CN2412964Y CN 00216347 CN00216347U CN2412964Y CN 2412964 Y CN2412964 Y CN 2412964Y CN 00216347 CN00216347 CN 00216347 CN 00216347 U CN00216347 U CN 00216347U CN 2412964 Y CN2412964 Y CN 2412964Y
Authority
CN
China
Prior art keywords
steel pipe
high bar
pulley
wire rope
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 00216347
Other languages
Chinese (zh)
Inventor
赵卫东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 00216347 priority Critical patent/CN2412964Y/en
Application granted granted Critical
Publication of CN2412964Y publication Critical patent/CN2412964Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to a multi-sectional high rod artificial installation device, which adopts a steel pipe which is provided with a demountable and movable annular buckle as a main component. The movable annular buckle on the steel pipe is tied with a steel cable, and is connected with a hoister through a pulley wheel. Small rings on the bottom and the top of the steel pipe can be tied with the steel cable to be connected with the pulley wheel which is fixed on the ground. Then, stable operation can be kept. A lifting ring on the upper part of the steel pipe is used for lifting a high rod. The utility model adopts the mode that the steel pipe and the high rod to be loaded are fastened and lifted section by section to realize installation, with the advantages of simple structure, convenient and safe construction, and the reduction of state investment cost. The utility model can adapt to various places where topographic conditions are poor to carry out the installation and construction of communication circuits and power circuits.

Description

The artificial erecting device of the high bar of multistage
The artificial erecting device of the high bar of a kind of multistage can be used for communicating by letter, the installation of the high bar circuit of department such as electric power, belongs to homework department's elevator, lifting appliance technical field.
Along with the continuous development of science and technology, every construction of country rapidly advances, and has occurred the high bar of various rigidity of grafting segmenteds such as many 40 meters, 50 meters, 60 meters at home, is widely used in communication, departments such as electric power.In the prior art, the general method that all adopts the machinery lifting of high bar is installed, not only the cost height also is subjected to the restriction of fabricating yard, the place that high bar is set up is corresponding to be restricted, and produces wasting of resources phenomenon thus, has also pind down the development of communication, electric utility.
The purpose of this utility model is to provide the high bar of the succinct multistage of a kind of convenience artificial erecting device, makes it with low cost, construction safety, and the high bar that can adapt to various occasions is installed.
For realizing such purpose, it is critical piece that the utility model adopts the steel pipe that has detachable movable latch closure, is equipped with pulley and wire rope, takes to tighten up installation, lifting mode realization installation smoothly piecemeal with high bar to be installed.
The steel pipe length that the utility model adopts is not limit, and can be formed by connecting with flange for whole steel pipe yet, and generally at 10~20 meters long, diameter of steel tube requires to decide according to the construction object, generally at 150mm~250mm.A little ring is arranged at the steel pipe bottom, connects a pulley by wire rope on the ring, during work this pulley is fixed on the ground, and the assurance operation is steadily carried out.Steel pipe top also has a little ring, connects pulley respectively by several wire rope in case of necessity and fixes on the ground, increases the operation stationarity.In the bottom of steel pipe (general 5~10 meters), around steel pipe several dismountable movable latch closures are arranged, can slide up and down at steel pipe when loosening, can maintain static when tightening up, be with wire rope on one of them latch closure and connect a pulley, this pulley is fixed on the high bar that is mounted during construction, and wire rope links to each other with ground hoist engine by pulley.The also available wire rope of movable latch closure substitutes.
When on-the-spot high bar is installed, the little ring in steel pipe bottom is fixed on the ground by the pulley that wire rope connects, the detachable loose collar in steel pipe bottom is buckled the pulley that connects with wire rope be fixed on the high bar to be installed, and steel pipe is fixed tightly in movable latch closure or wire rope with high bar to be installed.Hoist engine drags wire rope, and steel pipe and high bar are holded up simultaneously.After first section high bar is in place, unclamps steel pipe and make it and upwards climb, the pulley that connects by the little ring of the steel pipe top second section high bar of slinging, and utilization activity latch closure tightens up steel pipe with it, carry out the 3rd section high bar after being in place again and install, and so forth, until finishing integral installation.
For understanding the technical solution of the utility model better, be further described below in conjunction with accompanying drawing.
Fig. 1 is structure of the present utility model and installation exercise schematic diagram.
As shown in the figure, steel pipe 3 has several detachable movable latch closures 4, is connected with steel cable on the movable latch closure 4, connects ground hoist engine 10 by pulley 8, and pulley 8 is fixed on when operation on the high bar 9 of multistage.A little ring 6 is arranged at steel pipe 3 bottoms, is the pulley 7 that is fastened on ground with wire rope, to keep the steady of steel pipe 3.Suspension ring 2 are arranged at the top of steel pipe 3, are used to lift by crane high bar section 5 to be installed, and a little ring 1 is also arranged at the top of steel pipe 3, can mix several wire rope where necessary, is fastened on the pulley on ground, and are steady with the lifting of high bar section 5 to be installed to guarantee steel pipe 3.Several dismountable movable latch closures 4 are arranged in the bottom of steel pipe 3, can tighten up motionlessly, the sliding up and down of steel pipe 3, be with wire rope on the movable latch closure 4 and connect the hoist engine 10 on ground by pulley 8 in the time of also can loosening.During construction pulley 8 is fixed on the high bar 9.The also available wire rope of movable latch closure 4 substitutes.
When on-the-spot high bar is installed, the little ring 6 in steel pipe 3 bottoms is fixed on the ground by the pulley 7 that wire rope connects, the pulley 8 that the detachable movable latch closure 4 usefulness wire rope in steel pipe 3 bottoms are connected is fixed on the high bar to be installed, and steel pipe 3 is fixed tightly in movable latch closure 4 or wire rope with high bar to be installed.Hoist engine 10 drags wire rope, and steel pipe 3 and high bar are holded up simultaneously.After first section high bar is in place, unclamp the movable latch closure 4 of steel pipe and steel pipe 3 is upwards climbed, utilize steel pipe top suspension ring 2 to connect the pulleys second section high bar of slinging again, and steel pipe 3 is tightened up with it with movable latch closure 4, carrying out the 3rd section high bar after being in place again installs, and so forth, until finishing integral installation.
The utility model is simple in structure, cost of investment is low, easy construction safety, be suitable on the mountain top, little roadside, and various vehicles can't open into or the relatively poor place construction of orographic condition such as resident Ji Mi district, make the installation of telecommunication circuit, power circuit not limited by geographical conditions, reduce the government investment cost.

Claims (2)

1, the artificial erecting device of the high bar of a kind of multistage, it is characterized in that detachable movable latch closure 4 is arranged on the steel pipe 3, be wire rope to be arranged and connect hoist engine 10 on the movable latch closure 4 by pulley 8, little ring 6 is arranged at steel pipe 3 bottoms, system is fastened on the pulley 7 on ground with wire rope, suspension ring 2 are arranged at steel pipe 3 tops, and little ring 1 is arranged at the top.
2, a kind of as the artificial erecting device of the high bar of the said multistage of claim 1, it is characterized in that said detachable movable latch closure 4 can substitute with wire rope.
CN 00216347 2000-01-28 2000-01-28 Multi-sectional high pole artificial mounting device Expired - Fee Related CN2412964Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 00216347 CN2412964Y (en) 2000-01-28 2000-01-28 Multi-sectional high pole artificial mounting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 00216347 CN2412964Y (en) 2000-01-28 2000-01-28 Multi-sectional high pole artificial mounting device

Publications (1)

Publication Number Publication Date
CN2412964Y true CN2412964Y (en) 2001-01-03

Family

ID=33582103

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 00216347 Expired - Fee Related CN2412964Y (en) 2000-01-28 2000-01-28 Multi-sectional high pole artificial mounting device

Country Status (1)

Country Link
CN (1) CN2412964Y (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101701499B (en) * 2009-10-30 2011-07-27 中国一冶集团有限公司 Hoisting method for mounting steel chimney tower
CN102635265A (en) * 2012-05-11 2012-08-15 辽宁省电力有限公司盘锦供电公司 Buffer
WO2015106481A1 (en) * 2014-01-16 2015-07-23 于佩 Nodular cast iron inserting-connection tower rods
CN105133916A (en) * 2015-09-26 2015-12-09 国网青海省电力公司 Auxiliary hanging bracket for mounting of upper frame on telegraph pole
CN105781218A (en) * 2016-03-24 2016-07-20 中铁十局集团有限公司 Hoisting construction method for steel column in construction of protective support for existing overcrossing railway
CN107013080A (en) * 2015-11-13 2017-08-04 高世龙 A kind of power network electric pole erection construction method
CN111620254A (en) * 2020-06-10 2020-09-04 中国电建集团山东电力建设有限公司 Torch tube lifting and mounting system and method
CN111779349A (en) * 2020-05-22 2020-10-16 嘉兴恒创电力设计研究院有限公司平湖分公司 Convenient tower mounting device and method

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101701499B (en) * 2009-10-30 2011-07-27 中国一冶集团有限公司 Hoisting method for mounting steel chimney tower
CN102635265A (en) * 2012-05-11 2012-08-15 辽宁省电力有限公司盘锦供电公司 Buffer
CN102635265B (en) * 2012-05-11 2014-07-09 辽宁省电力有限公司盘锦供电公司 Buffer
WO2015106481A1 (en) * 2014-01-16 2015-07-23 于佩 Nodular cast iron inserting-connection tower rods
CN105133916A (en) * 2015-09-26 2015-12-09 国网青海省电力公司 Auxiliary hanging bracket for mounting of upper frame on telegraph pole
CN107013080A (en) * 2015-11-13 2017-08-04 高世龙 A kind of power network electric pole erection construction method
CN105781218A (en) * 2016-03-24 2016-07-20 中铁十局集团有限公司 Hoisting construction method for steel column in construction of protective support for existing overcrossing railway
CN105781218B (en) * 2016-03-24 2018-08-17 中铁十局集团有限公司 The construction method for hanging of steel column in upper spanning existing railway protective stent construction
CN111779349A (en) * 2020-05-22 2020-10-16 嘉兴恒创电力设计研究院有限公司平湖分公司 Convenient tower mounting device and method
CN111620254A (en) * 2020-06-10 2020-09-04 中国电建集团山东电力建设有限公司 Torch tube lifting and mounting system and method

Similar Documents

Publication Publication Date Title
CN2412964Y (en) Multi-sectional high pole artificial mounting device
CN102022019B (en) A kind of method of complex terrain route split tower erection
CN201010459Y (en) Flexible attaching device used for tower crane body
CN105794587B (en) Fixing device and mounting method for transplanting tree body of hydropower engineering old big tree
CN209896574U (en) High-altitude line sliding operation platform
CN211113194U (en) Bracket-free hoisting swing system for steel box girder in shallow beach area of suspension bridge
CN212050266U (en) Self-climbing crane for fan
CN210723967U (en) Auxiliary tool for replacing 35-110kV strain single-string insulator
CN110512910A (en) A kind of steel-making main building height integrally increases installation method across steel construction
CN106564819B (en) A kind of heavy loop wheel machine peculiar to vessel and underwater mounting process
CN201343379Y (en) Crane used for maintenance of large-size wind power equipment
CN212612005U (en) Aerial work platform for cylindrical pier construction
CN211110944U (en) Hoisting tool for converter valve anode reactor
CN112777496A (en) Climbing type wind power generation hoisting crane
CN210313389U (en) Hanging flower basket system that transversely slides
CN209780257U (en) Steel structure high altitude construction device
CN205972979U (en) Wheel hub transports frock
CN208516758U (en) A kind of lightweight flange ring transfer device
CN214220652U (en) Fixing device for assembling and disassembling cross beam
CN215711084U (en) Hoisting structure of horizontal water turbine generator set
CN217840807U (en) Suspension cage for steel structure welding
CN217705550U (en) Portable quick detach dress tower wagon specialized tool case of track traffic contact net
CN216240042U (en) Holding pole standing device
CN215926943U (en) Transmission line steel pipe tower ring-shaped steel rib horizontal installation adjusting device
CN218397982U (en) Electric power overhauls operation panel

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee