CN221837726U - Support-free assembled integral high-rise reinforced concrete frame structure - Google Patents

Support-free assembled integral high-rise reinforced concrete frame structure Download PDF

Info

Publication number
CN221837726U
CN221837726U CN202420122500.1U CN202420122500U CN221837726U CN 221837726 U CN221837726 U CN 221837726U CN 202420122500 U CN202420122500 U CN 202420122500U CN 221837726 U CN221837726 U CN 221837726U
Authority
CN
China
Prior art keywords
cast
prefabricated
support
reinforced concrete
frame structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202420122500.1U
Other languages
Chinese (zh)
Inventor
崔伯臻
李靓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuhai Huafa City Research Institute Co ltd
Original Assignee
Zhuhai Huafa City Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhuhai Huafa City Research Institute Co ltd filed Critical Zhuhai Huafa City Research Institute Co ltd
Priority to CN202420122500.1U priority Critical patent/CN221837726U/en
Application granted granted Critical
Publication of CN221837726U publication Critical patent/CN221837726U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

本实用新型公开了一种免撑装配整体式高层钢筋混凝土框架结构,包括现浇混凝土柱;所述现浇混凝土柱的顶部设置有现浇柱帽;所述现浇柱帽的顶部设置有两个预制主梁,且两个预制主梁位于同一直线上;两个预制主梁的一侧上均安装有预应力双T板;所述预应力双T板的顶部设置有现浇叠合层。该实用新型实现主要结构构件全预制装配,减少现场湿作业,减少现场施工劳动力的需求,满足快速施工、绿色低碳的导向;土建施工实现全过程免撑,减少脚手架安装和拆除的巨大工作量;预制构件主要为框架主梁+预应力双T板,相对于传统做法规避了预制次梁,减少了一道工艺流程,且预应力双T板能实现大跨度的布置,充分发挥了其使用效果。

The utility model discloses a support-free assembled integral high-rise reinforced concrete frame structure, including cast-in-place concrete columns; the top of the cast-in-place concrete columns is provided with cast-in-place column caps; the top of the cast-in-place column caps is provided with two prefabricated main beams, and the two prefabricated main beams are located on the same straight line; prestressed double T-plates are installed on one side of the two prefabricated main beams; the top of the prestressed double T-plates is provided with cast-in-place overlapping layers. The utility model realizes the full prefabrication and assembly of the main structural components, reduces on-site wet operations, reduces the demand for on-site construction labor, and meets the guidance of rapid construction, green and low-carbon; the civil construction realizes the whole process of support-free, reducing the huge workload of scaffolding installation and removal; the prefabricated components are mainly frame main beams + prestressed double T-plates, which avoid prefabricated secondary beams compared to traditional practices, reduce a process flow, and the prestressed double T-plates can achieve large-span layout, giving full play to their use effect.

Description

一种免撑装配整体式高层钢筋混凝土框架结构A support-free assembled integral high-rise reinforced concrete frame structure

技术领域Technical Field

本实用新型涉及建筑施工技术领域,具体为一种免撑装配整体式高层钢筋混凝土框架结构。The utility model relates to the technical field of building construction, in particular to a support-free assembled integral high-rise reinforced concrete frame structure.

背景技术Background Art

相比民用建筑,工业建筑(厂房、仓库和停车场等)功能简单,基本为混凝土框架结构,柱网规整,平面、立面变化较少,无特殊的造型要求,构件标准化程度较高,模具成本较低,规避高支模;再加上大规模建设的通用厂房把标准化推到了高位,大开间、统一平面、标准化,因此装配建造在高层厂房建设中能发挥其先天优势。Compared with civil buildings, industrial buildings (factories, warehouses and parking lots, etc.) have simple functions, are basically concrete frame structures, have regular column grids, few changes in plan and elevation, no special modeling requirements, a high degree of standardization of components, low mold costs, and avoidance of high formwork; in addition, large-scale construction of general factories has pushed standardization to a high level, with large bays, unified planes, and standardization, so prefabricated construction can play its inherent advantages in the construction of high-rise factories.

目前装配式混凝土框架结构的预制构件的常用做法,一般为预制柱安装、脚手架支撑系统安装、预制主梁安装、预制次梁安装、预制叠合板安装、现浇钢筋混凝土施工、脚手架支撑系统拆除等操作;该装配方案存在以下问题:At present, the common practices for prefabricated components of prefabricated concrete frame structures are generally prefabricated column installation, scaffolding support system installation, prefabricated main beam installation, prefabricated secondary beam installation, prefabricated composite slab installation, cast-in-place reinforced concrete construction, and scaffolding support system removal. This assembly plan has the following problems:

一是脚手架支撑系统安装和拆除需要花费较多的人力物力、较长的时间,未能充分发挥装配式建造方式的优势;First, the installation and removal of the scaffolding support system requires a lot of manpower and material resources and a long time, which fails to give full play to the advantages of the prefabricated construction method;

二是对于一些楼层较高的建筑,搭建脚手架支撑系统难度较高,施工成本高;Second, for some high-rise buildings, it is difficult to build a scaffolding support system and the construction cost is high;

三是楼盖结构体系涉及有预制主梁、预制次梁及叠合板多种规格,施工次序较多;Third, the floor structure system involves prefabricated main beams, prefabricated secondary beams and composite slabs of various specifications, and there are many construction sequences;

四是目前针对高层框架结构采用装配式的案例较少。Fourth, there are currently few cases of using prefabricated structures for high-rise frame structures.

实用新型内容Utility Model Content

本实用新型的目的在于提供一种免撑装配整体式高层钢筋混凝土框架结构,以解决上述背景技术中提出的问题。The purpose of the utility model is to provide a support-free assembled integral high-rise reinforced concrete frame structure to solve the problems raised in the above-mentioned background technology.

为实现上述目的,本实用新型提供如下技术方案:一种免撑装配整体式高层钢筋混凝土框架结构,包括现浇混凝土柱;To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a support-free assembled integral high-rise reinforced concrete frame structure, including cast-in-place concrete columns;

所述现浇混凝土柱的顶部设置有现浇柱帽;A cast-in-place column cap is provided on the top of the cast-in-place concrete column;

所述现浇柱帽的顶部设置有两个预制主梁,且两个预制主梁位于同一直线上;Two prefabricated main beams are arranged on the top of the cast-in-place column cap, and the two prefabricated main beams are located on the same straight line;

两个预制主梁的一侧上均安装有预应力双T板;Prestressed double T-plates are installed on one side of the two prefabricated main beams;

所述预应力双T板的顶部设置有现浇叠合层。A cast-in-place laminated layer is arranged on the top of the prestressed double T-plate.

优选的,所述预制主梁上设置有橡胶支座,且预应力双T板安装在橡胶支座上。Preferably, a rubber bearing is provided on the prefabricated main beam, and the prestressed double T-plate is installed on the rubber bearing.

优选的,所述预应力双T板的顶部设置有叠合层钢筋,预制主梁顶部设置有面筋,叠合层钢筋和面筋上现浇叠合层。Preferably, a laminated layer of steel bars is provided on the top of the prestressed double T-plate, a surface reinforcement is provided on the top of the prefabricated main beam, and a laminated layer is cast on the laminated layer of steel bars and the surface reinforcement.

优选的,所述预制主梁为L型结构,且预应力双T板设置在预制主梁的水平端上。Preferably, the prefabricated main beam is an L-shaped structure, and the prestressed double T-plate is arranged on the horizontal end of the prefabricated main beam.

优选的,所述现浇柱帽为正方形结构。Preferably, the cast-in-place column cap is a square structure.

优选的,所述预应力双T板的底部设置有两个加强板。Preferably, two reinforcing plates are provided at the bottom of the prestressed double T-plate.

与现有技术相比,本实用新型的有益效果是:Compared with the prior art, the beneficial effects of the utility model are:

1.实现主要结构构件全预制装配,减少现场湿作业,减少现场施工劳动力的需求,满足快速施工、绿色低碳的导向;1. Realize full prefabrication and assembly of main structural components, reduce on-site wet work, reduce the demand for on-site construction labor, and meet the guidance of rapid construction, green and low-carbon;

2.土建施工实现全过程免撑,减少脚手架安装和拆除的巨大工作量;2. The whole process of civil construction is free of support, which reduces the huge workload of scaffolding installation and removal;

3.预制构件主要为框架主梁+预应力双T板,相对于传统做法规避了预制次梁,减少了一道工艺流程,且预应力双T板能实现大跨度的布置,充分发挥了其使用效果;3. The prefabricated components are mainly frame main beams + prestressed double T-plates. Compared with the traditional method, the prefabricated secondary beams are avoided, a process flow is reduced, and the prestressed double T-plates can achieve large-span layout, giving full play to their use effect;

4.免撑装配整体式高层钢筋混凝土框架结构体系,结构高度接近50m,为后续高层框架装配做法提供了案例参考。4. The support-free assembled integral high-rise reinforced concrete frame structure system has a structure height of nearly 50m, providing a case reference for subsequent high-rise frame assembly practices.

附图说明BRIEF DESCRIPTION OF THE DRAWINGS

图1为本实用新型平面结构示意图;Fig. 1 is a schematic diagram of the planar structure of the utility model;

图2为本实用新型三维示意图;Figure 2 is a three-dimensional schematic diagram of the utility model;

图3为本实用新型梁柱节点结构示意图;Figure 3 is a schematic diagram of the beam-column node structure of the utility model;

图4为本实用新型梁板节点结构示意图。FIG4 is a schematic diagram of the beam-slab node structure of the utility model.

图中:1-现浇混凝土柱;2-预制主梁;3-预应力双T板;4-现浇柱帽;5-橡胶支座;6-现浇叠合层。In the figure: 1- cast-in-place concrete column; 2- precast main beam; 3- prestressed double T-plate; 4- cast-in-place column cap; 5- rubber bearing; 6- cast-in-place composite layer.

具体实施方式DETAILED DESCRIPTION

下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

请参阅图1-4,本实用新型提供一种技术方案:一种免撑装配整体式高层钢筋混凝土框架结构,包括现浇混凝土柱1;Please refer to Figures 1-4. The utility model provides a technical solution: a support-free assembled integral high-rise reinforced concrete frame structure, including a cast-in-place concrete column 1;

现浇混凝土柱1的顶部设置有现浇柱帽4;A cast-in-place column cap 4 is provided on the top of the cast-in-place concrete column 1;

现浇柱帽4的顶部设置有两个预制主梁2,且两个预制主梁2位于同一直线上;Two prefabricated main beams 2 are arranged on the top of the cast-in-place column cap 4, and the two prefabricated main beams 2 are located on the same straight line;

两个预制主梁2的一侧上均安装有预应力双T板3;Prestressed double T-plates 3 are installed on one side of the two prefabricated main beams 2;

预应力双T板3的顶部设置有现浇叠合层6。A cast-in-place laminate layer 6 is provided on the top of the prestressed double T-slab 3 .

结合图4所示,预制主梁2上设置有橡胶支座5,且预应力双T板3安装在橡胶支座5上。As shown in FIG. 4 , a rubber support 5 is provided on the prefabricated main beam 2 , and the prestressed double T-plate 3 is installed on the rubber support 5 .

结合图1、4所示,预应力双T板3的顶部设置有叠合层钢筋,预制主梁2顶部设置有面筋,叠合层钢筋和面筋上现浇叠合层6。As shown in Figures 1 and 4, a laminated layer of steel bars is arranged on the top of the prestressed double T-slab 3, a surface bar is arranged on the top of the prefabricated main beam 2, and a laminated layer 6 is cast on the laminated layer of steel bars and the surface bar.

结合图2所示,预制主梁2为L型结构,且预应力双T板3设置在预制主梁2的水平端上。As shown in FIG. 2 , the prefabricated main beam 2 is an L-shaped structure, and the prestressed double T-plate 3 is arranged on the horizontal end of the prefabricated main beam 2 .

结合图1-3所示,现浇柱帽4为正方形结构,预应力双T板3的底部设置有两个加强板。As shown in FIGS. 1-3 , the cast-in-place column cap 4 is a square structure, and two reinforcing plates are provided at the bottom of the prestressed double T plate 3 .

本实用新型工作原理:通过设置多个现浇框架柱1,在现浇框架柱1的顶部现浇柱帽4,在现浇柱帽4的顶部四角位置均设置预制主梁2,预制主梁2上安装预应力双T板3,在预应力双T板3和预制主梁2上现浇叠合层6。The working principle of the utility model is as follows: a plurality of cast-in-place frame columns 1 are arranged, column caps 4 are cast-in-place on the top of the cast-in-place frame columns 1, prefabricated main beams 2 are arranged at the four corners of the top of the cast-in-place column caps 4, prestressed double T-plates 3 are installed on the prefabricated main beams 2, and a cast-in-place composite layer 6 is arranged on the prestressed double T-plates 3 and the prefabricated main beams 2.

因框架柱重量较大,在高层结构中吊装较为不便,故框架柱采用现浇形式,也规避了预制柱安装阶段套筒灌浆的质量风险;对楼盖结构体系,采用预制主梁+预应力双T板形式,真正意义上实现快速安装+免模板+免支撑+免次梁的装配体系,从而实现工期更优、安装便捷的目的。As the frame columns are heavy and it is inconvenient to hoist them in high-rise structures, the frame columns are cast in place, which also avoids the quality risk of sleeve grouting during the installation stage of prefabricated columns. For the floor structure system, prefabricated main beams + prestressed double T-plates are adopted to truly realize a quick installation + formwork-free + support-free + secondary beam-free assembly system, thereby achieving a better construction period and convenient installation.

本说明书中未作详细描述的内容属于本领域专业技术人员公知的现有技术,尽管已经示出和描述了本实用新型的实施例,对于本领域的普通技术人员而言,可以理解在不脱离本实用新型的原理和精神的情况下可以对这些实施例进行多种变化、修改、替换和变型,本实用新型的范围由所附权利要求及其等同物限定。The contents not described in detail in this specification belong to the prior art known to professional and technical personnel in the field. Although the embodiments of the utility model have been shown and described, it is understandable to those of ordinary skill in the art that various changes, modifications, substitutions and variations may be made to these embodiments without departing from the principle and spirit of the utility model. The scope of the utility model is defined by the attached claims and their equivalents.

Claims (6)

1. The utility model provides a support-free assembled integral high-rise reinforced concrete frame structure which characterized in that: comprises a cast-in-situ concrete column (1);
A cast-in-situ column cap (4) is arranged at the top of the cast-in-situ concrete column (1);
The top of the cast-in-situ column cap (4) is provided with two prefabricated main beams (2), and the two prefabricated main beams (2) are positioned on the same straight line;
One side of each prefabricated girder (2) is provided with a pre-stress double T plate (3);
The top of the prestressed double-T plate (3) is provided with a cast-in-situ lamination layer (6).
2. A support-free assembled monolithic high-rise reinforced concrete frame structure as defined in claim 1, wherein: the prefabricated girder (2) is provided with a rubber support (5), and the prestress double-T plate (3) is arranged on the rubber support (5).
3. A support-free assembled monolithic high-rise reinforced concrete frame structure as defined in claim 1, wherein: the top of the prestressed double-T plate (3) is provided with a superposed layer steel bar, the top of the prefabricated main beam (2) is provided with gluten, and a superposed layer (6) is cast in situ on the superposed layer steel bar and the gluten.
4. A support-free assembled monolithic high-rise reinforced concrete frame structure as defined in claim 1, wherein: the prefabricated girder (2) is of an L-shaped structure, and the prestressed double-T plate (3) is arranged at the horizontal end of the prefabricated girder (2).
5. A support-free assembled monolithic high-rise reinforced concrete frame structure as defined in claim 1, wherein: the cast-in-situ column cap (4) is of a square structure.
6. A support-free assembled monolithic high-rise reinforced concrete frame structure as defined in claim 1, wherein: two reinforcing plates are arranged at the bottom of the pre-stress double-T plate (3).
CN202420122500.1U 2024-01-18 2024-01-18 Support-free assembled integral high-rise reinforced concrete frame structure Active CN221837726U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202420122500.1U CN221837726U (en) 2024-01-18 2024-01-18 Support-free assembled integral high-rise reinforced concrete frame structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202420122500.1U CN221837726U (en) 2024-01-18 2024-01-18 Support-free assembled integral high-rise reinforced concrete frame structure

Publications (1)

Publication Number Publication Date
CN221837726U true CN221837726U (en) 2024-10-15

Family

ID=92998035

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202420122500.1U Active CN221837726U (en) 2024-01-18 2024-01-18 Support-free assembled integral high-rise reinforced concrete frame structure

Country Status (1)

Country Link
CN (1) CN221837726U (en)

Similar Documents

Publication Publication Date Title
CN1298946C (en) Steel-steel concrete fully prefabricated assembling structure
CN105089178B (en) A kind of pre-splicing Standard formula building of prefabricated steel reinforced concrete shear walls
CN101173542A (en) Two-way steel-laminated slab concrete composite floor
CN211473051U (en) Prestressed truss wallboard and wall body manufactured by using same
CN111206680B (en) Combined floor system frame structure building system
CN103306374B (en) Long-span Multi-storey Frame degree public building and industrial premises assembling Integral box type structure and preparation method
CN111305439A (en) Laminated slab with disassembly-free die steel frame
CN105040879A (en) Regular-hexagon honeycomb grid floor structure and method for manufacturing same
CN108360722B (en) A prefabricated large module semi-welded composite beam-slab structure with temporary support of plane truss
CN202530614U (en) Cast-in-situ steel mesh concrete slab
CN102635235B (en) Method for cast-in-place of ferrocement panel by spliced net frame suspension template
CN108867991A (en) Precast concrete insulation board, modular architectural unit and production method based on UHPC
CN110777998A (en) Building floor and combined floor system
CN108999326A (en) Light steel grating concrete folding plate
WO2019072119A1 (en) Modular building for civil use
CN209603378U (en) A Multi-Cavity Rectangular Steel Tube Concrete Special-shaped Column Structure
CN116411702A (en) Construction Method of Long-span Reinforced Concrete Horizontal Members
CN221837726U (en) Support-free assembled integral high-rise reinforced concrete frame structure
CN207714507U (en) The assembled architecture component system of a set of novel dismountable
CN212897158U (en) Assembled multi-ribbed composite horizontal warehouse and horizontal warehouse wall
CN202202413U (en) Rectangular steel tube concrete special-shaped column and steel beam frame corner node
CN108086474A (en) Prefabricated reinforced concrete convex support body for prefabricated buildings
CN108978854A (en) One kind being bolted Precast Concrete Frame
CN204919932U (en) Assemble integral non -reinforced concrete ribbed floor
CN109881781B (en) A fire-resistant glulam frame system based on recycled concrete and its construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant