CN220469344U - Detachable concrete pouring platform capable of preventing reinforcing steel bar meshes from being damaged - Google Patents
Detachable concrete pouring platform capable of preventing reinforcing steel bar meshes from being damaged Download PDFInfo
- Publication number
- CN220469344U CN220469344U CN202321952985.9U CN202321952985U CN220469344U CN 220469344 U CN220469344 U CN 220469344U CN 202321952985 U CN202321952985 U CN 202321952985U CN 220469344 U CN220469344 U CN 220469344U
- Authority
- CN
- China
- Prior art keywords
- plate
- support column
- connecting plate
- bearing plate
- placement platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 229910001294 Reinforcing steel Inorganic materials 0.000 title abstract description 28
- 230000003014 reinforcing effect Effects 0.000 claims description 13
- 238000010276 construction Methods 0.000 claims description 2
- 238000000034 method Methods 0.000 description 5
- 238000005336 cracking Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 239000000758 substrate Substances 0.000 description 1
- 239000002344 surface layer Substances 0.000 description 1
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model relates to a detachable concrete pouring platform for preventing a reinforcing steel mesh from being damaged. The detachable concrete pouring platform for preventing the damage of the reinforcing steel bar net piece comprises a plurality of operation pedals for bearing constructors, wherein two adjacent operation pedals are connected through a connecting plate, and the operation pedals are spliced with the connecting plate; the lower end of the operation pedal is connected with a first support column, and the lower end of the connecting plate is connected with a second support column. The operation pedal of the detachable concrete pouring platform for preventing the damage of the reinforcing steel bar net piece is spliced with the connecting plate, so that the detachable concrete pouring platform is convenient to install and detach. Meanwhile, the detachable concrete pouring platform capable of preventing the damage of the reinforcing steel mesh can be erected along the route to be poured, and the operation pedals are mutually connected, so that the stability is higher.
Description
Technical Field
The utility model belongs to the technical field of building construction, and particularly relates to a detachable concrete pouring platform capable of preventing a reinforcing steel bar net piece from being damaged.
Background
At present, in the concrete pouring process, a reinforcing steel mesh is generally paved before pouring so as to play a role in preventing the cracking of a concrete surface layer. However, in the pouring process, pouring personnel need to stand on the reinforcing steel bar net sheet to perform pouring, vibrating and the like of concrete, and the reinforcing steel bar net sheet is damaged in the pouring and vibrating processes, so that the reinforcing steel bar net sheet cannot play a role in preventing cracking.
The utility model patent with the application publication number of CN215978618U discloses a concrete pouring platform, which comprises a main body platform and a supporting part; the main body platform comprises a main body frame, a supporting frame and a platform plate, wherein the supporting part comprises a vertical supporting rod, a supporting base and a limiting rod, the vertical supporting rod can move in the vertical direction relative to the supporting base, and the height from the main body platform to the supporting base can be changed by vertically moving the vertical supporting rod and the main body platform, so that the height of the concrete pouring platform can be adjusted. When pouring different places, a plurality of concrete pouring platforms are required to be placed together, or used concrete pouring platforms are moved to required positions; however, there is no connection between the concrete pouring platforms, and a single concrete pouring platform is unstable and is troublesome to carry.
Disclosure of Invention
The utility model aims to provide a detachable concrete pouring platform for preventing damage of a reinforcing steel mesh, which solves the technical problems that when pouring different places, the carrying of the pouring platform is troublesome and the single pouring platform is unstable.
In order to achieve the above purpose, the technical scheme adopted by the utility model is as follows: the detachable concrete pouring platform for preventing the damage of the reinforcing steel bar net sheet comprises a plurality of operation pedals for bearing constructors, wherein two adjacent operation pedals are connected through a connecting plate, and the operation pedals are spliced with the connecting plate; the lower end of the operation pedal is connected with a first support column, and the lower end of the connecting plate is connected with a second support column.
Further, the operation pedal is integrally formed, and the operation pedal is a Z-shaped plate; the operation pedal comprises a bearing plate I at the middle part and extension plates I at the left end and the right end of the bearing plate I; the first extension plate is spliced with the connecting plate.
Furthermore, a plug hole is formed in the first extension plate, a plug pin matched with the plug hole is arranged on the connecting plate, and the plug pin penetrates through the plug hole to connect the connecting plate with the first extension plate.
Further, a plurality of plug holes are formed; the plurality of plug holes are distributed along the front-back direction of the extension plate.
Further, the connecting plates are integrally formed, and the connecting plates are Z-shaped plates; the connecting plate comprises a second bearing plate in the middle and a second extension plate positioned at the left end and the right end of the second bearing plate; the bolt is connected with the second extending plate.
Further, the second bearing plate and the first bearing plate are located on the same horizontal plane.
Further, the first extension plate and the second extension plate have the same size so that the first extension plate clings to the second bearing plate, and the second extension plate clings to the first bearing plate.
Further, the first support column is located below the first bearing plate, and the second support column is located below the second bearing plate.
Further, the first support column and the second support column are telescopic columns.
The utility model has the beneficial effects that:
the operation pedal of the detachable concrete pouring platform for preventing the damage of the reinforcing steel bar net piece is spliced with the connecting plate, so that the detachable concrete pouring platform is convenient to install and detach. Meanwhile, the detachable concrete pouring platform capable of preventing the damage of the reinforcing steel mesh can be erected along the route to be poured, construction staff is convenient to construct, a plurality of operation pedals are connected with one another, and stability is higher.
According to the detachable concrete pouring platform for preventing the damage of the reinforcing steel bar net, the first support column and the second support column are telescopic columns, so that concrete structures with different thicknesses can be used for the detachable concrete pouring platform for preventing the damage of the reinforcing steel bar net.
The detachable concrete pouring platform for preventing the damage of the reinforcing steel bar net sheet effectively solves the problems of deformation and damage of the reinforcing steel bar net sheet caused by the fact that constructors work on the reinforcing steel bar net sheet in the concrete pouring process.
Drawings
Fig. 1 is a schematic view showing the overall structure of a detachable concrete placement platform for preventing damage to a reinforcing mesh in embodiment 1;
fig. 2 is a schematic view showing the structure of an operation pedal of the detachable concrete placement platform for preventing damage to the reinforcing mesh in embodiment 1;
fig. 3 is a schematic structural view of a connection plate of a detachable concrete placement platform for preventing damage to a reinforcing mesh in embodiment 1.
In the figure: 1. operating the pedal; 11. a bearing plate I; 12. an extension board I; 2. a connecting plate; 21. a bearing plate II; 22. an extension plate II; 3. a plug hole; 4. a plug pin; 5. a first support column; 6. and a second support column.
Detailed Description
The technical solutions in the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model.
Embodiments of the removable concrete placement platform of the present utility model that prevents damage to the reinforcing mesh are shown in fig. 1-3.
Example 1
The detachable concrete pouring platform capable of preventing damage of the reinforcing steel bar meshes comprises a plurality of operation pedals 1 used for bearing constructors, wherein two adjacent operation pedals 1 are connected through a connecting plate 2, and the operation pedals 1 are spliced with the connecting plate 2. The operation pedal 1 is integrally formed, and the operation pedal 1 is a Z-shaped plate. The operating pedal 1 includes a bearing plate one 11 in the middle and an extension plate one 12 at the left and right ends of the bearing plate one 11. Three plug holes 3 are formed in each first extension plate 12, and the three plug holes 3 are distributed along the front-back direction of the first extension plate 12. The connecting plate 2 is connected with a bolt 4 matched with the plug hole 3, and the bolt 4 penetrates through the plug hole 3 to connect the connecting plate 2 with the first extension plate 12. The connecting plate 2 is integrally formed, and the connecting plate 2 is a Z-shaped plate. The connecting plate 2 comprises a second bearing plate 21 in the middle and a second extension plate 22 positioned at the left end and the right end of the second bearing plate 21. The bolt 4 is connected with the second extension plate 22. After the connecting plate 2 connects two adjacent operation pedals 1, the upper surfaces and the lower surfaces of the connecting plate 2 and the operation pedals 1 are positioned on the same horizontal plane. The first extension plate 12 is sized to correspond to the second extension plate 22 such that the first extension plate 12 is in close proximity to the second bearing plate 21 and the second extension plate 22 is in close proximity to the first bearing plate 11. The thickness of the first extension plate is half of the thickness of the first bearing plate, and the thickness of the second extension plate is half of the thickness of the second bearing plate, so that the first extension plate clings to the second extension plate.
Six first support columns 5 are connected to the lower end of the first bearing plate 11, and three second support columns 6 are connected to the lower end of the second bearing plate 21. The first support column 5 and the second support column 6 are telescopic columns so that the detachable concrete pouring platform capable of preventing the damage of the reinforcing steel meshes is suitable for concrete structures with different thicknesses.
Using method of detachable concrete pouring platform capable of preventing reinforcing steel bar meshes from being damaged
When a plurality of operation pedals are needed to be used, the operation pedals can be placed on the pouring route, two adjacent operation pedals are connected through the connecting plate, the operation pedals form the detachable concrete pouring platform capable of preventing the damage of the reinforcing steel mesh along the pouring route, and constructors can conveniently move along the detachable concrete pouring platform capable of preventing the damage of the reinforcing steel mesh so as to pour and vibrate concrete. The first support column and the second support column of the detachable concrete pouring platform for preventing the damage of the reinforcing steel bar net are placed on the substrate from the middle holes of the reinforcing steel bar net, so that the damage of the reinforcing steel bar net is avoided.
Finally, it should be noted that: in the description of the present utility model, it should be noted that the azimuth or positional relationship indicated by the terms "vertical", "upper", "lower", "horizontal", etc. are based on the azimuth or positional relationship shown in the drawings, and are merely for convenience of describing the present utility model and simplifying the description, and do not indicate or imply that the apparatus or element referred to must have a specific azimuth, be constructed and operated in a specific azimuth, and thus should not be construed as limiting the present utility model.
In the description of the present utility model, it should also be noted that, unless explicitly specified and limited otherwise, the terms "disposed," "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; can be directly connected or indirectly connected through an intermediate medium, and can be communication between two elements. The specific meaning of the above terms in the present utility model can be understood by those of ordinary skill in the art according to the specific circumstances.
Claims (9)
1. Can dismantle concrete placement platform that prevents reinforcing bar net piece damage, its characterized in that: the construction equipment comprises a plurality of operation pedals for bearing constructors, wherein two adjacent operation pedals are connected through a connecting plate, and the operation pedals are spliced with the connecting plate; the lower end of the operation pedal is connected with a first support column, and the lower end of the connecting plate is connected with a second support column.
2. The removable concrete placement platform for preventing damage to a reinforcing mesh of claim 1, wherein: the operation pedals are integrally formed, and the operation pedals are Z-shaped plates; the operation pedal comprises a bearing plate I at the middle part and extension plates I at the left end and the right end of the bearing plate I; the first extension plate is spliced with the connecting plate.
3. The removable concrete placement platform for preventing damage to a reinforcing mesh of claim 2, wherein: the first extension plate is provided with a plug hole, the connecting plate is provided with a plug pin matched with the plug hole, and the plug pin penetrates through the plug hole to connect the connecting plate with the first extension plate.
4. The removable concrete placement platform for preventing damage to a reinforcing mesh of claim 3, wherein: the plug holes are formed in a plurality of parts; the plurality of plug holes are distributed along the front-back direction of the extension plate.
5. The removable concrete placement platform for preventing damage to a reinforcing mesh of claim 3, wherein: the connecting plates are integrally formed, and the connecting plates are Z-shaped plates; the connecting plate comprises a second bearing plate in the middle and a second extension plate positioned at the left end and the right end of the second bearing plate; the bolt is connected with the second extending plate.
6. The removable concrete placement platform for preventing damage to a reinforcing mesh of claim 5, wherein: the upper surface and the lower surface of the bearing plate II and the bearing plate I are both positioned on the same horizontal plane.
7. The removable concrete placement platform for preventing damage to a reinforcing mesh of claim 5, wherein: the first extension plate and the second extension plate are consistent in size so that the first extension plate clings to the second bearing plate, and the second extension plate clings to the first bearing plate.
8. The removable concrete placement platform for preventing damage to a reinforcing mesh of claim 5, wherein: the first support column is located below the first bearing plate, and the second support column is located below the second bearing plate.
9. The removable concrete placement platform for preventing damage to a reinforcing mesh of claim 1, wherein: the first support column and the second support column are telescopic columns.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202321952985.9U CN220469344U (en) | 2023-07-24 | 2023-07-24 | Detachable concrete pouring platform capable of preventing reinforcing steel bar meshes from being damaged |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202321952985.9U CN220469344U (en) | 2023-07-24 | 2023-07-24 | Detachable concrete pouring platform capable of preventing reinforcing steel bar meshes from being damaged |
Publications (1)
Publication Number | Publication Date |
---|---|
CN220469344U true CN220469344U (en) | 2024-02-09 |
Family
ID=89781052
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202321952985.9U Active CN220469344U (en) | 2023-07-24 | 2023-07-24 | Detachable concrete pouring platform capable of preventing reinforcing steel bar meshes from being damaged |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN220469344U (en) |
-
2023
- 2023-07-24 CN CN202321952985.9U patent/CN220469344U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101243775B1 (en) | Apparatus of Constructing Bridge and Method of Constructing Bridge by Using the Same | |
CN212715972U (en) | Prefabricated bed-jig suitable for multiple specification pier stud reinforcing bar | |
CN107724671B (en) | Integral type sliding formwork system and construction method thereof | |
CN114517575A (en) | Formwork-attached assembling type double-layer integral hoisting elevator shaft construction method | |
CN220469344U (en) | Detachable concrete pouring platform capable of preventing reinforcing steel bar meshes from being damaged | |
CN212582721U (en) | Bearing platform of tower crane for vertical tower of top plate of foundation garage | |
CN211340840U (en) | Tower crane foundation of internal climbing tower crane | |
CN109989590B (en) | Auxiliary fixing device for mounting roof overlong steel beam and hoisting method of steel beam | |
CN111395192A (en) | Support for upper-layer member construction by using lower steel box girder bearing and construction method | |
JP3237751U (en) | Concrete placing platform | |
CN214272960U (en) | Precast concrete assembled structure and supporting structure for same | |
CN212561184U (en) | Support for upper layer member construction by using lower steel box girder bearing | |
CN113062229A (en) | Detachable stiff framework of high pier and construction method | |
CN112536910A (en) | Manufacturing method of prefabricated part | |
CN216007333U (en) | Assembled precast beam and post steel sheet connecting piece | |
CN110318460B (en) | Construction method of inverted-step-shaped special-shaped steel structure | |
CN218776842U (en) | Prefabricated beam storage bench | |
CN220100634U (en) | Template supporting device for synchronous construction of sandwich plate and upper structure plate thereof | |
CN216921330U (en) | Aluminum alloy template | |
CN221143058U (en) | Steel structural column and concrete beam slab connection structure | |
CN215052191U (en) | Detachable stiff framework of high pier | |
CN220908719U (en) | Steel construction frame pre-buried formula base | |
CN214939379U (en) | Construction tool for cast-in-situ beam of crossing provincial road support | |
CN117779822B (en) | Combined jacket manufacturing, assembling and supporting device and application method thereof | |
CN220059026U (en) | A can assemble, adjustable interim fixed stay device for steel construction hoist and mount |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |