CN220827695U - Bracket platform - Google Patents

Bracket platform Download PDF

Info

Publication number
CN220827695U
CN220827695U CN202322148238.6U CN202322148238U CN220827695U CN 220827695 U CN220827695 U CN 220827695U CN 202322148238 U CN202322148238 U CN 202322148238U CN 220827695 U CN220827695 U CN 220827695U
Authority
CN
China
Prior art keywords
platform
construction
pile foundation
abutment
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322148238.6U
Other languages
Chinese (zh)
Inventor
黄培
黄永成
张露
王俊
杨志鹏
周领
方康
潘祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
Original Assignee
China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Group Co Ltd MBEC filed Critical China Railway Major Bridge Engineering Group Co Ltd MBEC
Priority to CN202322148238.6U priority Critical patent/CN220827695U/en
Application granted granted Critical
Publication of CN220827695U publication Critical patent/CN220827695U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a bracket platform, and relates to the technical field of high pile cap construction. The bracket platform comprises a construction platform which is used for being arranged on a pile foundation; abutment pouring platform, it is used for setting up in the top of pile foundation, and is located construction platform's upper portion, and it is including being used for setting up bearing assembly and basement membrane on the pile foundation, and the basement membrane sets up in bearing assembly's upper portion. The utility model can be directly built on the pile foundation without building the support from the ground, thereby solving the problems of large slope angle of the abutment area and lower bearing capacity of the foundation, and if the conventional support is used for construction, the problems of poor stability of the support and difficult construction are faced, so the material cost of the support can be saved, and the abutment pouring platform can be suitable for different pile foundation heights, so the abutment pouring platform is simpler to construct, and the construction platform building cost and construction period are reduced.

Description

Bracket platform
Technical Field
The utility model relates to the technical field of high pile cap construction, in particular to a bracket platform.
Background
In the bridge construction process, a support is needed when concrete pouring is carried out on a bridge abutment bearing platform, a floor type support is usually used in the construction process, and a conventional floor type support erecting method comprises the following steps of: firstly, treating the foundation to enable the bearing capacity of the foundation to meet the corresponding requirement, then, sitting the scaffold on a backfill layer of the foundation, and then, connecting the longitudinal horizontal rod, the transverse horizontal rod and the diagonal brace according to the corresponding construction sequence.
However, in the existing floor stand erecting method, because the slope angle of the bridge abutment area is large and the bearing capacity of the foundation is low, if the conventional stand is used for construction, the problems of poor stability of the stand and difficult construction are faced; for the general bridge abutment, the working condition of large single pouring square quantity is required to be erected with a complicated floor stand, and under the condition, the construction is complicated and the construction period is long.
Disclosure of utility model
Aiming at the defects in the prior art, the utility model solves the technical problems as follows: how to reduce the construction cost and construction period of the construction platform.
In order to achieve the above object, the present utility model provides a bracket platform, comprising:
The construction platform is used for being arranged on the pile foundation;
Abutment pouring platform, it is used for setting up in the top of pile foundation, and is located construction platform's upper portion, and it is including being used for setting up bearing assembly and basement membrane on the pile foundation, and the basement membrane sets up in bearing assembly's upper portion.
On the basis of the technology, the bearing assembly comprises a distribution beam arranged at the top of the pile foundation, a spandrel girder arranged on the pile foundation and a bracket, wherein the spandrel girder is arranged at the bottom of the distribution beam, and the bracket is arranged at the bottom of the spandrel girder.
On the basis of the technology, the bottom film is arranged on the top of the distribution beam.
On the basis of the technology, the bracket is connected to the pile foundation through the climbing cone.
Based on the technology, the bottom film is a bamboo plywood.
On the technical basis, the construction platform comprises a supporting component and a construction station, wherein the supporting component is arranged on a pile foundation, and the construction station is arranged on the supporting component.
On the basis of the technology, the supporting component is a tripod.
On the basis of the technology, the tripod is connected to the pile foundation through the climbing cone.
On the basis of the technology, a cat ladder is arranged between the construction platform and the bottom film.
On the basis of the technology, the construction platform is provided with the fence.
Compared with the prior art, the utility model has the advantages that:
According to the utility model, the construction platform is built on the pile foundation, constructors can build the abutment pouring platform on the construction platform, and the bearing assembly of the abutment pouring platform can support the basement membrane and pouring construction. Compared with the existing floor stand erecting method, the bridge abutment pouring platform can be directly built on pile foundations without building a support from the ground, so that the problems that the slope angle of a bridge abutment area is large, the bearing capacity of a foundation is low, if a conventional support is used for construction, the stability of the support is poor, the construction is difficult are solved, the material cost of the support can be saved, the bridge abutment pouring platform can be suitable for different pile foundation heights, the bridge abutment pouring platform is simpler to construct, and the construction platform building cost and construction period are reduced.
Drawings
Fig. 1 is a schematic structural view of a bracket platform according to an embodiment of the present utility model.
In the figure: 1-distribution beam, 2-cat ladder, 3-rail, 4-construction station, 5-supporting component, 6-basement membrane, 7-spandrel girder, 8-bracket.
Detailed Description
Embodiments of the present utility model are described in further detail below with reference to the accompanying drawings.
Referring to fig. 1, a bracket platform in an embodiment of the present utility model includes: the construction platform, it is used for setting up on the pile foundation, and the upper portion of construction platform is provided with the abutment and pours the platform, and it is used for setting up in the top of pile foundation, and abutment pours the platform including being used for setting up bearing assembly and basement membrane 6 on the pile foundation, basement membrane 6 sets up in bearing assembly's upper portion.
Therefore, by building the construction platform on the pile foundation, constructors can build the bridge abutment pouring platform on the construction platform, and the bearing assembly of the bridge abutment pouring platform can support the basement membrane 6 and pouring construction. Compared with the existing floor stand erecting method, the bridge abutment pouring platform can be directly built on pile foundations without building a support from the ground, so that the problems that the slope angle of a bridge abutment area is large, the bearing capacity of a foundation is low, if a conventional support is used for construction, the stability of the support is poor, the construction is difficult are solved, the material cost of the support can be saved, the bridge abutment pouring platform can be suitable for different pile foundation heights, the bridge abutment pouring platform is simpler to construct, and the construction platform building cost and construction period are reduced.
Preferably, the bearing assembly comprises a distribution beam 1 arranged at the top of the pile foundation, a spandrel girder 7 arranged on the pile foundation and a bracket 8, wherein the spandrel girder 7 is arranged at the bottom of the distribution beam 1, and the bracket 8 is arranged at the bottom of the spandrel girder 7.
The design has the advantages that: the design can directly fix the bearing assembly on the pile foundation, and the bottom film can be directly built on the top of the bearing assembly, and the bracket 8 can be replaced by other supporting assemblies, but the strength is enough.
Preferably, the carrier film 6 is arranged on top of the distribution beam 1.
The design has the advantages that: the distribution beam 1 is a horizontally placed beam at the top of the pile foundation for supporting the basement membrane 6.
Preferably, bracket 8 is connected to the pile foundation by a climbing cone.
The design has the advantages that: the bracket 8 can be fixed on the pile foundation through a plurality of climbing cones, the climbing cones can be pre-buried in the construction process of manufacturing the pile foundation, and the bracket 8 is convenient to install through the design.
Preferably, the bottom film 6 is a bamboo plywood.
The design has the advantages that: the bamboo plywood has the advantages of high strength, good toughness, smooth and flat surface and easy demoulding, and is suitable for concrete pouring work.
Preferably, the construction platform comprises a support assembly 5 and a construction station 4, wherein the support assembly 5 is arranged on the pile foundation, and the construction station 4 is arranged on the support assembly 5.
The design has the advantages that: the construction platform 4 is arranged on the pile foundation through the supporting component 5, and the construction platform 4 can facilitate the construction and installation of the bridge abutment pouring platform.
Preferably, the support assembly 5 is a tripod.
The design has the advantages that: the supporting component 5 can be a tripod or a bracket, and only needs to support the construction table 4 and constructors.
Preferably, the tripod is connected to the pile foundation by a climbing cone.
The design has the advantages that: the tripod can be fixed on the pile foundation through the plurality of climbing cones, the climbing cones can be pre-buried in the construction process of manufacturing the pile foundation, and the tripod is convenient to install through the design.
Preferably, a ladder stand 2 is arranged between the construction table 4 and the bottom film 6.
The design has the advantages that: in order to facilitate the construction of the abutment casting platform and the subsequent concrete casting work, a cat ladder 2 is arranged between the construction abutment 4 and the basement membrane 6.
Preferably, the construction platform is provided with a fence 3.
The design has the advantages that: in order to improve the safety of construction, a fence 3 is erected on a construction platform, and the position of the fence 3 can be designed according to the construction requirement.
The utility model is not limited to the above-mentioned best mode, any person can obtain other various products under the teaching of the utility model, but any change in shape or structure is within the scope of protection of the utility model, and all the technical schemes are the same or similar to the utility model.

Claims (10)

1. A pallet platform, comprising:
The construction platform is used for being arranged on the pile foundation;
Abutment pouring platform, it is used for setting up in the top of pile foundation, and is located construction platform's upper portion, and it is including being used for setting up bearing assembly and basement membrane (6) on the pile foundation, and basement membrane (6) set up in bearing assembly's upper portion.
2. The tray platform of claim 1, wherein: the bearing assembly comprises a distribution beam (1) arranged at the top of the pile foundation, a spandrel girder (7) arranged on the pile foundation and a bracket (8), wherein the spandrel girder (7) is arranged at the bottom of the distribution beam (1), and the bracket (8) is arranged at the bottom of the spandrel girder (7).
3. The tray platform of claim 2, wherein: the bottom film (6) is arranged on the top of the distribution beam (1).
4. The tray platform of claim 2, wherein: the bracket (8) is connected to the pile foundation through a climbing cone.
5. The tray platform of claim 1, wherein: the bottom film (6) is a bamboo plywood.
6. The tray platform of claim 1, wherein: the construction platform comprises a supporting component (5) and a construction platform (4), wherein the supporting component (5) is arranged on a pile foundation, and the construction platform (4) is arranged on the supporting component (5).
7. The tray platform as claimed in claim 6, wherein: the support component (5) is a tripod.
8. The tray platform of claim 7, wherein: the tripod is connected to the pile foundation through the climbing cone.
9. The tray platform as claimed in claim 6, wherein: a cat ladder (2) is arranged between the construction platform (4) and the basement membrane (6).
10. The tray platform of claim 1, wherein: and a fence (3) is arranged on the construction platform.
CN202322148238.6U 2023-08-10 2023-08-10 Bracket platform Active CN220827695U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322148238.6U CN220827695U (en) 2023-08-10 2023-08-10 Bracket platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322148238.6U CN220827695U (en) 2023-08-10 2023-08-10 Bracket platform

Publications (1)

Publication Number Publication Date
CN220827695U true CN220827695U (en) 2024-04-23

Family

ID=90726090

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322148238.6U Active CN220827695U (en) 2023-08-10 2023-08-10 Bracket platform

Country Status (1)

Country Link
CN (1) CN220827695U (en)

Similar Documents

Publication Publication Date Title
CN111206768A (en) Light beam plate structure platform and construction method thereof
CN212582721U (en) Bearing platform of tower crane for vertical tower of top plate of foundation garage
CN220827695U (en) Bracket platform
CN211113217U (en) Curved surface support
CN110005198A (en) Taper pile shuttering support system and its construction method
CN202831628U (en) Combined type bailey frame load-bearing shelving for pouring large span concrete beam
CN215802536U (en) Novel hyperboloid curtain skeleton
CN115726462A (en) Super high-rise core tube and steel structure flat layer construction method and temporary support frame
CN212270703U (en) Bridge deck bearing combined support
CN113565346A (en) Assembled floor landing-free adjustable supporting structure and construction method
CN111305596A (en) Rapid dismounting and mounting reinforcing structure for beamless floor slab of basement and construction method thereof
CN220725814U (en) Floor-free temporary support structure for floor support plate
CN212271228U (en) Jig frame system for building truss in complex terrain
CN219862418U (en) Supporting structure of assembled viaduct bent cap
CN112030747B (en) Assembling and hoisting method for main gallery frame of super-large-diameter efficient concentrator
CN220789460U (en) Small box girder adjusting jacking frame
CN115162697B (en) Special-shaped column construction work I-shaped steel cantilever platform and construction method
CN217782866U (en) Self-bearing type formwork support device for slope concrete pouring
CN103711112A (en) Combined type bailey frame load-bearing shelving used for pouring large-span concrete beam
CN221422602U (en) DOME steel construction platform
CN220394301U (en) Can dismantle interim braced system of regulation steel case roof beam
CN219638391U (en) Standard plane multi-clamping template for water inlet tower construction
CN220059026U (en) A can assemble, adjustable interim fixed stay device for steel construction hoist and mount
CN216074806U (en) High mound pier pivot bridge construction structures
CN216130659U (en) Radial support for construction of water tower

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant