting anchorage according to claim 3, is characterized in that, described foundation pit excavation process is specifically: make slope top (13), slope top (13)- A grading (2) is arranged for side inclination, a foundation pit (14) is arranged at the bottom of the grading (2), a drainage ditch (1) is arranged on the top of the slope (13), and soil nails (3) are arranged on the grading (2).
CN201510899993.5A 2015-12-08 2015-12-08 Foundation fit support and peat-soil deep-foundation-pit-support high-pressure jet grouting anchoring method Pending CN105604065A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510899993.5A CN105604065A (en) 2015-12-08 2015-12-08 Foundation fit support and peat-soil deep-foundation-pit-support high-pressure jet grouting anchoring method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510899993.5A CN105604065A (en) 2015-12-08 2015-12-08 Foundation fit support and peat-soil deep-foundation-pit-support high-pressure jet grouting anchoring method

Publications (1)

Publication Number Publication Date
CN105604065A true CN105604065A (en) 2016-05-25

Family

ID=55984372

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510899993.5A Pending CN105604065A (en) 2015-12-08 2015-12-08 Foundation fit support and peat-soil deep-foundation-pit-support high-pressure jet grouting anchoring method

Country Status (1)

Country Link
CN (1) CN105604065A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120808A (en) * 2016-07-28 2016-11-16 上海宝冶集团有限公司 A kind of in the soft comprehensive support method moulded in clay foundation ditch
CN107237332A (en) * 2017-06-15 2017-10-10 上海二十冶建设有限公司 A kind of foundation pit stope support containing drifting sand layer method of use composite soil-nailed retaining wall
CN108149691A (en) * 2017-12-11 2018-06-12 上海市基础工程集团有限公司 Face the method for excavation of deep foundation pit of inner city under complicated geological
CN109403350A (en) * 2018-12-18 2019-03-01 山西建筑工程集团有限公司 Foundation pit supporting construction and foundation pit supporting method
CN109853556A (en) * 2019-01-22 2019-06-07 华北有色工程勘察院有限公司 The ultra-deep that can bear explosion influence adopts hole supporting and retaining system and its construction method
CN111705814A (en) * 2020-07-29 2020-09-25 杭州福世德岩土科技有限公司 A kind of oblique support pile structure and its foundation pit enclosure method
CN115613565A (en) * 2022-11-12 2023-01-17 北京中润宝成工程技术有限公司 A Construction Method of Underwater Bolt in Rich Sand Stratum

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120808A (en) * 2016-07-28 2016-11-16 上海宝冶集团有限公司 A kind of in the soft comprehensive support method moulded in clay foundation ditch
CN107237332A (en) * 2017-06-15 2017-10-10 上海二十冶建设有限公司 A kind of foundation pit stope support containing drifting sand layer method of use composite soil-nailed retaining wall
CN108149691A (en) * 2017-12-11 2018-06-12 上海市基础工程集团有限公司 Face the method for excavation of deep foundation pit of inner city under complicated geological
CN109403350A (en) * 2018-12-18 2019-03-01 山西建筑工程集团有限公司 Foundation pit supporting construction and foundation pit supporting method
CN109853556A (en) * 2019-01-22 2019-06-07 华北有色工程勘察院有限公司 The ultra-deep that can bear explosion influence adopts hole supporting and retaining system and its construction method
CN111705814A (en) * 2020-07-29 2020-09-25 杭州福世德岩土科技有限公司 A kind of oblique support pile structure and its foundation pit enclosure method
CN115613565A (en) * 2022-11-12 2023-01-17 北京中润宝成工程技术有限公司 A Construction Method of Underwater Bolt in Rich Sand Stratum

Similar Documents

Publication Publication Date Title
CN103147442B (en) Ultra-deep foundation pit press-grouting pile and prestressed anchor combined supporting construction method
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN105604065A (en) Foundation fit support and peat-soil deep-foundation-pit-support high-pressure jet grouting anchoring method
CN114233385B (en) Treatment method for mud-bursting water of inclined shaft
CN106988302B (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN106013171B (en) A kind of semi-rigid supporting construction semi-flexible and method of deep-foundation side wall
CN102518135A (en) Foundation pit support construction method combining horizontal rotary jet-grouting soil bolting and bore concrete piles
CN206034454U (en) Supporting construction
CN105155550A (en) Construction method for digging deep foundation pit in large-thickness highly weathered sandstone stratum in combined supporting mode
CN110593254A (en) Construction method of cast-in-situ bored pile in stratum with karst cave in joint zone
CN210104758U (en) A foundation pit support system of soil-nailed cast-in-place pile and anchor-cable combination
CN102660955A (en) Quick construction method for foundation pit slope support
Lu et al. Overview of typical excavation failures in China
CN101691760A (en) Composite foundation combining anchor rods with excavation and construction method thereof
CN205954638U (en) Half semi -rigid flexible supporting construction of deep basal pit lateral wall
CN115717397A (en) Larsen steel sheet pile and prestressed anchor cable combined supporting construction method
CN113863706B (en) Construction method and application device of existing building low-clearance lower rotary-jet static pressure composite pile
CN106223344B (en) A kind of ground line piled anchor frame foundation pit supporting method
CN201908313U (en) Side slope reinforcement structure
CN114934518B (en) A deep foundation pit reinforcement method combining backfilling, decompression and grouting
CN106049413A (en) Hybrid power drainage consolidation system applied to deep saturated soft soil foundation and construction method
CN115404885A (en) Gradual retaining construction method suitable for multi-step high and steep slopes
CN106284447A (en) A kind of steel pipe grouting behind shaft or drift lining preloading underpinning pile construction method
CN217974507U (en) Protection system of subway tunnel structure crouches down during soft soil foundation ditch excavation
CN112796301A (en) Pre-reinforced structure and construction method of underground diaphragm wall in alluvial layer

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160525

WD01 Invention patent application deemed withdrawn after publication