CN220667468U - Drilling positioning device for bridge engineering - Google Patents

Drilling positioning device for bridge engineering Download PDF

Info

Publication number
CN220667468U
CN220667468U CN202322405508.7U CN202322405508U CN220667468U CN 220667468 U CN220667468 U CN 220667468U CN 202322405508 U CN202322405508 U CN 202322405508U CN 220667468 U CN220667468 U CN 220667468U
Authority
CN
China
Prior art keywords
fixedly connected
drilling
frame
positioning device
connecting plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322405508.7U
Other languages
Chinese (zh)
Inventor
李以磊
商玉石
张吉海
谷光耀
杜鲁民
崔琪
梁建勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinan Kingyue Highway Engineering Co Ltd
Original Assignee
Jinan Kingyue Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinan Kingyue Highway Engineering Co Ltd filed Critical Jinan Kingyue Highway Engineering Co Ltd
Priority to CN202322405508.7U priority Critical patent/CN220667468U/en
Application granted granted Critical
Publication of CN220667468U publication Critical patent/CN220667468U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model relates to the technical field of bridge processing equipment and discloses a drilling positioning device for bridge engineering. According to the utility model, through the mutual matching among the frame, the first fixed block, the first connecting block, the limiting plate, the first connecting plate, the second connecting plate, the locating frame, the pile fixing column, the second fixed block, the hydraulic rod, the second connecting block and the steel plate, the effect of accurately locating the drill bit is achieved, the problem that the drill bit shakes due to friction between the drill bit and the bridge surface caused by the fact that the traditional partial drilling locating device is relatively simple in structure and relatively poor in locating accuracy is solved, and the practicability of equipment is improved.

Description

Drilling positioning device for bridge engineering
Technical Field
The utility model relates to the technical field of bridge processing equipment, in particular to a drilling positioning device for bridge engineering.
Background
The drilling positioning device for bridge engineering is a device for punching, installing and fixing some street lamps and guardrails on a bridge, along with continuous progress of society, cities are continuously expanded and developed, roads and bridges become an integral part of urban construction and become important facilities for promoting economy in great wall, and some street lamps and guardrails on the bridge are required to be punched, installed and fixed, so that the bridge drilling positioning device is required to be used for facilitating workers to punch bridge floors.
When traditional part drilling positioner is drilling, probably because drilling positioner structure is comparatively simple leads to the accuracy of location relatively poor, can produce the friction with the bridge floor when using the drill bit to work, lead to drilling post to rock to make the drill bit skew predetermined position, consequently can influence the construction quality of bridge.
Disclosure of Invention
In order to make up for the defects, the utility model provides a drilling positioning device for bridge engineering, which aims to solve the problems that the positioning accuracy is poor possibly due to the fact that the structure of the drilling positioning device is simple, when a drill bit is used for working, friction is generated between the drilling positioning device and a bridge deck, a drilling column is caused to shake, and the drill bit is deviated from a preset position, so that the construction quality of a bridge is possibly affected.
In order to achieve the above purpose, the present utility model adopts the following technical scheme: the utility model provides a drilling positioner for bridge engineering, includes the frame, the inside threaded connection of frame has drilling post, drilling post lateral wall fixedly connected with handle, frame diapire fixedly connected with fixed block one, frame lateral wall fixedly connected with connecting block one, drilling post lateral wall threaded connection has the limiting plate, one side of connecting plate one of the inside fixedly connected with of fixed block one, one side of connecting plate one's inside fixedly connected with connecting plate two, frame lateral wall fixedly connected with locating rack, the inside sliding connection of locating rack has fixed stake, locating rack diapire fixedly connected with fixed block two, locating rack lateral wall fixedly connected with hydraulic stem, the output fixedly connected with connecting block two of hydraulic stem, fixed stake lateral wall fixedly connected with steel sheet, the inside rotation of fixed block two is connected with one side of rotating plate one, the inside rotation of connecting block two is connected with one side of rotating plate two.
As a further description of the above technical solution:
the other side fixed connection of connecting plate one is on connecting block one, the opposite side fixed connection of connecting plate two is on the limiting plate, the opposite side of rotating plate one rotates to be connected on connecting block two, the opposite side of rotating plate two rotates to be connected on the steel sheet, the frame is inside to be provided with hole two, the frame is inside to be provided with dust absorption mouth two.
As a further description of the above technical solution:
the side wall of the frame is fixedly connected with a water tank, and the bottom wall of the water tank is fixedly connected with a placement tank.
As a further description of the above technical solution:
the inside hole one that is provided with of placing the case, place the incasement portion and be provided with the suction pump.
As a further description of the above technical solution:
the water pump is characterized in that the input end of the water pump is fixedly connected with one end of a first water pipe, the other end of the first water pipe is fixedly connected to the water tank, and the output end of the water pump is fixedly connected with a second water pipe.
As a further description of the above technical solution:
the side wall of the frame is fixedly connected with a sewage storage tank, and the bottom wall of the sewage storage tank is fixedly connected with an air box.
As a further description of the above technical solution:
the dust collection device is characterized in that a dust collection opening I is formed in the air box, a dust tube is fixedly connected to the side wall of the air box, and the other side of the dust tube is fixedly connected to the dirt storage box.
As a further description of the above technical solution:
the inside dust absorption fan that is provided with of bellows, dust absorption fan lateral wall fixedly connected with safety cover.
The utility model has the following beneficial effects:
according to the utility model, the accurate positioning effect of the drill bit is achieved by the mutual matching of the frame, the first fixed block, the first connecting block, the limiting plate, the first connecting plate, the second connecting plate, the positioning frame, the pile fixing column, the second fixed block, the hydraulic rod, the second connecting block and the steel plate, the problem that the drill bit shakes and deviates from a preset position due to friction between the drill bit and the bridge surface caused by the fact that the traditional partial drilling positioning device is relatively simple in structure and relatively poor in positioning accuracy is solved, and the practicability of equipment is improved.
According to the utility model, the water tank, the water pump, the first water pipe, the second water pipe, the dirt storage box, the bellows, the first dust collection port, the second dust collection port, the dust pipe and the dust collection fan are mutually matched, so that the effect of dust prevention and dust reduction is achieved, the problem that a large amount of dust can be caused when the traditional partial drilling positioning device is used for drilling holes is solved, the environment is seriously polluted, the damage is caused to constructors, and the practicability of the device is improved.
Drawings
Fig. 1 is a schematic perspective view of a drilling positioning device for bridge engineering according to the present utility model;
FIG. 2 is a schematic view of a pile setting structure of a drilling positioning device for bridge engineering according to the present utility model;
fig. 3 is a schematic diagram of a frame structure of a drilling positioning device for bridge engineering according to the present utility model.
Fig. 4 is a schematic diagram of a water tank structure of a drilling positioning device for bridge engineering according to the present utility model.
Fig. 5 is a schematic diagram of a dirt storage tank structure of a drilling positioning device for bridge engineering according to the present utility model.
Legend description:
1. a frame; 2. drilling a column; 3. a handle; 4. a first fixed block; 5. a first connecting block; 6. a limiting plate; 7. a first connecting plate; 8. a second connecting plate; 9. a positioning frame; 10. pile fixing; 11. a second fixed block; 12. a hydraulic rod; 13. a second connecting block; 14. a steel plate; 15. rotating the first plate; 16. a second rotating plate; 17. a water tank; 18. placing a box; 19. a first hole; 20. a water pump; 21. a first water pipe; 22. a second water pipe; 23. a dirt storage tank; 24. a wind box; 25. a dust collection port I; 26. a dust tube; 27. a dust collection fan; 28. a protective cover; 29. a second hole; 30. and a dust collection port II.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1-5, one embodiment provided by the present utility model is: a drilling positioner for bridge engineering, including frame 1, frame 1 inside threaded connection has drilling post 2, drilling post 2 lateral wall fixedly connected with handle 3, frame 1 diapire fixedly connected with fixed block one 4, frame 1 lateral wall fixedly connected with connecting block one 5, drilling post 2 lateral wall threaded connection has limiting plate 6, the one side of fixed block one 4 inside fixedly connected with connecting plate one 7, the one side of connecting plate one 5's inside fixedly connected with connecting plate two 8, frame 1 lateral wall fixedly connected with locating rack 9, the inside sliding connection of locating rack 9 has fixed stake 10, locating rack 9 diapire fixedly connected with fixed block two 11, locating rack 9 lateral wall fixedly connected with hydraulic stem 12, the output fixedly connected with connecting block two 13 of hydraulic stem 12, fixed stake 10 lateral wall fixedly connected with steel sheet 14, the inside rotation of fixed block two 11 is connected with one side of rotating plate one 15, the inside rotation of connecting block two 13 is connected with one side of rotating plate two 16.
When the device is required to be used, the drilling device is initially positioned through the positioning frame 9, then the hydraulic rod 12 is started to drive the connecting block II 13 to move through the hydraulic press 12, so that the rotating plate I15 and the rotating plate II 16 rotate, the steel plate 14 is moved through the rotation of the rotating plate I15 and the rotating plate II 16, the pile fixing column 10 moves downwards and is nailed into the ground to achieve the positioning effect, then the drilling column 2 moves downwards through the rotating handle 3 to punch holes, the limiting plate 6 is kept stable through the fixed connecting plate I7 and the fixed connecting plate II 8, the limiting plate 6 limits the drilling column 2 to move up and down, the drilling column 2 does not generate position deviation during working, and the positioning effect is achieved again.
The opposite side fixed connection of connecting plate one 7 is on connecting block one 5, and the opposite side fixed connection of connecting plate two 8 is on limiting plate 6, and the opposite side of rotating plate one 15 rotates to be connected on connecting block two 13, and the opposite side of rotating plate two 16 rotates to be connected on steel sheet 14, and frame 1 is inside to be provided with hole two 29, and frame 1 is inside to be provided with dust absorption mouth two 30.
The side wall of the frame 1 is fixedly connected with a water tank 17, and the bottom wall of the water tank 17 is fixedly connected with a placement tank 18.
The placing box 18 is internally provided with a first hole 19, and the placing box 18 is internally provided with a water pump 20.
The input end of the water pump 20 is fixedly connected with one end of a first water pipe 21, the other end of the first water pipe 21 is fixedly connected to the water tank 17, and the output end of the water pump 20 is fixedly connected with a second water pipe 22.
The side wall of the frame 1 is fixedly connected with a sewage storage tank 23, and the bottom wall of the sewage storage tank 23 is fixedly connected with an air box 24.
The interior of the bellows 24 is provided with a dust collection port I25, the side wall of the bellows 24 is fixedly connected with a dust tube 26, and the other side of the dust tube 26 is fixedly connected to the dirt storage tank 23.
The bellows 24 is inside to be provided with dust absorption fan 27, and dust absorption fan 27 lateral wall fixedly connected with safety cover 28.
When the drilling column 2 starts to work, a large amount of dust can be generated on the bridge floor to pollute the air, at the moment, the dust suction fan 27 is started to suck the wind through the dust suction fan 27, so that the dust is sucked into the air box 24 through the dust suction opening I25 and the dust suction opening II 30, the dust is stored in the dirt storage box 23 through the dust suction pipe 26, at the moment, the water in the water tank 17 is pumped through the water pipe I21 by starting the water suction pump 20, and the water in the water tank 17 is sprayed through the water pipe II 22, so that the effect of dust fall is achieved.
Working principle: when the device is required to be used, the drilling device is initially positioned through the positioning frame 9, then the hydraulic rod 12 is started to drive the connecting block II 13 to move through the hydraulic machine 12, so that the rotating plate I15 and the rotating plate II 16 rotate, the steel plate 14 is moved through the rotation of the rotating plate I15 and the rotating plate II 16, the pile fixing column 10 moves downwards, the ground is nailed to achieve the positioning effect, then the handle 3 is rotated to enable the drilling column 2 to move downwards for punching, the limiting plate 6 is kept stable through the fixed connecting plate I7 and the fixed connecting plate II 8, the limiting plate 6 is used for limiting the drilling column 2 to move upwards and downwards, the position deviation is not generated when the drilling column 2 works, the positioning effect is achieved again, when the drilling column 2 starts to work, a large amount of dust can be generated on the bridge floor, at the moment, the dust suction fan 27 is started to suck the air through the dust suction fan 27, the dust suction box 24 is enabled to be driven to pass through the dust suction opening I25 and the dust suction box 30, the dust suction pipe 26 is stored in the dust storage box 23, the dust suction pump 20 is started to pump the dust in the water tank 17, and the water in the water tank 17 is discharged through the water tank 17, and the water is discharged from the water tank 17 is enabled to achieve the effect.
Finally, it should be noted that: the foregoing description of the preferred embodiments of the present utility model is not intended to be limiting, but rather, although the present utility model has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described, or equivalents may be substituted for elements thereof, and any modifications, equivalents, improvements or changes may be made without departing from the spirit and principles of the present utility model.

Claims (8)

1. Drilling positioning device for bridge engineering, comprising a frame (1), characterized in that: the novel drilling machine comprises a frame (1), wherein a drilling column (2) is connected to the inside of the frame (1) through threads, a handle (3) is fixedly connected to the side wall of the drilling column (2), a first fixing block (4) is fixedly connected to the bottom wall of the frame (1), a first connecting block (5) is fixedly connected to the side wall of the frame (1), a limiting plate (6) is fixedly connected to the side wall of the drilling column (2), one side of a first connecting plate (7) is fixedly connected to the first fixing block (4), one side of a second connecting plate (8) is fixedly connected to the inside of the first connecting block (5), a locating frame (9) is fixedly connected to one side of a second connecting block (16), one side of a second connecting block (11) is fixedly connected to the side wall of the locating frame (9), a second hydraulic rod (12) is fixedly connected to the output end of the hydraulic rod (12), a second connecting block (13) is fixedly connected to the side wall of the second fixing block (10), and one side of a second connecting block (16) is connected to the second rotating plate (16).
2. A drilling positioning device for bridge engineering according to claim 1, wherein: the utility model discloses a dust collection device, including connecting plate one (7), limiting plate one (6), connecting plate two (8), connecting plate one (16), frame (1) inside is provided with hole two (29), frame (1) inside is provided with dust absorption mouth two (30), connecting plate one (7) opposite side fixed connection on connecting block one (5), connecting plate two (6) on the opposite side fixed connection of connecting plate two (8), the opposite side rotation of rotating plate one (15) is connected on connecting block two (13), the opposite side rotation of rotating plate two (16) is connected on steel sheet (14).
3. A drilling positioning device for bridge engineering according to claim 1, wherein: the side wall of the frame (1) is fixedly connected with a water tank (17), and the bottom wall of the water tank (17) is fixedly connected with a placement box (18).
4. A drill hole positioning device for bridge construction according to claim 3, wherein: the novel water pump is characterized in that a first hole (19) is formed in the placement box (18), and a water pump (20) is arranged in the placement box (18).
5. The drilling and positioning device for bridge engineering according to claim 4, wherein: the water pump is characterized in that the input end of the water pump (20) is fixedly connected with one end of a first water pipe (21), the other end of the first water pipe (21) is fixedly connected to the water tank (17), and the output end of the water pump (20) is fixedly connected with a second water pipe (22).
6. A drilling positioning device for bridge engineering according to claim 1, wherein: the side wall of the frame (1) is fixedly connected with a sewage storage tank (23), and the bottom wall of the sewage storage tank (23) is fixedly connected with an air box (24).
7. The drilling and positioning device for bridge engineering according to claim 6, wherein: the dust collection device is characterized in that a dust collection opening I (25) is arranged in the air box (24), a dust tube (26) is fixedly connected to the side wall of the air box (24), and the other side of the dust tube (26) is fixedly connected to the dirt storage box (23).
8. The drilling and positioning device for bridge engineering according to claim 6, wherein: the dust collection fan (27) is arranged in the air box (24), and a protective cover (28) is fixedly connected to the side wall of the dust collection fan (27).
CN202322405508.7U 2023-09-05 2023-09-05 Drilling positioning device for bridge engineering Active CN220667468U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322405508.7U CN220667468U (en) 2023-09-05 2023-09-05 Drilling positioning device for bridge engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322405508.7U CN220667468U (en) 2023-09-05 2023-09-05 Drilling positioning device for bridge engineering

Publications (1)

Publication Number Publication Date
CN220667468U true CN220667468U (en) 2024-03-26

Family

ID=90330041

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322405508.7U Active CN220667468U (en) 2023-09-05 2023-09-05 Drilling positioning device for bridge engineering

Country Status (1)

Country Link
CN (1) CN220667468U (en)

Similar Documents

Publication Publication Date Title
CN220667468U (en) Drilling positioning device for bridge engineering
CN209706704U (en) A kind of thickness detection apparatus for asphalt pavement construction management
CN204677120U (en) A kind of pile digger of modified node method
CN212177030U (en) Drilling equipment for engineering building construction
CN209339850U (en) A kind of drilling machine drilling rod positioning device
CN219864851U (en) Deep piling equipment for civil building foundation
CN210738468U (en) Positioning and guiding device of rotary drilling rig
CN214091729U (en) Constructional engineering pile device
CN214460376U (en) Novel building engineering pile device
CN206246055U (en) A kind of outdoor portable soil puncher
CN214842919U (en) Bituminous paving thickness detection device for traffic engineering
CN214405322U (en) Building engineering cost on-site mapping device based on BIM technology
CN111893999B (en) Pile pulling guide frame and pile pulling method for waste inclined piles
CN212614533U (en) Rotary drilling rig for fishing method construction
JP2779389B2 (en) Rotary press-in device for steel pipe piles for settlement settlement
CN217531380U (en) Building of diversified work detects uses puncher
CN218255969U (en) Perforating device for building repair
CN218492501U (en) Earth-wood pile foundation construction pile foundation hole fixed point device
JP2002030658A (en) Support for hammer drill
CN215672059U (en) Fixing and supporting device for water mill drill construction
CN218117696U (en) Water mill bores pore-forming construction positioner
CN217896442U (en) Inspection device structure for highway engineering construction
CN218557577U (en) Wall drilling equipment is used to house decoration
CN221421958U (en) Be suitable for in-situ pile hole soil cleaning equipment of many specifications
CN216999707U (en) Pile cutting device for prestressed concrete square pile

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant