CN2770896Y - Large-sized die storage device - Google Patents

Large-sized die storage device Download PDF

Info

Publication number
CN2770896Y
CN2770896Y CN 200520033241 CN200520033241U CN2770896Y CN 2770896 Y CN2770896 Y CN 2770896Y CN 200520033241 CN200520033241 CN 200520033241 CN 200520033241 U CN200520033241 U CN 200520033241U CN 2770896 Y CN2770896 Y CN 2770896Y
Authority
CN
China
Prior art keywords
mould
utility
model
melt pit
large mold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 200520033241
Other languages
Chinese (zh)
Inventor
万白谦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Changan Automobile Co Ltd
Original Assignee
Changan Automobile Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changan Automobile Group Co Ltd filed Critical Changan Automobile Group Co Ltd
Priority to CN 200520033241 priority Critical patent/CN2770896Y/en
Application granted granted Critical
Publication of CN2770896Y publication Critical patent/CN2770896Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a large-sized die storage device, which is provided with a ground pit on a concrete foundation and at least three supporting seats are arranged around the ground pit. Two guide posts are symmetrically arranged outside the supporting seats at both sides of the ground pit, two supporting frames are symmetrically arranged outside the two guide posts and a transverse beam of each supporting frame is provided with a device used for clamping dies. The utility model has the advantage of simple structure and can be used for upright storing large dies, the utility model also has the advantages of small ground occupying, high stability, die deformation proofing, convenient overhaul and part dismounting and not storage place environment pollution and the utility model increases operational safety and optimizes die storage management.

Description

The storing unit of large mold
Technical field
The utility model relates to a kind of device of depositing mould, particularly a kind ofly is used for the vertical device of depositing large mold.
Background technology
At present, in mould manufacturing enterprise at home and abroad, punching production enterprise and the Foundry Production enterprise, to large mold to deposit, overhaul generally be to adopt ground to keep flat to be main mode, after also mould being decomposed sometimes, to adopt the sleeper formula form of standing up of removing stage makeup and costume to deposit large mold.The mode center of gravity that mould keeps flat is low, it is stable to deposit, but this location mode makes mold storing plate facial disfigurement easily, deposits, overhaul that to take floor area big, and the floor area utilization rate is lower, causes the land resource serious waste; Mould adopts decomposition, the sleeper formula of removing stage makeup and costume to stand up form, though reduced the floor space of die main body, but still need taking up an area of, deposits the mold component that disassembles, and the sleeper that is used to support easy deformation under weight, it is too high to add the mold center of gravity, storage configuration is extremely unstable, makes it to exist security hidden trouble; Simultaneously, two kinds of location modes all exist greasy dirt residual in the mould to trickle out to pollute storage area, cause the storage space environmental pollution, influence operating environment and production safety more than.And, under such location mode and such storage environment, extremely inconvenient to the mould part that overhauls, removes stage makeup and costume.
Summary of the invention
The purpose of this utility model provides a kind of storing unit of large mold.Vertical to deposit the large mold floor space little with it, and good stability can improve the ability of mould resistance to deformation, and the part operation of overhauling, remove stage makeup and costume is comparatively convenient, can not pollute the storage space environment, improves the security of operation.
The purpose of this utility model is achieved in that
A melt pit is set on concrete foundation, be provided with at least three supporting bases around the melt pit, the lead that two upper ends are the inclined-plane is symmetricly set on the supporting base outside of melt pit both sides, two bracing frames are symmetricly set on two lead outsides, and the crossbeam of each bracing frame is provided with the device that is used for the clamping mould.
Supporting base, lead, bracing frame are all fixedlyed connected with the built-in fitting in the basis.
The level of the upper surface of all supporting bases, highly consistent.
The inclined-plane of two leads is connected with blade fin in opposite directions on the inclined-plane.
The device that is used for the clamping mould is two grip slippers, and grip slipper is connected on the crossbeam of bracing frame by bolt respectively.
Owing to adopted such scheme, concrete foundation is provided with melt pit, and the basis around the melt pit is provided with at least three supporting bases, and the level of the upper surface of all supporting bases, highly consistent can stand up on the ground mould reposefully; Loosing core of mould can be stretched in the melt pit in the setting of melt pit, makes the vertical reduction of mould center of gravity, the greasy dirt of depositing enter the hole.Two upper end inclined-plane leads in opposite directions are symmetrical arranged, and lead when mould is hung, and can aim at the melt pit center line automatically when making mould hang off center under the guiding of the blade fin that connects on the lead inclined-plane.The blade fin that connects with screw on the lead inclined-plane can change, and selects different guiding angles and allows retention gap between lead inclined-plane and the mould according to the guiding needs, prevents that the location from appearring in mold storing on the ground.The device that is used for the clamping mould that is provided with on the crossbeam with the bracing frame of two symmetries from the fore-and-aft direction mould that reclines, can prevent mould centre-of gravity shift and toppling under external force by the grip block on its two grip slipper, realizes the supporting mould purpose.Supporting base, lead, bracing frame are all fixedlyed connected with the built-in fitting in the basis, make supporting base, lead, bracing frame connect the location securely, and be reliable and stable with the storing unit that guarantees large mold.
The utility model is simple in structure, and it can make, and large mold is vertical to be deposited, and has reduced to deposit the floor space of large mold, makes the standard, safer more of depositing of large mold, and makes the maintenance mould convenient.
The utility model is described in further detail below in conjunction with drawings and Examples.
Description of drawings
Fig. 1 is a structural representation of the present utility model;
Fig. 2 is that the A-A of Fig. 1 is to cutaway view;
Fig. 3 is a vertical view of the present utility model;
Fig. 4 is the schematic diagram of mold storing on the utility model.
The specific embodiment
Referring to Fig. 1, Fig. 2, Fig. 3, a melt pit 7 is set on the concrete foundation, melt pit is a rectangle, posts ceramic tile in the hole.4, three supporting bases 4 of supporting base that it is cast steel that melt pit 7 is provided with three materials on every side are " product " font and are distributed in around the melt pit 7.The basis of each supporting base 4 below is embedded with the steel built-in fitting 9 with four clubfoots, and supporting base 4 is fixedly connected on the pre-buried steel basis built-in fitting 9 by four hexagon socket head cap screws, and firm with concreting.Upper surface and the basic ground flat of the supporting base 4 after fixing, the level of the upper surface of three supporting bases 4, unanimity highly, the mould of depositing in order to supporting.Two leads 3 are symmetrical arranged against supporting base 4 outsides of melt pit 7 both sides, and the basis of lead 3 belows is embedded with the steel built-in fitting 9 with four clubfoots, and basis and 9 welding of steel built-in fitting are sunk in the bottom of lead 3, and firm with concreting.The upper end of lead 3 is the inclined-plane, and the inclined-plane of two leads 3 is connected with blade fin 10 with sunk screw on this inclined-plane in opposite directions, and this blade fin can change.Two " ∏ " shape bracing frames 1 are symmetrical arranged near two leads, 3 outsides respectively, the basis of bracing frame 1 column below is embedded with the steel built-in fitting 9 with four clubfoots, basis and 9 welding of steel built-in fitting are sunk in the bottom of bracing frame 1 column, and firm with concreting.Bracing frame 1 crossbeam after fixing keeps level, and its crossbeam is adjacent to lead 3 upper ends, to strengthen the ability that lead 3 bears bump; The upper surface of crossbeam is approximately higher than the upper end of lead 3.The crossbeam of each bracing frame 1 is provided with two axial strip holes 11, and bolt 6 passes the device that strip hole 11 will be used for the clamping mould and is connected crossbeam.The device that is used for the clamping mould is two grip slippers 2, two grip slippers 2 are fastenedly connected by the crossbeam of bolt 6 with bracing frame 1 respectively, the feather key at 2 ends of grip slipper inserts in the strip hole 11, looser a bolt after 6, grip slipper 2 can be along the strip hole 11 slides, the mould of depositing is formed clamping, tight a bolt 6 then, finish mould and support the location.Be fastenedly connected with grip block 5 with screw on each grip slipper 2, the length of grip block 5 can be determined according to the mould holding needs, in order to support before and after the mould that will deposit; The location of grip block 5 highly is approximately higher than the mould center of gravity, to stablize mould, prevents that mould from toppling under external force influence.Melt pit 7 near coal-mine is equipped with the mosaic type hole cover 8, in order to capping vacate near coal-mine, walk or take for the staff.
Referring to Fig. 4, when using this device to deposit mould, at first mould 12 is erect and sling, allow the slideway of loosing core of mould slowly put down towards melt pit 7; When the position skew appearred in mould 12 declines, the blade fin 10 on the lead 3 can guide mould to aim at the melt pit center line automatically, steadily is placed on three supporting bases 4 until mould.The mould slideway of loosing core enters melt pit 7, and the height of C.G. of mould is minimized.Grip slipper 2 on mobile subsequently bracing frame 1 crossbeam makes grip block 5 on the grip slipper near mould 12, and 6 location that tight a bolt, and forms the front and back clamping of mould is supported, and prevents that mould from toppling under external force; Mould 12 place stable after, gapped with the crossbeam of blade fin 10 on the lead 3 and bracing frame 1, can avoid forming the location.Then the tube head of mould oil pipe is put into the hole, allow the interior Residual oil of mould flow in the hole, wait for regular waste oil disposal from oil pipe.Cover near coal-mine that 8 cappings vacate with mosaic type combination hole, for the mould maintainer use of walking.This vertical mode of depositing mould has reduced the floor space that large mold is deposited, and has improved the reserve capabillity in mold storing zone.For example: deposited the floor space (taking up an area of 12 meters * 12 meters) of 2 secondary compression mods originally, adopt this device after, can deposit 6 secondary compression mods.And, owing to be provided with melt pit, reduced the height of C.G. when mould stands up relatively, the more convenient maintenance of mould, disassembling section have improved operational security, have also avoided the pollution of greasy dirt to ground, standard Tooling Warehouse.
This device also is applicable to the board-like product that has the plane quality of fit to require that vertical storage area is big, utilizes this form of standing up to reach its resistance to deformation requirement.

Claims (5)

1. the storing unit of a large mold, it is characterized in that: a melt pit (7) is set on concrete foundation, be provided with at least three supporting bases (4) around the melt pit, the lead (3) that two upper ends are the inclined-plane is symmetricly set on supporting base (4) outside of melt pit (7) both sides, two bracing frames (1) are symmetricly set on two leads (3) outside, and the crossbeam of each bracing frame (1) is provided with the device that is used for the clamping mould.
2. the storing unit of large mold according to claim 1, it is characterized in that: supporting base (4), lead (3), bracing frame (1) are all fixedlyed connected with the built-in fitting (9) in the basis.
3. the storing unit of large mold according to claim 1 is characterized in that: the level of the upper surface of all supporting bases (4), highly consistent.
4. the storing unit of large mold according to claim 1, it is characterized in that: the inclined-plane of two leads (3) is connected with blade fin (10) in opposite directions on the inclined-plane.
5. the storing unit of large mold according to claim 1, it is characterized in that: the device that is used for the clamping mould is two grip slippers (2), and grip slipper (2) is connected on the crossbeam of bracing frame (1) by bolt respectively.
CN 200520033241 2005-02-03 2005-02-03 Large-sized die storage device Expired - Fee Related CN2770896Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 200520033241 CN2770896Y (en) 2005-02-03 2005-02-03 Large-sized die storage device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 200520033241 CN2770896Y (en) 2005-02-03 2005-02-03 Large-sized die storage device

Publications (1)

Publication Number Publication Date
CN2770896Y true CN2770896Y (en) 2006-04-12

Family

ID=36704682

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 200520033241 Expired - Fee Related CN2770896Y (en) 2005-02-03 2005-02-03 Large-sized die storage device

Country Status (1)

Country Link
CN (1) CN2770896Y (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109895045A (en) * 2019-04-29 2019-06-18 中信戴卡股份有限公司 A kind of lifting workbench

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109895045A (en) * 2019-04-29 2019-06-18 中信戴卡股份有限公司 A kind of lifting workbench

Similar Documents

Publication Publication Date Title
CN105421741B (en) A kind of self-supporting tower crane integrated operation platform system integrated with mould bases
CN114182635A (en) Walking type jacking formwork for high pier of thin-wall pier of bridge and construction method of walking type jacking formwork
CN107471413B (en) Automatic scaling device for internal mold of large square culvert
CN2770896Y (en) Large-sized die storage device
CN2770895Y (en) Movable dieframe for storing large-sized dies
CN211306246U (en) Lifting platform
CN116553405A (en) Supporting device for climbing of internal climbing type tower crane and climbing construction method thereof
CN104912322B (en) Early dismantling supporting system for plastic template and construction method thereof
CN207862973U (en) A kind of simple trolley formwork system of concrete pipe gallery
CN213625255U (en) Pier stud bent cap template strutting arrangement
CN215033370U (en) Cylinder cap pouring subassembly for diesel engine
CN210550791U (en) Street lamp mounting tool
CN214834824U (en) Large-scale modularization template demolding structure
CN210482577U (en) A prop up top circulation system for three-dimensional prefabricated full assembled concrete structure
CN211007650U (en) Steel mould for sinking type toilet inclined suspension mould
CN210507161U (en) Novel outer hanging anticollision barrier construction dolly
CN218291646U (en) Culvert head structure of culvert gate
CN217174374U (en) High mound walking type jacking die carrier of bridge thin wall pier
CN216640281U (en) Girder steel shore device of pier stud position for girder box bridge construction
CN218522366U (en) Bearing 2000T wine jar overhauls ditch
CN212053763U (en) Door and window mould
CN220723402U (en) Support device for climbing internal climbing type tower crane
CN220487095U (en) Automatic template for slope pouring
CN219826168U (en) T roof beam template is demolishd and is used support
CN214772812U (en) Prefabricated staircase mould subassembly

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20090220

Address after: No. 260, Jianxin East Road, Jiangbei District, Chongqing, China: 400023

Patentee after: Chongqing Changan Automobile Co., Ltd.

Address before: No. 260, Jianxin East Road, Jiangbei District, Chongqing, China: 400023

Patentee before: Chang'an Automobile (Group) Co., Ltd.

ASS Succession or assignment of patent right

Owner name: CHONGQING CHANG AN AUTOMOBILE CO., LTD.

Free format text: FORMER OWNER: CHANGAN AUTOMOBILE (GROUP) CO., LTD.

Effective date: 20090220

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20060412

Termination date: 20120203