CN2883532Y - Partition board connection structure-centipede type locking tenon - Google Patents
Partition board connection structure-centipede type locking tenon Download PDFInfo
- Publication number
- CN2883532Y CN2883532Y CN 200620102900 CN200620102900U CN2883532Y CN 2883532 Y CN2883532 Y CN 2883532Y CN 200620102900 CN200620102900 CN 200620102900 CN 200620102900 U CN200620102900 U CN 200620102900U CN 2883532 Y CN2883532 Y CN 2883532Y
- Authority
- CN
- China
- Prior art keywords
- partition board
- locking tenon
- tenon
- groove
- wallboard
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Finishing Walls (AREA)
Abstract
The utility model discloses a new structure for a partition wall plate connection-centipede-type locking tenon, comprising two partition wall plates. A concavo and a convex mortise and the tenon are respectively arranged at the edge of the plate of the two partition wall plates and a plurality of locking tenon grooves with small edge and large inside are arranged in order at the edge of the two partition wall plates. The locking tenon grooves are regular or irregular geometrical figure design, generally of a trapezoid or a circular. The tenon grooves are called a centipede-type locking tenon because the foot-arrangement is like a trapezoid. When arranged, higher-grade of sizing agent is filled into the locking tenon grooves and the clearance between the two plates. The utility model is suitable for all partition wall plates.
Description
Technical field
The utility model relates to a kind of syndeton of partition board, especially relates to a kind of connection new construction of partition board of centipede formula locking tenon.
Background technology
In order to protect land resources, energy conservation alleviates environment pollution; country forbids the use of loam brick gradually; advocate energetically and use novel wall material,, in building field, more and more used as the non in the frame construction as light heat-insulating fireproof partition board.
Though partition board has the light heat-insulating fire prevention, and the effect of environment protecting and power-saving, and installation is fast, and can effectively solve " Fei Liang, thick post, deep foundation " situation in building construction, but make between the wallboard and wallboard and the also solution completely of pillar junction generation problem of cracks because the drying of wallboard is shunk, thereby influence the paces of applying of partition board to a certain extent.
Apply mechanically the connected mode of floor or floor on the connected mode of partition board, promptly in panel edges setting " concave-convex tongue and groove " (as shown in Figure 1, 2), and this structure is for upright partition board, can only be to playing fixation before and after it, be convenient to installation, and for not involving effect between the wallboard at all.In order to prevent that the crack from producing, as shown in Figure 2, lengthening tenon projection makes to form a gap between plate and the plate, after practice of construction is installed, filler is squeegeeed in these gaps, then between plate and plate, paste grid cloth again, but only rely on filler to squeegee and the bonding force of grid cloth, also be not enough to overcome wallboard and the dry shrinkage stress in back be installed and produced the crack, use this processing mode, crack problem is not effectively solved.
In order effectively to solve crack problem between plate and the plate, about R﹠D institution, construction and installation unit and wallboard manufacture producer all attempt, existing three kinds of ways.
A kind of is to adopt a kind of " 8 fonts locking tenon " structure, (as shown in Figure 3) this structure is to open a big hole in the little inside of outer rim in the middle of the partition board edge, wallboard install the back toward about be in the milk in two holes, be after the drying and lock about " 8 fonts locking tenon " carries out.This " 8 fonts locking tenon " produce effective tractive force to the two sides wallboard, have solved the longitudinal crack problem of wallboard really, but installation is when taking a lot of work, but also will pour into slip with special tool.Moreover its edge does not have " concave-convex tongue and groove " structure, location, front and back trouble in installation, and fixation before and after not having, in addition.Can not use this structure to the wallboard that cross through hole is set.
Another kind is so-called " double hook groove locking tenon " structure (as shown in Figure 4), and this structure is that panel edges makes that " I-shape construction is installed the back and put two set " bracket shape external members " in the wallboard junction two wallboards are entangled.This structure also can produce effective tractive force to two blocks of wallboards, thereby can effectively solve the longitudinal crack problem of wallboard, remains construction cost man-hour but install, and the limit is molded bothers demoulding difficulty.Equally, its edge does not have concave-convex tongue and groove structure, location, front and back trouble in installation, fixation before and after yet not having.
Also having a kind of is on the basis of " concave-convex tongue and groove ", at the pre-buried bar dowel in the two edges of wallboard, after wallboard is installed, with electric welding machine two reinforcing bar welding of symmetry are lived, this method not only efficiently solves the longitudinal crack problem of wallboard theoretically, and the edge is " a concave-convex tongue and groove ", before and after the wallboard fixation is arranged still, the wallboard installing and locating is convenient and swift.
