CN2483420Y - Noval railway special sleppers for switches - Google Patents

Noval railway special sleppers for switches Download PDF

Info

Publication number
CN2483420Y
CN2483420Y CN 01249881 CN01249881U CN2483420Y CN 2483420 Y CN2483420 Y CN 2483420Y CN 01249881 CN01249881 CN 01249881 CN 01249881 U CN01249881 U CN 01249881U CN 2483420 Y CN2483420 Y CN 2483420Y
Authority
CN
China
Prior art keywords
sleeper
plate
switch
pillow
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 01249881
Other languages
Chinese (zh)
Inventor
熊学政
李伟
樊嘉谦
欧阳荣庆
林栋材
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Iron and Steel Group Corp
Original Assignee
Wuhan Iron and Steel Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Iron and Steel Group Corp filed Critical Wuhan Iron and Steel Group Corp
Priority to CN 01249881 priority Critical patent/CN2483420Y/en
Application granted granted Critical
Publication of CN2483420Y publication Critical patent/CN2483420Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Railway Tracks (AREA)

Abstract

The utility model relates to a new railway switch sleeper, mainly comprising concrete switch sleepers (1), steel frogs (2) and rails (3) which are arranged on the concrete switch sleepers (1), backing plates (4) which are arranged between concrete switch sleepers (1) and steel frogs (2) and rails (3); connecting holes (5) on the backing plates (4). The utility model is characterized in that a concrete switch sleeper (1) is spliced by two or three slab sleepers (6) and is shaped non-shoulder; a slab sleeper (6) has at least one lateral inner hole (7) at one end of the rail; the steel bar (8) whose length is longer than the slab sleeper (6) is arranged in the inner hole (7); every two slab sleepers (6) are connected by the steel plate (8) which is arranged on the steel bar (9) through the holes at the two ends.

Description

The novel railway switch tie
The utility model relates to railway sleeper, especially belongs to switch sleeper.
As everyone knows, the sleeper that is adopted on the railway has three kinds at present: a kind of is sleeper, and its deficiency is to need a large amount of timber, does not meet the Policy Conditions of the relevant environmental protection of country, and rots easily, and maintenance is also big; Another kind adopts that concrete is integral prefabricated to form, though this kind sleeper has solved the problem of not using timber, owing to be integral prefabricated forming, make train cause the middle part hogging moment of switch tie excessive under steam, thereby influence its application life, and its body weight, specification many (reaching tens of kinds), give make, transportation, installation, replacing bring many difficulties, and labour intensity and maintenance are also very big; Though also have a kind of short switch tie of radial type splicing of once attempting to adopt, because its connected mode is horizontal, railway roadbed stress can not be improved, still there is the excessive problem of middle part hogging moment of switch tie, so do not applied.
The purpose of this utility model is to provide the no hogging moment in a kind of switch tie middle part, long service life, few, the easy manufacturing of manufacturing specification, transportation, the novel railway switch tie of installation, replacing.
The purpose of this utility model is achieved in that and mainly comprises the concrete sleeper plate, be installed in railway frog and rail on the concrete sleeper plate, be connected backing plate between concrete sleeper plate and railway frog and the rail, connect the novel railway switch ties such as connecting hole on the backing plate, be on the switch tie, for making switch tie middle part hogging moment little, long service life, easily make, transportation, installation, change, employing is spliced its concrete sleeper plate and for there not being " shoulder " shape by 2 or 3 pillow plate, the pillow plate has at least an end proximal head place that one lateral bore is arranged, reinforcing bar is housed in the endoporus, reinforcing bar is longer than the width of pillow plate, steel plate by be arranged at hole on its two ends be contained on the reinforcing bar will be per two rest the head on plates and couple together.
For guaranteeing the distance between the track, can regulate by the position that is provided with of the connecting hole on steel plate or buckle and the pillow plate.
This novel railway switch tie middle part hogging moment is little, long service life, manufacturing specification few (only 6 kinds of specifications), easily make, transportation, installation, replacing, labour intensity is little, maintenance is little, locomotive operation is steady.
Description of drawings is as follows:
Fig. 1 is the structural representation of novel railway switch tie
Fig. 2 is a structural representation by two sections splicings for the novel railway switch tie
Fig. 3 is a structural representation by three sections splicings for the novel railway switch tie
Be described in further detail as follows below in conjunction with accompanying drawing:
Mainly comprise concrete sleeper plate (1), be installed in railway frog (2) and rail (3) on the concrete sleeper plate (1), be connected backing plate (4) between concrete sleeper plate (1) and railway frog (2) and the rail (3), connect the connecting hole novel railway switch ties such as (5) on the backing plate (4), be on the switch tie, for making switch tie middle part hogging moment little, long service life, easily make, transportation, installation, change, employing is that length each concrete sleeper plate (1) in 2.6 meters~3.4 meters sections of railway switch and coupling part concrete sleeper plate (1) is spliced by 2 blocks of pillow plates (6) at narrow place, turnout, and the length of every block of pillow plate (6) is 1/2nd of every concrete sleeper plate of its section (1) total length.In this section, every block of pillow plate (6) only has an end to be embedded with a lateral bore (7) from the end, and reinforcing bar (8) is housed in the endoporus (7), and both belong to secure fit.And owing to length difference, so the pre-buried distance of vertical endoporus (7) from the end is 30~50 millimeters at every concrete sleeper plate of this section (1).The length that pillow plate (6) is stretched out at reinforcing bar (8) two ends is 20~25 millimeters, steel plate (9) by be embedded in hole (10) on its two ends be fixedly hinged reinforcing bar (8) go up will be per two rest the head on plates (6) and couple together.
The length that at wide place, turnout is railway frog and guard rail part concrete sleeper plate (1) is in 3.6 meters~4.8 meters sections, every concrete sleeper plate (1) is spliced by 3 blocks of pillow plates (6), and the length of every block of pillow plate (6) is 1/3rd of every required concrete sleeper plate (1) total length.In this section, every block of pillow plate (6) at every concrete sleeper plate (1) two ends only has an end to be embedded with a lateral bore (7) from the end, and middle pillow plate (6) two ends all are embedded with lateral bore (7) far from the end.Equally, reinforcing bar (8) is housed in the endoporus (7), both belong to secure fit.And owing to length difference, so the pre-buried distance of vertical endoporus (7) from the end is 30~50 millimeters at every concrete sleeper plate of this section (1).The length that pillow plate (6) is stretched out at reinforcing bar (8) two ends is 20~25 millimeters, steel plate (9) by be embedded in hole (10) on its two ends be fixedly hinged reinforcing bar (8) go up will be per two rest the head on plates (6) and couple together.Adopting bolt to be connected between rail (3) or railway frog (2) and pillow plate (6) is connected on the backing plate (4).Every root is nothing " shoulder " shape by the concrete sleeper plate (1) that pillow plate (6) splices.For guaranteeing the distance between the track, regulate with the set position of resting the head on the connecting hole (12) on the plate (6) by steel plate (9) or buckle (11).Note,, then just can't change again in case this set positions is good.

Claims (4)

1, the novel railway switch tie, mainly comprise concrete switch sleeper (1), be installed in railway frog (2) and rail (3) on the concrete switch sleeper (1), backing plate (4) between concrete switch sleeper (1) and railway frog (2) and the rail (3), connecting hole (5) on the backing plate (4) etc., it is characterized in that on the switch tie, its concrete switch sleeper (1) is by 2 or 3 blocks of pillow plates (6) are spliced and be nothing " shoulder " shape, pillow plate (6) has at least an end sleeper head place that one lateral bore (7) is arranged, reinforcing bar (8) is housed in the endoporus (7), reinforcing bar (8) is longer than the width of pillow plate (6), steel plate (9) by be arranged at hole (10) on its two ends be contained in reinforcing bar (8) go up will be per two rest the head on plates (6) and couple together.
2, novel railway switch tie according to claim 1, it is characterized in that being spliced by 2 blocks of pillow plates (6), and the length of every block of pillow plate (6) can be 1/2nd of required concrete switch sleeper (1) total length at every concrete switch sleeper of changing points and coupling part (1).
3, novel railway switch tie according to claim 1, it is characterized in that being spliced by 3 blocks of pillow plates (6), and the length of every block of pillow plate (6) can be 1/3rd of required concrete switch sleeper (1) total length at track switch railway frog and every concrete switch sleeper of guard rail part (1).
4, novel railway switch tie according to claim 1, the position that it is characterized in that resting the head on the connecting hole (12) on the plate (6) are to need to set according to the position that concrete switch sleeper (1) is connected with railway frog (2).
CN 01249881 2001-06-20 2001-06-20 Noval railway special sleppers for switches Expired - Fee Related CN2483420Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 01249881 CN2483420Y (en) 2001-06-20 2001-06-20 Noval railway special sleppers for switches

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 01249881 CN2483420Y (en) 2001-06-20 2001-06-20 Noval railway special sleppers for switches

Publications (1)

Publication Number Publication Date
CN2483420Y true CN2483420Y (en) 2002-03-27

Family

ID=33660156

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 01249881 Expired - Fee Related CN2483420Y (en) 2001-06-20 2001-06-20 Noval railway special sleppers for switches

Country Status (1)

Country Link
CN (1) CN2483420Y (en)

Similar Documents

Publication Publication Date Title
US5181657A (en) Composite rubber/concrete railroad grade crossing system
CN207091835U (en) A kind of cast-in-place sleeper plate-type ballastless track
CN2758309Y (en) Prestressed concrete rail board
CN202208869U (en) Symmetrical three-throw turnout for line rails of urban rail transit engineering
CN2758310Y (en) Biblock type rail bearing
CN2483420Y (en) Noval railway special sleppers for switches
CN101880994B (en) Replacing technology for special track switch
CN210134294U (en) Switch structure of track line turnout area
CN202073037U (en) Bridge ballastless track structure
CN200940241Y (en) Concrete switch sleeper used for ballast-free rail switch
CN217324965U (en) Face track laying base bridge that combines forever
CN216156258U (en) Railway track supporting structure
CN212000396U (en) New Zealand steel rail and track gauge No. 7.5 compound intersection
CN203229867U (en) Manipulator for replacing and demounting elastic locking strip of bridge expansion device
CN201144380Y (en) Crossing track plate
CN211922092U (en) Double-block sleeper for mounting quick elastic strip fastener
CN205999787U (en) A kind of track structure suitable for high-speed railway bridge
CN2372353Y (en) Bolt-free adjustable safety rail connected on steel rail
CN213447888U (en) No. 6 intersection points of 60kg/m steel rail
CN110205875A (en) Existing Railway Line double crossover integrally inserts paving construction method
CN209722634U (en) A kind of prefabricated whole crossing plates structure in special purpose railroad level crossing location
CN220132665U (en) Railway switch frog backing plate
CN108625230A (en) A kind of pin-connected panel railway entirety crossing plates pillow
US2652981A (en) Railway crossing
CN216761759U (en) A switch ware mounting base for concrete sleeper

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20020327