CN220613643U - Movable type foldable quick-dismantling pipe bench vice operating platform - Google Patents

Movable type foldable quick-dismantling pipe bench vice operating platform Download PDF

Info

Publication number
CN220613643U
CN220613643U CN202322198604.9U CN202322198604U CN220613643U CN 220613643 U CN220613643 U CN 220613643U CN 202322198604 U CN202322198604 U CN 202322198604U CN 220613643 U CN220613643 U CN 220613643U
Authority
CN
China
Prior art keywords
folding panel
movable
operating platform
bench vice
trolley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322198604.9U
Other languages
Chinese (zh)
Inventor
王贵堂
庄俊
辜润宇
游浩
邹林志
唐菡雪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan No6 Construction Co ltd
Original Assignee
Sichuan No6 Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan No6 Construction Co ltd filed Critical Sichuan No6 Construction Co ltd
Priority to CN202322198604.9U priority Critical patent/CN220613643U/en
Application granted granted Critical
Publication of CN220613643U publication Critical patent/CN220613643U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Handcart (AREA)

Abstract

The utility model discloses a movable foldable quick-dismantling pipe bench vice operation platform, which relates to the technical field of pipeline construction equipment and comprises the following components: the movable trolley is internally provided with a storage cavity for storing the bench vice; one end of the folding panel is hinged with the side surface of the top of the movable trolley; the movable trolley top is provided with an operation surface, and the folding panel can rotate to be flush with the operation surface. The platform is convenient to transport, can store and store tools, can expand an operation panel rapidly, and greatly improves the construction efficiency of the pipeline.

Description

Movable type foldable quick-dismantling pipe bench vice operating platform
Technical Field
The utility model relates to the technical field of pipeline construction equipment, in particular to a movable foldable quick-dismantling type pipe bench vice operating platform.
Background
The bench vice is a universal fixture for clamping a workpiece, and is assembled on a workbench for clamping and stably processing the workpiece.
In the installation engineering of the site, when the pipeline is constructed by adopting the threaded connection, workers often manufacture a tiger clamp operating platform for pipeline construction, but the operating platform has the defects of large volume, inconvenient transportation and large influence on the pipeline construction efficiency because of being incapable of being provided with a storage tool.
Disclosure of Invention
The utility model aims to solve the defects of the prior art, and aims to provide a movable foldable quick-dismantling pipe bench vice operating platform which is convenient to transport, can store and store tools, can quickly expand an operating panel and greatly improves the pipeline construction efficiency.
The utility model is realized by the following technical scheme:
a mobile collapsible quick disconnect pipe vise operating platform comprising:
the movable trolley is internally provided with a storage cavity for storing the bench vice;
one end of the folding panel is hinged with the side surface of the top of the movable trolley; the movable trolley top is provided with an operation surface, and the folding panel can rotate to be flush with the operation surface.
Compared with the prior art, when the pipeline is constructed by adopting the threaded connection in the installation engineering of the site construction, a worker often can manufacture a bench tiger clamp operation platform for pipeline construction, but the operation platform has the problems of large volume, inconvenient transportation and large influence on the pipeline construction efficiency because of being incapable of being provided with a storage tool; the movable trolley is internally provided with a storage cavity for storing the bench vice and other tools, and the bench vice and the other tools are transported by walking through a plurality of rollers at the bottom, so that the bench vice can be rapidly transported to a site for rapid construction through the movable trolley; the top of the trolley is provided with an operation surface, and the bench vice is taken out and placed on the operation surface during site construction; when carrying out centre gripping pipeline construction through the bench vice, owing to need great operation platform, the one end of travelling car is had folding panel in solid this scheme, and folding panel one end is articulated with travelling car roof portion side, when needing to enlarge operation platform, through rotatory folding panel for flush with the operation face, can increase operation platform's operation face.
In a further scheme, in order to support the folding panel and prevent the folding panel from rotating in the pipeline construction process, first inclined struts are arranged on two sides of the folding panel, and two ends of each first inclined strut are detachably connected to the side wall of the movable trolley and the side edge of the folding panel respectively; in the scheme, two ends of the first diagonal brace can be connected with the side wall of the trolley and the side edge of the folding panel through bolts, and the inclined support is used for improving stability; when the folding panel is required to be retracted, one end of the first diagonal brace is detached.
In a further scheme, in order to improve the stability of the folding panel, two sides of the other end of the folding panel are hinged with supporting rods; according to the scheme, the support rods are supported on the ground, so that the folding panel cannot shake in the operation process, and the support rods and the folding panel are mutually perpendicular to each other, namely the optimal support angle is achieved.
In a further scheme, in order to improve the supporting and stabilizing effect of the supporting rod, two sides of the folding panel are also provided with second inclined struts, and two ends of each second inclined strut are detachably connected with the supporting rod and the side edges of the folding panel respectively; according to the scheme, the angle between the support rod and the folding panel can be fixed through the second diagonal brace, so that the rotation of the support rod is avoided, and the support strength is improved; the second diagonal bracing can be connected through the bolt, and when needing to withdraw, one end of the second diagonal bracing can be disassembled.
In a further scheme, in order to adjust the supporting length of the supporting rod, one end of the supporting rod, which is far away from the folding panel, is provided with a first stud, one end of the first stud is in threaded connection with the end part of the supporting rod, and the first stud can move along the length direction of the supporting rod; the other end of the first stud is provided with a first hard column head; in this scheme, for the rotatory recovery of bracing piece of being convenient for, its length probably is less than the whole height of travelling car, so for adjusting the supporting height of bracing piece, there is the screw rod at bracing piece tip threaded connection, can adjust the length through the screw rod is rotatory, and rethread first stereoplasm column cap carries out stable support, has improved folding panel's stability, avoids its rotatory or production slip in the operation in-process.
In a further scheme, the outer side of the movable trolley is provided with a locking piece, and the locking piece is used for being connected with the supporting rod; the folding panel and the support rod can be rotated to the outer side of the mobile trolley and vertically arranged by fixing the retracted support rod through the locking piece, namely, rotating the folding panel downwards, then rotating the support rod upwards, and then connecting the support rod through the locking piece, so that the support rod cannot rotate downwards under the action of gravity; wherein the locking piece can be connected by adopting a plate lock, a hook, a movable pin and the like.
Because the operation table is required to be ensured to be stable in the pipeline construction process, and the tires at the bottom of the movable trolley are in flexible contact with the ground, the operation surface is easy to slide in the pipeline construction process, and therefore, in order to improve the stability of the operation surface, the bottom of the movable trolley is provided with a second stud, one end of the second stud is in threaded connection with the bottom of the movable trolley, and the other end of the second stud is provided with a second hard column head; the second hard column head can be abutted against the ground through the length adjustment of the second stud, so that the tire is replaced, and the table top can be prevented from shaking through the hard support.
Still further scheme, follow travelling car outside bottom circumference direction has a plurality of installed parts, the installed part is including upper and lower interval distribution's first mounting panel and second mounting panel, all have on first mounting panel and the second mounting panel with second double-screw bolt threaded connection's screw hole.
In a further scheme, the inner side of the storage cavity is provided with a supporting plate, and the bench vice is placed on the supporting plate; namely, the bench vice is placed through the supporting plate, so that the bench vice is separated from other tools, and the bench vice can be conveniently and rapidly taken.
In a further scheme, in order to more conveniently place the bench vice on the operation surface, a lifting assembly is fixed on the supporting plate, and the lifting assembly is applied to drive the bench vice to lift and extend out of the operation surface at the top of the movable trolley; the operating surface of the top of the movable trolley is provided with a hinge door for the bench vice to extend out; the lifting assembly is started by opening the hinge door, so that the bench vice extends out of the hinge door; wherein the lifting assembly adopts a lifting motor; the front side of the mobile trolley is provided with a switch door and a door lock, the switch door is opened to open the storage cavity, and when the folding panel is unfolded, the switch door is opened or closed if needed, and one end of the first diagonal brace is detached.
Compared with the prior art, the utility model has the following advantages and beneficial effects:
1. the movable foldable quick-dismantling pipe bench vice operating platform provided by the utility model is convenient to transport, can store and store tools, can expand an operating panel quickly, and greatly improves the pipeline construction efficiency.
2. According to the movable foldable quick-dismantling pipe bench vice operating platform, the supporting height is adjusted through the first stud, the second stud and the hard column head at the bottom, meanwhile, the stability of the operating surface can be maintained, and the operating surface is prevented from shaking in the construction process due to flexible support of the tire.
3. According to the movable foldable quick-release pipe bench vice operating platform provided by the utility model, the bench vice can be driven to quickly rise to the operating surface from the storage cavity through the lifting assembly, so that the pipeline construction efficiency is improved.
Drawings
The accompanying drawings, which are included to provide a further understanding of embodiments of the utility model and are incorporated in and constitute a part of this application, illustrate embodiments of the utility model. In the drawings:
FIG. 1 is a schematic view of an operation platform according to an embodiment of the present utility model after being unfolded;
FIG. 2 is a schematic view of a folding and recycling operation platform according to an embodiment of the present utility model;
FIG. 3 is a schematic structural diagram of an operation platform according to an embodiment of the present utility model after folding and recycling;
fig. 4 is a left side view of fig. 1 provided by the present utility model.
In the drawings, the reference numerals and corresponding part names:
1-travelling car, 101-storage chamber, 102-first mounting plate, 103-second mounting plate, 104-backup pad, 105-lifting assembly, 2-bench vice, 3-folding panel, 4-bracing piece, 5-first bracing, 6-second bracing, 7-first double-screw bolt, 701-first hard column cap, 8-snap fastener, 9-second double-screw bolt, 901-second hard column cap.
Detailed Description
For the purpose of making apparent the objects, technical solutions and advantages of the present utility model, the present utility model will be further described in detail with reference to the following examples and the accompanying drawings, wherein the exemplary embodiments of the present utility model and the descriptions thereof are for illustrating the present utility model only and are not to be construed as limiting the present utility model.
Examples: the present embodiment provides a movable foldable quick-release pipe vice 2 operating platform, as shown in fig. 1-4, comprising:
the movable trolley 1 is provided with a storage cavity 101 for storing the bench vice 2 inside the movable trolley 1;
the folding panel 3, one end of the folding panel 3 is hinged with the side surface of the top of the mobile trolley 1; the travelling car 1 has an operating surface on top and the folding panel 3 can be rotated to its own plane flush with the operating surface.
Compared with the prior art, when the pipeline is constructed by adopting the threaded connection in the installation engineering of the site construction, a worker often can manufacture a tiger clamp operating platform for pipeline construction, but the operating platform has the problems of large volume, inconvenient transportation and large influence on the pipeline construction efficiency because of being incapable of being provided with a storage tool; the movable trolley 1 is provided with a storage cavity 101 inside, and is used for storing the bench vice 2 and a plurality of other tools, and walking and transportation are performed through a plurality of rollers at the bottom, so that the bench vice 2 can be quickly transported to a site for quick construction through the movable trolley 1; the top of the trolley is provided with an operation surface, and the bench vice 2 is taken out and placed on the operation surface during site construction; when carrying out centre gripping pipeline construction through bench vice 2, owing to need great operation platform, the solid this scheme has folding panel 3 in the one end of travelling car 1, and folding panel 3 one end is articulated with travelling car 1 top side, when needs enlarge operation platform, through rotatory folding panel 3 for flush with the operation face, can increase operation platform's operation face.
In this embodiment, in order to support the folding panel 3 and prevent the folding panel 3 from rotating during the pipe construction process, both sides of the folding panel 3 are provided with first diagonal braces 5, and both ends of the first diagonal braces 5 are detachably connected to the side wall of the travelling car 1 and the side edge of the folding panel 3 respectively; in the scheme, two ends of the first diagonal brace 5 can be connected with the side wall of the trolley and the side edge of the folding panel 3 through bolts, and the inclined support is used for improving stability; when the folding panel 3 needs to be retracted, one end of the first diagonal stay 5 is detached.
In this embodiment, in order to improve stability of the folding panel 3, two sides of the other end of the folding panel 3 are hinged with support rods 4; according to the scheme, the support rods 4 are supported on the ground, so that the folding panel 3 cannot shake in the operation process, and the support rods 4 and the folding panel 3 are mutually perpendicular to each other, namely the optimal support angle is achieved.
In this embodiment, in order to improve the supporting stabilization of the supporting rod 4, two sides of the folding panel 3 are also provided with second diagonal braces 6, and two ends of the second diagonal braces 6 are detachably connected to the supporting rod 4 and the side edges of the folding panel 3 respectively; according to the scheme, the second diagonal brace 6 can fix the angle between the support rod 4 and the folding panel 3, so that the support rod 4 is prevented from rotating, and the support strength is improved; the second diagonal bracing 6 can be connected through bolts, and when the second diagonal bracing 6 needs to be retracted, one end of the second diagonal bracing 6 is detached.
In this embodiment, in order to adjust the supporting length of the supporting rod 4, one end of the supporting rod 4 far away from the folding panel 3 is provided with a first stud 7, one end of the first stud 7 is in threaded connection with the end of the supporting rod 4, and the first stud 7 can move along the length direction of the supporting rod 4; the other end of the first stud 7 is provided with a first hard column head 701; in this scheme, for the rotatory recovery of bracing piece 4 of being convenient for, its length probably is less than travelling car 1's overall height, so for adjusting the supporting height of bracing piece 4, there is the screw rod at bracing piece 4 tip threaded connection, can adjust the length through the screw rod rotation, and rethread first stereoplasm column cap 701 carries out stable support, has improved folding panel 3's stability, avoids its rotatory or production slip in the operation in-process.
In the embodiment, the outer side of the mobile trolley 1 is provided with a locking piece 8, and the locking piece 8 is used for being connected with the support rod 4; the folding panel 3 and the support rod 4 can be rotated to the outer side of the mobile trolley 1 through the locking piece 8 and then vertically arranged by rotating the folding panel 3 downwards and then rotating the support rod 4 upwards, and then the support rod 4 is connected through the locking piece 8, so that the support rod 4 cannot rotate downwards under the action of gravity; wherein the locking piece 8 can be connected by adopting a plate lock, a hook, a movable pin and the like.
In this embodiment, since the stability of the operation table needs to be ensured in the pipeline construction process, and the tire at the bottom of the moving trolley 1 is in flexible contact with the ground, the operation surface is very easy to slide in the pipeline construction process, so, in order to improve the stability of the operation surface, the bottom of the moving trolley 1 is provided with the second stud 9, one end of the second stud 9 is in threaded connection with the bottom of the moving trolley 1, and the other end of the second stud 9 is provided with the second hard column head 901; namely, the second hard column head 901 can be abutted against the ground by adjusting the length of the second stud 9, so that the table top can be prevented from shaking by the hard support instead of the tire.
In this embodiment, a plurality of mounting pieces are provided along the circumferential direction of the bottom outside the travelling car 1, each mounting piece comprises a first mounting plate 102 and a second mounting plate 103 which are vertically and alternately distributed, and the first mounting plate 102 and the second mounting plate 103 are respectively provided with a threaded hole in threaded connection with the second stud 9.
In the embodiment, the inner side of the storage cavity 101 is provided with a supporting plate 104, and the bench vice 2 is placed on the supporting plate 104; i.e. the bench vice 2 is placed by the support plate 104, the bench vice 2 is separated from the rest of the tools, facilitating the quick taking of the bench vice 2.
In this embodiment, in order to more conveniently place the bench vice 2 on the operation surface, the lifting assembly 105 is fixed on the supporting plate 104, and the lifting assembly 105 is applied to drive the bench vice 2 to lift and extend out of the operation surface at the top of the travelling car 1; the operation surface at the top of the movable trolley 1 is provided with a hinge door for the bench vice 2 to extend out; namely, the lifting assembly 105 is started by opening the hinge door, so that the bench vice 2 extends out of the hinge door; wherein the lifting assembly 105 employs a lifting motor; the front side of the mobile trolley 1 is provided with a switch door and a door lock, the switch door is opened to open the storage cavity 101, and when the folding panel 3 is unfolded, if the switch door is opened or closed, one end of the first diagonal brace 5 is detached.
The foregoing description of the embodiments has been provided for the purpose of illustrating the general principles of the utility model, and is not meant to limit the scope of the utility model, but to limit the utility model to the particular embodiments, and any modifications, equivalents, improvements, etc. that fall within the spirit and principles of the utility model are intended to be included within the scope of the utility model.

Claims (10)

1. A portable collapsible quick detach formula pipe bench vice operation platform, characterized in that includes:
a moving trolley (1), wherein a storage cavity (101) for storing the bench vice (2) is arranged in the moving trolley (1);
the folding panel (3), one end of the folding panel (3) is hinged with the side surface of the top of the mobile trolley (1); the top of the movable trolley (1) is provided with an operation surface, and the folding panel (3) can rotate to be flush with the operation surface.
2. The movable type foldable quick-dismantling pipe bench vice operating platform according to claim 1, wherein first inclined struts (5) are arranged on two sides of the folding panel (3), and two ends of the first inclined struts (5) are detachably connected to the side wall of the movable trolley (1) and the side edge of the folding panel (3) respectively.
3. The movable foldable quick-release pipe vice operating platform according to claim 1, wherein the two sides of the other end of the folding panel (3) are hinged with supporting rods (4).
4. A portable collapsible quick release pipe vice operating platform as claimed in claim 3, wherein,
the folding panel (3) both sides still are equipped with second bracing (6), the both ends of second bracing (6) respectively can dismantle connect in bracing piece (4) and folding panel (3) side.
5. A movable foldable quick-release pipe vice operating platform according to claim 3, characterized in that one end of the support rod (4) far away from the folding panel (3) is provided with a first stud (7), one end of the first stud (7) is in threaded connection with the end part of the support rod (4), and the first stud (7) can move along the length direction of the support rod (4); the other end of the first stud (7) is provided with a first hard column head (701).
6. A mobile collapsible quick-release pipe vice operating platform according to claim 3, characterized in that the outside of the travelling car (1) is provided with a locking element (8), said locking element (8) being adapted to be connected to the support bar (4).
7. The movable foldable quick-release pipe vice operating platform according to claim 1, wherein a second stud (9) is arranged at the bottom of the movable trolley (1), one end of the second stud (9) is in threaded connection with the bottom of the movable trolley (1), and a second hard column head (901) is arranged at the other end of the second stud (9).
8. The movable foldable quick-release pipe vice operating platform according to claim 7, wherein a plurality of mounting pieces are arranged along the circumferential direction of the bottom of the outer side of the movable trolley (1), each mounting piece comprises a first mounting plate (102) and a second mounting plate (103) which are distributed at intervals up and down, and threaded holes in threaded connection with the second studs (9) are formed in each of the first mounting plates (102) and the second mounting plates (103).
9. A mobile, collapsible, quick-release pipe vice operating platform according to claim 1, characterized in that the storage chamber (101) is provided with a support plate (104) inside, the vice (2) being placed on the support plate (104).
10. The movable type foldable quick-release pipe bench vice operating platform according to claim 9, characterized in that a lifting assembly (105) is fixed on the supporting plate (104), and the lifting assembly (105) is applied to drive the bench vice (2) to lift and extend out of an operating surface at the top of the mobile trolley (1); the operation surface at the top of the movable trolley (1) is provided with a hinge door for the bench vice (2) to extend out.
CN202322198604.9U 2023-08-15 2023-08-15 Movable type foldable quick-dismantling pipe bench vice operating platform Active CN220613643U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322198604.9U CN220613643U (en) 2023-08-15 2023-08-15 Movable type foldable quick-dismantling pipe bench vice operating platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322198604.9U CN220613643U (en) 2023-08-15 2023-08-15 Movable type foldable quick-dismantling pipe bench vice operating platform

Publications (1)

Publication Number Publication Date
CN220613643U true CN220613643U (en) 2024-03-19

Family

ID=90213361

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322198604.9U Active CN220613643U (en) 2023-08-15 2023-08-15 Movable type foldable quick-dismantling pipe bench vice operating platform

Country Status (1)

Country Link
CN (1) CN220613643U (en)

Similar Documents

Publication Publication Date Title
CN217193634U (en) Bellows welding frock
CN111441648B (en) Building construction protective fence
CN220613643U (en) Movable type foldable quick-dismantling pipe bench vice operating platform
CN112847175A (en) Cylinder anchor clamps convenient to fine setting interval
CN115139037A (en) Welding equipment for petrochemical accessory production
CN205312921U (en) Transformer on -load switch suspended core instrument
CN211257802U (en) Folding type building templates
CN212095099U (en) Detachable large-scale penstock Mi word props device
CN210976538U (en) Foldable scaffold
CN215747289U (en) Pressure steel pipe welding scaffold for water diversion tunnel
CN212951177U (en) Emergency airstairs convenient to build
CN114472952A (en) Drilling equipment is used in hardware processing with adjustable multi-angle of difficult slippage
CN214942168U (en) Portable scaffold
CN206854931U (en) Thin-wall steel tube weld jig and thin-wall steel tube welding equipment
CN207825183U (en) The prefabricated stripper apparatus of tee girder
CN214739904U (en) Adjustable window opening template supporting mechanism
CN219548337U (en) Engineering construction work frame with protection architecture
CN216811259U (en) Rotatable construction enclosure
CN217976238U (en) Steel frame rapid installation hinging device based on three-arm arch frame installation trolley
CN214869953U (en) Mechanical structure longeron additional strengthening
CN215254639U (en) Wall body bracing mechanism for aluminum mould
CN116397864B (en) Scaffold device for open caisson construction
CN217208118U (en) Can dismantle turnover concrete pump pipe fixing device
CN219746771U (en) Right-angle double-sided steel plate welding device
CN115198655B (en) Equipment for assisting in combined installation of hydraulic climbing formwork

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant