CN220265089U - Heavy pipeline mechanical lifting device - Google Patents

Heavy pipeline mechanical lifting device Download PDF

Info

Publication number
CN220265089U
CN220265089U CN202321757736.4U CN202321757736U CN220265089U CN 220265089 U CN220265089 U CN 220265089U CN 202321757736 U CN202321757736 U CN 202321757736U CN 220265089 U CN220265089 U CN 220265089U
Authority
CN
China
Prior art keywords
pipeline
track
lifting device
groove
heavy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321757736.4U
Other languages
Chinese (zh)
Inventor
李鹏鹏
胡李强
薛菁鑫
苏滨
李重阳
王辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Construction Engineering Group Co Ltd
Original Assignee
Shanxi Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Construction Engineering Group Co Ltd filed Critical Shanxi Construction Engineering Group Co Ltd
Priority to CN202321757736.4U priority Critical patent/CN220265089U/en
Application granted granted Critical
Publication of CN220265089U publication Critical patent/CN220265089U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model belongs to the field of heavy pipeline installation, and particularly relates to a heavy pipeline mechanical lifting device.

Description

Heavy pipeline mechanical lifting device
Technical Field
The utility model belongs to the field of heavy pipeline installation, and particularly relates to a heavy pipeline mechanical lifting device.
Background
Underground construction of large-scale building is equipment room usually, and fire control ring canal and hollow pipe ring canal use the material to be DN150 seamless galvanized steel pipe generally, and single seamless galvanized steel pipe is 6 meters long, and standard layer mounting height is 2.5m, and basement mounting height is 3.6m.
At present, the seamless galvanized steel pipe is installed by manpower. When lifting, scaffold erection is carried out at the pipeline installation position, and then the scaffold is manually lifted to a proper height. The existing installation mode cannot guarantee safety, construction operators are often injured, and the construction progress is slow.
Disclosure of Invention
In order to solve the problems that the existing heavy pipeline is low in installation efficiency and the safety cannot be guaranteed in the installation process, the mechanical lifting device for the heavy pipeline is provided. The heavy pipeline mechanical lifting device of the utility model better protects the safety of operators, saves labor force and accelerates the engineering construction progress.
In order to solve the technical problems, the utility model adopts the technical scheme that: the utility model provides a heavy pipeline machinery hoisting device, includes the support base, and the universal wheel is all installed at four bights of support base, is provided with two vertical bracing pieces side by side on the support base, and horizontal pole fixed connection is passed through at the top of vertical bracing piece, and the middle part of horizontal pole is provided with the fixed pulley, and the fixed electric hoist engine that is provided with on the support base, the wire rope of electric hoist engine walk around the fixed pulley and then is connected with the couple.
Further, be provided with the pipeline on the vertical bracing piece and prop up, the pipeline is propped up and is held in the palm including the support frame, and the inboard of support frame is V font pipeline storage tank, and the lateral surface of support frame is provided with the track draw-in groove, all is provided with the track on two vertical bracing pieces, and the pipeline is propped up and is held in the palm and can slide on the track through the track draw-in groove, and the spacing is equipped with the mounting hole on track draw-in groove and the track, and the bolt passes the mounting hole and fixes track draw-in groove and track.
Further, a row of guide wheels are arranged on two side walls of the pipeline storage groove, the guide wheels are arranged on the pulley seat, and the pulley seat is fixedly arranged on the side wall of the pipeline storage groove.
Further, the support base is provided with an inclined strut, one end of the inclined strut is hinged to the support base, and the other end of the inclined strut is hinged to the longitudinal support rod.
Further, a plurality of reinforcing rods are arranged between the two longitudinal support rods at intervals.
Compared with the prior art, the utility model has the following beneficial effects: according to the utility model, the electric hoist is used for lifting the steel pipe to be installed to the designed installation height by using the hook, the pipeline is placed on the pipeline jacking support, and then the constructor can perform welding operation, so that the complicated working procedures of erecting a scaffold are avoided, the danger of high-place operation is reduced, and excellent protection measures are provided for the constructor.
Drawings
The utility model is further described below with reference to the accompanying drawings.
Fig. 1 is a schematic structural view of the present utility model.
Fig. 2 is a partial enlarged view of fig. 1 at a.
Fig. 3 is a schematic view of the position of the reinforcing rod.
In the figure, 1 is a supporting base, 2 is a universal wheel, 3 is a longitudinal supporting rod, 4 is a cross rod, 5 is a fixed pulley, 6 is an electric winch, 7 is a steel wire rope, 8 is a pipeline jacking, 81 is a supporting frame, 82 is a pipeline storage groove, 83 is a guide wheel, 84 is a pulley seat, 9 is an inclined strut, and 10 is a reinforcing rod.
Detailed Description
As shown in fig. 1 to 3, the heavy pipe machine lifting device comprises a support base 1, universal wheels 2 are installed at four corners of the support base 1, other equipment and a support frame 81 are arranged on the support base 1, and the support base 1 can be pushed to move the whole heavy pipe machine lifting device by using the universal wheels 2. And according to the installation position, the heavy pipeline mechanical lifting device is moved at any time.
Two longitudinal support rods 3 are arranged on the support base 1 side by side, the tops of the longitudinal support rods 3 are fixedly connected through a cross rod 4, a fixed pulley 5 is arranged in the middle of the cross rod 4, an electric hoist 6 is fixedly arranged on the support base 1, a steel wire rope 7 of the electric hoist 6 bypasses the fixed pulley 5 and then is communicated with a hook, the hook is matched with the diameter of a pipeline, and the height of the pipeline can be improved by the aid of the electric hoist 6.
In order to guarantee the stability of pipeline in the work progress, be provided with pipeline jacking 8 on vertical bracing piece 3, pipeline jacking 8 includes support frame 81, and the inboard of support frame 81 is V font pipeline storage tank 82, and the lateral surface of support frame 81 is provided with the track draw-in groove, all is provided with the track on two vertical bracing pieces, and pipeline jacking 8 can slide on the track through the track draw-in groove, and the interval is equipped with the mounting hole on track draw-in groove and the track, and the bolt passes the mounting hole and fixes track draw-in groove and track.
Firstly, according to the design height, the height of the pipeline jacking 8 is adjusted to a proper position, then the position of the pipeline jacking 8 is fixed, then a galvanized steel pipe to be lifted is hooked by a hook, an electric winch 6 is started, the galvanized steel pipe is lifted onto the pipeline jacking 8, the pipeline jacking 8 is used for supporting the steel pipe, and a constructor can perform welding operation. Because the galvanized steel pipe is longer, can use two sets of heavy pipeline machinery hoisting device, place respectively in galvanized steel pipe's both ends, can stably promote galvanized steel pipe like this, can not take place the slope.
In the operation process of constructors, the galvanized steel pipe may need to be pushed left and right, in order to facilitate pushing of the galvanized steel pipe, a row of guide wheels 83 are arranged on two side walls of the pipe storage groove 82, the guide wheels 83 are arranged on the pulley seats 84, and the pulley seats 84 are fixedly arranged on the side walls of the pipe storage groove 82. The guide wheels 83 reduce friction force, and are convenient for constructors to move the galvanized steel pipe left and right.
In addition, in order to promote the stability of the whole support frame 81, a diagonal brace 9 is provided on the support base 1, one end of the diagonal brace 9 is hinged on the support base 1, and the other end of the diagonal brace 9 is hinged on the longitudinal support rod 3. A plurality of reinforcing bars 10 are arranged between the two longitudinal support bars 3 at intervals. The longitudinal support rods 3 are supported through the reinforcing rods 10 and the diagonal braces 9, so that stability of the longitudinal support rods 3 in the pipeline lifting process is guaranteed, and the longitudinal support rods are prevented from tilting. The safety of the whole device is improved.
The heavy pipeline installation lifting machine is adopted for working, so that the working efficiency of heavy pipeline installation with large diameter is improved, and meanwhile, complicated working procedures of building up a scaffold are avoided for higher pipeline installation parts, the danger of high-place operation is reduced, and excellent protection measures are played for workers.
The embodiments of the present utility model have been described in detail with reference to the accompanying drawings, but the present utility model is not limited to the above embodiments, and various changes can be made within the knowledge of those skilled in the art without departing from the spirit of the present utility model.

Claims (5)

1. Heavy pipeline machinery hoisting device, its characterized in that: including supporting base (1), universal wheel (2) are all installed at four bights of supporting base (1), are provided with two vertical bracing pieces (3) side by side on supporting base (1), and horizontal pole (4) fixed connection is passed through at the top of vertical bracing piece (3), and the middle part of horizontal pole (4) is provided with fixed pulley (5), and the fixed electric hoist engine (6) that are provided with on supporting base (1), and wire rope (7) of electric hoist engine (6) are walked around behind fixed pulley (5) and are connected with the couple.
2. The heavy pipe machinery lifting device of claim 1, wherein: be provided with pipeline jacking (8) on vertical bracing piece (3), pipeline jacking (8) are including support frame (81), and the inboard of support frame (81) is V font pipeline storage tank (82), and the lateral surface of support frame (81) is provided with track draw-in groove, all is provided with the track on two vertical bracing pieces (3), and pipeline jacking (8) can slide on the track through the track draw-in groove, and the interval is equipped with the mounting hole on track draw-in groove and the track, and the bolt passes the mounting hole and fixes track draw-in groove and track.
3. The heavy pipe machinery lifting device of claim 2, wherein: a row of guide wheels (83) are arranged on each side wall of the pipeline storage groove (82), the guide wheels (83) are arranged on pulley seats (84), and the pulley seats (84) are fixedly arranged on the side walls of the pipeline storage grooves (82).
4. A heavy pipe machinery lifting device according to claim 3, characterized in that: the support base (1) is provided with an inclined strut (9), one end of the inclined strut (9) is hinged to the support base (1), and the other end of the inclined strut (9) is hinged to the longitudinal support rod (3).
5. The heavy pipe machinery lifting device of claim 4, wherein: a plurality of reinforcing rods (10) are arranged between the two longitudinal support rods (3) at intervals.
CN202321757736.4U 2023-07-06 2023-07-06 Heavy pipeline mechanical lifting device Active CN220265089U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321757736.4U CN220265089U (en) 2023-07-06 2023-07-06 Heavy pipeline mechanical lifting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321757736.4U CN220265089U (en) 2023-07-06 2023-07-06 Heavy pipeline mechanical lifting device

Publications (1)

Publication Number Publication Date
CN220265089U true CN220265089U (en) 2023-12-29

Family

ID=89316798

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321757736.4U Active CN220265089U (en) 2023-07-06 2023-07-06 Heavy pipeline mechanical lifting device

Country Status (1)

Country Link
CN (1) CN220265089U (en)

Similar Documents

Publication Publication Date Title
CN102877637B (en) Method for implementing operating platform in bottom wall construction of cantilever beam
CN211736298U (en) Double-rod diagonal cantilever scaffold
CN211899582U (en) Hanging flower basket device is used in construction of roof steel construction platform glass curtain wall
CN212247900U (en) A artifical beam device that traverses that is used for bridge and tunnel zero distance to erect T roof beam
CN111648585A (en) Construction method and device of suspended support type steel truss platform
CN201793330U (en) Gantry hanger frame device
CN105819352B (en) Lifting device for detachable door type mast building and construction method thereof
CN220265089U (en) Heavy pipeline mechanical lifting device
CN116853963A (en) Hoisting device and hoisting method for main girder of cable-stayed bridge
CN215978530U (en) Steel beam sliding installation device
CN115807532A (en) Device for attaching suspension bracket and construction method
CN112502475B (en) Supporting bearing capacity conversion device and using method thereof
CN213572927U (en) Movable steel platform with adjustable size and capable of being circulated
CN211873772U (en) Externally-hung operating steel platform
CN209816682U (en) Bridge steel box girder aerial working operation platform
CN111305433A (en) Construction structure and construction method of inclined glass curtain wall of roof steel structure platform
CN111255132A (en) Unit type glass curtain wall construction method
CN204960280U (en) Scaffold capable of being integrally hoisted and repeatedly used
CN220149092U (en) ALC wallboard hoisting device
CN212613671U (en) Construction device of suspended support type steel truss platform
CN216105699U (en) Hoisting and dismantling device for track beam of hydropower station suspended ceiling trolley
CN221094848U (en) Bracket for erecting bearing rope of suspension bridge catwalk
CN220687339U (en) Assembled reinforcing bar rack
CN211397600U (en) Automatic installation working trolley for tunnel primary arch and primary arch
CN215756285U (en) Convenient hoisting tool for assembled concrete precast slab

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant