CN220927919U - Safety construction platform for pouring bearing platform and tower base - Google Patents

Safety construction platform for pouring bearing platform and tower base Download PDF

Info

Publication number
CN220927919U
CN220927919U CN202322157160.4U CN202322157160U CN220927919U CN 220927919 U CN220927919 U CN 220927919U CN 202322157160 U CN202322157160 U CN 202322157160U CN 220927919 U CN220927919 U CN 220927919U
Authority
CN
China
Prior art keywords
bracket
support
anchor rod
anchor
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322157160.4U
Other languages
Chinese (zh)
Inventor
欧长阳
盛亮
史永龙
魏鹏飞
刘杰
彭通洲
余贵杨
刘亮
储长青
王荣
马兴红
骆俊
周彬
刘红成
王敏
刘益
汪兴檀
岳小彪
王皓冬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SICHUAN ROAD AND BRIDGE HUADONG CONSTRUCTION CO Ltd
Sichuan Road and Bridge Group Co Ltd
Original Assignee
SICHUAN ROAD AND BRIDGE HUADONG CONSTRUCTION CO Ltd
Sichuan Road and Bridge Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SICHUAN ROAD AND BRIDGE HUADONG CONSTRUCTION CO Ltd, Sichuan Road and Bridge Group Co Ltd filed Critical SICHUAN ROAD AND BRIDGE HUADONG CONSTRUCTION CO Ltd
Priority to CN202322157160.4U priority Critical patent/CN220927919U/en
Application granted granted Critical
Publication of CN220927919U publication Critical patent/CN220927919U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a safety construction platform for pouring a bearing platform and a tower seat, which comprises a mounting frame body, wherein the mounting frame body is of layered design, and the safety construction platform further comprises: a plurality of positioning structures; a plurality of anchors. According to the utility model, the anchor rod sequentially penetrates through the first bracket, the second bracket, the third bracket and the fourth bracket from bottom to top, the two ends of the anchor rod are respectively connected with the first bracket and the fourth bracket in an abutting locking manner, and meanwhile, the anchor rod is respectively connected with the second bracket, the third bracket and the fourth bracket by utilizing a plurality of positioning structures. When the bearing platform and the tower seat are constructed, layered pouring construction is carried out from bottom to top according to the construction sequence of the first bracket, the second bracket, the third bracket and the fourth bracket, and meanwhile, when layered pouring is carried out, the installation position of the anchor rod can be rechecked and adjusted by utilizing the positioning structure, so that the overall positioning and adjusting precision of the anchor rod on the bearing platform and the tower seat is ensured, and the defect that the construction precision of the anchor rod on the bridge bearing platform and the tower seat is low in the prior art is effectively overcome.

Description

Safety construction platform for pouring bearing platform and tower base
Technical Field
The utility model relates to the technical field of bridge bearing platform and tower seat construction, in particular to a safety construction platform for casting a bearing platform and a tower seat.
Background
Bridge bearing platform and tower seat are a foundation structure for supporting and transmitting bridge load. The bridge bearing platform and the tower seat are responsible for bearing the self weight of the bridge and carrying the load, and transmitting the forces into soil layers or rocks under the ground.
The materials of the bridge bearing platform and the tower seat are usually reinforced concrete combined structures formed by concrete and steel structures. Concrete is one of the most commonly used materials because it has sufficient strength, durability and economy to meet the requirements of the deck and tower foundation.
At present, for the construction of a bearing platform and a tower seat which need to be embedded with a steel tower anchoring system, an anchor rod positioning and installation is generally carried out in a field scattered splicing temporary positioning support mode, a construction channel and a platform are imperfect, positioning and adjusting steps of the anchor rod are complex, the construction efficiency of the bearing platform and the tower seat is low, and the positioning and adjusting precision of the anchor rod is insufficient.
Disclosure of Invention
The utility model aims to solve the defect of low construction precision of anchor rods on a bridge bearing platform and a tower seat in the prior art, and provides a safety construction platform for casting the bearing platform and the tower seat.
In order to achieve the above purpose, the present utility model adopts the following technical scheme:
the first aspect of the utility model provides a safe construction platform for pouring a bearing platform and a tower seat
A table comprising
The mounting bracket body, the mounting bracket body is the layering design, include: the device comprises a first bracket, a second bracket, a third bracket and a fourth bracket, wherein the first bracket, the second bracket, the third bracket and the fourth bracket are of square frame structures, the first bracket, the second bracket, the third bracket and the fourth bracket are sequentially stacked from bottom to top, and a plurality of connecting plates are arranged among the first bracket, the second bracket, the third bracket and the fourth bracket; further comprises:
The positioning structures are respectively arranged on the second bracket, the third bracket and the fourth bracket, and the positioning structures on the second bracket, the third bracket and the fourth bracket are vertically and penetratingly communicated;
The anchor rods are arranged along square structures of the first support, the second support, the third support and the fourth support, penetrate through the first support, the second support, the third support and the fourth support in sequence, are respectively connected with the second support, the third support and the fourth support through positioning structures, and are respectively locked and connected with the first support and the fourth support at two ends.
In a possible embodiment, the positioning structure comprises:
The mounting plate is arranged on the fourth bracket or the third bracket or the second bracket;
The backing plates are of C-shaped steel structures, two backing plates are oppositely arranged on the mounting plate, a gap is formed between the two backing plates, the anchor rods pass through the gap and between the two first backing plates, and the arrangement directions of the two backing plates are perpendicular to the arrangement direction of the mounting plate;
The locating plate, be provided with the semicircle orifice on the locating plate, two semicircle orifice butt sets up on the locating plate, forms a round hole, the stock runs through in two locating plates through the round hole, the locating plate with the backing plate links to each other.
In a possible embodiment, the mounting frame body further includes:
the two locking parts are symmetrically arranged at two ends of the anchor rod, one locking part is connected with the bottom of the first bracket in an abutting mode, and the other locking part is connected with the top of the fourth bracket in an abutting mode.
In a possible embodiment, the locking portion includes:
The abutting plate is sleeved on the anchor rod and is in abutting connection with the fourth bracket or the first bracket;
The gasket is sleeved on the anchor rod, is connected with the abutting plate in an abutting mode, and is positioned on one surface far away from the fourth bracket or the first bracket;
The lock nut is sleeved on the anchor rod and connected with the anchor rod through threads, and the lock nut is connected with one side, away from the abutting plate, of the gasket in an abutting mode.
In a possible embodiment, the first bracket is further provided with an anchor beam mounting structure, the anchor beam mounting structure is arranged along the square structure of the first bracket, and the anchor beam mounting structure is used for locking and mounting the end, far away from the fourth bracket, of the anchor rod on the first bracket.
In one possible embodiment, the anchor beam mounting structure comprises:
The anchor beam installation groove is of a strip U-shaped structure and is arranged along the periphery of the first bracket;
One end, far away from the fourth bracket, of the anchor rod penetrates through the anchor beam mounting groove;
The connecting steel bar is sleeved on the anchor rod, and one end of the connecting steel bar is abutted to the anchor beam mounting groove;
The steel bar net is square, the steel bar net sleeve is arranged on the anchor rod, the steel bar net sleeve is arranged outside the connecting steel bars, the bottom end of the steel bar net is lapped on the anchor beam mounting groove, and the anchor beam mounting structure for limiting the anchor rod is formed.
In a possible embodiment, the reinforcement mesh is provided in a multi-layered structure.
In a possible embodiment, the shape of the shim plate is replaced by a C-section steel.
In a possible embodiment, the arrangement structure of the connection plate between the first bracket, the second bracket, the third bracket and the fourth bracket includes:
One or more of an inclined support structure, a crossed support structure and a vertical support structure.
The beneficial effects of the utility model are as follows:
In the embodiment of the utility model, the anchor rod sequentially penetrates through the first bracket, the second bracket, the third bracket and the fourth bracket from bottom to top, the two ends of the anchor rod are respectively connected with the first bracket and the fourth bracket in an abutting locking manner, and simultaneously, a plurality of positioning structures are used for respectively connecting the anchor rod to the second bracket, the third bracket and the fourth bracket. When the bearing platform and the tower seat are required to be constructed, layered pouring construction can be carried out from bottom to top according to the construction sequence of the first bracket, the second bracket, the third bracket and the fourth bracket, and meanwhile, when layered pouring is carried out, the installation position of the anchor rod can be rechecked and adjusted by utilizing the positioning structure, so that the overall positioning and adjusting precision of the anchor rod on the bearing platform and the tower seat are ensured, and the defect that the construction precision of the anchor rod on the bridge bearing platform and the tower seat is low in the prior art is effectively overcome.
Drawings
Fig. 1 is a schematic diagram of the overall structure of a safety construction platform for pouring a bearing platform and a tower base (without a mounting platform) provided in an embodiment of the utility model;
fig. 2 is a schematic diagram of a first support structure of a safety construction platform for pouring a bearing platform and a tower base according to an embodiment of the present utility model;
Fig. 3 is a schematic structural diagram of a first bracket and a second bracket of a safety construction platform for pouring a bearing platform and a tower base according to an embodiment of the present utility model;
Fig. 4 is a schematic structural diagram of a fourth bracket of a safety construction platform for pouring a bearing platform and a tower base according to an embodiment of the present utility model;
fig. 5 is a schematic structural diagram of an anchor beam installation structure of a safety construction platform for pile cap and pile foundation casting according to an embodiment of the present utility model;
FIG. 6 is a schematic structural diagram of a positioning structure of a safety construction platform for pouring a bearing platform and a tower base according to an embodiment of the present utility model;
Fig. 7 is a schematic diagram of a positioning plate structure in a positioning structure of a safety construction platform for pouring a bearing platform and a tower base according to an embodiment of the present utility model.
The labels in the figures are as follows:
1. A first bracket; 11. a connecting plate; 12. embedding a steel plate; 13. an anchor beam mounting groove; 14. a reinforcing mesh; 141. connecting steel bars;
2. A second bracket;
3. A third bracket;
4. A fourth bracket;
5. A bolt; 51. a lock nut; 52. a gasket; 53. an abutting plate;
6. a positioning structure; 61. a mounting plate; 62. a backing plate; 63. a positioning plate; 64. a reinforcing plate;
7. a guardrail.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and fully with reference to the accompanying drawings, in which it is evident that the embodiments described are only some, but not all embodiments of the utility model. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
It should be noted that all directional indicators (such as up, down, left, right, front, and rear … …) in the embodiments of the present utility model are merely used to explain the relative positional relationship, movement, etc. between the components in a particular posture (as shown in the drawings), and if the particular posture is changed, the directional indicator is changed accordingly.
In the present utility model, unless specifically stated and limited otherwise, the terms "connected," "affixed," and the like are to be construed broadly, and for example, "affixed" may be a fixed connection, a removable connection, or an integral body; can be mechanically or electrically connected; either directly or indirectly, through intermediaries, or both, may be in communication with each other or in interaction with each other, unless expressly defined otherwise. The specific meaning of the above terms in the present utility model can be understood by those of ordinary skill in the art according to the specific circumstances.
In addition, if there is a description of "first", "second", etc. in the embodiments of the present utility model, the description of "first", "second", etc. is for descriptive purposes only and is not to be construed as indicating or implying a relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defining "a first" or "a second" may explicitly or implicitly include at least one such feature. In addition, the meaning of "and/or" as it appears throughout includes three parallel schemes, for example "A and/or B", including the A scheme, or the B scheme, or the scheme where A and B are satisfied simultaneously. In addition, the technical solutions of the embodiments may be combined with each other, but it is necessary to base that the technical solutions can be realized by those skilled in the art, and when the technical solutions are contradictory or cannot be realized, the combination of the technical solutions should be considered to be absent and not within the scope of protection claimed in the present utility model.
Example 1
Referring to fig. 1 to 7, a safety construction platform for pouring a bearing platform and a tower base, the construction platform comprises: the mounting bracket body, a plurality of stock 5 and location structure 6. The mounting frame body is layered design, and is divided into four layers of brackets, specifically: a first bracket 1, a second bracket 2, a third bracket 3 and a fourth bracket 4. The first support 1, the second support 2, the third support 3 and the fourth support 4 are square frame structures, the first support 1, the second support 2, the third support 3 and the fourth support 4 are sequentially stacked from bottom to top, a plurality of connecting plates 11 are arranged between the first support 1, the second support 2, the third support 3 and the fourth support 4, so that the first support 1, the second support 2, the third support 3 and the fourth support 4 can be supported by using the plurality of connecting plates 11, namely the plurality of connecting plates 11 are arranged between the first support 1, the second support 2, the third support 3 and the fourth support 4 to support the upper and lower gaps of the first support 1, the second support 2, the third support 3 and the fourth support 4, and the first support 1, the second support 2, the third support 3 and the fourth support 4 are layered, so that layered construction is carried out on a bearing platform and a tower seat by using a mounting frame body. The positioning structures 6 are respectively arranged on the second bracket 2, the third bracket 3 and the fourth bracket 4, and the positioning structures 6 on the second bracket 2, the third bracket 3 and the fourth bracket 4 are vertically and penetratingly communicated. A plurality of stock 5 are followed square structure setting of first support 1, second support 2, third support 3 and fourth support 4 (i.e. a plurality of stock 5 are followed square periphery of first support 1, second support 2, third support 3 and fourth support 4 sets up), stock 5 runs through in proper order first support 1, second support 2, third support 3 and fourth support 4, stock 5 pass through location structure 6 respectively with first support 1, second support 2, third support 3 and fourth support 4 link to each other, the both ends of stock 5 respectively with first support 1, 4 butt locking links to each other of fourth support 4. That is, in this embodiment, the anchor rod 5 sequentially penetrates through the first bracket 1, the second bracket 2, the third bracket 3 and the fourth bracket 4 from bottom to top, and two ends of the anchor rod 5 respectively perform abutting locking connection with the first bracket 1 and the fourth bracket 4, and simultaneously, a plurality of positioning structures 6 are used to respectively connect the anchor rod 5 to the second bracket 2, the third bracket 3 and the fourth bracket 4. When the bearing platform and the tower seat are required to be constructed, layered pouring construction can be carried out from bottom to top according to the construction sequence of the first bracket 1, the second bracket 2, the third bracket 3 and the fourth bracket 4, and meanwhile, when layered pouring is carried out, the installation position of the anchor rod 5 can be rechecked and adjusted by utilizing the positioning structure 6, so that the overall positioning and adjusting precision of the anchor rod on the bearing platform and the tower seat are ensured, and the defect that the construction precision of the anchor rod on the bridge bearing platform and the tower seat is low in the prior art is effectively overcome.
Referring to fig. 1, 3, 4, 6 and 7, in this embodiment, for convenience of description, a positioning structure 6 disposed on the fourth bracket 4 is described herein by way of example, and specifically, the positioning structure 6 includes: a mounting plate 61, two backing plates 62 and two locating plates 63. The mounting plate 61 is provided on the fourth bracket 4. The backing plates 62 are of C-shaped steel structures, two backing plates 62 are oppositely arranged on the mounting plate 61, a gap is formed between the two backing plates 62, the anchor rod 5 passes through the gap and between the two first backing plates 62, and the setting directions of the two backing plates 62 are perpendicular to the setting directions of the mounting plate 61. The locating plate 63 is provided with a semicircular hole, two semicircular holes on the locating plate 63 are in butt joint to form a circular hole, the anchor rod 5 penetrates through the two locating plates 63 through the circular hole, the locating plates 63 are connected with the base plate 62 through electric welding, on one hand, the limiting force is convenient to provide for the anchor rod 5, on the other hand, when the position of the anchor rod 5 needs to be adjusted, the position of the anchor rod 5 can be adjusted by adjusting the position of the installation block. In one possible embodiment, the backing plate 62 may also be provided in an I-beam configuration. In this embodiment, in order to further strengthen the overall connection strength of the positioning structures 6 on the second bracket 2, the third bracket 3 and the fourth bracket 4, the mounting frame body is further provided with a plurality of reinforcing plates 64, the reinforcing plates 64 are disposed between every two mutually adjacent backing plates 62, the reinforcing plates 64 are far away from the anchor rods 5, and the reinforcing plates 64 are used for integrally reinforcing every two adjacent backing plates 62, so as to strengthen the connection strength of the second bracket 2, the third bracket 3 and the fourth bracket 4.
Referring to fig. 1, 5 and 6, in this embodiment, in order to facilitate locking of both ends of the anchor rod 5 to the first bracket 1 and the fourth bracket 4, the mounting frame body further includes: the two locking parts are symmetrically arranged at two ends of the anchor rod 5, one locking part is connected with the bottom of the first bracket 1 in an abutting mode, and the other locking part is connected with the top of the fourth bracket 4 in an abutting mode. Here, for convenience of description of the structure of the locking portion, a locking portion mounted on the anchor rod 5 and abutting against the fourth bracket 4 is exemplified, and specifically, one of the locking portions includes: a lock nut 51, a washer 52 and an abutment plate 53. The abutting plate 53 is sleeved on the anchor rod 5, and the abutting plate 53 is in abutting connection with the fourth bracket 4. The washer 52 is sleeved on the anchor rod 5, the washer 52 is in abutting connection with the abutting plate 53, and the washer 52 is located on one surface far away from the fourth bracket 4. The lock nut 51 is sleeved on the anchor rod 5, the lock nut 51 is in threaded connection with the anchor rod 5, and the lock nut 51 is in abutting connection with one surface, away from the abutting plate 53, of the gasket 52. That is, in this embodiment, two locking nuts 51 are respectively disposed on two ends of the anchor rod 5, and a washer 52 and an abutting plate 53 are used in a matched manner, so that the anchor rod 5 is respectively abutted and locked with the first bracket 1 and the fourth bracket 4 at two ends of the anchor rod 5, and accurate installation and positioning of the anchor rod 5 are ensured. In this embodiment, the positioning plate and the abutting plate 53 may be the same component, but the abutting plate 53 on the first bracket 1 may be formed by two separate components or may be the whole, but the positioning plates on the second bracket 2, the third bracket 3 and the fourth bracket 4 must be formed by splicing two plate structures with semicircular holes. So as to realize the convenience of subsequent layered pouring to adjust the installation position of the anchor rod 5.
Referring to fig. 2, 3 and 5, in this embodiment, in order to ensure that the installation positioning position of the anchor rod 5 on the first bracket 1 is more accurate, an anchor beam installation structure is further provided on the first bracket 1, and the anchor beam installation structure is disposed along the square structure of the first bracket 1 (i.e., the anchor beam installation structure is disposed in a square shape on the first bracket 1), and the anchor beam installation structure is used for locking and installing one end of the anchor rod 5 away from the fourth bracket 4 on the first bracket 1. For convenience of description of the anchor beam mounting structure, an anchor beam mounting structure will be described herein. The anchor beam mounting structure includes: anchor beam mounting groove 13, reinforcing mesh 14 and connecting reinforcement 141. The anchor beam mounting groove 13 is of a strip U-shaped structure, and the anchor beam mounting groove 13 is formed along the periphery of the first bracket 1, wherein one end, far away from the fourth bracket 4, of the anchor rod 5 penetrates through the anchor beam mounting groove 13. The connecting steel bars 141 are sleeved on the anchor rods 5, and one ends of the connecting steel bars 141 are abutted to the anchor beam mounting grooves 13. The steel bar mesh 14 is square, the steel bar mesh 14 is sleeved on the anchor rod 5, the steel bar mesh 14 is sleeved outside the connecting steel bars 141, and the bottom end of the steel bar mesh 14 is lapped on the anchor beam mounting groove 13 for realizing forming an anchor beam mounting structure limiting the anchor rod 5. In one possible embodiment, the reinforcing mesh 14 may be provided in a multi-layered structure in order to further strengthen the strength of the anchor beam installation structure to the installation construction positioning structure 6 of the anchor rod 5.
In a possible embodiment, in order to ensure the stable support of the connection plate 11 between the first bracket 1, the second bracket 2, the third bracket 3 and the fourth bracket 4, the connection plate 11 may be provided as one or more of an inclined support, a crossed support and a vertical support. Namely, the connecting plate 11 is in an inclined type supporting structure (for reinforcing the supporting force of the two parallel connecting plates) between the first bracket 1, the second bracket 2, the third bracket 3 and the fourth bracket 4, a crossed type supporting structure (for reinforcing the supporting force of the two parallel connecting plates), and a vertical type supporting structure (for vertically supporting the first bracket 1, the second bracket 2, the third bracket 3 and the fourth bracket 4).
In a possible embodiment, in order to facilitate the installation of the first bracket 1, the second bracket 2, the third bracket 3 and the fourth bracket 4 and the positioning installation of the anchor rod 5, the outer circumferences of the first bracket 1, the second bracket 2, the third bracket 3 and the fourth bracket 4 may be provided with installation platforms (not shown in the figure), and the first bracket 1, the second bracket 2, the third bracket 3 and the fourth bracket 4 are placed on the bracket body through the installation platforms and the positioning operation of the anchor rod 5. That is, in this embodiment, by installing the mounting platforms on the first bracket 1, the second bracket 2, the third bracket 3 and the fourth bracket 4, the operator may set up the frame bodies on the first bracket 1, the second bracket 2, the third bracket 3 and the fourth bracket 4 through the mounting platforms, and may perform the working flow of the first bracket 1, the second bracket 2, the third bracket 3 and the fourth bracket 4 through the mounting platforms, so that the operator may walk on the mounting platforms on the first bracket 1, the second bracket 2, the third bracket 3 and the fourth bracket 4, that is, the operator may perform the mounting work on the first bracket 1, the second bracket 2, the third bracket 3 and the fourth bracket 4, and the anchor rod 5. In a possible embodiment, the mounting platforms on the first bracket 1, the second bracket 2, the third bracket 3 and the fourth bracket 4 are provided with two-way guardrails 7 for preventing operators from falling accidentally on the inner side and the outer side of the mounting platform.
In this embodiment, the mounting frame body is disposed in a construction area (not shown in the figure) of the bearing platform and the tower base, so as to ensure that the mounting frame body is stably connected with the bearing platform and the tower base, a plurality of embedded steel plates 12 are disposed at the bottom end of the mounting frame body, and the embedded steel plates 12 and the construction area of the bearing platform and the tower base are formed by integrally casting concrete.
In this embodiment, in order to ensure the mounting accuracy of the mount body. The mounting frame body is manufactured intelligently in an integral factory, and the mounting accuracy of the anchor rod 5 is guaranteed from the machining accuracy of the mounting frame body. And (5) accurately machining the anchor rod 5 and hoisting and positioning after the assembly part of the positioning bracket is transported to the site. Namely, the first bracket 1, the second bracket 2, the third bracket 3 and the fourth bracket 4 are integrally processed and formed in a factory.
The foregoing is only a preferred embodiment of the present utility model, but the scope of the present utility model is not limited thereto, and any person skilled in the art, who is within the scope of the present utility model, should make equivalent substitutions or modifications according to the technical scheme of the present utility model and the inventive concept thereof, and should be covered by the scope of the present utility model.

Claims (9)

1. The utility model provides a cushion cap and tower seat are pour with safe construction platform, includes the mounting bracket body, its characterized in that, the mounting bracket body is layered design, includes: the device comprises a first bracket, a second bracket, a third bracket and a fourth bracket, wherein the first bracket, the second bracket, the third bracket and the fourth bracket are of square frame structures, the first bracket, the second bracket, the third bracket and the fourth bracket are sequentially stacked from bottom to top, and a plurality of connecting plates are arranged among the first bracket, the second bracket, the third bracket and the fourth bracket; further comprises:
The positioning structures are respectively arranged on the second bracket, the third bracket and the fourth bracket, and the positioning structures on the second bracket, the third bracket and the fourth bracket are vertically and penetratingly communicated;
The anchor rods are arranged along square structures of the first support, the second support, the third support and the fourth support, penetrate through the first support, the second support, the third support and the fourth support in sequence, are respectively connected with the second support, the third support and the fourth support through positioning structures, and are respectively locked and connected with the first support and the fourth support at two ends.
2. The safety construction platform for pouring a bearing platform and a tower base according to claim 1, wherein the positioning structure comprises:
The mounting plate is arranged on the fourth bracket or the third bracket or the second bracket;
The backing plates are of C-shaped steel structures, two backing plates are oppositely arranged on the mounting plate, a gap is formed between the two backing plates, the anchor rods pass through the gap and between the two first backing plates, and the arrangement directions of the two backing plates are perpendicular to the arrangement direction of the mounting plate;
The locating plate, be provided with the semicircle orifice on the locating plate, two semicircle orifice butt sets up on the locating plate, forms a round hole, the stock runs through in two locating plates through the round hole, the locating plate with the backing plate links to each other.
3. The safety construction platform for pouring a bearing platform and a tower base according to claim 2, wherein the mounting frame body further comprises:
the two locking parts are symmetrically arranged at two ends of the anchor rod, one locking part is connected with the bottom of the first bracket in an abutting mode, and the other locking part is connected with the top of the fourth bracket in an abutting mode.
4. A safety construction platform for pouring a pile cap and a foundation according to claim 3, wherein the locking portion comprises:
The abutting plate is sleeved on the anchor rod and is in abutting connection with the fourth bracket or the first bracket;
The gasket is sleeved on the anchor rod, is connected with the abutting plate in an abutting mode, and is positioned on one surface far away from the fourth bracket or the first bracket;
The lock nut is sleeved on the anchor rod and connected with the anchor rod through threads, and the lock nut is connected with one side, away from the abutting plate, of the gasket in an abutting mode.
5. The safe construction platform for pouring a bearing platform and a tower base according to claim 4, wherein an anchor beam mounting structure is further arranged on the first bracket, the anchor beam mounting structure is arranged along the square structure of the first bracket, and the anchor beam mounting structure is used for locking and mounting one end, far away from the fourth bracket, of the anchor rod on the first bracket.
6. The safety construction platform for pouring a bearing platform and a tower base according to claim 5, wherein the anchor beam mounting structure comprises:
The anchor beam installation groove is of a strip U-shaped structure and is arranged along the periphery of the first bracket;
One end, far away from the fourth bracket, of the anchor rod penetrates through the anchor beam mounting groove;
The connecting steel bar is sleeved on the anchor rod, and one end of the connecting steel bar is abutted to the anchor beam mounting groove;
The steel bar net is square, the steel bar net sleeve is arranged on the anchor rod, the steel bar net sleeve is arranged outside the connecting steel bars, the bottom end of the steel bar net is lapped on the anchor beam mounting groove, and the anchor beam mounting structure for limiting the anchor rod is formed.
7. The safety construction platform for pouring a bearing platform and a tower base according to claim 6, wherein the reinforcing mesh is of a multi-layer structure.
8. The safety construction platform for pouring a bearing platform and a tower base according to claim 2, wherein the shape of the base plate is replaced by I-steel by C-steel.
9. The safety construction platform for pouring a pile cap and a foundation according to any one of claims 1 to 8, wherein the arrangement structure of the connection plate between the first bracket, the second bracket, the third bracket and the fourth bracket comprises:
One or more of an inclined support structure, a crossed support structure and a vertical support structure.
CN202322157160.4U 2023-08-11 2023-08-11 Safety construction platform for pouring bearing platform and tower base Active CN220927919U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322157160.4U CN220927919U (en) 2023-08-11 2023-08-11 Safety construction platform for pouring bearing platform and tower base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322157160.4U CN220927919U (en) 2023-08-11 2023-08-11 Safety construction platform for pouring bearing platform and tower base

Publications (1)

Publication Number Publication Date
CN220927919U true CN220927919U (en) 2024-05-10

Family

ID=90969637

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322157160.4U Active CN220927919U (en) 2023-08-11 2023-08-11 Safety construction platform for pouring bearing platform and tower base

Country Status (1)

Country Link
CN (1) CN220927919U (en)

Similar Documents

Publication Publication Date Title
KR101391637B1 (en) Constrution methoed for Prestressed Composite Truss girder using steel truss member
CN117107807A (en) Safety construction platform for pouring bearing platform and tower base and construction method
CN220927919U (en) Safety construction platform for pouring bearing platform and tower base
CN215925691U (en) Bearing support for casting No. 0 block of bridge
CN211733671U (en) Bearing structure and hoisting equipment
CN220927920U (en) Safety construction platform and system for pouring bearing platform and tower base
CN218292430U (en) Girder steel side direction backup plate building carrier plate internal connection
CN215167184U (en) Angle-adjustable oblique angle I-shaped steel beam
CN220927836U (en) Bearing platform and anchor structure for positioning anchor rod of tower seat and safe construction platform
CN216515100U (en) Hollow rectangular section assembled pier
CN220927921U (en) Safety construction supporting structure, construction platform and supporting system for pouring of bearing platform and tower base
CN215166027U (en) Combined counterweight for excavator, counterweight for excavator and excavator
CN213805443U (en) Steel construction, frame beam structure, side slope reinforced structure and reinforcement and support structure
CN207567998U (en) A kind of composite structure of steel plate shear force wall and steel column
CN102127962B (en) The bidirectional stress base section of the attached lift scaffold improved
CN210562653U (en) Assembled structure connecting piece
CN209620078U (en) A kind of assembling type steel structure tower crane
CN220117021U (en) Be used for discontinuous steel anchor beam accurate positioning bracket system
CN217000226U (en) Escalator in building and peripheral shock insulation seam structure thereof
CN214940973U (en) Connecting node of modularized steel structural member and modularized steel structure thereof
CN219931669U (en) Accurate positioning device suitable for steel pipe upright post in reservoir area of metro vehicle section
CN109252527B (en) Foundation support beam for building construction and construction method thereof
CN218581226U (en) Portable tying and hanging component of H-beam safety belt
CN218813869U (en) Basement returns top supporting structure
CN219527350U (en) Gravity type anchorage main cable prestress anchoring positioning device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant