CN220878228U - Cooling dust collector is used in green construction of pile foundation - Google Patents

Cooling dust collector is used in green construction of pile foundation Download PDF

Info

Publication number
CN220878228U
CN220878228U CN202322829727.8U CN202322829727U CN220878228U CN 220878228 U CN220878228 U CN 220878228U CN 202322829727 U CN202322829727 U CN 202322829727U CN 220878228 U CN220878228 U CN 220878228U
Authority
CN
China
Prior art keywords
fixedly connected
water
cooling
filter screen
green construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322829727.8U
Other languages
Chinese (zh)
Inventor
胡磊
杨熙
占俊
张传龙
何乃义
易承权
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Anzhen Geotechnical Engineering Co ltd
Original Assignee
Wuhan Anzhen Geotechnical Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Anzhen Geotechnical Engineering Co ltd filed Critical Wuhan Anzhen Geotechnical Engineering Co ltd
Priority to CN202322829727.8U priority Critical patent/CN220878228U/en
Application granted granted Critical
Publication of CN220878228U publication Critical patent/CN220878228U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Filtration Of Liquid (AREA)

Abstract

The utility model relates to the technical field of building construction and discloses a cooling and dust removing device for green construction of pile foundations, which comprises a bottom plate, wherein a water tank is fixedly connected to the left side of the top end of the bottom plate, a purifying box is fixedly connected to the front side of the right end of the water tank, mounting blocks are fixedly connected to the front side and the rear side of the outer part of the purifying box, a movable groove is formed in the mounting blocks, a push rod is slidably connected to the inner part of the movable groove, a filter screen is arranged in the purifying box, a placing groove is formed in the front side and the rear side of the inner part of the filter screen, a spring II is fixedly connected to the inner part of the placing groove, and a clamping block is fixedly connected to one end of the spring II. The utility model can utilize domestic wastewater and water with poor water quality, provides a reliable water source, realizes effective cooling and dust removal in areas with water shortage or poor water quality, and has more convenient replacement of the filter screen and higher use flexibility.

Description

Cooling dust collector is used in green construction of pile foundation
Technical Field
The utility model relates to the technical field of building construction, in particular to a cooling and dedusting device for green construction of pile foundations.
Background
The green construction of the pile foundation is an environment-friendly and sustainable development pile foundation construction method, and in the traditional pile foundation construction process, large-scale mechanical equipment can generate a large amount of heat and dust, so that the environment and the health of workers are negatively influenced. Therefore, the environment-friendly construction measures are adopted to reduce the negative effects, promote the environment protection and the resource conservation, and the cooling and dust removing device is a common green construction measure and plays an important role in pile foundation construction, and the effect of cooling and dust removing can be achieved by spraying water mist, so that the working environment of workers is improved, the uncomfortable feeling of the workers in the high-temperature environment is reduced, the working efficiency and the safety of the workers are improved, and the pollution to the surrounding environment is reduced.
Through retrieving, chinese patent publication No. CN214573653U (-kind of cooling dust collector for green construction of pile foundation), including storage water tank, support automatically controlled pole, pump, thick hose, shunt tubes, flexible automatically controlled pole, atomising head, thin hose isotructure, can carry water to the atomising head blowout to reduce the temperature and dust to construction environment improves cooling dust removal efficiency and quality, however above-mentioned patent has certain limitation, for example in lack of water or the poor area of quality of water, because need be to construction environment last mist cooling, clear water resource can not obtain effectual satisfaction for mist cooling is difficult to effectively implement, for this the technical field person proposes a cooling dust collector for green construction of pile foundation to solve above-mentioned problem.
Disclosure of utility model
In order to make up for the defects, the utility model provides a cooling and dedusting device for green construction of pile foundations, and aims to solve the problem that spray cooling is affected in areas with water shortage or poor water quality.
In order to achieve the above purpose, the present utility model provides the following technical solutions: the utility model provides a green construction of pile foundation is with cooling dust collector, includes the bottom plate, the top left side fixedly connected with water tank of bottom plate, the right-hand member front side fixedly connected with purifying box of water tank, the equal fixedly connected with installation piece in both sides around the outside of purifying box, the removal groove has been seted up to the inside of installation piece, the inside sliding connection of removal groove has the push rod, the inside of purifying box is provided with the filter screen, the standing groove has all been seted up to both sides around the inside of filter screen, the inside fixedly connected with spring two of standing groove, the one end fixedly connected with fixture block of spring two, the inside bottom fixedly connected with of purifying box places the board, the inside middle side of placing the board is provided with spring one, the top right side of bottom plate is provided with water spray mechanism.
Through the technical scheme, pollutants and solid particles in wastewater in water can be removed or reduced to a certain extent, so that the water quality is improved and meets specific use requirements, thereby being capable of utilizing wastewater in life and water with poor water quality, providing a reliable water source, realizing effective cooling and dust removal in areas with water shortage or poor water quality, simultaneously being more convenient for replacing a filter screen and ensuring the use effect of the filter screen.
Further, the water spraying mechanism comprises a fixing frame, the fixing frame is fixedly connected to the top end of the bottom plate, and the top end of the fixing frame is fixedly connected with a spray head;
through above-mentioned technical scheme for the water spray of shower nozzle is more stable, and the cooling dust removal effect is better.
Further, a pumping pump is fixedly connected to the rear side of the right end of the water tank, a connecting pipe is fixedly connected to the input end of the pumping pump, a water pipe is fixedly connected to the output end of the pumping pump, the front side of the connecting pipe is fixedly connected with the rear side of the purifying tank, and the right side of the water pipe is fixedly connected with the left side of the spray head;
Through the technical scheme, the filtered water can be conveyed into the spray head for cooling and dedusting treatment.
Further, the outer part of the clamping block is in sliding connection with the inner part of the placing groove, and the outer part of the clamping block is clamped with the inner part of the moving groove;
through above-mentioned technical scheme, realized the installation fixed or the dismantlement change to the filter screen.
Further, the outer part of the filter screen is in sliding connection with the inner part of the placing plate, and the bottom end of the placing plate is in contact with the top end of the first spring;
Through the technical scheme, the filter screen can be detached more conveniently.
Further, the top end of the water tank is provided with a water inlet;
Through above-mentioned technical scheme, through the water inlet, the water tank can be poured into required water source and supplied to maintain the operation of device and the required water yield in the cooling dust removal process.
Further, the lower surface of the clamping block is provided with an inclined plane, and one side of the clamping block, which is far away from the second spring, is contacted with one side of the push rod in the moving groove;
Through above-mentioned technical scheme, can be convenient for install the filter screen through the setting of fixture block inclined plane.
Further, the top end of the filter screen is fixedly connected with a sealing plate;
Through above-mentioned technical scheme, guaranteed the leakproofness at purifying box top.
The utility model has the following beneficial effects:
according to the utility model, through the mutual cooperation of the structures of the purifying box, the filter screen, the first spring, the clamping block, the spray head, the push rod and the like, pollutants and solid particles in the wastewater can be removed or reduced to a certain extent, so that the water quality is improved and meets specific use requirements, the wastewater in life and the water with poor water quality can be utilized, a reliable water source is provided, effective cooling and dust removal are realized in areas with water shortage or poor water quality, meanwhile, the filter screen is convenient to replace, and the use flexibility is high.
Drawings
Fig. 1 is a perspective view of a cooling and dedusting device for green construction of pile foundations, which is provided by the utility model;
FIG. 2 is an enlarged view of FIG. 1 at A;
Fig. 3 is a schematic diagram of a connecting pipe structure of a cooling and dedusting device for green construction of pile foundations;
FIG. 4 is a cross-sectional view of a water tank of the cooling and dedusting device for green construction of pile foundations;
FIG. 5 is an enlarged view of FIG. 4 at B;
FIG. 6 is a cross-sectional view of a purifying box of the cooling and dedusting device for green construction of pile foundation, which is provided by the utility model;
Fig. 7 is an enlarged view at C in fig. 6.
Legend description:
1. A bottom plate; 2. a water tank; 3. a water inlet; 4. a pump; 5. a water pipe; 6. a purifying box; 7. a water spraying mechanism; 701. a fixing frame; 702. a spray head; 8. a connecting pipe; 9. a sealing plate; 10. a filter screen; 11. placing a plate; 12. a mounting block; 13. a push rod; 14. a first spring; 15. a moving groove; 16. a clamping block; 17. a second spring; 18. and (5) placing a groove.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1-7, one embodiment provided by the present utility model is: the utility model provides a green construction of pile foundation is with cooling dust collector, includes bottom plate 1, the top left side fixedly connected with water tank 2 of bottom plate 1, the right-hand member front side fixedly connected with purifying box 6 of water tank 2, and water tank 2 is used for holding the waste water, provides the water source supply, under the inside filter screen 10 effect of purifying box 6, can filter solid particle and the pollutant in the waste water. The inside of installing the movable tank 15 has been seted up to the outside front and back both sides of purifying box 6 equal fixedly connected with installation piece 12, the inside of installing the movable tank 15 is slidingly connected with push rod 13, the inside of purifying box 6 is provided with filter screen 10, the standing groove 18 has all been seted up to both sides around the inside of filter screen 10, the inside fixedly connected with spring two 17 of standing groove 18, the one end fixedly connected with fixture block 16 of spring two 17, the inside bottom fixedly connected with of purifying box 6 places board 11, the inside middle side of placing board 11 is provided with spring one 14, through pressing push rod 13, can make it promote fixture block 16 to remove to the inside of standing groove 18, when the inside of standing groove 18 is moved to fixture block 16 completely, can upwards pop out filter screen 10 under the elasticity effect of spring one 14, pulling closing plate 9 alright come out filter screen 10 follow the inside of purifying box 6 at this moment, it is comparatively convenient to use, the top right side of bottom plate 1 is provided with water spray mechanism 7.
Referring to fig. 1-4, the water spraying mechanism 7 comprises a fixing frame 701, the fixing frame 701 is fixedly connected to the top end of the bottom plate 1, a spray head 702 is fixedly connected to the top end of the fixing frame 701, the fixing frame 701 can effectively fix the spray head 702, water can be sprayed to a construction environment through the spray head 702, and therefore the effects of cooling and dust removal are achieved.
Referring to fig. 1 to 4, the right end rear side of the water tank 2 is fixedly connected with the extraction pump 4, the input end of the extraction pump 4 is fixedly connected with the connecting pipe 8, the output end of the extraction pump 4 is fixedly connected with the water pipe 5, the front side of the connecting pipe 8 is fixedly connected with the rear side of the purification tank 6, the right side of the water pipe 5 is fixedly connected with the left side of the spray head 702, water in the purification tank 6 can be extracted through the connecting pipe 8 by the operation of the extraction pump 4, and the water can be conveyed into the spray head 702 through the water pipe 5, so that the construction environment is cooled and dedusted.
Referring to fig. 7, the outside of the clamping block 16 is slidably connected with the inside of the placement groove 18, the outside of the clamping block 16 is engaged with the inside of the moving groove 15, and the filter screen 10 can be fixed inside the purifying box 6 by the engagement of the clamping block 16 and the moving groove 15, so that the waste water can be effectively filtered and purified, and when the clamping block 16 moves into the placement groove 18, the filter screen 10 can be taken out, so that the waste water can be cleaned or replaced conveniently.
Referring to fig. 4 to 5, the outside of the filter screen 10 is slidably connected to the inside of the placement plate 11, the bottom end of the placement plate 11 contacts with the top end of the first spring 14, and when the filter screen 10 is fixed inside the purifying box 6, the bottom end of the filter screen 10 presses the first spring 14 to be in a compressed state, so that after the filter screen 10 is released from the fixation, the filter screen 10 can be ejected under the action of the first spring 14.
Referring to fig. 1, a water inlet 3 is provided at the top of a water tank 2, and the water inlet 3 is an inlet for introducing an external water source into the water tank 2, and the water tank 2 can be filled with a required water source supply through the water inlet 3 to maintain the operation of the device and the amount of water required in the cooling and dust removing processes.
Referring to fig. 6 to 7, the lower surface of the clamping block 16 is provided with an inclined surface, one side of the clamping block 16 away from the second spring 17 is contacted with one side of the push rod 13 in the moving groove 15, and the filter screen 10 can be conveniently installed through the arrangement of the inclined surface.
Referring to fig. 4, a sealing plate 9 is fixedly coupled to the top end of the filter screen 10, and the sealing plate 9 functions to ensure sealability of the top of the purge bin 6, thereby preventing water from leaking through the top end of the purge bin 6.
Working principle: when specifically using this device, can add water to the inside of water tank 2, afterwards when needing to cool down and remove dust, can operate through starting pump 4, thereby can be with the inside water of water tank 2, through purifying box 6, and filter the purification under the effect of filter screen 10, water after the purification can pass through connecting pipe 8 and carry the shower nozzle 702 inside under the effect of raceway 5, thereby carry out water spray cooling and remove dust, when needs change filter screen 10, can make it promote fixture block 16 to remove to the inside of standing groove 18 through pressing push rod 13, when fixture block 16 completely removes the inside of standing groove 18, under the elasticity effect of spring one 14, can upwards pop out filter screen 10, pulling closing plate 9 alright extract out filter screen 10 from the inside of purifying box 6 this moment, when installing filter screen 10, then place filter screen 10 in the inside of purifying box 6 again, because the inclined plane setting of fixture block 16 receives the extrusion effect of purifying box 6, can remove the inside of standing groove 18 and extrude spring two 17 again, make it be compressed state, afterwards, the elasticity of two-side spring 17 is under the elasticity effect of driving the fixture block 16 can be with the filter screen 10, the inside of this kind has guaranteed that the filter screen 10 is changed conveniently, the filter screen 10 is more convenient, and more convenient has been changed.
Finally, it should be noted that: the foregoing description is only illustrative of the preferred embodiments of the present utility model, and although the present utility model has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described, or equivalents may be substituted for elements thereof, and any modifications, equivalents, improvements or changes may be made without departing from the spirit and principles of the present utility model.

Claims (8)

1. The utility model provides a green construction of pile foundation is with cooling dust collector, includes bottom plate (1), its characterized in that: the utility model discloses a water purification device, including bottom plate (1), filter screen (10), standing groove (18) have all been seted up to the inside of bottom plate (1), the right-hand member front side fixedly connected with purifying box (6) of bottom plate (1), all fixedly connected with installation piece (12) of both sides around the outside of purifying box (6), removal groove (15) have been seted up to the inside of installation piece (12), the inside sliding connection of removal groove (15) has push rod (13), the inside of purifying box (6) is provided with filter screen (10), standing groove (18) have all been seted up to both sides around the inside of filter screen (10), the inside fixedly connected with spring two (17) of standing groove (18), the one end fixedly connected with fixture block (16) of spring two (17), the inside bottom fixedly connected with of purifying box (6) places board (11), the inside middle side of placing board (11) is provided with spring one (14), the top right side of bottom plate (1) is provided with water spray mechanism (7).
2. The cooling and dedusting device for green construction of pile foundations according to claim 1, wherein: the water spraying mechanism (7) comprises a fixing frame (701), wherein the fixing frame (701) is fixedly connected to the top end of the bottom plate (1), and a spray head (702) is fixedly connected to the top end of the fixing frame (701).
3. The cooling and dedusting device for green construction of pile foundations according to claim 1, wherein: the water tank is characterized in that a pumping pump (4) is fixedly connected to the rear side of the right end of the water tank (2), a connecting pipe (8) is fixedly connected to the input end of the pumping pump (4), a water pipe (5) is fixedly connected to the output end of the pumping pump (4), the front side of the connecting pipe (8) is fixedly connected with the rear side of the purifying box (6), and the right side of the water pipe (5) is fixedly connected with the left side of the spray head (702).
4. The cooling and dedusting device for green construction of pile foundations according to claim 1, wherein: the outside of fixture block (16) and the inside sliding connection of standing groove (18), the outside of fixture block (16) and the inside looks block of removal groove (15).
5. The cooling and dedusting device for green construction of pile foundations according to claim 1, wherein: the outside of filter screen (10) and the inside sliding connection of placing board (11), the bottom of placing board (11) is contacted with the top of spring one (14).
6. The cooling and dedusting device for green construction of pile foundations according to claim 1, wherein: the top end of the water tank (2) is provided with a water inlet (3).
7. The cooling and dedusting device for green construction of pile foundations according to claim 1, wherein: the lower surface of the clamping block (16) is provided with an inclined plane, and one side of the clamping block (16) away from the second spring (17) is contacted with one side of the push rod (13) in the moving groove (15).
8. The cooling and dedusting device for green construction of pile foundations according to claim 1, wherein: the top end of the filter screen (10) is fixedly connected with a sealing plate (9).
CN202322829727.8U 2023-10-23 2023-10-23 Cooling dust collector is used in green construction of pile foundation Active CN220878228U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322829727.8U CN220878228U (en) 2023-10-23 2023-10-23 Cooling dust collector is used in green construction of pile foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322829727.8U CN220878228U (en) 2023-10-23 2023-10-23 Cooling dust collector is used in green construction of pile foundation

Publications (1)

Publication Number Publication Date
CN220878228U true CN220878228U (en) 2024-05-03

Family

ID=90867517

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322829727.8U Active CN220878228U (en) 2023-10-23 2023-10-23 Cooling dust collector is used in green construction of pile foundation

Country Status (1)

Country Link
CN (1) CN220878228U (en)

Similar Documents

Publication Publication Date Title
CN107171630B (en) A kind of dust-extraction unit of solar panel
CN220878228U (en) Cooling dust collector is used in green construction of pile foundation
CN209982885U (en) Special case for electronic communication equipment
CN209330047U (en) A kind of cleaning device for solar panels maintenance
CN218306939U (en) Central authorities' dust pelletizing system
CN214021382U (en) Stirring station dust collector based on 5G internet of things control
CN209735215U (en) Environment-friendly dust removal device with purification function and used for building construction
CN221015029U (en) High-efficient environmental protection electroplating exhaust treatment device
CN210874655U (en) Clean dust collector is used in cement manufacture
CN221015234U (en) Kiln waste gas treatment device
CN219977036U (en) Heat recovery device
CN219681813U (en) Filter equipment for sewage treatment
CN219942277U (en) Solar-energy-level high-purity silicon dust removal device
CN219580114U (en) Waste gas treatment device for recycling high-temperature waste gas
CN213577920U (en) Ventilation energy-saving equipment of green building
CN220142945U (en) Printing gas cleaning device
CN213363524U (en) Waste heat utilization device of diesel generator
CN211215977U (en) Environmental protection dust collecting equipment for interior decoration
CN216396690U (en) Automatic temperature control type electric bag composite dust removal device
CN218741091U (en) Gas purification treatment device
CN216909727U (en) Blast furnace flue gas processing apparatus
CN215027350U (en) Waste gas treatment device for cathode carbon production
CN213666688U (en) Independently clean formula far infrared sauna room
CN218721611U (en) Flue gas waste heat recycling device
CN218466710U (en) Municipal administration drainage is with efficient silt device of arranging

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant