CN220550920U - Quick support structure that erects of construction template - Google Patents

Quick support structure that erects of construction template Download PDF

Info

Publication number
CN220550920U
CN220550920U CN202322085254.5U CN202322085254U CN220550920U CN 220550920 U CN220550920 U CN 220550920U CN 202322085254 U CN202322085254 U CN 202322085254U CN 220550920 U CN220550920 U CN 220550920U
Authority
CN
China
Prior art keywords
wall
fixedly connected
horizontal pole
rod
branch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322085254.5U
Other languages
Chinese (zh)
Inventor
曹玉娟
闫冰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Southwest Engineering Project Management Consulting Co ltd Shandong Branch
Original Assignee
Sichuan Southwest Engineering Project Management Consulting Co ltd Shandong Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Southwest Engineering Project Management Consulting Co ltd Shandong Branch filed Critical Sichuan Southwest Engineering Project Management Consulting Co ltd Shandong Branch
Priority to CN202322085254.5U priority Critical patent/CN220550920U/en
Application granted granted Critical
Publication of CN220550920U publication Critical patent/CN220550920U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a rapid erection support structure of a construction formwork, which comprises a first cross rod, wherein a first transverse pipe is inserted into the outer wall of the first cross rod, first supporting rods are fixedly connected to the ends, far away from each other, of the first cross rod and the first transverse pipe, second supporting rods are movably connected to the outer walls of the two first supporting rods, and electric pushing rods are fixedly connected to the upper parts of the outer walls of the two second supporting rods. The utility model relates to the technical field of building construction, and discloses a combined type building construction system which comprises a first supporting rod, a second supporting rod, a first cross rod, a first transverse pipe, a second cross rod, a second transverse pipe, an electric push rod, a first clamping plate, a second clamping plate and a threaded rod.

Description

Quick support structure that erects of construction template
Technical Field
The utility model relates to the technical field of building construction, in particular to a rapid erection support structure of a construction template.
Background
The building construction refers to the production activity of engineering construction implementation stage, which is the construction process of various buildings, and can be said to be the process of changing various lines on a design drawing into real objects at a designated place. The construction method comprises foundation engineering construction, main structure construction, roof engineering construction, decoration engineering construction and the like, and when the construction template is erected, a support structure is required to be quickly erected by using the construction template;
when the existing construction template rapid erection support structure is used, the effect of supporting the construction template is mainly achieved, the existing support frame is mostly spliced and fixed by fasteners such as bolts when the existing support frame is used, and the support frame can be put into use after installation is finished;
the supporting structure is erect fast to traditional construction template when using, because adopt mounting such as bolt to splice fixedly, this just makes consuming time longer when the installation for work efficiency is lower, and because long-time use, the phenomenon of corrosion takes place for the bolt easily moreover, and then makes the staff all comparatively inconvenient when carrying out the dismouting.
Disclosure of Invention
Aiming at the defects of the prior art, the utility model provides the rapid erection support structure for the construction template, which solves the problems that the time consumption is long during installation and the working efficiency is low because the fixing pieces such as bolts are adopted for splicing and fixing when the conventional rapid erection support structure for the construction template is used, and the bolts are easy to rust and are inconvenient for workers during disassembly and assembly because of long-time use.
In order to achieve the above purpose, the present utility model is realized by the following technical scheme: the utility model provides a support structure is erect fast to construction template, includes first horizontal pole, the outer wall grafting of first horizontal pole has first violently pipe, the equal fixedly connected with first branch of one end that first horizontal pole and first violently pipe kept away from each other, two the equal swing joint of outer wall of first branch has second branch, two the equal fixedly connected with electric putter in outer wall top of second branch, two the bottom of electric putter respectively with the outer wall looks rigid coupling of first horizontal pole and first violently pipe, the outer wall top fixedly connected with second horizontal pole of the second branch that is close to first violently pipe one side, the outer wall grafting of second horizontal pole has the second violently pipe, the outer wall of second violently pipe and the outer wall top looks rigid coupling that is close to the second branch of first horizontal pole one side, the inner wall grafting of second violently pipe has the second inserted bar that is pegged graft mutually with the second horizontal pole inner wall of second, two the equal fixedly connected with first splint of top of second branch and the outer wall of first horizontal pole, two the top fixedly connected with second splint have the second splint to peg graft mutually with the second splint, the inner wall grafting of second horizontal pipe has the second splint to peg graft mutually with the second splint.
Preferably, the top of the threaded rod is fixedly connected with a handle.
Preferably, the rubber pads are fixedly connected to one sides of the first clamping plate and the second clamping plate, which are close to each other.
Preferably, the bottom of the first clamping plate is fixedly connected with a connecting rod fixedly connected with the inner wall of the second supporting rod.
Preferably, the bottoms of the second cross rod and the second cross tube are fixedly connected with a first reinforcing rod fixedly connected with the upper part of the outer wall of the second supporting rod, and the tops of the first cross rod and the first cross tube are fixedly connected with a second reinforcing rod fixedly connected with the outer wall of the first supporting rod.
Advantageous effects
The utility model provides a rapid erection support structure for a construction formwork. The beneficial effects are as follows: this construction template erects bearing structure fast through first branch, second branch, first horizontal pole, first violently managing, second horizontal pole, the cooperation of second violently managing, electric putter, first splint, second splint and threaded rod for the construction template bearing structure is erect that the staff can be quick, and need not utilize the bolt to fix, consequently can greatly reduced staff's operation intensity, and can also effectively reduce holistic erection time, and then improved work efficiency, brought convenience for staff's use.
Drawings
FIG. 1 is a schematic diagram of the structure of the present utility model;
FIG. 2 is a cross-sectional view of FIG. 1;
FIG. 3 is a schematic view of the electric putter, the first strut and the second strut of FIG. 2;
fig. 4 is a schematic view of the threaded rod, the second clamping plate and the first clamping plate in fig. 2.
In the figure: 1. the first support rod, 2, the second support rod, 3, the third inserted link, 4, the electric putter, 5, the first horizontal pole, 6, the first horizontal pipe, 7, the first inserted link, 8, the second horizontal pole, 9, the second horizontal pipe, 10, the second inserted link, 11, the connecting rod, 12, first splint, 13, the second splint, 14, the threaded rod, 15, the rubber pad, 16, the gag lever post, 17, the first stiffener, 18, the second stiffener.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
The components in the present case are sequentially connected by a person skilled in the art, and specific connection and operation sequence should be referred to the following working principle, and the detailed connection means thereof are known in the art, and the following working principle and process are mainly described.
When the traditional construction formwork rapid erection support structure is used, due to the fact that fixing pieces such as bolts are adopted for splicing and fixing, time consumption is long during installation, working efficiency is low, and due to the fact that the bolts are easy to rust during long-time use, workers are inconvenient to disassemble and assemble;
in view of the above, the utility model provides a rapid erection support structure for construction templates, which enables workers to rapidly erect the support structure for construction templates by matching a first support rod, a second support rod, a first cross rod, a first transverse pipe, a second cross rod, a second transverse pipe, an electric push rod, a first clamping plate, a second clamping plate and a threaded rod, and does not need to fix by bolts, so that the operation intensity of the workers can be greatly reduced, the overall erection time can be effectively reduced, the working efficiency is further improved, and convenience is brought to the use of the workers.
Embodiment one: as can be seen from fig. 1, 2, 3 and 4, a support structure is rapidly erected to construction template, including first horizontal pole 5, the outer wall of first horizontal pole 5 is pegged graft and is had first violently pipe 6, the equal fixedly connected with first branch 1 of one end that first horizontal pole 5 and first violently pipe 6 kept away from each other, the equal swing joint of outer wall of two first branches 1 has second branch 2, the equal fixedly connected with electric putter 4 in outer wall top of two second branches 2, the model of electric putter 4 is TG-700, electric putter 4 can ground pad second branch 2 is along the outer wall motion of first branch 1, and then can improve this construction template and erect support structure's overall height, and then can satisfy multiple different user demands, the bottom of two electric putter 4 is fixed with first horizontal pole 5 and first violently pipe 6's outer wall looks rigid coupling respectively, the outer wall top of second branch 8 is fixedly connected with, the outer wall grafting of second horizontal pole 8, the outer wall grafting of second branch 9 and the second branch 5 is close to one side of first horizontal pole 6, the outer wall of second horizontal pole 9 is equipped with second horizontal pole 9 and the second connecting rod 5 is equipped with the second clamp plate through the second clamp plate 5, the inner wall that first horizontal pole 12 is more in order to carry out the second template is pegged graft with the second horizontal pole 12, the top of first horizontal pole 12 is more than the second clamp plate is more convenient for the top of putting up to install the second horizontal pole 12, the top of this construction template is more than the second horizontal pole 12 is more convenient, the top of this construction template is more has the top of second horizontal pole 12 is more vertical to be equipped with the second horizontal pole 12, the top is more convenient to be equipped with the top to be equipped with the second horizontal to be more, the position between the first clamping plate 12 and the second clamping plate 13 can be changed by twisting the threaded rod 14, so that the external template can be stably installed and fixed, the lower part of the outer wall of the threaded rod 14 is rotationally connected with the inner wall of the first clamping plate 12 through a bearing, the bottom of the second clamping plate 13 is fixedly connected with a limiting rod 16 which is spliced with the inner wall of the first clamping plate 12, and the inner wall of the second supporting rod 2 is spliced with a third inserting rod 3 which is spliced with the inner wall of the first supporting rod 1;
in the specific implementation process, it is worth particularly pointing out that the electric push rod 4 can cushion the second supporting rod 2 to move along the outer wall of the first supporting rod 1, so that the overall height of the construction formwork rapid erection support structure can be improved, various different use requirements can be met, the construction formwork rapid erection support structure can be retracted and released through the cooperation of the second transverse pipe 9, the second transverse rod 8, the first transverse pipe 6 and the first transverse rod 5, further, a worker can store the construction formwork rapid erection support structure more conveniently, the position between the first clamping plate 12 and the second clamping plate 13 can be changed through the torsion threaded rod 14, and the external formwork can be stably installed and fixed;
further, the top of the threaded rod 14 is fixedly connected with a handle, one side, close to each other, of the first clamping plate 12 and the second clamping plate 13 is fixedly connected with a rubber pad 15, the bottom of the first clamping plate 12 is fixedly connected with a connecting rod 11 fixedly connected with the inner wall of the second supporting rod 2, the bottoms of the second cross rod 8 and the second cross tube 9 are fixedly connected with a first reinforcing rod 17 fixedly connected with the upper part of the outer wall of the second supporting rod 2, and the tops of the first cross rod 5 and the first cross tube 6 are fixedly connected with a second reinforcing rod 18 fixedly connected with the outer wall of the first supporting rod 1;
in the specific implementation process, the design of the handle is worth particularly pointing out, so that a worker can more conveniently operate the threaded rod 14 and the rubber pad 15, the friction among the construction template, the first clamping plate 12 and the second clamping plate 13 can be increased, the installation stability is further ensured, the connection strength of the first clamping plate 12 and the second supporting rod 2 can be improved through the design of the connecting rod 11, the integral strength of the construction template for quickly erecting the supporting structure can be improved through the first reinforcing rod 17 and the second reinforcing rod 18, and the supporting stability is further ensured;
specifically, when using this construction template to erect bearing structure fast, at first the staff chooses the construction template of suitable quantity to erect bearing structure fast, then the staff pulls first branch 1, drive first horizontal pole 5 and first violently pipe 6 and second horizontal pole 8 and second violently pipe 9 motion, and then with this construction template to erect bearing structure fast and expand, after expanding, the staff inserts first inserted bar 7 and second inserted bar 10 respectively the inner wall of first violently pipe 6 and second violently pipe 9, then the staff opens the external power supply of electric putter 4, at this moment electric putter 4 can drive the outer wall motion of second branch 2 along first branch 1, and then can change the whole height of this construction template and erect bearing structure fast, after the altitude mixture control, the staff inserts second branch 2 and the inner wall of first branch 1 with third inserted bar 3, then the staff puts into the construction template between first splint 12 and the second splint 13 at this moment, then the staff twists 14, at this moment threaded bar 14 can drive second splint 13 motion, and then can change the outer wall motion of second splint along the outer wall motion of first branch 1, and then can accomplish the construction template position fixing operation between the splint at this moment.
It is noted that relational terms such as first and second, and the like are used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Moreover, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation. The term "comprising" an element defined by the term "comprising" does not exclude the presence of other identical elements in a process, method, article or apparatus that comprises the element.
In the present utility model, unless explicitly specified and limited otherwise, the terms "mounted," "configured," "connected," "secured," "screwed," and the like are to be construed broadly and may be, for example, fixedly connected, detachably connected, or integrally formed; can be mechanically or electrically connected; either directly or indirectly through intermediaries, or in communication with each other or in interaction with each other, unless explicitly defined otherwise, the meaning of the terms described above in this application will be understood by those of ordinary skill in the art in view of the specific circumstances.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides a support structure is erect fast to construction template, includes first horizontal pole (5), its characterized in that: the utility model discloses a clamp plate, including first horizontal pole (5) and second horizontal pole (6), the outer wall of first horizontal pole (5) is pegged graft and is had first horizontal pipe (6), the first horizontal pole (5) is all fixedly connected with first branch (1) with the one end that first horizontal pipe (6) kept away from each other, two the equal swing joint of outer wall of first branch (1) has second branch (2), two equal fixedly connected with electric putter (4) above the outer wall of second branch (2), two electric putter (4) the bottom respectively with first horizontal pole (5) and first horizontal pipe (6) outer wall looks rigid coupling, the outer wall top fixedly connected with second horizontal pole (8) of second branch (2) that is close to first horizontal pipe (6) one side, the outer wall grafting of second horizontal pole (8) has second horizontal pipe (9), the outer wall of second horizontal pipe (9) and the outer wall top looks rigid coupling of second branch (2) that is close to first horizontal pole (5) one side, the inner wall grafting of second horizontal pole (9) has second inserted pole (10) looks inner wall (8) with second horizontal pole (6), the top of first horizontal pole (12) is pegged graft and is had clamp plate (12), the inner wall threaded connection of second splint (13) has threaded rod (14), the outer wall below of threaded rod (14) rotates with the inner wall of first splint (12) through the bearing and links to each other, the bottom fixedly connected with of second splint (13) is with gag lever post (16) that first splint (12) inner wall pegged graft mutually, the inner wall grafting of second branch (2) has third inserted bar (3) that peg graft mutually with first branch (1) inner wall.
2. A construction formwork rapid erection support structure as claimed in claim 1, wherein: the top of the threaded rod (14) is fixedly connected with a handle.
3. A construction formwork rapid erection support structure as claimed in claim 1, wherein: rubber pads (15) are fixedly connected to one sides, close to each other, of the first clamping plate (12) and the second clamping plate (13).
4. A construction formwork rapid erection support structure as claimed in claim 1, wherein: the bottom of the first clamping plate (12) is fixedly connected with a connecting rod (11) fixedly connected with the inner wall of the second supporting rod (2).
5. A construction formwork rapid erection support structure as claimed in claim 1, wherein: the bottoms of the second cross rod (8) and the second cross tube (9) are fixedly connected with a first reinforcing rod (17) fixedly connected with the upper part of the outer wall of the second supporting rod (2), and the tops of the first cross rod (5) and the first cross tube (6) are fixedly connected with a second reinforcing rod (18) fixedly connected with the outer wall of the first supporting rod (1).
CN202322085254.5U 2023-08-04 2023-08-04 Quick support structure that erects of construction template Active CN220550920U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322085254.5U CN220550920U (en) 2023-08-04 2023-08-04 Quick support structure that erects of construction template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322085254.5U CN220550920U (en) 2023-08-04 2023-08-04 Quick support structure that erects of construction template

Publications (1)

Publication Number Publication Date
CN220550920U true CN220550920U (en) 2024-03-01

Family

ID=90003762

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322085254.5U Active CN220550920U (en) 2023-08-04 2023-08-04 Quick support structure that erects of construction template

Country Status (1)

Country Link
CN (1) CN220550920U (en)

Similar Documents

Publication Publication Date Title
CN201546435U (en) Bolted stayed cantilever scaffold
CN210316454U (en) Large-span roof overhanging support system
CN220550920U (en) Quick support structure that erects of construction template
CN109098423B (en) Full steel pipe scaffold structure for assembling annular suspended dome structure and construction method thereof
CN208586899U (en) A kind of support frame with oblique jacking
CN216098741U (en) Quick screwing device for adjustable bracket for jacking and flat supporting of disc-buckle type scaffold
CN106150082B (en) Formwork erection structure and erection method for pitched roof ridge cast-in-place structural
CN202559727U (en) Load-bearing support structure of template of overhead long-span floor slab of building
CN219587247U (en) Temporary device for tensioning ground of beam string structure
CN215716115U (en) Connecting device for connecting reinforced concrete beam and profile steel concrete column
CN216076179U (en) Safety foot rest is used in building engineering construction
CN214424114U (en) Foldable steel structure support
CN218375373U (en) Assembly type canopy bifurcated column assembling jig frame
CN216840683U (en) High-hanging-performance light wallboard fixing mechanism
CN217557613U (en) Hanging basket supporting structure for inclined roof
CN214835263U (en) Auxiliary erecting device for cable upright stanchion
CN211081004U (en) Diagonal bracing mechanism
CN213898094U (en) Structure is set up in pre-buried installation of oblique-pulling type roof beam side of foot of encorbelmenting support frame that encorbelments
CN216892950U (en) Mountain energy-saving sunlight greenhouse wall with stable structure
CN219451491U (en) Horizontal reserved hole plugging template
CN211960296U (en) Green house is with big-arch shelter pipe of being convenient for installation
CN213115437U (en) Wall-attached type operation platform module under overhanging roof
CN217601776U (en) Assembled building wall component
CN204940523U (en) A kind of curved surface net frame four crutch mounting structure
CN212633932U (en) Arc-shaped stress framework processing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant