CN220705091U - Scaffold for building construction - Google Patents
Scaffold for building construction Download PDFInfo
- Publication number
- CN220705091U CN220705091U CN202322144369.7U CN202322144369U CN220705091U CN 220705091 U CN220705091 U CN 220705091U CN 202322144369 U CN202322144369 U CN 202322144369U CN 220705091 U CN220705091 U CN 220705091U
- Authority
- CN
- China
- Prior art keywords
- supporting seat
- supporting
- construction
- height
- telescopic
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000009435 building construction Methods 0.000 title claims abstract description 13
- 238000010276 construction Methods 0.000 claims abstract description 35
- 238000005452 bending Methods 0.000 claims description 7
- 230000007547 defect Effects 0.000 description 2
- 235000017166 Bambusa arundinacea Nutrition 0.000 description 1
- 235000017491 Bambusa tulda Nutrition 0.000 description 1
- 241001330002 Bambuseae Species 0.000 description 1
- 235000015334 Phyllostachys viridis Nutrition 0.000 description 1
- 229910000831 Steel Inorganic materials 0.000 description 1
- 239000011425 bamboo Substances 0.000 description 1
- 230000003139 buffering effect Effects 0.000 description 1
- 238000005034 decoration Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005065 mining Methods 0.000 description 1
- 230000001737 promoting effect Effects 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 229920002994 synthetic fiber Polymers 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
- 238000010626 work up procedure Methods 0.000 description 1
Landscapes
- Movable Scaffolding (AREA)
Abstract
The utility model relates to the technical field of building construction equipment and discloses a building construction scaffold, which comprises a supporting seat (1), wherein an air cylinder (2) is arranged at the bottom of the supporting seat (1), a through hole (101) is arranged in the center of the supporting seat (1), an air rod (201) of the air cylinder (2) penetrates through the through hole (101), a lifting plate (3) is arranged at the top of the air rod (201), supporting rods (4) capable of adjusting the height are arranged around the bottom of the supporting seat (1), and escalators (5) are arranged at two sides of the supporting seat (1). According to the building construction scaffold, the support seat and the lifting plate which can stretch and lift are used, so that the applicability and the flexibility of the scaffold are improved according to construction requirements, and the construction efficiency is improved.
Description
Technical Field
The utility model relates to the technical field of building construction equipment, in particular to a building construction scaffold.
Background
Scaffolding refers to various scaffolds that are operated for workers at a construction site and that address vertical and lateral transport. The general term in the construction field refers to places where external walls, interior decoration or higher floor heights cannot be directly performed on a construction site, and is mainly used for constructors to work up and down, maintain surrounding safety nets, install components at high altitudes, and the like. It can be said straightforwardly that the scaffold is made of bamboo, wood, steel pipe or synthetic material. Scaffolding is also used as a template in some projects and is also widely used in advertising, municipal, highway and bridge transportation, mining and other sectors. The existing construction scaffold has many defects, such as inconvenient lifting, inconvenient up and down of the scaffold by constructors, and reduced construction efficiency.
The application number CN201920184190.5 discloses a building construction frame which comprises four upright posts, wherein a ladder is arranged between the two upright posts in the width direction, and the upper side of the ladder is fixedly connected with a supporting platform; two crossed support rods are arranged between the two upright posts in the length direction, and the ends of the support rods are fixedly connected with the corresponding upright posts; the side edges of the upright posts on the upper side of the supporting platform are provided with opposite sliding grooves, a railing is connected between the two opposite sliding grooves in a sliding manner, and the upper side of each end of the railing is detachably connected with the upper end of the corresponding upright post through a fastener; both ends of the railing are respectively connected with the corresponding sliding grooves in a sliding fit manner through sliding parts. Above-mentioned patent is through promoting the railing, and the both ends of railing all slide through corresponding T shape slider respectively, promotes the back in place at the railing, cup joints the lantern ring on corresponding cylinder, fixes the railing in place, through the lift of railing to be convenient for construction and personnel's upper and lower scaffold. However, the overall height of the building construction frame cannot be raised and lowered, and construction limitations exist.
Disclosure of Invention
The utility model provides a scaffold for building construction aiming at the defects in the prior art.
In order to solve the technical problems, the utility model is solved by the following technical scheme:
the utility model provides a construction scaffold frame, includes the supporting seat, and the cylinder is installed to the supporting seat bottom, and the supporting seat center is equipped with the through-hole, and the gas pole of cylinder passes the through-hole, and the gas pole top is equipped with the lifter plate, and the supporting seat bottom is equipped with the bracing piece that can height-adjusting all around, and the supporting seat both sides are equipped with the staircase. Constructors usually construct on the supporting seat, adjust the height of lifter plate through setting up the cylinder in the supporting seat bottom, when constructors can not arrive the construction position, raise the height of lifter plate, improve the flexibility of construction.
Preferably, the support rod comprises a support column and a telescopic column, the telescopic column stretches into the support column, and the support column is connected with the telescopic column through a pin. The height of the supporting seat is changed through the supporting rod with adjustable height.
Preferably, the top of the telescopic column is connected with the bottom of the supporting seat, and the bottom of the supporting column is provided with a base.
Preferably, the upper surface of the supporting seat is provided with a buffer point at the bottom of the lifting plate. The buffer point reduces the sound of the falling of the lifting plate and the collision of the supporting seat.
Preferably, lifting ropes are further arranged around the upper surface of the supporting seat. The lifting rope is arranged to lift the height of the supporting seat by an external force such as a crane.
Preferably, the escalator comprises a supporting part and a telescopic part, wherein the telescopic part stretches into the supporting part, and the supporting part is connected with the telescopic part through a pin. The escalator can be adjusted according to the height of the supporting seat.
Preferably, the top of the telescopic part is connected with a bending plate, square grooves are formed in two side edges of the supporting seat, and the bending plate stretches into the square grooves.
The utility model has the remarkable technical effects due to the adoption of the technical scheme: the constructor usually carries out construction on the supporting seat, the height of the lifting plate is adjusted by arranging the air cylinder at the bottom of the supporting seat, and when the constructor can not reach the construction position, the height of the lifting plate is lifted, so that the construction flexibility is improved; the height of the supporting seat is changed through the supporting rod with adjustable height; the buffer points reduce the sound of the falling of the lifting plate and the collision of the lifting plate and the supporting seat; setting a lifting rope to lift the height of the supporting seat by external force such as a crane; the escalator can be adjusted according to the height of the supporting seat. According to the building construction scaffold, the support seat and the lifting plate which can stretch and lift are used, so that the applicability and the flexibility of the scaffold are improved according to construction requirements, and the construction efficiency is improved.
Drawings
Fig. 1 is a schematic structural view of the present utility model.
Fig. 2 is a schematic structural view of the support base.
Fig. 3 is a partial enlarged view of a in fig. 1.
The names of the parts indicated by the numerical reference numerals in the above drawings are as follows: the lifting device comprises a supporting seat 1, a through hole 101, a buffering point 102, a lifting rope 103, a square groove 104, a cylinder 2, an air rod 201, a lifting plate 3, a supporting rod 4, a supporting column 401, a telescopic column 402, a 5-staircase 501, a supporting part 502, a telescopic part 503, a bending plate 6 and a base.
Detailed Description
The present utility model will be described in further detail with reference to the accompanying drawings and examples.
Example 1
1-3, including supporting seat 1, cylinder 2 is installed to supporting seat 1 bottom, and supporting seat 1 center is equipped with through-hole 101, and the gas pole 201 of cylinder 2 passes through-hole 101, and the gas pole 201 top is equipped with lifter plate 3, and supporting seat 1 bottom is equipped with height-adjustable's bracing piece 4 all around, and supporting seat 1 both sides are equipped with staircase 5. Constructors normally construct on the supporting seat 1, adjust the height of the lifting plate 3 through setting up the cylinder 2 in the supporting seat 1 bottom, when constructors can not arrive the construction position, raise the height of the lifting plate 3, improve the flexibility of construction.
The support bar 4 comprises a support column 401 and a telescopic column 402, the telescopic column 402 extends into the support column 401, and the support column 401 and the telescopic column 402 are connected through pins. The height of the supporting seat 1 is changed by the supporting rod 4 with adjustable height.
The top of the telescopic column 402 is connected with the bottom of the supporting seat 1, and the bottom of the supporting column 401 is provided with a base 6.
The upper surface of the supporting seat 1 is provided with a buffer point 102 at the bottom of the lifting plate 3. The buffer point 102 reduces the sound of the lifting plate 3 falling down to collide with the supporting seat 1.
Lifting ropes 103 are also arranged around the upper surface of the supporting seat 1. The lifting string 103 is provided to lift the height of the support base 1 by an external force such as a crane.
The escalator 5 comprises a supporting part 501 and a telescopic part 502, wherein the telescopic part 502 stretches into the supporting part 501, and the supporting part 501 and the telescopic part 502 are connected through pins. The escalator 5 can be adjusted according to the height of the supporting seat 1.
The top of the telescopic part 502 is connected with a bending plate 503, two side edges of the supporting seat 1 are provided with square grooves 104, and the bending plate 503 extends into the square grooves 104.
Working principle: the constructor usually carries out construction on the supporting seat 1, the height of the lifting plate 3 is adjusted by arranging the air cylinder 2 at the bottom of the supporting seat 1, and when the constructor cannot reach the construction position, the height of the lifting plate 3 is lifted, so that the construction flexibility is improved; the height of the supporting seat 1 is changed through the supporting rod 4 with adjustable height; the buffer point 102 reduces the sound of the lifting plate 3 falling and colliding with the supporting seat 1; the lifting rope 103 is arranged to lift the height of the supporting seat 1 by an external force such as a crane; the escalator 5 can be adjusted according to the height of the supporting seat 1. According to the building construction scaffold, the support seat and the lifting plate which can stretch and lift are used, so that the applicability and the flexibility of the scaffold are improved according to construction requirements, and the construction efficiency is improved.
Example 2
The utility model provides a construction scaffold frame, as shown in fig. 1, includes supporting seat 1, and cylinder 2 is installed to supporting seat 1 bottom, and supporting seat 1 center is equipped with through-hole 101, and the gas pole 201 of cylinder 2 passes through-hole 101, and the gas pole 201 top is equipped with lifter plate 3, and supporting seat 1 bottom is equipped with height-adjustable's bracing piece 4 all around, and supporting seat 1 both sides are equipped with staircase 5. Constructors normally construct on the supporting seat 1, adjust the height of the lifting plate 3 through setting up the cylinder 2 in the supporting seat 1 bottom, when constructors can not arrive the construction position, raise the height of the lifting plate 3, improve the flexibility of construction.
Example 3
1-2, including supporting seat 1, cylinder 2 is installed to supporting seat 1 bottom, and supporting seat 1 center is equipped with through-hole 101, and the gas pole 201 of cylinder 2 passes through-hole 101, and the gas pole 201 top is equipped with lifter plate 3, and supporting seat 1 bottom is equipped with height-adjustable's bracing piece 4 all around, and supporting seat 1 both sides are equipped with staircase 5. Constructors normally construct on the supporting seat 1, adjust the height of the lifting plate 3 through setting up the cylinder 2 in the supporting seat 1 bottom, when constructors can not arrive the construction position, raise the height of the lifting plate 3, improve the flexibility of construction.
The support bar 4 comprises a support column 401 and a telescopic column 402, the telescopic column 402 extends into the support column 401, and the support column 401 and the telescopic column 402 are connected through pins. The height of the supporting seat 1 is changed by the supporting rod 4 with adjustable height.
The top of the telescopic column 402 is connected with the bottom of the supporting seat 1, and the bottom of the supporting column 401 is provided with a base 6.
The upper surface of the supporting seat 1 is provided with a buffer point 102 at the bottom of the lifting plate 3. The buffer point 102 reduces the sound of the lifting plate 3 falling down to collide with the supporting seat 1.
Lifting ropes 103 are also arranged around the upper surface of the supporting seat 1. The lifting string 103 is provided to lift the height of the support base 1 by an external force such as a crane.
Claims (7)
1. Building construction scaffold, including supporting seat (1), its characterized in that: the cylinder (2) is installed to supporting seat (1) bottom, and supporting seat (1) center is equipped with through-hole (101), and through-hole (101) are passed in gas pole (201) of cylinder (2), and gas pole (201) top is equipped with lifter plate (3), and supporting seat (1) bottom is equipped with bracing piece (4) that can height-adjusting all around, and supporting seat (1) both sides are equipped with staircase (5).
2. A construction scaffolding according to claim 1, wherein: the support rod (4) comprises a support column (401) and a telescopic column (402), the telescopic column (402) stretches into the support column (401), and the support column (401) and the telescopic column (402) are connected through pins.
3. A construction scaffolding according to claim 2, wherein: the top of the telescopic column (402) is connected with the bottom of the supporting seat (1), and the bottom of the supporting column (401) is provided with a base (6).
4. A construction scaffolding according to claim 1, wherein: the upper surface of the supporting seat (1) is positioned at the bottom of the lifting plate (3) and is provided with a buffer point (102).
5. A construction scaffolding according to claim 1, wherein: lifting ropes (103) are arranged around the upper surface of the supporting seat (1).
6. A construction scaffolding according to claim 1, wherein: the escalator (5) comprises a supporting part (501) and a telescopic part (502), wherein the telescopic part (502) stretches into the supporting part (501), and the supporting part (501) is connected with the telescopic part (502) through pins.
7. The construction scaffolding as claimed in claim 6 wherein: the top of the telescopic part (502) is connected with a bending plate (503), square grooves (104) are arranged on two side edges of the supporting seat (1), and the bending plate (503) stretches into the square grooves (104).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322144369.7U CN220705091U (en) | 2023-08-09 | 2023-08-09 | Scaffold for building construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202322144369.7U CN220705091U (en) | 2023-08-09 | 2023-08-09 | Scaffold for building construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN220705091U true CN220705091U (en) | 2024-04-02 |
Family
ID=90452340
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202322144369.7U Active CN220705091U (en) | 2023-08-09 | 2023-08-09 | Scaffold for building construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN220705091U (en) |
-
2023
- 2023-08-09 CN CN202322144369.7U patent/CN220705091U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109057365A (en) | A kind of Node In Large-span Pipe Truss roof truss air translation installation method | |
CN202055497U (en) | Movable combination scaffold for construction works | |
CN206707237U (en) | Cable-stayed type top layer construction platform for elevator installation | |
CN114753611A (en) | Curtain wall construction platform | |
CN220705091U (en) | Scaffold for building construction | |
CN212957538U (en) | Roof flower frame beam and outer wall decoration construction movable operation platform | |
CN209873572U (en) | Interim navigation lifting station of adjustable vertical lift height | |
CN218706213U (en) | Pedestrian bridge structure of belt conveyor | |
CN216662305U (en) | Super high-rise tower crane bottom attached hydraulic self-climbing hard protection platform | |
JP3950800B2 (en) | Suspension scaffold | |
CN212453549U (en) | Liftable scaffold for building decoration | |
CN113896124A (en) | Super high-rise tower crane bottom attached hydraulic self-climbing hard protection platform, installation process and climbing method thereof | |
CN211974269U (en) | From climbing formula elevartor shaft steel platform | |
CN109537868B (en) | Portable operation platform for hoisting assembled main beams | |
CN218933774U (en) | Building construction frame | |
CN109372242B (en) | Elevator shaft construction safety lifting platform device and using method | |
CN110965750A (en) | Liftable full hall scaffold | |
CN111305433A (en) | Construction structure and construction method of inclined glass curtain wall of roof steel structure platform | |
CN2177059Y (en) | Top lifting adhesive double stretching arm outer scaffold | |
CN214605199U (en) | Auxiliary device for punching high beam plate | |
CN217518109U (en) | Multipurpose operation platform that encorbelments | |
CN219952606U (en) | Safety platform for beam slab prefabricated field | |
CN215564337U (en) | Construction hanging basket used under beam and provided with hanger rods for replacement | |
CN218970751U (en) | Large-span steel truss gallery deflection control temporary buttress device | |
CN220549926U (en) | Auxiliary hoisting installation device for railway T-beam top beam moving jack |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |