CN2424371Y - Underground burning boiler - Google Patents

Underground burning boiler Download PDF

Info

Publication number
CN2424371Y
CN2424371Y CN 00211753 CN00211753U CN2424371Y CN 2424371 Y CN2424371 Y CN 2424371Y CN 00211753 CN00211753 CN 00211753 CN 00211753 U CN00211753 U CN 00211753U CN 2424371 Y CN2424371 Y CN 2424371Y
Authority
CN
China
Prior art keywords
chamber
combustion chamber
underground
combustion
ash
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 00211753
Other languages
Chinese (zh)
Inventor
张学忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 00211753 priority Critical patent/CN2424371Y/en
Application granted granted Critical
Publication of CN2424371Y publication Critical patent/CN2424371Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Solid-Fuel Combustion (AREA)
  • Incineration Of Waste (AREA)

Abstract

The utility model relates to an underground combustion boiler, which comprises an underground operating chamber and an underground ash falling chamber between which two side walls are arranged and a combustion chamber arranged with calandrias at the top and the bottom. A uniformly air-dispersing chamber is arranged below the combustion chamber. The upper end of the operating chamber is provided with a top cover of an inlet communicated with the ground and the lower end of the operating chamber is provided with a draught chamber blocked by a bottom board. A smoke vent is arranged between the upper part of the combustion chamber and the ash falling chamber. The ash falling chamber is provided with a flue which is communicated with a draught fan. A cold water tank, a hot water tank and an expansion water tank which are connected with pipelines are respectively arranged at the upper end of the combustion chamber. A hot water device and a heating device are respectively connected with the pipelines. The utility model has the advantages of simple structure, convenient operation, small ground occupation, energy saving, and good heating effect.

Description

Underground burning boiler
The utility model relates to a kind of burner, particularly relates to a kind of underground combustion furnace.
At present, the boiler heat supplying that the warming heat supply generally adopts the large-sized boiler room to be provided with, above-mentioned practice floor space is big, and the burning coal consumption is big, and the thermal efficiency is low, and volume of smoke is discharged contaminated environment.
It is a kind of simple in structure, easy to operate that the purpose of this utility model is to provide, and the consumption coal is few, the underground combustion furnace that the thermal efficiency is high.
In order to achieve the above object, the technical solution adopted in the utility model is: the combustion chamber that is provided with the two side between the operating room of underground setting and the ash-falling chamber and comb is installed up and down, the below of combustion chamber is provided with equal air compartment, the operating room upper end is provided with and ground inlet communicating loam cake, the lower end is provided with the draft chamber that is cut off by base plate, has exhaust opening between top, combustion chamber and the ash-falling chamber; Ash-falling chamber is provided with the flue that communicates with air-introduced machine, and the upper end, combustion chamber is respectively equipped with cold water storage cistern, boiler, the expansion tank that links to each other with pipeline, is connected to hot water apparatus and heating plant on the pipeline respectively.
The utility model has the advantages that:
Simple in structure, easy to operate, floor space is little, and the consumption coal is few, and thermal efficiency height in the underground ash-falling chamber of the flue dust collecting after the burning, has reduced the pollution to environment.
Description of drawings:
Fig. 1 is a structural representation of the present utility model.
Below in conjunction with accompanying drawing the utility model structural representation is described in further detail.
As shown in Figure 1, the utility model is the combustion chamber 2 that is provided with the two side and comb 4 is installed up and down between the operating room 1 of underground setting and ash-falling chamber 3, the below of combustion chamber 2 is provided with equal air compartment 16, operating room 1 upper end is provided with and ground inlet communicating loam cake 5, the lower end is provided with the draft chamber 6 that is cut off by base plate 7, has exhaust opening between 2 tops, combustion chamber and the ash-falling chamber 3; Ash-falling chamber 3 is provided with the flue 8 that communicates with air-introduced machine, and 2 upper ends, combustion chamber are respectively equipped with cold water storage cistern 9, boiler 10, the expansion tank 11 that links to each other with pipeline, are connected to hot water apparatus 12 and heating plant 13 on the pipeline respectively.
Be provided with actuating doors 14 between described combustion chamber 2 and the operating room 1.
Be provided with lighting-up tuyere 17 between described equal air compartment 16 and the draft chamber 6.
Described flue 8 is provided with regulating gate 18.
The sidewall of described operating room 1 is provided with the top and has the air intake passage 15 that shutter 19 communicates with draft chamber 6.
Operation principle of the present utility model:
When using the utility model, respectively opening operation room cover plate and combustion chamber advance the coal ash door, fire coal is placed in the combustion chamber, then, close into coal ash door, open the cover plate of upper end, draft chamber, by lighting-up tuyere, the coal in the ignition combustion chamber, build draft chamber and operating room cover plate, combustion chamber coal combustion heat supply, once igniting can move 20-30 days, and heat can be by regulating gate, shutter and air-introduced machine control heating load size at ordinary times.

Claims (5)

1, a kind of underground combustion furnace, form by the heating installation that pipeline connects, it is characterized in that: be provided with the two side between operating room of underground setting (1) and the ash-falling chamber (3) and the combustion chamber (2) of comb (4) is installed up and down, the below of combustion chamber (2) is provided with equal air compartment (16), operating room (1) upper end is provided with and ground inlet communicating loam cake (5), the lower end is provided with the draft chamber (6) that is cut off by base plate (7), has exhaust opening between (2) top, combustion chamber and the ash-falling chamber (3); Ash-falling chamber (3) is provided with the flue (8) that communicates with air-introduced machine, and combustion chamber (2) upper end is respectively equipped with cold water storage cistern (9), boiler (10), the expansion tank (11) that links to each other with pipeline, is connected to hot water apparatus (12) and heating plant (13) on the pipeline respectively.
2, according to the described underground combustion furnace of claim 1, it is characterized in that; Be provided with actuating doors (14) between combustion chamber (2) and the operating room (1).
3, according to the described underground combustion furnace of claim 1, it is characterized in that: all be provided with lighting-up tuyere (17) between air compartment (16) and draft chamber (6).
4, according to the described underground combustion furnace of claim 1, it is characterized in that: flue (8) is provided with regulating gate (18).
5, according to the described underground combustion furnace of claim 1, it is characterized in that: the sidewall of operating room (1) is provided with the top and has the air intake passage (15) that shutter (19) communicates with draft chamber (6).
CN 00211753 2000-04-30 2000-04-30 Underground burning boiler Expired - Fee Related CN2424371Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 00211753 CN2424371Y (en) 2000-04-30 2000-04-30 Underground burning boiler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 00211753 CN2424371Y (en) 2000-04-30 2000-04-30 Underground burning boiler

Publications (1)

Publication Number Publication Date
CN2424371Y true CN2424371Y (en) 2001-03-21

Family

ID=33578395

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 00211753 Expired - Fee Related CN2424371Y (en) 2000-04-30 2000-04-30 Underground burning boiler

Country Status (1)

Country Link
CN (1) CN2424371Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103968414A (en) * 2014-05-22 2014-08-06 北京蓝天瑞德环保技术股份有限公司 Automatic control device of basement boiler room air inlet amount
CN106439988A (en) * 2016-11-09 2017-02-22 北京瑞特爱能源科技股份有限公司 Building-integrated electrode heating and heat storage device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103968414A (en) * 2014-05-22 2014-08-06 北京蓝天瑞德环保技术股份有限公司 Automatic control device of basement boiler room air inlet amount
CN106439988A (en) * 2016-11-09 2017-02-22 北京瑞特爱能源科技股份有限公司 Building-integrated electrode heating and heat storage device

Similar Documents

Publication Publication Date Title
CN2424371Y (en) Underground burning boiler
CN1321857A (en) Underground combustion furnace
CN200958786Y (en) Energy-saving cooker
CN2921598Y (en) Energy-saving environment protection gasification boiler
CN214223402U (en) Energy-saving boiler
CN2375878Y (en) Energy-saving efficient combustion stove and range
CN2767895Y (en) Intelligently controlled household boiler adapted to multiple fuels
CN2416428Y (en) Horizontal coal heating water boiler
CN2470751Y (en) Coal-burning boiler
CN201081400Y (en) Indirect air-flow hot-blast stove
CN2542928Y (en) Quick-heating efficient smokeless evaporation coal-saving boiler
CN2310940Y (en) Low-pressure energy-saving household heating stove
CN2532417Y (en) Coal combustion hot-blast stove
CN2431526Y (en) Horizontal briquette boiler for heating water
CN205747481U (en) A kind of burned multi-pass boiler
CN2694132Y (en) Double blowing type heating stove
CN2283817Y (en) Controllable internal ventilating combustion-supporting energy-saving boiler
CN2380858Y (en) Smokeless environment-protective furnace
CN2636111Y (en) Blasting charcoal/coal furnace
CN2585118Y (en) Caol-fired automatic hot-air stove
CN2472141Y (en) Smoke eliminating and dust collecting coal combustor
CN2062013U (en) Dual-direction burner
CN2524168Y (en) Synergistic energy-saving boiler
CN2457470Y (en) Civil energy saving stove
CN2320912Y (en) Civil heating boiler

Legal Events

Date Code Title Description
C57 Notification of unclear or unknown address
DD01 Delivery of document by public notice

Addressee: Zhang Xuezhong

Document name: Notice of cost mitigation

C14 Grant of patent or utility model
GR01 Patent grant
C57 Notification of unclear or unknown address
DD01 Delivery of document by public notice

Addressee: Zhang Xuezhong

Document name: Notice of termination

C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee