CN221589679U - Precast angle steel foundation of charging pile equipment and processing positioning device thereof - Google Patents

Precast angle steel foundation of charging pile equipment and processing positioning device thereof Download PDF

Info

Publication number
CN221589679U
CN221589679U CN202323386894.6U CN202323386894U CN221589679U CN 221589679 U CN221589679 U CN 221589679U CN 202323386894 U CN202323386894 U CN 202323386894U CN 221589679 U CN221589679 U CN 221589679U
Authority
CN
China
Prior art keywords
support
bolt
support frame
charging pile
upper connecting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202323386894.6U
Other languages
Chinese (zh)
Inventor
张勋锋
李雪锋
李斌
刘俊虎
史亚丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shanxi Sijian Group Co Ltd
Original Assignee
China Shanxi Sijian Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shanxi Sijian Group Co Ltd filed Critical China Shanxi Sijian Group Co Ltd
Priority to CN202323386894.6U priority Critical patent/CN221589679U/en
Application granted granted Critical
Publication of CN221589679U publication Critical patent/CN221589679U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model belongs to the technical field of angle steel foundations, and in particular relates to a prefabricated angle steel foundation of charging pile equipment and a processing and positioning device thereof, which comprises the following components: the upper connecting support frame is a rectangular frame, bolt connecting holes connected with the charging pile equipment are formed in the upper connecting support frame, at least two bolt connecting holes are formed in the upper connecting support frame, and the bolt connecting holes are waist-shaped holes; the bendable baffle is arranged below the bolt connection hole; one end of the bendable baffle is fixedly connected with the lower surface of the upper connecting support frame, the middle part of the bendable baffle can be bent, and a support part for supporting a bolt can be formed after bending; the four support columns are arranged, and the tops of the four support columns are fixedly connected with the upper connecting support frame; the bolt used for being connected with the charging pile is inserted into the corresponding bolt connecting hole, then the middle part of the bendable baffle plate can be bent, a supporting part used for supporting the bolt can be formed after bending, and then the bolt is supported, so that the installation is convenient.

Description

Precast angle steel foundation of charging pile equipment and processing positioning device thereof
Technical Field
The utility model belongs to the technical field of angle steel foundations, and particularly relates to a prefabricated angle steel foundation of charging pile equipment and a processing and positioning device thereof.
Background
The foundation of the new energy automobile charging pile is generally formed by casting concrete once, a cable tube is required to be pre-buried in the concrete foundation in advance, if the cable tube is not reserved before casting, the cable tube is irrecoverable after casting is completed, foundation positioning is required to be carried out for many times before earthwork excavation and before concrete casting, maintenance of the concrete foundation is carried out after casting, and the final plastering and surface collecting work is carried out, so that the manufacturing period is long, and the finished product is poor in attractiveness.
For this reason, patent application number 202122869227.8 discloses a lightweight assembled charging pile foundation, which adopts a prefabricated structure arrangement, and all parts are produced in a standardized way through factories, so that the quality is stable and reliable; the installation is carried out through an on-site assembly type construction process, and large-scale mechanical auxiliary construction is not needed.
Although the structure is arranged, the pouring of concrete is avoided, and bolts connected with the charging piles can be pre-buried in advance in the concrete pouring process; when the structure is adopted, bolt holes are required to be formed in the angle steel frame, and due to the limitation of the positions of the bolt holes, the angle steel frame is supported by hands when being installed with a charging pile, otherwise, the angle steel frame falls off, so that certain inconvenience exists during installation.
Disclosure of utility model
In view of the above technical problems, an aspect of the present utility model is to provide a prefabricated angle steel foundation for a charging pile device, which is convenient for connection with a bolt of a charging pile; on the other hand, the aim at provides a processing positioner who conveniently processes this angle steel basis.
In order to solve the technical problems, the utility model adopts the following technical scheme:
A precast angle steel foundation of a charging pile device, comprising:
The upper connecting support frame is a rectangular frame, bolt connecting holes connected with the charging pile equipment are formed in the upper connecting support frame, at least two bolt connecting holes are formed in the upper connecting support frame, and the bolt connecting holes are waist-shaped holes;
the bendable baffle is arranged below the bolt connection hole; one end of the bendable baffle is fixedly connected with the lower surface of the upper connecting support frame, the middle part of the bendable baffle can be bent, and a support part for supporting a bolt can be formed after bending;
the four support columns are arranged, and the tops of the four support columns are fixedly connected with the upper connecting support frame;
The column feet are provided with connecting holes, and the bottoms of the supporting columns are fixedly connected with one column foot;
the shrouding, the shrouding is equipped with two, and two shrouding are fixed respectively in the front and back both sides of upper junction support frame.
The upper connecting support frame is formed by welding four angle steels.
The sealing plate is fixedly connected with the upper connecting support frame in a riveting mode.
The sealing plate adopts a steel plate.
The processing positioning device comprises a supporting table and four supporting legs, wherein the four supporting legs are fixedly connected with the supporting table; the upper connecting support frame is placed on the support table, the four support columns are respectively spliced with the corresponding support legs, and the support legs are respectively provided with corresponding slots.
And the four supporting legs are respectively provided with a fixing frame, and a space exists between two adjacent side edges of the fixing frames and the supporting legs, and the space forms a slot.
The bottoms of the supporting legs are connected with adjusting supporting bolts through threads, and the bottoms of the column bases are contacted with the corresponding adjusting supporting bolts.
Compared with the prior art, the utility model has the beneficial effects that:
the bolt used for being connected with the charging pile is inserted into the corresponding bolt connecting hole, then the middle part of the baffle plate which can be bent, a supporting part used for supporting the bolt can be formed after bending, and then the bolt is supported, so that the installation of the bolt is convenient.
Through being provided with processing positioner, can conveniently carry out the location between each support column and the last connection braced frame, be convenient for weld.
Drawings
FIG. 1 is a schematic structural view of embodiment 1 of the present utility model;
FIG. 2 is a schematic structural view of a bendable baffle of embodiment 1 of the present utility model;
FIG. 3 is an enlarged view of a portion of FIG. 2 at A;
FIG. 4 is a schematic diagram of a bending state of a bendable baffle in embodiment 1 of the present utility model;
FIG. 5 is a partial enlarged view at B in FIG. 4;
FIG. 6 is a cross-sectional view of embodiment 1 of the present utility model;
FIG. 7 is an enlarged view of a portion of FIG. 6 at C;
fig. 8 is a schematic structural view of embodiment 2 of the present utility model;
FIG. 9 is a schematic view showing the use state of embodiment 2 of the present utility model;
Wherein: 1 is an upper connecting support frame, 2 is a bendable baffle, 3 is a vertical part, 4 is a support part, 5 is a bolt, 6 is a bolt connecting hole, 7 is a support column, 8 is a column foot, 9 is a sealing plate, 10 is a connecting hole, 11 is a support table, 12 is a supporting leg, 13 is a slot, 14 is a fixed frame, and 15 is an adjusting support bolt.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely, and it is apparent that the described embodiments are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
As shown in fig. 1 to 7, a prefabricated angle steel foundation of a charging pile device comprises an upper connecting support frame 1, a support upright post 7 and a sealing plate 9. The upper connecting support frame 1 is a rectangular frame and is used for being connected with the charging pile equipment; on which there are provided bolting holes 6 for connection with the charging pile device, the bolting holes 6 being provided with at least two. The bolt connection hole 6 is preferably a waist-shaped hole. And a bendable baffle plate 2 is arranged below the bolt connecting holes 6. The two sealing plates 9 are arranged, and the two sealing plates 9 are respectively fixed on the front side and the rear side of the upper connecting support frame 1.
The four support columns 7 are arranged, and the tops of the four support columns 7 are fixedly connected with the upper connecting support frame 1; a column base 8 is fixedly connected to the bottom of each supporting column 7, and each column base 8 is provided with a connecting hole 10.
During installation, the bolts 5 are respectively inserted into the corresponding bolt connecting holes 6, then the middle part of the bendable baffle plate 2 can be bent, and a supporting part 4 for supporting the bolts 5 can be formed after bending; at the same time, a vertical portion 3 is also formed, the vertical portion 3 being in contact with the head of the bolt 5, thereby restricting its rotation. Then, the expansion bolts 5 corresponding to the connection holes 10 of the column base 8 are implanted on the ground, and the whole is fixed on the ground by screwing nuts on the expansion bolts 5. And finally, placing the charging pile equipment on the upper connecting support frame 1, enabling the bolts 5 to pass through the reserved through holes of the charging pile equipment, and screwing nuts on the bolts 5 after passing through the through holes.
Further, the upper connecting support frame 1 is formed by welding four angle steels; meanwhile, the supporting upright post 7 can also adopt angle steel.
Further, the sealing plate 9 is preferably fixedly connected to the upper connection support frame 1 by caulking.
Further, the material of the sealing plate 9 is preferably steel plate.
The structure arrangement in the above embodiment 1 requires ensuring that each support post 7 is aligned with the upper connection support frame 1 and then welding and combining the same during processing; the supporting upright post 7 is required to be supported by hands in the welding combination process, so that certain inconvenience exists in the welding process. In order to facilitate processing, the present embodiment provides a processing positioning device.
As shown in fig. 8 and 9, the support comprises a support table 11 and support legs 12, wherein four support legs 12 are arranged, and the four support legs 12 are fixedly connected with the support table 11; the upper connecting support frame 1 is placed on the support table 11, the four support columns 7 are respectively spliced with corresponding support legs 12, and corresponding slots 13 are formed in each support leg 12. Specifically, the four sides in the upper connecting support frame 1 are attached to the four sides outside the support table 11.
During welding and assembling, the four support columns 7 are respectively inserted into the slots 13 of the corresponding support legs 12, and the inner surfaces of the support columns 7 are attached to the outer surfaces of the corresponding support legs 12; then the upper connection support frame 1 is placed on the support table 11; at this time, the top of the upper connecting support frame 1 is attached to the lower surfaces of the four support columns 7, so that welding and combination can be performed.
Further, the slot 13 may be implemented in various structures, such as: the four support legs 12 are provided with fixing frames 14, and two adjacent sides of the fixing frames 14 are spaced from the support legs 12, and the space forms a slot 13.
Further, the bottom of each leg 12 is connected with an adjusting support bolt 15 through threads, and the bottom of each support column 7 is contacted with the corresponding adjusting support bolt 15. The extension length of each adjusting support bolt 15 can be adjusted according to the needs, so that after each support upright post 7 is spliced, the upper planes of the support upright posts 7 are positioned on the same horizontal plane, and the upper connecting support frame 1 is attached to each four support upright posts 7.
The preferred embodiments of the present utility model have been described in detail, but the present utility model is not limited to the above embodiments, and various changes can be made within the knowledge of those skilled in the art without departing from the spirit of the present utility model, and the various changes are included in the scope of the present utility model.

Claims (7)

1. Fill electric pile equipment prefabricated angle steel basis, a serial communication port, include:
The upper connection support frame (1), wherein the upper connection support frame (1) is a rectangular frame, bolt connection holes (6) connected with the charging pile equipment are formed in the upper connection support frame, at least two bolt connection holes (6) are formed in the upper connection support frame, and the bolt connection holes (6) are waist-shaped holes;
The bendable baffle plate (2) is arranged below the bolt connecting holes (6); one end of the bendable baffle plate (2) is fixedly connected with the lower surface of the upper connecting support frame (1), the middle part of the bendable baffle plate (2) can be bent, and a support part (4) for supporting a bolt (5) can be formed after bending;
The four support columns (7) are arranged, and the tops of the four support columns (7) are fixedly connected with the upper connecting support frame (1);
The column bases (8) are provided with connecting holes (10), and the bottoms of the supporting columns (7) are fixedly connected with one column base (8);
The two sealing plates (9) are arranged, and the two sealing plates (9) are respectively fixed on the front side and the rear side of the upper connecting support frame (1).
2. A precast angle iron foundation for a charging pile device according to claim 1, characterized in that the upper connection support frame (1) consists of four angle iron welds.
3. The prefabricated angle steel foundation of the charging pile equipment according to claim 1, wherein the sealing plate (9) is fixedly connected with the upper connecting supporting frame (1) in a riveting mode.
4. A precast angle foundation for a charging pile device according to any one of claims 1 or 3, characterized in that the closing plate (9) is made of steel plate.
5. A machine-positioning device for use in a prefabricated angle base according to claim 1, wherein: the support comprises a support table (11) and support legs (12), wherein the support legs (12) are provided with four support legs (12) which are fixedly connected with the support table (11); the upper connecting support frame (1) is placed on the support table (11), the four support columns (7) are respectively spliced with the corresponding support legs (12), and the support legs (12) are respectively provided with corresponding slots (13).
6. A tooling positioning apparatus according to claim 5, wherein: the four support legs (12) are respectively provided with a fixed frame (14), and a space is reserved between two adjacent side edges of the fixed frames (14) and the support legs (12), and the space forms a slot (13).
7. A tooling positioning apparatus according to claim 5, wherein: the bottoms of the supporting legs (12) are connected with adjusting supporting bolts (15) through threads, and the bottoms of the column bases (8) are contacted with the corresponding adjusting supporting bolts (15).
CN202323386894.6U 2023-12-13 2023-12-13 Precast angle steel foundation of charging pile equipment and processing positioning device thereof Active CN221589679U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202323386894.6U CN221589679U (en) 2023-12-13 2023-12-13 Precast angle steel foundation of charging pile equipment and processing positioning device thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202323386894.6U CN221589679U (en) 2023-12-13 2023-12-13 Precast angle steel foundation of charging pile equipment and processing positioning device thereof

Publications (1)

Publication Number Publication Date
CN221589679U true CN221589679U (en) 2024-08-23

Family

ID=92404288

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202323386894.6U Active CN221589679U (en) 2023-12-13 2023-12-13 Precast angle steel foundation of charging pile equipment and processing positioning device thereof

Country Status (1)

Country Link
CN (1) CN221589679U (en)

Similar Documents

Publication Publication Date Title
CN214195730U (en) Combined workshop steel structure
CN202117074U (en) Foundation bed steel structure for positioning and mounting base of tower crane
CN114482691B (en) Assembled airport enclosure foundation template and use method thereof
CN221589679U (en) Precast angle steel foundation of charging pile equipment and processing positioning device thereof
CN210013342U (en) Connecting device for green fabricated building light steel wall and foundation
CN216740588U (en) Large-span telescopic scaffold
CN216740781U (en) Small-size steel stand positioner
CN216713346U (en) Energy-concerving and environment-protective type house construction is with steel construction node component
CN216766217U (en) Steel construction container formula house column base connected node device
CN111472536B (en) Template support, steel template and spliced single-side vertical die structure
CN113898224A (en) Construction method of assembled steel-concrete structure ladder stand
CN212453822U (en) Swimming pool steel bounding wall structure
CN111561073B (en) High-rise building shear wall barrel overhanging wall cap building structure system
CN211735785U (en) Assembly type building main structure convenient to install
CN209837287U (en) Steel beam and steel plate shear wall, otic placode, angle steel stud welding connection structure
CN211201306U (en) Steel construction that transformer substation used
CN211571774U (en) Prefabricated foundation structure of screen cabinet
CN218813934U (en) Steel pipe micro pile underpins and consolidates deviation correcting device with basis
CN216516159U (en) Peripheral revetment body braced system of fast-assembling
CN216515138U (en) Box girder assembling support
CN216974098U (en) Scaffold for building engineering
CN217500293U (en) Prefabricated square pile and photovoltaic support
CN216713332U (en) Staple bolt steel bracket exempts from support system can be dismantled to assembled beam column
CN221895931U (en) Modularized spliced house building module for house living
CN219431022U (en) Full-assembled modularized building node connection structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant