CN220891285U - Pipeline bracket for reconstruction construction of white spirit conveying pipeline - Google Patents

Pipeline bracket for reconstruction construction of white spirit conveying pipeline Download PDF

Info

Publication number
CN220891285U
CN220891285U CN202322840822.8U CN202322840822U CN220891285U CN 220891285 U CN220891285 U CN 220891285U CN 202322840822 U CN202322840822 U CN 202322840822U CN 220891285 U CN220891285 U CN 220891285U
Authority
CN
China
Prior art keywords
pipeline
bracket
fixing plate
white spirit
newly
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322840822.8U
Other languages
Chinese (zh)
Inventor
郭春江
罗志勇
李远树
宋洪坤
陈艺为
廖娇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Luzhou Pinchuang Technology Co Ltd
Luzhou Laojiao Co Ltd
Luzhou Laojiao Brewing Co Ltd
Original Assignee
Luzhou Pinchuang Technology Co Ltd
Luzhou Laojiao Co Ltd
Luzhou Laojiao Brewing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Luzhou Pinchuang Technology Co Ltd, Luzhou Laojiao Co Ltd, Luzhou Laojiao Brewing Co Ltd filed Critical Luzhou Pinchuang Technology Co Ltd
Priority to CN202322840822.8U priority Critical patent/CN220891285U/en
Application granted granted Critical
Publication of CN220891285U publication Critical patent/CN220891285U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model discloses a pipeline bracket for the reconstruction construction of a white spirit conveying pipeline, which belongs to the technical field of white spirit production and manufacturing. According to the utility model, the newly-added pipeline bracket is connected with the first fixing plate, and the first fixing plate and the second fixing plate are fixed on the original pipeline bracket through bolts, so that the fixing of the newly-added pipeline bracket is realized, and the anchor bolt drilling and welding and other fire-moving operations are not needed in the fixing process, so that a series of front-mounted operations in the prior art for ensuring the construction safety are omitted, the influence of pipeline transformation construction on normal production is reduced, the base wine loss is avoided, the cost is saved, and the construction safety risk is reduced.

Description

Pipeline bracket for reconstruction construction of white spirit conveying pipeline
Technical Field
The utility model relates to the technical field of white spirit production and manufacturing, in particular to a pipeline bracket for white spirit conveying pipeline reconstruction construction.
Background
The current white spirit enterprises commonly adopt a pipeline system for transferring and conveying the wine source. The wine conveying pipeline support is various in form, and is laid outdoors in a form of a low support or a pipe gallery and the like by generally selecting a T-shaped or door-shaped support prefabricated by steel such as angle steel, channel steel and the like indoors. Due to production requirements, process adjustment and other reasons, the wine conveying pipeline is transformed and newly added, and the original pipeline bracket often does not reserve enough installation space, so that the newly added pipeline bracket is needed.
The newly-added bracket is generally fixed by adopting foundation bolts or directly welded with the original bracket, but because white spirit is inflammable, explosive and volatile liquid, the fire hazard is high, and the fire-moving operation such as drilling, welding and the like is performed near a storage area or a conveying pipeline, so that the safety risk is higher. Therefore, a series of prepositions are needed to ensure the construction safety before the fire operation such as drilling, welding and the like. The method specifically comprises the following steps: the pipeline is emptied, the wine liquid in the pipeline is replaced, clear water is thoroughly washed, blown off and the like, and the pipeline is detected to be qualified by flammable gas. The preparation operation is long in time consumption, high in cost, and the production schedule is influenced, so that certain base wine is lost, the rinse-through water is difficult to recover and treat, and certain environmental protection hidden trouble exists.
Disclosure of utility model
In order to solve the problems of time and labor consumption for guaranteeing construction safety in the conventional white spirit production and during the reconstruction construction of a conveying pipeline, the utility model provides a pipeline bracket for the reconstruction construction of a white spirit conveying pipeline.
The technical scheme adopted for solving the technical problems is as follows:
The utility model provides a white spirit pipeline reforms transform construction and uses pipeline support, contains former pipeline support, still contains newly-increased pipeline support, first fixed plate and second fixed plate, and newly-increased pipeline support is connected with first fixed plate, and first fixed plate and second fixed plate pass through the bolt fastening on former pipeline support, and newly-increased pipeline support is used for laying new pipeline.
According to the application, the newly-added pipeline bracket is connected with the first fixing plate, the first fixing plate and the second fixing plate are fixed on the original pipeline bracket through bolts, so that the newly-added pipeline bracket is fixed, and additional anchor bolt drilling and welding fire operation is not needed in the fixing process, so that a series of prepositive operations for ensuring construction safety in the prior art are omitted, the influence of pipeline transformation construction on normal production is reduced, base wine loss is avoided, cost is saved, and construction safety risks are reduced. Bolts are commonly in the forms of stud bolts, common bolts and the like; the common form of the new pipeline laid on the newly added pipeline bracket is U-shaped pipe clamps, pipe brackets and the like.
In some embodiments, the first and second securing plates are secured to the original conduit bracket by studs.
In this embodiment, the first fixing plate and the second fixing plate are preferably connected by using stud bolts, which is suitable for the situation where the length of the required connecting piece is longer, and the bearing performance is good, so that the dismounting is allowed for many times without damaging the connected piece.
In some embodiments, lock washers are provided at both ends of the stud.
In the embodiment, the connection fixing positions between the stud bolts and the two fixing plates, namely the first fixing plate and the second fixing plate, are provided with the anti-loosening washers so as to ensure firm and reliable connection.
In some embodiments, the first fixing plate is disposed above the original pipe support, the second fixing plate is disposed below the original pipe support, and the first fixing plate is provided with a through slot, and the width of the through slot is adapted to the width of the upper end face of the original pipe support.
In this embodiment, first fixed plate and second fixed plate set up respectively in original pipeline support upper and lower both sides, add logical groove on the first fixed plate of upside, lead to the width looks adaptation of groove width and original pipeline support up end to guarantee to the spacing of first fixed plate, avoid installing or during the use, the skew of newly-increased pipeline support position.
In some embodiments, the newly-added pipeline bracket is a door-shaped bracket, and two ends of an opening of the door-shaped bracket are respectively connected with the first fixing plate.
In the embodiment, the newly-added pipeline support is a door-shaped support, so that the newly-added pipeline is conveniently paved and implemented.
In some embodiments, a plurality of U-shaped pipe clamps are arranged on the newly added pipeline bracket.
In the embodiment, the newly-added pipeline bracket is provided with a U-shaped pipe clamp so as to realize multidirectional limiting and fixing on the newly-laid pipeline.
The beneficial effects of the utility model are as follows:
1. The newly-added pipeline bracket is connected to the original pipeline bracket through the first fixing plate and the second fixing plate, so that fire operation such as drilling or welding is avoided, a series of prepositions for ensuring construction safety in the prior art are omitted, the influence of pipeline transformation construction on normal production is reduced, and meanwhile base liquor loss is avoided, cost is saved, and construction safety risks are reduced.
2. The two fixing plates are fixedly connected through the stud, and the connecting part is further provided with a lock washer for ensuring the firmness and reliability of connection, and the lock washer is suitable for the situation that the length of a connecting piece is required to be longer, the bearing performance is good, and the connecting piece is not damaged due to the fact that the connecting piece is allowed to be disassembled and assembled for multiple times.
3. The newly-increased pipeline support is a door-shaped support, and a plurality of U-shaped pipe clamps are arranged on the newly-increased pipeline support to realize limit fixation on newly-laid pipelines.
Drawings
FIG. 1 is a perspective view showing an installation state of a newly added pipeline bracket according to a first embodiment of the present utility model;
FIG. 2 is a front view of an installation state of a newly added pipeline bracket according to a first embodiment of the present utility model;
FIG. 3 is a cross-sectional view taken along line A-A of FIG. 2;
Fig. 4 is a schematic diagram of an installation state of a newly added pipeline bracket according to a second embodiment of the present utility model;
Fig. 5 is a schematic diagram of an installation state of a newly added pipeline bracket according to a third embodiment of the present utility model;
Fig. 6 is a schematic diagram of an installation state of a newly added pipeline bracket according to a fourth embodiment of the present utility model.
The drawing is marked as 1-original pipeline bracket, 21-first fixed plate, 22-second fixed plate, 3-newly added pipeline bracket, 4-U-shaped pipe clamp, 5-stud, 6-through groove and 7-pipe bracket.
Detailed Description
The utility model is further described below with reference to the accompanying drawings.
The present utility model will be described in further detail with reference to the drawings and examples, in order to make the objects, technical solutions and advantages of the present utility model more apparent. It should be understood that the specific embodiments described herein are for purposes of illustration only and are not intended to limit the scope of the utility model.
Example 1
As shown in fig. 1-3, the utility model provides a pipeline bracket for reconstruction construction of a white spirit conveying pipeline.
As shown in fig. 1, the pipeline laying device comprises a newly-added pipeline support 3, wherein a U-shaped pipe clamp 4,U and a pipe clamp 4 are arranged on the newly-added pipeline support 3 and used for limiting and fixing a new pipeline to be laid.
As shown in fig. 2 and 3, in the present embodiment, the lower part of the newly added pipe bracket 3 is integrally provided with the first fixing plate 21, and the first fixing plate 21 and the second fixing plate 22 are connected by the stud bolts 5.
In this embodiment, the above connection method avoids the fire-moving operations such as drilling and welding during the adjustment of the conveying pipeline in the white spirit production, so a series of pre-operations in order to ensure the construction safety in the prior art are omitted, so as to reduce the influence of the pipeline transformation construction on the normal production, avoid the base wine loss, save the cost and reduce the construction safety risk.
Alternatively, in the present embodiment, the first fixing plate 21 and the second fixing plate 22 are fixedly connected by the stud bolts 5, and obviously, common connection fixing forms such as common bolts can be also realized.
In the present embodiment, the upper and lower ends of the stud bolts 5 are fixed by nuts, respectively, to achieve fixed connection of the first fixing plate 21 and the second fixing plate 22.
Further, in this embodiment, lock washers (not shown) are provided at the fixing positions of the upper and lower ends of the stud bolts 5 to ensure firm and reliable connection.
In the present embodiment, the first fixing plate 21 is disposed above the original pipe bracket 1, and the second fixing plate 22 is disposed below the original pipe bracket 1.
Example two
The main differences between the pipeline bracket for the reconstruction construction of the white spirit conveying pipeline in the embodiment and the first embodiment are that: the first fixing plate 21 is provided with a through groove 6.
Specifically, fig. 3 and fig. 4 can be compared, in this embodiment, the first fixing plate 21 is provided with a through groove 6, the direction of the through groove 6 is consistent with the length direction of the original pipe support 1, and the width of the through groove 6 is adapted to the width of the upper end face of the original pipe support 1, so as to ensure the limit of the first fixing plate 21, and avoid the offset of the position of the newly added pipe support 3 during installation or use.
Example III
The main differences between the pipeline bracket for the reconstruction construction of the white spirit conveying pipeline in the embodiment and the first embodiment are that: the structure of the newly added pipeline bracket 3 is different.
In the first embodiment, the newly added pipe bracket 3 is a portal bracket, and in this embodiment, the newly added pipe bracket 3 is structured as shown in the figure. The structure of the newly added pipe bracket 3 is not limited to that of the first embodiment, and the newly laid pipe is not necessarily disposed above the newly added pipe bracket 3.
In both embodiments, the newly added pipe bracket 3 is angle steel. Obviously, the common forms such as channel steel and the like can be replaced. The shape of the newly added pipe bracket 3 is not limited to that shown in the first embodiment.
Example IV
The main differences between the pipeline bracket for the reconstruction construction of the white spirit conveying pipeline in the embodiment and the first embodiment are that: the newly added pipeline bracket 3 is used for limiting and fixing the newly laid pipeline in different modes.
In particular, as shown in example one, a U-shaped pipe clamp 4 is used to limit the securing of a newly laid pipe. In this embodiment, the pipe carrier 7 is used to limit the newly laid pipe.
The foregoing description of the preferred embodiments of the utility model is not intended to be limiting, but rather is intended to cover all modifications, equivalents, and alternatives falling within the spirit and principles of the utility model.

Claims (6)

1. Pipeline support is used in white spirit pipeline transformation construction contains original pipeline support (1), characterized by: the novel pipeline laying device further comprises a novel pipeline support (3), a first fixing plate (21) and a second fixing plate (22), wherein the novel pipeline support (3) is connected with the first fixing plate (21), the first fixing plate (21) and the second fixing plate (22) are fixed on the original pipeline support (1) through bolts, and the novel pipeline support (3) is used for laying a novel pipeline.
2. The pipeline bracket for white spirit conveying pipeline reconstruction construction according to claim 1, wherein: the first fixing plate (21) and the second fixing plate (22) are fixed on the original pipeline bracket (1) through stud bolts (5).
3. The pipeline bracket for the reconstruction construction of the white spirit conveying pipeline as set forth in claim 2, wherein: and anti-loosening washers are arranged at the fixing positions of the two ends of the stud bolts (5).
4. A pipeline bracket for white spirit conveying pipeline reconstruction construction according to any one of claims 1 to 3, characterized in that: the first fixed plate (21) is arranged above the original pipeline bracket (1), the second fixed plate (22) is arranged below the original pipeline bracket (1), the first fixed plate (21) is provided with a through groove (6), and the width of the through groove (6) is matched with the width of the upper end face of the original pipeline bracket (1).
5. The pipeline bracket for white spirit conveying pipeline reconstruction construction according to claim 1, wherein: the newly-added pipeline bracket (3) is a door-shaped bracket, and two ends of the opening of the door-shaped bracket are respectively connected with a first fixing plate (21).
6. The pipeline bracket for white spirit conveying pipeline reconstruction construction according to claim 1, wherein: a plurality of U-shaped pipe clamps (4) are arranged on the newly added pipeline bracket (3).
CN202322840822.8U 2023-10-23 2023-10-23 Pipeline bracket for reconstruction construction of white spirit conveying pipeline Active CN220891285U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322840822.8U CN220891285U (en) 2023-10-23 2023-10-23 Pipeline bracket for reconstruction construction of white spirit conveying pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322840822.8U CN220891285U (en) 2023-10-23 2023-10-23 Pipeline bracket for reconstruction construction of white spirit conveying pipeline

Publications (1)

Publication Number Publication Date
CN220891285U true CN220891285U (en) 2024-05-03

Family

ID=90836776

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322840822.8U Active CN220891285U (en) 2023-10-23 2023-10-23 Pipeline bracket for reconstruction construction of white spirit conveying pipeline

Country Status (1)

Country Link
CN (1) CN220891285U (en)

Similar Documents

Publication Publication Date Title
CN207880235U (en) Reinforced non-solder pipe joint hoop
CN220891285U (en) Pipeline bracket for reconstruction construction of white spirit conveying pipeline
CN201795174U (en) Fixing support for erecting and laying ductile iron pipes
CN204554137U (en) Air conduit fast connector anchor ear
CN205534843U (en) Insulation cover can be dismantled to bellows antiskid stainless steel
CN212163212U (en) Photovoltaic module mounting system
KR100930123B1 (en) Clamp for gas meter pipe for easy removal and attachment
CN217874665U (en) Composite pipe connecting piece
JP3218691U (en) Photovoltaic generator support stand connection kit
CN216112748U (en) Compensator for heating pipeline
CN219954578U (en) Transformer oiling flange
CN217330191U (en) Factory building assembled exhaust duct system
CN214743940U (en) Connecting device for gas pipeline
CN218970063U (en) Pre-buried assembled piping lane support
CN211502336U (en) Gas installation system of registering one's residence
CN215763660U (en) Pipe code and pipeline assembly
CN215674172U (en) Pipe joint for connecting steel pipes
CN211118002U (en) Supporting and fixing part for electromechanical pipeline on steel beam
CN220102394U (en) Pipeline connecting device convenient to installation is dismantled
CN204905785U (en) From locking -type photovoltaic cable protection device
CN211010164U (en) Quick mounting structure of water pipe
CN211290230U (en) Heating system individual transmission and distribution pipeline component in pipe well and pipe well heating pipeline
CN215344447U (en) Photovoltaic device
CN218914180U (en) Temporary plugging device for pipe orifice of embedded pipe of power station house
CN212176063U (en) Connection structure of prefabricated building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant