CN2486529Y - Internal climbing jacket frame lifting mechanism - Google Patents

Internal climbing jacket frame lifting mechanism Download PDF

Info

Publication number
CN2486529Y
CN2486529Y CN 01206614 CN01206614U CN2486529Y CN 2486529 Y CN2486529 Y CN 2486529Y CN 01206614 CN01206614 CN 01206614 CN 01206614 U CN01206614 U CN 01206614U CN 2486529 Y CN2486529 Y CN 2486529Y
Authority
CN
China
Prior art keywords
jacket frame
crossbeam
climbing jacket
jacking
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 01206614
Other languages
Chinese (zh)
Inventor
胡建锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 01206614 priority Critical patent/CN2486529Y/en
Application granted granted Critical
Publication of CN2486529Y publication Critical patent/CN2486529Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model relates to an internal climbing jacket frame hoist mechanism of tower crane, the characteristic is equipped with the promotion crossbeam in the standard festival on tower body upper portion, and the both ends of promoting the crossbeam are equipped with directive wheel and chain, and chain one end is fixed on the internal climbing jacket frame, and the other end passes the race, hangs down to the both sides of jacking crossbeam, and the leading truck is established to the below of internal climbing jacket frame, links to each other through hanging the steel sheet between two, establishes the couple at the both ends of entablature and jacking crossbeam, the utility model discloses utilize hydraulic jacking mechanism's jacking force as promoting power ingeniously, make the internal climbing jacket frame existing sufficient power supply at the lifting process, can steady promotion again.

Description

The inner climbing jacket frame lift system
The utility model relates to the inner climbing jacket frame lift system of tower crane auxiliary device, particularly a kind of internal-climbing tower crane.
Existing internal-climbing tower crane climbing device is divided into side jacking and two kinds of patterns of central jacking, adopt the tower machine of side jacking, climb in every once need successively upstairs to remove Hydraulic Station, hydraulic ram, in climb framework and bearing beam, not only labor strength is big, and the dismounting trouble, time-consuming.Need not move Hydraulic Station and hydraulic ram though adopt the tower machine of central jacking, but still climb framework, bearing beam and cat ladder in needing to remove in the dismounting, in order to climb framework and bearing beam in installing, often to do specific (special) requirements to the design and construction of elevator, both waste materials, increase cost again, so that have influence on promoting the use of of internally climbing tower crane.
Patent application (the patent No.: 98228957.X) that the applicant once proposed a kind of " internal-climbing tower crane climbing device ", by inner climbing jacket frame, hydraulic lifting mechanism, crossbeam, internal climbing foundation is formed, inner climbing jacket frame is a tower structure, both sides are provided with cat ladder, integral assembling is on body of the tower, body of the tower places in the elevator of building, this technical scheme has solved the problem that existing internally climbing tower crane climbing device exists preferably, but still find to exist some problems in the practice, as it is also unsatisfactory to promote inner climbing jacket frame mechanism, because the hoisting speed of winch is too fast, inner climbing jacket frame stability in the process of climbing is not enough, meet obstacle and can't in time find again and eliminating rapidly, cause accident to take place easily.
The purpose of this utility model is on the basis of existing internally climbing tower crane climbing device, problem at its existence, develop a kind of new internal-climbing tower crane inner climbing jacket frame lift system, the advantage in order to further bringing into play internally climbing tower crane makes it to be more widely used in high-building construction.
The purpose of this utility model is achieved through the following technical solutions:
The inner climbing jacket frame lift system is characterized in that:
A. be provided with the lifting crossbeam in the standard knot on body of the tower top, stretch out outside the body of the tower standard knot at the two ends that promote crossbeam, and its termination is equipped with wheel flutter;
B. wheel flutter is provided with chain, and an end of chain is fixed on two straight beams of inner climbing jacket frame, and the other end passes and turns to race, and hanging is to the both sides of jacking crossbeam;
C. below inner climbing jacket frame, be provided with guide frame, link to each other by hanging steel disc between inner climbing jacket frame and the guide frame;
D. be provided with hook at the two ends of entablatrance and jacking crossbeam.
Four jiaos at inner climbing jacket frame and guide frame are provided with track adjusting wheel.
According to the inner climbing jacket frame lift system that the utility model proposes, the top lift that utilizes hydraulic lifting mechanism dexterously is as promoting power, make inner climbing jacket frame existing enough propulsions source in lifting process, can promote by pulsation-free again, thereby can get rid of various obstacles and the resistance that runs in the inner climbing jacket frame lifting process effectively, save a twin drum winch and relevant electric equipment simultaneously, reach purpose safe and reliable and the reduction manufacturing cost.
Fig. 1 is the running condition scheme drawing that the utility model is used for internally climbing tower crane;
Fig. 2 is the structural representation of inner climbing jacket frame lift system.
The utility model will be further described according to accompanying drawing embodiment below:
As shown in Figure 1 and Figure 2, internal-climbing tower crane mainly by the internal-climbing tower crane pylom and in climb mechanism's two major parts and constitute.Wherein pylom by base, body of the tower, tower cap, crane arm, equilibrium arm and hoist, luffing, revolution and hydraulic mechanism etc. form.In climb mechanism and partly form by inner climbing jacket frame 13, hydraulic lifting mechanism 9, entablatrance 10, jacking crossbeam 8, internal climbing foundation 7 (forming), cat ladder 11 etc. with the transformation of pylom base.Inner climbing jacket frame 13 is a tower structure, and both sides are provided with cat ladder 11, and integral assembling is on body of the tower 14, and body of the tower 14 places in the elevator of building.In when climbing operation, internal climbing foundation 7, entablatrance 10, jacking crossbeam 8, hydraulic lifting mechanism 9 all climb with pylom, inner climbing jacket frame 13 and cat ladder 11 etc. then places outside the pylom, must use a kind of lift system that it is upwards promoted.
The inner climbing jacket frame lift system that the utility model proposed is exactly to climb on the mechanism basis in internally climbing tower crane is existing, for being provided with interior devices such as inner climbing jacket frame and cat ladder are upwards promoted when climbing operation, it is that (approximately apart from about 25 meters of tower machine bases) is provided with lifting crossbeam 1 in the standard knot on body of the tower 14 tops, stretch out outside the body of the tower standard knot at the two ends that promote crossbeam 1, its two ends all is equipped with wheel flutter 2, wheel flutter 2 is provided with chain 3, about about 35 meters of chain length, the one end is fixed on two straight beams of inner climbing jacket frame 13, the other end passes the race of wheel flutter 2, hanging is to the both sides of jacking crossbeam 8, guide frame 12 is set below inner climbing jacket frame 13, hanging steel disc 5 by four between inner climbing jacket frame 13 and the guide frame 12 links to each other, be provided with hook 6 at the two ends of entablatrance 10 and jacking crossbeam 8, the hook 6 of this example adopts short chain to be fixed in the two ends of entablatrance 10 and jacking crossbeam 8, hangs respectively during the jacking operation in the hole of people's chain 3, changes step to use for inner climbing jacket frame lifting and hydraulic pressure lift.
Four jiaos at inner climbing jacket frame 13 and guide frame 12 are provided with 12 track adjusting wheels 4 altogether, be installed in the straight beam inboard of inner climbing jacket frame and guide frame, corresponding up and down, the maintenance level rose when inner climbing jacket frame 13 was promoted, thereby made the cat ladder vertical uplift that is vertically mounted on the inner climbing jacket frame.
When being applied to promote, utilize hydraulic lifting mechanism 9 with the 8 downward jackings of jacking crossbeam, the hook 6 at jacking crossbeam 8 two ends tangles the lower ends downward of chain 3 and draws, at this moment, promote crossbeam 1 and born the downward top lift of piston rod in the hydraulic ram, turn to through wheel flutter 2 again, be delivered on the inner climbing jacket frame 13, inner climbing jacket frame is upwards promoted.Simultaneously, the cat ladder 11 that is fixed on 13 liang of straight beams of inner climbing jacket frame rises thereupon, and guide frame 12 also rises thereupon.
1~1.5 meter of the each jacking downwards of hydraulic ram, inner climbing jacket frame is just carried 1~1.5 meter by counter pulling on, and when jacking stops, hanging in the hole of both sides chain 3 with the hook at entablatrance 10 two ends, and chain is held, and makes the unlikely downslide of inner climbing jacket frame.Subsequently, starting hydraulic lifting mechanism 9 allows jacking cylinder drive on the jacking crossbeam 8 to carry, and the two ends of jacking crossbeam 8 hook taken out from the chain cylindrical void of being hung, treat that jacking cylinder all regains, when mentioning on the jacking crossbeam, again the two ends hook is hung in the chain cylindrical void, push up downwards about 10 centimetres, taking-up entablatrance two ends hang over the hook in the chain cylindrical void, have promptly finished changing step of a jacking.
After jacking is changed step several times, be about to inner climbing jacket frame and upwards promote 10--12 rice, concordant with the embedded box that is embedded in hoistway wall, at this moment, telescopic outrigger in inner climbing jacket frame two straight beams is pulled out the embedded box that places hoistway wall, just finished the lifting of an inner climbing jacket frame.

Claims (2)

1. inner climbing jacket frame lift system is characterized in that:
A. be provided with in the standard knot on body of the tower (14) top and promote crossbeam (1), stretch out outside the body of the tower standard knot at the two ends that promote crossbeam (1), and its termination is equipped with wheel flutter (2);
B. wheel flutter (2) is provided with chain (3), and an end of chain (3) is fixed on two straight beams of inner climbing jacket frame (13), and the other end passes wheel flutter (2) groove, and hanging is to the both sides of jacking crossbeam (8);
C. be provided with guide frame (12) in the below of inner climbing jacket frame (13), link to each other by hanging steel disc (5) between inner climbing jacket frame (13) and the guide frame (12);
D. be provided with hook (6) at the two ends of entablatrance (10) and jacking crossbeam (8).
2. inner climbing jacket frame lift system as claimed in claim 1 is characterized in that four jiaos at inner climbing jacket frame (13) and guide frame (12) are provided with track adjusting wheel (4).
CN 01206614 2001-06-19 2001-06-19 Internal climbing jacket frame lifting mechanism Expired - Fee Related CN2486529Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 01206614 CN2486529Y (en) 2001-06-19 2001-06-19 Internal climbing jacket frame lifting mechanism

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 01206614 CN2486529Y (en) 2001-06-19 2001-06-19 Internal climbing jacket frame lifting mechanism

Publications (1)

Publication Number Publication Date
CN2486529Y true CN2486529Y (en) 2002-04-17

Family

ID=33627215

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 01206614 Expired - Fee Related CN2486529Y (en) 2001-06-19 2001-06-19 Internal climbing jacket frame lifting mechanism

Country Status (1)

Country Link
CN (1) CN2486529Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101774512B (en) * 2009-11-12 2012-09-05 胡建锋 Electric hoisting mechanism of internally climbing tower crane
CN103950842A (en) * 2014-06-06 2014-07-30 徐州徐工液压件有限公司 Electric-hydraulic hybrid tower crane jacking system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101774512B (en) * 2009-11-12 2012-09-05 胡建锋 Electric hoisting mechanism of internally climbing tower crane
CN103950842A (en) * 2014-06-06 2014-07-30 徐州徐工液压件有限公司 Electric-hydraulic hybrid tower crane jacking system
CN103950842B (en) * 2014-06-06 2016-04-27 徐州徐工液压件有限公司 A kind of tower machine jack-up system of electrohydraulic mixed power

Similar Documents

Publication Publication Date Title
CN110104522B (en) Traction type construction lifter for folding roof beam and construction method thereof
CN201301179Y (en) Crawler crane self-dismounting device
CN203128062U (en) Roof crane
CN116119517B (en) Automatic anti-torsion device for port crane lifting appliance
CN201458560U (en) Hanging-type crane trolley
CN207671388U (en) Inflation film winder quickly up and down winding apparatus
CN210048319U (en) Traction type construction elevator with foldable top beam
CN107720569B (en) A kind of dismounting inner climbing crane tower is hung with masts type roofing
CN2486529Y (en) Internal climbing jacket frame lifting mechanism
CN212101590U (en) Full-automatic steel plate sucker energy-saving crane
CN103101847B (en) Tower type truss installing structure and method without cooperation with altitude hoisting equipment
CN203112386U (en) Tower type truss mounting structure without assistance of high altitude hoisting equipment
CN2224191Y (en) Self-lifting tower crane capable of carrying person
CN201762053U (en) Simple automatic derrick
CN2292781Y (en) Self-lifting device of lifter for gantry construction
CN201770429U (en) Portal type framework used for hoisting and slipping
CN201406825Y (en) Hanging basket for flue maintenance
CN210117158U (en) Boom nut mounting device for large-tonnage bridging machine
CN101774512B (en) Electric hoisting mechanism of internally climbing tower crane
CN2184684Y (en) Self lifting high speed derrick lift
CN2301428Y (en) Lower extension attached portal building lifter
CN201713235U (en) Tower crane jacket frame electric control device
CN2212037Y (en) Mulitfunction high speed wellhead by hydraulic lift
CN2057658U (en) Self-lifting type crane
CN201545634U (en) Electric hoisting mechanism of inner tower climbing machine

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20020417