CN2591092Y - 厂坝共用门机式水力发电站 - Google Patents
厂坝共用门机式水力发电站 Download PDFInfo
- Publication number
- CN2591092Y CN2591092Y CN02277724U CN02277724U CN2591092Y CN 2591092 Y CN2591092 Y CN 2591092Y CN 02277724 U CN02277724 U CN 02277724U CN 02277724 U CN02277724 U CN 02277724U CN 2591092 Y CN2591092 Y CN 2591092Y
- Authority
- CN
- China
- Prior art keywords
- dam
- power station
- factory building
- shared
- roof
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/20—Hydro energy
Landscapes
- Barrages (AREA)
Abstract
一种厂坝共用门机式水力发电站,包括电站厂房、泄水闸(坝)和起重门机,所述的泄水闸(坝)与电站厂房共用一根轨道梁,泄水闸(坝)闸顶与电站厂房房顶高程相同,在闸顶设有一台共用起重门机;电站厂房房顶对应发电机组相应位置开设有吊物孔,吊物孔上设有活动屋盖。具有降低电站厂房高程、减少一台起吊设备、运行管理方便、适用于航电和水电枢纽工程中。
Description
技术领域 本实用新型属于一种水力发电站,具体涉及水力发电站的结构及其布局的改进。
背景技术 航电和水电枢纽工程中,水力发电站一般包括电站厂房、泄水闸(或大坝)、通航建筑物三部分。由于厂房内机电设备安装和检修的需要,电站厂房内必须设置专用桥吊,设置专用桥吊后,因工作净空需要,厂房建筑高度一般较高。泄水闸顶因闸门等检修也需设置专用起重门机。目前均采用电站厂房和泄水闸(坝)各设置一台门(吊)机,这使得电站厂房建筑高度高,设备和土建投资费用大。
发明内容 本实用新型所要解决的技术问题是克服现有技术的不足,提供一种可降低电站厂房高程、减少一台起吊设备、节约土建和设备投资费用、运行管理方便、整个发电站坝顶布置简洁明快、协调美观的厂坝共用门机式水力发电站。
本实用新型解决其技术问题所采用的技术方案是:本实用新型的厂坝共用门机式水力发电站,包括电站厂房、泄水闸(坝)和起重门机等,其特征在于所述的泄水闸(坝)与电站厂房共用一根轨道梁,泄水闸(坝)闸顶与电站厂房房顶高程相同,在闸顶设有一台共用起重门机。
作为本实用新型的进一步改进,所述的电站厂房房顶对应发电机组相应位置开设有吊物孔,吊物孔上设有活动屋盖;活动屋盖两侧设置有滚轮,电站厂房房顶设有导梁,活动屋盖通过滚轮置于导梁上。
本实用新型的有益效果在于:泄水闸(坝)与电站厂房共用一台起重门机,减少了一台起吊设备,同时厂房建筑高度降低,节约了土建和设备投资费用,而且运营管理方便;泄水闸(坝)顶与电站厂房房顶采用统一顶高程后,整个发电站的坝顶布置简洁明快、协调美观。
附图说明
图1为本实用新型实施例的结构示意图;
图2为图1的俯视图;
图3为本实用新型实施例活动屋盖的安装示意图;
图4为图3的A-A剖视图。
图中各标号表示:1、泄水闸(坝),2、轨道梁,3、共用起重门机4、电站厂房,5、吊物孔,6、活动屋盖,7、滚轮,8、导梁。
具体实施方式 如图1、2所示,本实用新型中,泄水闸(坝)1与电站厂房4共用一根轨道梁2,泄水闸(坝)1闸顶与电站厂房4房顶高程相同,在闸顶设有一台共用起重门机3,共用起重门机3沿着轨道梁2可行驶到电站厂房4和泄水闸(坝)1的任一位置;电站厂房4房顶对应发电机组相应位置开设有吊物孔5,吊物孔5上设有活动屋盖6;如图3、4所示,该活动屋盖6两侧设置有滚轮7,电站厂房4房顶设有导梁8,活动屋盖6通过滚轮7置于导梁8上,可在导梁8上移动;当电站厂房4内需要起吊设备时,将共用起重门机3行驶到电站厂房4的起吊位置,移开房顶的活动屋盖6,即可进行起吊作业;当泄水闸(坝)1需要起吊闸门等设备时,可将共用起重门机3行驶到泄水闸(坝)1的相应起吊位置进行起吊作业。活动屋盖6可采用网架结构,其移动可采用电力驱动。
Claims (4)
1、一种厂坝共用门机式水力发电站,包括电站厂房(4)、泄水闸(坝)(1)和起重门机,其特征在于所述的泄水闸(坝)(1)与电站厂房(4)共用一根轨道梁(2),泄水闸(坝)(1)闸顶与电站厂房(4)房顶高程相同,在闸顶设有一台共用起重门机(3)。
2、根据权利要求1所述的厂坝共用门机式水力发电站,其特征在于所述的电站厂房(4)房顶对应发电机组相应位置开设有吊物孔(5),吊物孔(5)上设有活动屋盖(6)。
3、根据权利要求2所述的厂坝共用门机式水力发电站,其特征在于所述的活动屋盖(6)两侧设置有滚轮(7),电站厂房(4)房顶设有导梁(8),活动屋盖(6)通过滚轮(7)置于导梁(8)上。
4、根据权利要求2或3所述的厂坝共用门机式水力发电站,其特征在于所述的活动屋盖(6)为网架结构。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN02277724U CN2591092Y (zh) | 2002-11-22 | 2002-11-22 | 厂坝共用门机式水力发电站 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN02277724U CN2591092Y (zh) | 2002-11-22 | 2002-11-22 | 厂坝共用门机式水力发电站 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN2591092Y true CN2591092Y (zh) | 2003-12-10 |
Family
ID=33741250
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN02277724U Expired - Lifetime CN2591092Y (zh) | 2002-11-22 | 2002-11-22 | 厂坝共用门机式水力发电站 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN2591092Y (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102108694A (zh) * | 2010-12-14 | 2011-06-29 | 中国水电建设集团十五工程局有限公司 | 闸坝式水电站工程中门机轨道梁的吊装方法 |
CN102374106A (zh) * | 2011-09-04 | 2012-03-14 | 张昊慧 | 潮汐、江河发电站 |
CN112482316A (zh) * | 2020-10-21 | 2021-03-12 | 中铁二十局集团第六工程有限公司 | 闸坝门机梁施工方法及闸坝门机梁结构 |
-
2002
- 2002-11-22 CN CN02277724U patent/CN2591092Y/zh not_active Expired - Lifetime
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102108694A (zh) * | 2010-12-14 | 2011-06-29 | 中国水电建设集团十五工程局有限公司 | 闸坝式水电站工程中门机轨道梁的吊装方法 |
CN102108694B (zh) * | 2010-12-14 | 2012-05-30 | 中国水电建设集团十五工程局有限公司 | 闸坝式水电站工程中门机轨道梁的吊装方法 |
CN102374106A (zh) * | 2011-09-04 | 2012-03-14 | 张昊慧 | 潮汐、江河发电站 |
CN112482316A (zh) * | 2020-10-21 | 2021-03-12 | 中铁二十局集团第六工程有限公司 | 闸坝门机梁施工方法及闸坝门机梁结构 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206395349U (zh) | 一种半自动充气柜生产转移装置 | |
CN2591092Y (zh) | 厂坝共用门机式水力发电站 | |
CN202441047U (zh) | 一种曲面上的吊篮导向装置 | |
CN2586756Y (zh) | 厂坝共用门机式电站专用屋顶 | |
CN2591091Y (zh) | 泄水闸 | |
CN206211334U (zh) | 一种箱式变电站 | |
CN204875717U (zh) | 一种闸坝电站吊物孔兼作门库结构 | |
CN204238193U (zh) | 水电站地下厂房洞室装修结构 | |
CN202296732U (zh) | 一种轿顶安装式门机的加固结构 | |
CN203295978U (zh) | 风能发电装置与桥塔一体化结构 | |
CN218991073U (zh) | 一种新型光伏车棚 | |
CN207469305U (zh) | 综合管廊检修与逃生通道综合系统 | |
CN202049964U (zh) | 一种便于维修和拆换的建筑pv构件 | |
CN206180955U (zh) | 太阳能电池板维护系统及其维护设备 | |
CN210900174U (zh) | 一种环保净化机电设备机箱 | |
CN205998895U (zh) | 安装无人机停机坪的塔吊 | |
CN212506983U (zh) | 一种展翼式可开合屋盖结构 | |
CN209195103U (zh) | 一种带活动屋面的发电厂房结构 | |
CN210262965U (zh) | 水电站厂房主机间与安装间布置结构 | |
CN219690830U (zh) | 一种结构稳定的易装式幕墙 | |
CN202998956U (zh) | 一种光伏发电农业大棚安装系统 | |
CN211228403U (zh) | 应用于升船机、门机、启闭机孔洞的风琴式自控密封装置 | |
CN215888430U (zh) | 新型电厂循环水泵房结构 | |
CN210975748U (zh) | 一种应用于水利水电工程和景观工程中的自动升降式闸门 | |
CN204022310U (zh) | 一种超低净空双梁起重机小车 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CX01 | Expiry of patent term |