But there are three shortcomings: the one, wallboard is installed in the time of need splicing up and down, and some dislocation of the right and left reinforcement bar not on same horizontal plane, just can not effectively be welded; The 2nd, the cementitious material of wallboard do to(for) magnesia oxychloride cement has corrosiveness to iron and steel, steel products such as unsuitable pre-buried bar dowel; The 3rd, when the wallboard fabrication and installation are taken a lot of work, and increase cost.
Summary of the invention
The purpose of this utility model is to provide a kind of reasonable in design at the situation that occurs crack problem after the above partition board installation easily, and Mold Making is simple, and partition board is connected new construction one " centipede formula locking tenon " to wallboard manufacture with installing again very easily.
In order to achieve the above object, the utility model is mainly realized by the following technical solutions.The utility model is made up of two partition boards, panel edges at two partition boards is respectively equipped with the concave-convex tongue and groove, on the edge of two partition boards, also be provided with several and arrange little, the inner big locking tenon groove in orderly edge, described locking tenon groove is rule or the design of irregular geometric figure, generally adopts trapezoidal or circular.Owing to arrange just as the Scolopendra foot shape, be called centipede formula locking tenon.During installation, a high grade slurry is filled into locking tenon groove and is located in the gap between two plates.
The utility model compared with prior art has following tangible advantage and innovation.(1) wallboard left and right sides holdback force is big, and the crack solves fully between plate.The edge of every partition board all is provided with the locking tenon groove of several likeness in form Scolopendra foots; after wallboard is installed; to rule or the high first-class slip of establishing on the gap between two wallboards (likeness in form centipede body) and the edge of the interior pad of irregular geometric figure locking tenon groove (likeness in form Scolopendra foot); the outside is pasted and is gone up grid cloth; treat to form a centipede shape after the slip drying; utilize the polypody of centipede; firmly two wallboards are pind down; thereby solved the crack problem of wallboard effectively, also met building mould ash standard simultaneously.(2) utilize the concave-convex tongue and groove, wallboard is quick and easy for installation.Owing to utilize " concave-convex tongue and groove " structure, there is mounting method fixing, the positioning action wallboard fully the same before and after the wallboard with the concave-convex tongue and groove, almost do not increase erector's cost, wallboard is easy for installation quick again.(3) do not increase die cost, wallboard manufacture is made simple.Because " Scolopendra foot " mould with plastics or rubber, sticks on the plastics of the end, face after the making or above the rubber pattern, so, almost do not increase the cost of manufacture of the cost and the wallboard of mould, in the process of making wallboard, almost do not increase numerous and diverse operation, manufacture craft is simple.
The utility model is applicable to all partition boards.
Below in conjunction with the drawings and specific embodiments the utility model is described in further detail.
Description of drawings
Fig. 1 is the connected mode schematic diagram of partition board " concave-convex tongue and groove " formula.
Fig. 2 is the connected mode schematic diagram of partition board " concave-convex tongue and groove " formula after improving.
Fig. 3 is the connected mode schematic diagram of partition board " 8 fonts locking tenon " formula.
Fig. 4 is the connected mode schematic diagram of partition board " double hook groove locking tenon " formula.
Fig. 5 is the connected mode schematic diagram of partition board " bar dowel spot welding " formula.
Fig. 6 is the structural representation of the utility model " centipede formula locking tenon " formula.
The specific embodiment
As shown in Figure 1, partition board 1 is provided with groove 2, and partition board 4 is provided with tenon 3.
As shown in Figure 2, partition board 1 is provided with groove 2, and partition board 4 is provided with tenon 3.
Also be provided with gap 5 between partition board 1 and the partition board 4.
As shown in Figure 3, partition board 1 is provided with groove 2, and partition board 4 is provided with groove 2.
Also be provided with gap 5 between partition board 1 and the partition board 4.
As shown in Figure 4, partition board 1 is provided with I-shaped tenon 3, also is provided with I-shaped tenon 3 on the partition board 4, in the outer bracket shape locking external member 6 that is provided with of two I-shaped tenons 3.
As shown in Figure 5, the partition board connected mode is to carry out being provided with on the basis of Fig. 2, is respectively equipped with pre-buried reinforcing bar 7 on the partition board 1,4.
As shown in Figure 6, setting of the present utility model also is to carry out on the basis of Fig. 2, the utility model is made up of 1,4 of two partition boards, panel edges at two partition boards 1,4 is respectively equipped with concave-convex tongue and groove 2,3, on the edge of two partition boards 1,4, also be respectively equipped with several and arrange little, the inner big locking tenon groove 8,9 in orderly edge, described locking tenon groove 8,9 is rule or the design of irregular geometric figure, generally adopts trapezoidal or circular.Owing to arrange just as the Scolopendra foot shape, be called centipede formula locking tenon.During installation, a high grade slurry is filled into locking tenon groove 8,9 and is located in the gap 5 between two plates 1,4.
The utility model is applicable to all partition boards.
Claims (2)
1, a kind of partition board connects new construction-centipede formula locking tenon, formed by two partition boards (1), (4), panel edges in two partition boards (1), (4) is respectively equipped with concave-convex tongue and groove (2), (3), it is characterized in that also being respectively equipped with several and arrange orderly edge little, inner big locking tenon groove (8), (9) on the edge of two partition boards (1), (4).
2, described a kind of partition board according to claim 1 connects new construction-centipede formula locking tenon, it is characterized in that locking tenon groove (8), (9) for rule or the design of irregular geometric figure, generally adopts trapezoidal or circular.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200620102900 CN2883532Y (en) | 2006-04-20 | 2006-04-20 | Partition board connection structure-centipede type locking tenon |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 200620102900 CN2883532Y (en) | 2006-04-20 | 2006-04-20 | Partition board connection structure-centipede type locking tenon |
Publications (1)
Publication Number | Publication Date |
---|---|
CN2883532Y true CN2883532Y (en) | 2007-03-28 |
Family
ID=37956593
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 200620102900 Expired - Fee Related CN2883532Y (en) | 2006-04-20 | 2006-04-20 | Partition board connection structure-centipede type locking tenon |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN2883532Y (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102756740A (en) * | 2012-07-12 | 2012-10-31 | 长春轨道客车股份有限公司 | Air spring adjusting cushion for bogie |
CN103696491A (en) * | 2014-01-02 | 2014-04-02 | 黄军海 | Novel mounting structure of building and house using mounting structure |
CN103898980A (en) * | 2013-08-02 | 2014-07-02 | 应亿企业有限公司 | Connection mode and composition of spacing object |
CN101761140B (en) * | 2010-01-04 | 2014-07-16 | 刘长生 | Dovetail mortise-tenon connection method between assembly parts in building project |
CN105926841A (en) * | 2015-03-30 | 2016-09-07 | 姚景祥 | Zipper-type wall part and zipper key for producing the same |
CN107152435A (en) * | 2017-04-16 | 2017-09-12 | 廖华勇 | It is applicable the loose joint mechanism that AB plates are mutually nibbled |
CN109667351A (en) * | 2019-01-16 | 2019-04-23 | 中南大学 | Assembled architecture prefabricated panel horizontal joint mud jacking Alveolus type waterproof connecting structure |
CN110056094A (en) * | 2019-05-24 | 2019-07-26 | 蓬莱正泰木业有限公司 | A kind of plate plug side structure and connecting element and assemble method |
CN110778111A (en) * | 2019-11-07 | 2020-02-11 | 张永祥 | Fixed template structure of pouring frame for civil construction engineering construction |
CN111945986A (en) * | 2020-07-23 | 2020-11-17 | 山东芳林昊天钢结构工程有限公司 | Novel outer wall interior wall coating wallboard |
CN113137004A (en) * | 2021-03-31 | 2021-07-20 | 恒尊集团有限公司 | Quick assembly type building wallboard |
CN117419995A (en) * | 2023-12-18 | 2024-01-19 | 中铁十八局集团第四工程有限公司 | Saturated red clay triaxial sample demoulding structure |
-
2006
- 2006-04-20 CN CN 200620102900 patent/CN2883532Y/en not_active Expired - Fee Related
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101761140B (en) * | 2010-01-04 | 2014-07-16 | 刘长生 | Dovetail mortise-tenon connection method between assembly parts in building project |
CN102756740A (en) * | 2012-07-12 | 2012-10-31 | 长春轨道客车股份有限公司 | Air spring adjusting cushion for bogie |
CN103898980A (en) * | 2013-08-02 | 2014-07-02 | 应亿企业有限公司 | Connection mode and composition of spacing object |
CN103898980B (en) * | 2013-08-02 | 2017-01-04 | 应亿企业有限公司 | Interval object unit |
CN103696491A (en) * | 2014-01-02 | 2014-04-02 | 黄军海 | Novel mounting structure of building and house using mounting structure |
CN103696491B (en) * | 2014-01-02 | 2016-02-17 | 黄军海 | A kind of mounting structure of building and apply the house of this mounting structure |
CN105926841A (en) * | 2015-03-30 | 2016-09-07 | 姚景祥 | Zipper-type wall part and zipper key for producing the same |
CN107152435A (en) * | 2017-04-16 | 2017-09-12 | 廖华勇 | It is applicable the loose joint mechanism that AB plates are mutually nibbled |
CN109667351A (en) * | 2019-01-16 | 2019-04-23 | 中南大学 | Assembled architecture prefabricated panel horizontal joint mud jacking Alveolus type waterproof connecting structure |
CN109667351B (en) * | 2019-01-16 | 2024-01-30 | 中南大学 | Tooth socket type waterproof connecting structure of prefabricated wallboard horizontal joint grouting method of assembled building |
CN110056094A (en) * | 2019-05-24 | 2019-07-26 | 蓬莱正泰木业有限公司 | A kind of plate plug side structure and connecting element and assemble method |
CN110056094B (en) * | 2019-05-24 | 2024-03-12 | 蓬莱正泰木业有限公司 | Board plugging edge structure, plugging assembly and assembly method |
CN110778111A (en) * | 2019-11-07 | 2020-02-11 | 张永祥 | Fixed template structure of pouring frame for civil construction engineering construction |
CN110778111B (en) * | 2019-11-07 | 2021-04-30 | 张永祥 | Fixed template structure of pouring frame for civil construction engineering construction |
CN111945986A (en) * | 2020-07-23 | 2020-11-17 | 山东芳林昊天钢结构工程有限公司 | Novel outer wall interior wall coating wallboard |
CN113137004A (en) * | 2021-03-31 | 2021-07-20 | 恒尊集团有限公司 | Quick assembly type building wallboard |
CN117419995A (en) * | 2023-12-18 | 2024-01-19 | 中铁十八局集团第四工程有限公司 | Saturated red clay triaxial sample demoulding structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN2883532Y (en) | Partition board connection structure-centipede type locking tenon | |
CN203393894U (en) | Thin-wall profile steel compounded external wallboard | |
CN203334663U (en) | Aluminum formwork for stairway structure | |
CN208792737U (en) | For hanging the detachable connecting part of external platform hanging girder steel | |
CN110374322A (en) | A kind of assembled waffle beam plate device | |
CN110344535A (en) | A kind of prefabricated assembled combined wall board and construction method realized concealed beam and exempt from formwork | |
CN205024949U (en) | Take steel bar truss gypsum board of heat preservation, novel -in -place mould | |
CN114293688A (en) | UHPC-necking profiled sheet composite template composite shear wall | |
CN105386538A (en) | CL composite concrete shear wall construction process | |
CN204676608U (en) | A kind of template-setup structure reserving ater-casting for basement wall | |
CN207553505U (en) | Assembled wall anchoring assembly | |
CN108018972B (en) | Full prefabricated floor slab and composite floor slab combined structure, manufacturing and assembling method | |
CN203626261U (en) | Construction structure of concrete spreader in aluminum alloy formwork system | |
CN105155838B (en) | A kind of quick detachable high-strength building formwork | |
CN204510817U (en) | Hole to be provided regularization adjustable steel frame template | |
CN215471884U (en) | Cast concrete superimposed sheet preparation mould with location structure | |
CN105178469A (en) | Efficient thermal insulation construction method of outer wall window opening | |
CN206189449U (en) | Integrated wood formwork system of foundation slab and guide wall | |
CN206220132U (en) | A kind of base plate and exterior wall junction construction typified form support | |
CN202214982U (en) | One-shot forming ground beam template | |
CN105239770B (en) | Integrated casting steel framework plastic building template system | |
CN205531319U (en) | Prefabricated wallboard and precast beam piece plugging device and block structure | |
CN204876276U (en) | Building heat preservation prefabricated section | |
CN205894401U (en) | Curtain slot type buries a top and buries positioner | |
CN201187146Y (en) | Novel plastics-steel building formwork |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C53 | Correction of patent for invention or patent application | ||
CB03 | Change of inventor or designer information |
Designer after: Fu Jinsong Designer after: Tong Peiyin Designer before: Fu Jinsong Designer before: He Chaoyun Designer before: Tong Peiyin |
|
COR | Change of bibliographic data |
Free format text: CORRECT: DESIGNER; FROM: FU JINSONG; HE CHAOYUN; TONG PEIYIN TO: FU JINSONG; TONG PEIYIN |
|
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20070328 Termination date: 20120420 |