CN220786664U - Prefabricated segment storage device for construction - Google Patents

Prefabricated segment storage device for construction Download PDF

Info

Publication number
CN220786664U
CN220786664U CN202322235801.3U CN202322235801U CN220786664U CN 220786664 U CN220786664 U CN 220786664U CN 202322235801 U CN202322235801 U CN 202322235801U CN 220786664 U CN220786664 U CN 220786664U
Authority
CN
China
Prior art keywords
mounting
storage device
arc
screw rod
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322235801.3U
Other languages
Chinese (zh)
Inventor
吴春来
黄天贵
王鹏
张会传
谢南宇
霍东海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cccc First Cqmunicipal Construction Development Co ltd
Original Assignee
Cccc First Cqmunicipal Construction Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cccc First Cqmunicipal Construction Development Co ltd filed Critical Cccc First Cqmunicipal Construction Development Co ltd
Priority to CN202322235801.3U priority Critical patent/CN220786664U/en
Application granted granted Critical
Publication of CN220786664U publication Critical patent/CN220786664U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a prefabricated duct piece storage device for construction, which relates to the technical field of storage devices and comprises a bottom plate, wherein supporting tables are arranged on two sides of the upper surface of the bottom plate, an arc-shaped supporting plate is movably arranged at the top of each supporting table, two mounting rods are arranged on two sides of the upper surface of the bottom plate, and an adjusting mechanism for adjusting the position of a duct piece is arranged between the mounting rods. According to the utility model, the height of the mounting plate can be adjusted under the meshing action between the adjusting screw rod and the screw rod sleeve through the driving of the driving motor, the arc-shaped push plate can be pushed to move through the work of the hydraulic cylinder, the pipe piece at the corresponding position can be pushed, the position of the pipe piece can be adjusted, the pipe pieces at different positions can be adjusted through adjusting the height of the arc-shaped push plate, so that the stacking position of each pipe piece is consistent, the stress points are the same, the stability is higher, and the storage process is safer.

Description

Prefabricated segment storage device for construction
Technical Field
The utility model relates to the technical field of storage devices, in particular to a prefabricated pipe piece storage device for construction.
Background
Along with the continuous progress of technology, the subway is put into use in more and more cities, in the building construction process of subway tunnel, the tunnel is built by adopting the shield method mostly, prefabricated segment bears very important roles therein, prefabricated segment is the atress mechanism that bears the soil pressure, maintain the safe operation of tunnel, for the convenience is transported prefabricated segment, use, also for can reducing space occupancy, usually stack prefabricated segment on the storage rack, a bracket that is arranged in the construction of TBM subway that patent of application number 201721647037.9 put forward, including fixed rubber pad, the support body, the universal wheel, the support frame, the curved surface layer board, the curved surface rubber pad, fixed hook, side hook and telescopic cylinder, respectively set up a support column on the four corners of support body, and support column and support body integrated into one piece, a fixed rubber pad is all installed on the top of every support column, fixed rubber pad area is greater than support column cross-section area, thereby increase the area with curved surface layer board's contact, the bottom installation side hook of curved surface layer board, side hook one end is connected with curved surface layer board through elastic belt, two support columns on curved surface layer board body one side.
But above-mentioned strorage device is when placing the pipe piece, and the pipe piece that newly places appears the position deviation with the pipe piece of bottom easily for every pipe piece's stress point is all different, and when stacking more pipe pieces, stability will reduce, has great potential safety hazard, so we improve this, propose a prefabricated pipe piece strorage device for construction.
Disclosure of Invention
The utility model mainly aims to provide a prefabricated pipe piece storage device for construction, which can effectively solve the problems that when a pipe piece is placed by the storage device, the newly placed pipe piece is easy to deviate from the position of the pipe piece at the bottom, so that the stress points of each pipe piece are different, and when more pipe pieces are stacked, the stability is reduced and a large potential safety hazard exists.
In order to achieve the above purpose, the technical scheme adopted by the utility model is as follows:
the utility model provides a prefabricated section of jurisdiction strorage device for construction, includes the bottom plate, the brace table is all installed to the upper surface both sides of bottom plate, every the equal movable mounting in top of brace table has the arc backup pad, two installation poles are all installed to the upper surface both sides of bottom plate, be provided with the adjustment mechanism who is used for adjusting the section of jurisdiction position between the installation pole, the universal wheel is all installed in the lower surface four corners department of bottom plate.
Preferably, the adjusting mechanism comprises a mounting groove and a driving motor, wherein the mounting groove is formed in each mounting rod, and the driving motor is mounted at the top of two mounting rods.
Preferably, an adjusting screw rod is mounted at the output end of each driving motor, one end of each adjusting screw rod is rotatably arranged on the inner wall of the mounting groove at the corresponding position, and a guide rod is mounted in the mounting groove far away from the adjusting screw rod.
Preferably, a screw rod sleeve is movably arranged on the rod body of each adjusting screw rod, and a sliding block is movably arranged on the rod body of each guide rod.
Preferably, a connecting block is mounted at one end of each screw rod sleeve and one end of each sliding block, and a sliding groove in sliding fit with the connecting block is formed in one side surface of each mounting rod.
Preferably, a mounting plate is arranged between the two connecting blocks positioned on the same side, hydraulic cylinders are arranged on the upper surface of each mounting plate, and an arc-shaped push plate is arranged at the output end of each hydraulic cylinder.
Preferably, clamping grooves are formed in two sides of the upper surface of each supporting table, clamping blocks are mounted on two sides of the lower surface of each arc-shaped supporting plate, and each clamping block is movably arranged in the corresponding clamping groove.
Preferably, the upper surface of each arc-shaped supporting plate is provided with a non-slip protrusion.
Compared with the prior art, the utility model has the following beneficial effects:
through driving of driving motor, under the meshing effect between accommodate screw and the screw rod cover, can adjust the height of mounting panel, can adjust the arc push pedal to with section of jurisdiction same height department, through the work of pneumatic cylinder, can promote the arc push pedal and remove, can promote the section of jurisdiction of corresponding position department, adjust the position of section of jurisdiction, through adjusting the height of arc push pedal, can carry out the position adjustment to the section of jurisdiction of different position departments for the stacking position of each section of jurisdiction is the unanimity, and the stress point is also the same, and stability is higher, and is also safer in the storage process.
Drawings
FIG. 1 is a schematic three-dimensional structure of the present utility model;
FIG. 2 is a side view of the present utility model;
FIG. 3 is a schematic perspective view of the cross-section of FIG. 2 at A-A in accordance with the present utility model;
FIG. 4 is a schematic perspective view of the cross-section of FIG. 2 at B-B in accordance with the present utility model.
In the figure: 1. a bottom plate; 2. a support table; 201. a clamping groove; 3. an arc-shaped supporting plate; 301. a clamping block; 302. a slip preventing protrusion; 4. a mounting rod; 5. an adjusting mechanism; 501. a mounting groove; 502. a driving motor; 503. adjusting a screw rod; 504. a screw rod sleeve; 5041. a connecting block; 5042. a chute; 505. a guide rod; 506. a sliding block; 507. a mounting plate; 508. a hydraulic cylinder; 509. an arc push plate; 6. and a universal wheel.
Detailed Description
The technical solutions of the embodiments of the present utility model will be clearly and completely described below in conjunction with the embodiments of the present utility model, and it is apparent that the described embodiments are only some embodiments of the present utility model, not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
As shown in FIG. 1, a prefabricated section of jurisdiction strorage device is used in construction, including bottom plate 1, supporting bench 2 is all installed to bottom plate 1's upper surface both sides, and the equal movable mounting in top of every supporting bench 2 has arc backup pad 3, and two installation poles 4 are all installed to bottom plate 1's upper surface both sides, are provided with the adjustment mechanism 5 that is used for adjusting the section of jurisdiction position between the installation pole 4, and universal wheel 6 is all installed to bottom plate 1's lower surface four corners department.
As shown in fig. 3 and 4, the adjusting mechanism 5 includes a mounting groove 501 and a driving motor 502, the mounting groove 501 is formed in each mounting rod 4, the driving motor 502 is mounted at the top of two mounting rods 4, an adjusting screw 503 is mounted at the output end of each driving motor 502, one end of each adjusting screw 503 is rotatably disposed on the inner wall of the mounting groove 501 at the corresponding position, a guide rod 505 is mounted in the mounting groove 501 far away from the adjusting screw 503, a screw sleeve 504 is movably mounted on the rod body of each adjusting screw 503, a sliding block 506 is movably mounted on the rod body of each guide rod 505, a connecting block 5041 is mounted at one end of each screw sleeve 504 and the sliding block 506, a sliding groove 5042 which is in sliding fit with the connecting block 5041 is formed in one side surface of each mounting rod 4, a mounting plate 507 is mounted between the two connecting blocks 5041 at the same side, a hydraulic cylinder 508 is mounted on the upper surface of each mounting plate 507, and an arc-shaped push plate 509 is mounted at the output end of each hydraulic cylinder 508.
Through the meshing transmission between adjusting screw 503 and the screw cover 504, under driving motor 502's drive, can adjust the height of mounting panel 507 for arc push pedal 509 can carry out the position adjustment to the section of jurisdiction of different positions, can make the storage position of every section of jurisdiction all keep unanimous, and the in-process of stacking is more stable, through sliding fit between sliding block 506 and the guide bar 505, can carry out spacingly to the removal orbit of mounting panel 507, makes mounting panel 507 more stable at the in-process of moving.
As shown in fig. 4, clamping grooves 201 are formed in two sides of the upper surface of each supporting table 2, clamping blocks 301 are mounted on two sides of the lower surface of each arc-shaped supporting plate 3, each clamping block 301 is movably arranged in the corresponding clamping groove 201, and anti-slip protrusions 302 are arranged on the upper surface of each arc-shaped supporting plate 3.
Through the interlude cooperation between fixture block 301 and the draw-in groove 201, can be with arc backup pad 3 movable mounting at the top of brace table 2, it is convenient to dismantle, can deposit the specification difference of section of jurisdiction according to sending out, adjusts the size of arc backup pad 3, and the surface of arc backup pad 3 is provided with anti-skidding arch 302, and is more stable when depositing the section of jurisdiction, difficult slip.
This prefabricated section of jurisdiction strorage device for construction theory of operation:
when the pipe piece storage device is used, pipe pieces are placed above two arc-shaped support plates 3 through hoisting machinery, after the placement of the pipe pieces is completed, the adjusting screw rod 503 is controlled to rotate through the driving of the driving motor 502, the screw rod sleeve 504 can be driven to move up and down under the meshing action between the adjusting screw rod 503 and the screw rod sleeve 504, so that the height of the mounting plate 507 can be adjusted, the arc-shaped push plate 509 can be adjusted to the same height as the pipe pieces, the arc-shaped push plate 509 can be pushed to move through the work of the hydraulic cylinder 508, the pipe pieces at corresponding positions can be pushed to adjust the positions of the pipe pieces, the pipe pieces at different positions can be adjusted through the adjustment of the height of the arc-shaped push plate 509, the stacking positions of each pipe piece are consistent, the stress points are the same, the stability is higher, and the pipe piece storage device is safer in the storage process.
It should be understood that the foregoing examples of the present utility model are merely illustrative of the present utility model and not limiting of the embodiments of the present utility model, and that various other changes and modifications can be made by one skilled in the art based on the above description, and it is not intended to be exhaustive of all embodiments, and all obvious changes and modifications that come within the scope of the utility model are still within the scope of the utility model.

Claims (8)

1. Prefabricated section of jurisdiction strorage device is used in construction, including bottom plate (1), its characterized in that: supporting tables (2) are arranged on two sides of the upper surface of the bottom plate (1), each supporting table (2) is movably provided with an arc-shaped supporting plate (3) at the top, two mounting rods (4) are arranged on two sides of the upper surface of the bottom plate (1), an adjusting mechanism (5) for adjusting the position of a duct piece is arranged between the mounting rods (4), and universal wheels (6) are arranged at four corners of the lower surface of the bottom plate (1).
2. The prefabricated segment storage device for construction according to claim 1, wherein: the adjusting mechanism (5) comprises a mounting groove (501) and a driving motor (502), the mounting groove (501) is formed in each mounting rod (4), and the driving motor (502) is mounted at the top of two mounting rods (4).
3. The prefabricated segment storage device for construction according to claim 2, wherein: an adjusting screw rod (503) is installed at the output end of each driving motor (502), one end of each adjusting screw rod (503) is rotatably arranged on the inner wall of the installation groove (501) at the corresponding position, and a guide rod (505) is installed in the installation groove (501) far away from the adjusting screw rod (503).
4. A prefabricated segment storage device for construction according to claim 3, wherein: a screw rod sleeve (504) is movably arranged on the rod body of each adjusting screw rod (503), and a sliding block (506) is movably arranged on the rod body of each guide rod (505).
5. The prefabricated segment storage device for construction according to claim 4, wherein: connecting blocks (5041) are arranged at one ends of the screw rod sleeves (504) and the sliding blocks (506), and sliding grooves (5042) which are in sliding fit with the connecting blocks (5041) are formed in one side surface of each mounting rod (4).
6. The prefabricated segment storage device for construction according to claim 5, wherein: a mounting plate (507) is arranged between the two connecting blocks (5041) positioned on the same side, a hydraulic cylinder (508) is arranged on the upper surface of each mounting plate (507), and an arc-shaped push plate (509) is arranged at the output end of each hydraulic cylinder (508).
7. The prefabricated segment storage device for construction according to claim 1, wherein: clamping grooves (201) are formed in two sides of the upper surface of each supporting table (2), clamping blocks (301) are mounted on two sides of the lower surface of each arc-shaped supporting plate (3), and each clamping block (301) is movably arranged in the corresponding clamping groove (201).
8. The prefabricated segment storage device for construction according to claim 1, wherein: the upper surface of each arc-shaped supporting plate (3) is provided with a non-slip protrusion (302).
CN202322235801.3U 2023-08-21 2023-08-21 Prefabricated segment storage device for construction Active CN220786664U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322235801.3U CN220786664U (en) 2023-08-21 2023-08-21 Prefabricated segment storage device for construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322235801.3U CN220786664U (en) 2023-08-21 2023-08-21 Prefabricated segment storage device for construction

Publications (1)

Publication Number Publication Date
CN220786664U true CN220786664U (en) 2024-04-16

Family

ID=90634713

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322235801.3U Active CN220786664U (en) 2023-08-21 2023-08-21 Prefabricated segment storage device for construction

Country Status (1)

Country Link
CN (1) CN220786664U (en)

Similar Documents

Publication Publication Date Title
CN207003980U (en) A kind of Moveable building construction platform
CN209324008U (en) A kind of bricklaying robot with lifting device
CN220786664U (en) Prefabricated segment storage device for construction
CN111997117A (en) High-efficient equipment that levels of ground for construction
CN218466225U (en) Subway rail laying construction device
CN216590248U (en) Municipal administration is pipe-laying auxiliary device for water supply and drainage
CN211075946U (en) Precast concrete board's reinforcing apparatus
CN209260563U (en) A kind of Bailey beam truss entirety transverse sliding device for cast-in-situ continuous beam
CN111749708A (en) Steel construction is used in tunnel excavation support
CN216546220U (en) Multi-functional hydraulic engineering pipeline handling device
CN111962911B (en) Building safety displacement device
CN221027455U (en) Lifting device
CN220080704U (en) Liftable scaffold for laying photovoltaic equipment
CN215706525U (en) Pile foundation handling device for hydraulic engineering
CN216971730U (en) Evaporate and press aerated concrete block production with hoisting device
CN215806767U (en) Pipeline laying device is used in municipal construction road construction
CN220665989U (en) Grouting device for road and bridge engineering construction
CN218290364U (en) Hydraulic lifting operating platform
CN212425277U (en) Be used for civil engineering construction strutting arrangement convenient to remove
CN217886453U (en) Outpatient nursing dressing change device
CN219281773U (en) Safety hydraulic device for mining
CN220220754U (en) Comprehensive waste liquid treatment device in laboratory
CN219971417U (en) Cable drum placing bracket
CN203653156U (en) Jack frame
CN220884484U (en) Brick transferring trolley

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant