CN221072666U - Based on BIM foundation ditch support string net guniting strutting arrangement - Google Patents

Based on BIM foundation ditch support string net guniting strutting arrangement Download PDF

Info

Publication number
CN221072666U
CN221072666U CN202322531946.8U CN202322531946U CN221072666U CN 221072666 U CN221072666 U CN 221072666U CN 202322531946 U CN202322531946 U CN 202322531946U CN 221072666 U CN221072666 U CN 221072666U
Authority
CN
China
Prior art keywords
support
bim
guniting
frame
shaped
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322531946.8U
Other languages
Chinese (zh)
Inventor
陈磊
夏新兵
台航迪
刘震宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Wokeman Construction Engineering Co ltd
Original Assignee
Henan Wokeman Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Wokeman Construction Engineering Co ltd filed Critical Henan Wokeman Construction Engineering Co ltd
Priority to CN202322531946.8U priority Critical patent/CN221072666U/en
Application granted granted Critical
Publication of CN221072666U publication Critical patent/CN221072666U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Catching Or Destruction (AREA)

Abstract

The utility model discloses a BIM-based foundation pit supporting and screening guniting supporting device, which comprises an I-shaped frame, rollers and inclined baffle plates, wherein the rollers are arranged at the bottom of the I-shaped frame, supports are vertically arranged at two sides behind the I-shaped frame, a support column penetrates through the top of the support column, the inclined baffle plates are arranged below the support column, the front end of the I-shaped frame is provided with a front end baffle plate, the middle part of the I-shaped frame is connected with an inserting plate in a sliding manner, the support is connected below the front end of the inserting plate through a lifting rope, and the end part of the spray pipe is fixed with the support through a positioning rope. According to the utility model, the front end baffle plate and the inclined baffle plate are arranged, so that the top of an edge slope can be shielded, pollution to surrounding buildings during guniting construction is avoided, the hanging rope is arranged at the lower end of the inserting plate, the support is connected to the bottom of the hanging rope, the hanging rope can be fixed with the end part of the spray pipe, the burden of double arms of a worker is relieved, and the hanging type spraying type grouting device is convenient to use, simple to operate and easy to popularize.

Description

Based on BIM foundation ditch support string net guniting strutting arrangement
Technical Field
The utility model relates to a net hanging and guniting support assembly, in particular to a net hanging and guniting support device based on BIM foundation pit support, and belongs to the technical field of slope construction.
Background
The hanging net guniting is also called a landslide protection net, is used for relieving disasters such as landslide collapse of an upper body, is not easy to break and is wear-resistant, and even if a certain part of a steel wire is broken, the hanging net can bear the impact of implementation; before spraying, workers can lay steel wire meshes on the side slope and then spray the sizing, so that a mesh-hanging sizing shell is formed.
When the existing screen hanging guniting construction is performed, the following defects exist: ① . The staff can hold or lift the spray pipe to spray the slurry on the slope, and the long-time holding or lifting of the spray pipe can cause the fatigue of the staff; ② . During the spraying construction process, workers can spray on the ground or a building at the top of the side slope, so that on one hand, the condition of concrete spraying liquid waste is caused, and on the other hand, the site or the building becomes messy, and the workload of the workers after construction is increased.
Disclosure of utility model
The technical problems to be solved by the utility model are as follows: overcomes the defects of the prior art, provides a shotcrete strutting arrangement based on BIM foundation pit support hanging net, adopts the mode of hanging the spray tube to carry out the shotcrete construction to the side slope, lightens the burden of staff's both arms, simultaneously, avoids causing the pollution to the environment around the side slope.
The technical scheme adopted by the utility model for solving the technical problems is as follows:
The utility model provides a screen spraying strutting arrangement is hung based on BIM foundation ditch support, includes I-shaped frame, gyro wheel and inclined baffle, the bottom of I-shaped frame is provided with the gyro wheel, the both sides at I-shaped frame rear are provided with first support perpendicularly, the top of first support is run through there is the pillar, the pillar below is provided with inclined baffle, the both sides of I-shaped frame front end are dug and are equipped with first U type recess, first U type recess interpolation is equipped with the front end baffle, the middle part of I-shaped frame is provided with displacement recess, sliding connection has displacement cover on the displacement recess, it has the picture peg to run through in the displacement cover, the below of picture peg front end is connected with the second support through the lifting rope, the bottom of second support is provided with the arc.
A second U-shaped groove is formed in front of the first bracket, a connecting plate is hinged to the lower end of the inclined baffle plate at a position corresponding to the second U-shaped groove, and the connecting plate is inserted into the second U-shaped groove and is fixed through a bolt; the bottom of pillar front end is provided with first U type ring, the upper end of inclined baffle is in the same place through hook and first U type ring connection.
The support column is fixedly connected with the first support through bolts.
The I-shaped frame is fixedly connected with the ground soil layer through a positioning drill rod.
The rear of first support is provided with the U type frame, the top of U type frame is dug and is equipped with the rectangle through-hole, the rear end of picture peg runs through the below of U type frame to be in the same place with U type frame fixed connection through the rope.
The plugboard 14 is fixedly connected with the displacement sleeve 13 through bolts, a second U-shaped ring is arranged at the bottom of the front end of the plugboard 14, the upper end of the lifting rope is fixedly connected with the second U-shaped ring in a region, and the lower end of the lifting rope is fixedly connected with the second bracket.
The second support is distributed in a U-shaped mode, an arc-shaped plate is connected to the end portion of the second support, and the arc-shaped plate is connected with the spray pipe through a positioning rope.
The utility model has the positive beneficial effects that:
1. According to the utility model, the inclined baffle is arranged below the support column, so that pollution to the outside building of the side slope during guniting construction is avoided, and the front baffle is inserted into the first U-shaped groove at the front end of the I-shaped frame, so that pollution to the ground at the upper part of the side slope is avoided, and the later workload of staff is reduced.
2. According to the utility model, the insert plate is arranged in the displacement sleeve, and the support is arranged below the front end of the insert plate, so that the spray pipe can be hung and fixed, the burden of double arms of a worker is reduced, meanwhile, the translation can be performed according to the spraying position, the use flexibility is improved, the use is convenient, and the operation is simple.
3. According to the utility model, the positioning drill rod is arranged on the I-shaped frame, so that the device can be fixed with the ground, and the stability of the device in construction is ensured; rectangular through holes are dug on the U-shaped frame, and the inserting plate is fixed with the U-shaped frame by utilizing ropes, so that stability of the inserting plate is guaranteed.
Drawings
FIG. 1 is a schematic diagram of the structure of the present utility model;
FIG. 2 is a schematic diagram of the structure of the spool of the present utility model;
Wherein: the device comprises a 1-I-shaped frame, 2-rollers, 3-brackets, 4-positioning rods, 5-first U-shaped grooves, 6-front end baffle plates, 7-support columns, 8-inclined baffle plates, 9-first U-shaped rings, 10-second U-shaped grooves, 11-displacement grooves, 12-U-shaped frames, 121-rectangular through holes, 13-displacement sleeves, 14-plugboards, 15-second U-shaped rings, 16-lifting ropes, 17-brackets, 18-arc plates and 19-positioning ropes.
Detailed Description
The utility model is further explained and illustrated below with reference to the drawings:
Referring to fig. 1-2, a hanging net guniting supporting device based on BIM foundation pit support comprises a spool frame 1, rollers 2 and inclined baffle plates 8, wherein the rollers 2 are arranged at the bottom of the spool frame 1, first brackets 3 are vertically arranged on two sides of the rear of the spool frame 1, a support column 7 penetrates through the top of each first bracket 3, inclined baffle plates 8 are arranged below each support column 7, first U-shaped grooves 5 are dug on two sides of the front end of the spool frame 1, front end baffle plates 6 are arranged in the first U-shaped grooves 5 in an inserted mode, displacement grooves 11 are arranged in the middle of the spool frame 1, a displacement sleeve 13 is connected to the displacement grooves 11 in a sliding mode, inserting plates 14 penetrate through the displacement sleeve 13, second brackets 17 are connected to the lower portions of the front ends of the inserting plates 14 through lifting ropes 16, and arc plates 18 are arranged at the bottoms of the second brackets 17.
A second U-shaped groove 10 is formed in front of the first bracket 3, a connecting plate is hinged to the lower end of the inclined baffle plate 8 at a position corresponding to the second U-shaped groove 10, and the connecting plate is inserted into the second U-shaped groove 10 and is fixed through bolts; the bottom of the front end of the pillar 7 is provided with a first U-shaped ring 9, and the upper end of the inclined baffle 8 is connected with the first U-shaped ring 9 through a hook.
The support column 7 is fixedly connected with the first bracket 3 through bolts.
The H-shaped frame 1 is fixedly connected with the ground soil layer through a positioning drill rod 4.
The rear of the first bracket 3 is provided with a U-shaped frame 12, the top of the U-shaped frame 12 is dug with a rectangular through hole 121, and the rear end of the plugboard 14 penetrates through the lower part of the U-shaped frame 12 and is fixedly connected with the U-shaped frame 12 through a rope.
The plugboard 14 is fixedly connected with the displacement sleeve 13 through bolts, a second U-shaped ring 15 is arranged at the bottom of the front end of the plugboard 14, the upper end of the lifting rope 16 is fixedly connected with the second U-shaped ring 15 in a region, and the lower end of the lifting rope 16 is fixedly connected with a second bracket 17.
The second bracket 17 is distributed in a U shape, an arc-shaped plate 18 is connected to the end part of the second bracket 17, and the arc-shaped plate 18 is connected with the spray pipe through a positioning rope 19.
In the above description, the connecting plate is hinged at the position below the writing baffle corresponding to the second U-shaped clamping groove, and when the connecting plate is positioned in the second U-shaped clamping groove, a gap exists between the bottom of the inclined baffle and the i-shaped frame, so that the rear end of the plugboard can penetrate through the bottom of the inclined baffle.
In the above description, the height of the U-shaped frame satisfies: the rear end of the plugboard can penetrate through the U-shaped frame, when the spray pipe is sprayed at a certain position of the side slope, a worker above the side slope can fix the rear end of the plugboard with the U-shaped frame by using the rope, and when the worker holds the spray pipe to change the position, the worker can unwind the rope.
In the above description, the front end of the insert plate extends beyond the front end baffle and beyond the side slope.
In the above description, the width of the front end baffle is determined according to the slope width.
In the above description, the length of the hoist rope is determined according to the construction location.
In the above description, the arcuate plate satisfies: the spray pipe can be tightly attached to the outer wall of the spray pipe, and then a worker fixes the spray pipe and the arc plate through a rope; positioning rings are arranged at two ends of the arc-shaped plate and penetrate through the rope.
In the above description, the positioning drill rod is in a shape of a cone with a sharp lower end and is used for fixing the H-shaped frame with the ground.
Before use, the inclined baffle and the front end baffle are installed, then the inserting plate is moved to a construction position, the support at the front end of the inserting plate is lowered into the foundation pit, a worker in the foundation pit fixes the spray pipe on the arc plate, the length of the lifting rope is adjusted, and then the worker only needs to hold the spray pipe to conduct guniting construction.
During construction, two workers are required to operate in a matched mode, one worker is arranged at the top of the side slope, the other worker is arranged in the foundation pit, and during construction, heavy objects can be placed on the I-shaped frame, so that stability of the I-shaped frame is guaranteed.
According to the utility model, the front end baffle plate and the inclined baffle plate are arranged, so that the top of an edge slope can be shielded, pollution to surrounding buildings during guniting construction is avoided, the hanging rope is arranged at the lower end of the inserting plate, the support is connected to the bottom of the hanging rope, the hanging rope can be fixed with the end part of the spray pipe, the burden of double arms of a worker is relieved, and the hanging type spraying type grouting device is convenient to use, simple to operate and easy to popularize.

Claims (7)

1. Based on BIM foundation ditch support string net guniting strutting arrangement, including I-shaped frame (1), gyro wheel (2) and inclined baffle (8), its characterized in that: the bottom of I-frame (1) is provided with gyro wheel (2), the both sides at I-frame (1) rear are provided with first support (3) perpendicularly, the top of first support (3) is run through and is had pillar (7), the below of pillar (7) is provided with inclined baffle (8), the both sides of I-frame (1) front end are dug and are equipped with first U type recess (5), the interpolation of first U type recess (5) is equipped with front end baffle (6), the middle part of I-frame (1) is provided with displacement recess (11), sliding connection has displacement cover (13) on displacement recess (11), it has picture peg (14) to run through in displacement cover (13), the below of picture peg (14) front end is connected with second support (17) through lifting rope (16), the bottom of second support (17) is provided with arc (18).
2. The BIM foundation pit support-based screen guniting support device of claim 1, wherein: a second U-shaped groove (10) is formed in front of the first bracket (3), a connecting plate is hinged to the lower end of the inclined baffle (8) at a position corresponding to the second U-shaped groove (10), and the connecting plate is inserted into the second U-shaped groove (10) and is fixed through bolts; the bottom of the front end of the support column (7) is provided with a first U-shaped ring (9), and the upper end of the inclined baffle plate (8) is connected with the first U-shaped ring (9) through a hook.
3. The BIM foundation pit support-based screen guniting support device of claim 2, wherein: the support column (7) is fixedly connected with the first support (3) through bolts.
4. The BIM foundation pit support-based screen guniting support device of claim 1, wherein: the I-shaped frame (1) is fixedly connected with a ground soil layer through a positioning drill rod (4).
5. The BIM foundation pit support-based screen guniting support device of claim 1, wherein: the rear of first support (3) is provided with U type frame (12), the top of U type frame (12) is dug and is equipped with rectangle through-hole (121), the rear end of picture peg (14) runs through the below of U type frame (12) to be in the same place through rope and U type frame (12) fixed connection.
6. The BIM foundation pit support-based screen guniting support device of claim 1, wherein: the lifting device is characterized in that the inserting plate (14) is fixedly connected with the displacement sleeve (13) through bolts, a second U-shaped ring (15) is arranged at the bottom of the front end of the inserting plate (14), the upper end of the lifting rope (16) is fixedly connected with the second U-shaped ring (15) in a region, and the lower end of the lifting rope (16) is fixedly connected with the second support (17).
7. The BIM foundation pit support-based screen guniting support device of claim 6, wherein: the second brackets (17) are distributed in a U shape, arc plates (18) are connected to the ends of the second brackets (17), and the arc plates (18) are connected with the spray pipe through positioning ropes (19).
CN202322531946.8U 2023-09-18 2023-09-18 Based on BIM foundation ditch support string net guniting strutting arrangement Active CN221072666U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322531946.8U CN221072666U (en) 2023-09-18 2023-09-18 Based on BIM foundation ditch support string net guniting strutting arrangement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322531946.8U CN221072666U (en) 2023-09-18 2023-09-18 Based on BIM foundation ditch support string net guniting strutting arrangement

Publications (1)

Publication Number Publication Date
CN221072666U true CN221072666U (en) 2024-06-04

Family

ID=91251257

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322531946.8U Active CN221072666U (en) 2023-09-18 2023-09-18 Based on BIM foundation ditch support string net guniting strutting arrangement

Country Status (1)

Country Link
CN (1) CN221072666U (en)

Similar Documents

Publication Publication Date Title
CN105862878B (en) A kind of support system of deep basal pit
CN106436718B (en) A kind of subway foundation pit large span support system and its construction method
CN107893530A (en) A kind of anti-fall climbing frame of high safety performance
CN221072666U (en) Based on BIM foundation ditch support string net guniting strutting arrangement
CN214737834U (en) Simple fastener type steel pipe operation platform
CN201793330U (en) Gantry hanger frame device
CN213461075U (en) Protection device for underground original pipeline
CN212506282U (en) Deep foundation pit supporting device
CN218150940U (en) Adjustable tunnel is first to be propped up and two lining supporting devices
CN115807532A (en) Device for attaching suspension bracket and construction method
CN217174727U (en) Auxiliary vibrating device
CN205778921U (en) A kind of down-hole filling type steel pipe concrete bracket
CN212405177U (en) Suspended enclosing purlin supporting system
CN206034461U (en) Subway foundation pit large -span support system
CN215060454U (en) Protection supporting structure of existing underground pipeline of shield machine hoisting operation field
CN220265089U (en) Heavy pipeline mechanical lifting device
CN112554922A (en) Supporting and bearing device for underground mine arch suspension bridge
CN214143725U (en) Foundation ditch supporting device for highway construction
CN217711628U (en) Channel steel cantilever support template supporting device
CN212428008U (en) Lower supporting type overhanging scaffold construction device
CN217419584U (en) U-shaped lower hanging Larsen steel sheet pile steel purlin bracket replacing device
CN220058983U (en) Quick-dismantling horizontal safety protection device
CN214169156U (en) Pile cap for cluster pile foundation and immersed tube tunnel pile foundation
CN216305921U (en) Shield starting reaction frame for covering and digging narrow space of top-down subway station
CN211175635U (en) Portable supporting device for pumping guide pipe in precipitation well

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant