CN2866589Y CN 200520037749 CN200520037749U CN2866589Y CN 2866589 Y CN2866589 Y CN 2866589Y CN 200520037749 CN200520037749 CN 200520037749 CN 200520037749 U CN200520037749 U CN 200520037749U CN 2866589 Y CN2866589 Y CN 2866589Y
Authority
CN
China
Prior art keywords
pressure divider
mine
pipeline
shower nozzle
spray
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN 200520037749
Other languages
Chinese (zh)
Inventor
刘训宁
郝永胜
蔺学
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shenhua Energy Co Ltd
Shenhua Zhungeer Energy Co Ltd
Original Assignee
China Shenhua Energy Co Ltd
Shenhua Zhungeer Energy Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shenhua Energy Co Ltd, Shenhua Zhungeer Energy Co Ltd filed Critical China Shenhua Energy Co Ltd
Priority to CN 200520037749 priority Critical patent/CN2866589Y/en
Application granted granted Critical
Publication of CN2866589Y publication Critical patent/CN2866589Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Nozzles (AREA)
  • Special Spraying Apparatus (AREA)

Abstract

The utility model discloses a spray watering dust fall system for mine transport road, comprising a water source system, a water pump boosting system that connected with the water source system through a water source pipe system, a plurality of pressure branch conduits parallel connected with the output terminal of the water pump boosting system, a plurality of burner caps arranged on said pressure branch conduits, a spray control system. The pressure branch conduits are provided with a plurality of standpipes that provided with valve bodies and blow heads which are above the ground. The pressure branch conduits are parallel arranged, and the blow heads is equidistantly arranged on every pressure branch conduit. The spray watering dust fall system for mine transport road of the utility model is capable of effectively reducing the dust pollution for mine transport road, thereby enhancing the air visibility, improving the traffic conditions and guaranteeing the traffic safety.

Description

Mine transport routes spray watering and lowering dust system
Technical field
The utility model relates to a kind of mine transport routes spray watering and lowering dust system.
Background technology
At present, it is very outstanding that open cut ore mine transport routes dust flies the ease problem, makes that air pollution is serious, low visibility, influences the healthy of traffic safety and workman.
Usually the depositing dust means of taking are to adopt the watering truck along water sprinkling path, but, because factors such as the transport routes vehicle density is big, temperature height, make the watering amount can not make the road top layer keep certain humidity, therefore road sand and floating dust are still very serious, particularly since night airborne dust road visibility too low, thereby have a strong impact on the truck security of operation even lead to great pernicious traffic accident.In fact, the open cut ore mine transport routes road conditions in a lot of areas of China are all relatively poor, and not only road is narrow, and the road surface cheats recessed injustice, simultaneously owing to make that driver's the visual field is very limited bend more; In addition, the vehicle on these roads mostly is heavy truck and some pony cars, so normal the appearance do not observed the phenomenon that pony car causes traffic accident because of the truck driver.In this case, road sand and floating dust make that undoubtedly transportation condition is more abominable, so under this road conditions, vehicle not only travel speed is restricted, and are easy to occur traffic accident, threaten traffic safety.
Therefore, be necessary to design a kind of new mine transport routes spray watering and lowering dust system in fact, to overcome above-mentioned defective.
The utility model content
The purpose of this utility model is to provide a kind of mine transport routes spray watering and lowering dust system that can effectively reduce mine transport routes dust pollution.
To achieve these goals, mine of the present utility model transport routes spray watering and lowering dust system is design like this:
A kind of mine transport routes spray watering and lowering dust system, the water pump booster system that it comprises water resource system, be connected with water resource system by the water pipeline system, many pressure divider pipelines in parallel, be installed in a plurality of shower nozzles on the described pressure divider pipeline and spray control system with water pump booster system output, on the described pressure divider pipeline vertical tube is housed, valve body and shower nozzle are installed on this vertical tube, this shower nozzle is above ground level, and described pressure divider pipeline is provided with and every shower nozzle each interval equidistance that the pressure divider pipeline is installed abreast.
By using mine of the present utility model transport routes spray watering and lowering dust system, can effectively reduce the dust pollution of mine transport routes, thereby improve air visibility, and then improve transportation condition, guarantee traffic safety.
Description of drawings
Fig. 1 is the schematic diagram of mine of the present utility model transport routes spray watering and lowering dust system;
Fig. 2 is the nozzle layout of sprinkler schematic diagram of mine of the present utility model transport routes spray watering and lowering dust system.
The specific embodiment
See also Fig. 1, the water pump booster system 12 that mine of the present utility model transport routes sprays watering and lowering dust system 1 comprises water resource system 10, be connected with water resource system 10 by water pipeline system 11, many pressure divider pipelines 14 in parallel, be installed in a plurality of shower nozzles 16 and sprinkling control system (not shown) on the described pressure divider pipeline 14 with water pump booster system 12 outputs.
Particularly, described water resource system 10 can adopt high-order water tower, and the water pump booster system 12 main vertical multi-stage centrifugal pumps that adopt raise to realize hydraulic pressure.
Water pipeline system 11 adopts spiral welded steel pipe, and welding is connected with snap joint.
On the described pressure divider pipeline 14 vertical tube 140 is housed, valve body 142 and shower nozzle 16 are installed on the vertical tube 140, this shower nozzle 16 300~500mm above ground level, vertical tube 140 bottoms are provided with basic courses department's (not shown), be removable gravity steel-concrete cube pier, to guarantee shower nozzle 16 working stabilities.These pressure divider pipelines 14 adopt steel pipe, pvc pipe or rubber tube.
The effect of described shower nozzle 16 is that the later concentrated flow of water pump booster system 12 pressurizations is dispersed into tiny water droplet and is spread in the road top layer equably.
Please in conjunction with consulting Fig. 2, the arrangement of the shower nozzle 16 of mine of the present utility model transport routes spray watering and lowering dust system 1 is promptly as shown in the drawing: described pressure divider pipeline 14 is arranged in parallel each other, promptly lay along the both sides of transport routes, a plurality of shower nozzles 16 are installed in respectively on the pressure divider pipeline 14, the distance that between the shower nozzle 16 that every pressure divider pipeline 14 is installed, equates at interval, and wherein the shower nozzle 16 installed of the shower nozzle 16 installed of pressure divider pipeline 14 and an other pressure divider pipeline 14 is crisscross arranged each other, promptly wherein the shower nozzle 16 on pressure divider pipeline 14 between two shower nozzles 16 that subpoint drops on and this subpoint is contiguous of an other pressure divider pipeline 14; Simultaneously, each shower nozzle 16 can only be done the fan-shaped sprinkling campaign of half cycle to the road surface direction, and the radius that sprays substantially just is advisable on the road surface of covering transportation overlappingly with the waters after spraying.
Adopt this kind arrangement not only spill cloth evenly better, sprinkler pattern range is less, intensity of spray irrigation is lower, instantaneous delivery is less, and continuous operation is longer.
By using mine of the present utility model transport routes spray watering and lowering dust system 1, can effectively reduce the dust pollution of mine transport routes, thereby improve air visibility, and then improve transportation condition, guarantee traffic safety.

Claims (4)

1. mine transport routes spray the watering and lowering dust system, it is characterized in that: this mine transport routes spray watering and lowering dust system comprises water resource system, the water pump booster system that is connected with water resource system by the water pipeline system, many the pressure divider pipelines in parallel with water pump booster system output, be installed in a plurality of shower nozzles on the described pressure divider pipeline and spray control system, on the described pressure divider pipeline vertical tube is housed, valve body and shower nozzle are installed on this vertical tube, this shower nozzle is above ground level, and described pressure divider pipeline is provided with and every shower nozzle each interval equidistance that the pressure divider pipeline is installed abreast.
2. mine as claimed in claim 1 transport routes spray watering and lowering dust system, it is characterized in that: described water resource system adopts high-order water tower, and the water pump booster system adopts vertical multi-stage centrifugal pump.
3. mine as claimed in claim 2 transport routes spray watering and lowering dust system, it is characterized in that: wherein the shower nozzle of the shower nozzle of a pressure divider piping erection and an other pressure divider piping erection is crisscross arranged each other.
4. mine as claimed in claim 3 transport routes spray watering and lowering dust system is characterized in that: the shower nozzle on wherein pressure divider pipeline of described relative pressure divider pipeline is between two shower nozzles that subpoint drops on and this subpoint is contiguous of an other pressure divider pipeline.
CN 200520037749 2005-12-30 2005-12-30 Mining transporting road spraying sprinkling and dust reducing system Expired - Lifetime CN2866589Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200520037749 CN2866589Y (en) 2005-12-30 2005-12-30 Mining transporting road spraying sprinkling and dust reducing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200520037749 CN2866589Y (en) 2005-12-30 2005-12-30 Mining transporting road spraying sprinkling and dust reducing system

Publications (1)

Publication Number Publication Date
CN2866589Y true CN2866589Y (en) 2007-02-07

Family

ID=37702291

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200520037749 Expired - Lifetime CN2866589Y (en) 2005-12-30 2005-12-30 Mining transporting road spraying sprinkling and dust reducing system

Country Status (1)

Country Link
CN (1) CN2866589Y (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102031988A (en) * 2010-11-17 2011-04-27 无锡市华能电力机械有限公司 Water-curtain dust fall system of storage bunker
CN105080889A (en) * 2015-09-14 2015-11-25 云南大红山管道有限公司 Workshop ground washing device
CN108071414A (en) * 2018-02-02 2018-05-25 珲春紫金矿业有限公司 A kind of surface mine dust suppression device by water spray

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102031988A (en) * 2010-11-17 2011-04-27 无锡市华能电力机械有限公司 Water-curtain dust fall system of storage bunker
CN102031988B (en) * 2010-11-17 2012-12-12 无锡市华能电力机械有限公司 Water-curtain dust fall system of storage bunker
CN105080889A (en) * 2015-09-14 2015-11-25 云南大红山管道有限公司 Workshop ground washing device
CN108071414A (en) * 2018-02-02 2018-05-25 珲春紫金矿业有限公司 A kind of surface mine dust suppression device by water spray

Similar Documents

Publication Publication Date Title
CN103201011B (en) It is installed on the water injector of electric car
CN203944254U (en) A kind of tower crane water injection system
CN104429833B (en) A kind of underground water greenbelt irrigation system powered based on solar street light
CN204163037U (en) A kind of sprinkling truck and water circuit system thereof
CN2866589Y (en) Mining transporting road spraying sprinkling and dust reducing system
CN104912019A (en) Autonomous synchronous micro-jet and dust suppression system for automobile
CN205276171U (en) Highway is with automatic safety protective guard that sprays
CN206090430U (en) Semi -automatic afforestation watering lorry
CN105475098A (en) Movable plantation sprinkling machine
CN207295591U (en) Road surface sweeper
CN2782759Y (en) Water spraying vehicle for roadway of mine
CN205804253U (en) Complete three-dimensional dust Control work station
CN204796388U (en) Plane watering structure
CN204335483U (en) A kind of underground water greenbelt irrigation system of powering based on solar street light
CN110646228A (en) Rainy day simulation system applied to rail vehicle
CN205934792U (en) Municipal administration road guardrail
KR20200141747A (en) Injecting system for reducing fine dust and heat island
CN205636853U (en) Draw yellow culverts and water gates desilting equipment
CN200945839Y (en) Multifunctional tricycle water car
CN115581985A (en) Automatic dust falling device
CN208101901U (en) A kind of Multi-functional bumper of automobile
CN206791474U (en) A kind of highway median nursery stock positions chemical spraying device
CN208201758U (en) A kind of mining area sprinkling truck
CN210946657U (en) Automatic spraying equipment for road raised dust curing material
CN107737502A (en) A kind of Coal Transport sprayer unit

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term

Granted publication date: 20070207