CN220435630U - Hydropower pipeline pre-buried fixing device - Google Patents

Hydropower pipeline pre-buried fixing device Download PDF

Info

Publication number
CN220435630U
CN220435630U CN202322156608.0U CN202322156608U CN220435630U CN 220435630 U CN220435630 U CN 220435630U CN 202322156608 U CN202322156608 U CN 202322156608U CN 220435630 U CN220435630 U CN 220435630U
Authority
CN
China
Prior art keywords
hydropower
main frame
fixing device
seat
jack catch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322156608.0U
Other languages
Chinese (zh)
Inventor
吴昌军
成珉
张启峰
瞿晓青
张小翀
陈苏东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Xinhua Construction Group Co ltd
Nantong University
Original Assignee
Nantong Xinhua Construction Group Co ltd
Nantong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Xinhua Construction Group Co ltd, Nantong University filed Critical Nantong Xinhua Construction Group Co ltd
Priority to CN202322156608.0U priority Critical patent/CN220435630U/en
Application granted granted Critical
Publication of CN220435630U publication Critical patent/CN220435630U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The utility model relates to a pre-buried fixing device of hydropower line relates to hydropower line erection equipment technical field, and it includes the main frame, one side inner wall of main frame is provided with the butt seat, and the opposite side is provided with adjustment mechanism, adjustment mechanism is towards one side of butt seat is provided with the jack catch, and the hydropower line sets up between butt seat and jack catch, adjustment mechanism is used for realizing adjusting the position of jack catch; the water and electricity pipeline adjusting device has the beneficial effects that the distance between the clamping jaw and the abutting seat is adjusted through the adjusting mechanism, and when the water and electricity pipeline is thicker, the distance between the clamping jaw and the abutting seat is increased; when the hydropower line is thinner, shorten the distance between jack catch and the butt seat, jack catch and butt seat can realize the fixed hydropower line of different specification sizes of adaptation promptly, convenient operation is swift, is favorable to improving the efficiency of construction.

Description

Hydropower pipeline pre-buried fixing device
Technical Field
The application relates to the technical field of hydropower pipeline installation equipment, in particular to a hydropower pipeline embedded fixing device.
Background
In the construction site, the hydropower pipeline is often required to be pre-buried, and the conventional operation mode is direct pre-burying. This can't fixed position of pre-buried water and electricity pipeline that just causes, runs the position easily in concrete placement in-process, causes pre-buried inaccuracy, perhaps causes the concrete of pipeline centralized department to water and stamp incompact, all has great influence to structure and later stage water and electricity poling.
The related prior art discloses pre-buried positioner of water and electricity pipeline, and it includes at least one mounting panel and a plurality of sleeve pipe, and the mounting panel is the L shaped plate, and the mounting panel is tied up on the wall body reinforcing bar, and the roof inner wall of mounting panel is connected with a plurality of the sleeve pipe to shutoff sleeve pipe's one end, the sheathed tube other end is used for inserting the water and electricity pipeline. When the hydraulic pipeline fixing device is used, the hydraulic pipeline is fixed by the hydraulic pipeline trolley society and the sleeve.
Aiming at the related technology, when the fixation of the hydropower pipeline is realized through the method, the sleeve is sleeved with the hydropower pipeline to realize fixation, so that the sleeve is required to be matched with the hydropower pipeline, in the practical process, the hydropower pipeline has various different specifications, and the sleeve for fixing the hydropower pipeline also needs to be used with various different specifications, so that the operation is complicated and the efficiency is low.
Disclosure of Invention
In order to adapt to hydropower pipelines of various different specifications and sizes, improve the efficiency of construction, this application provides a pre-buried fixing device of hydropower pipeline.
The application provides a pre-buried fixing device of water and electricity pipeline adopts following technical scheme:
the utility model provides a pre-buried fixing device of water and electricity pipeline, includes the main frame, one side inner wall of main frame is provided with the butt seat, and the opposite side is provided with adjustment mechanism, adjustment mechanism orientation one side of butt seat is provided with the jack catch, and the water and electricity pipeline sets up between butt seat and jack catch, adjustment mechanism is used for realizing adjusting the position of jack catch.
By adopting the technical scheme, the distance between the claw and the abutting seat is adjusted through the adjusting mechanism, and when the hydropower pipeline is thicker, the distance between the claw and the abutting seat is increased; when the hydropower line is thinner, shorten the distance between jack catch and the butt seat, jack catch and butt seat can realize the fixed hydropower line of different specification sizes of adaptation promptly, convenient operation is swift, is favorable to improving the efficiency of construction.
Optionally, adjustment mechanism includes adjusting bolt and connecting block, adjusting bolt threaded connection in the main frame, the connecting block rotate connect in adjusting bolt orientation one side of butt seat, the jack catch connect in the connecting block deviates from adjusting bolt's one side.
Through adopting above-mentioned technical scheme, rotatory adjusting bolt can realize driving the connecting block and remove to this position adjustment who realizes the connecting block, the connecting block rotates with adjusting bolt's tip to be connected, is convenient for realize that the connecting block aligns the water and electricity pipeline, has reduced the phenomenon of connecting block and water and electricity pipeline discomfort.
Optionally, the adjusting bolt is connected with a positioning nut in a threaded manner, and the positioning nut is located between the main frame and the connecting block.
Through adopting above-mentioned technical scheme, positioning nut can realize rotatory and with main frame butt after adjusting bolt adjusts in place to this realizes adjusting bolt's fixed in position, has improved the stability after the connecting block is adjusted in place, has reduced the phenomenon that hydropower pipeline breaks away from between connecting block and the butt seat in the use.
Optionally, the butt seat with the jack catch all is provided with the slipmat towards one side of water and electricity pipeline, the slipmat towards one side of water and electricity pipeline all is provided with the antiskid sand grip.
Through adopting above-mentioned technical scheme, the frictional force between butt seat and jack catch and the water and electricity pipeline that is fixed has been increased in the setting of slipmat and slipway, has further reduced the phenomenon that water and electricity pipeline takes place to loosen after fixed, has improved the fixed stability of water and electricity pipeline.
Optionally, an insert plate is arranged on the outer side wall of the main frame.
Through adopting above-mentioned technical scheme, the setting of picture peg has improved the structural strength of main frame on the one hand, and on the other hand has strengthened when main frame buries with in the building, with the joint strength of building body, has reduced the main frame and has taken place to rock the phenomenon of off normal in the use.
Optionally, the side wall of the plugboard is provided with a reinforcing rib plate, and the reinforcing rib plate is connected with the outer side wall of the main frame.
Through adopting above-mentioned technical scheme, the setting of deep floor makes the picture peg, deep floor and main frame between form triangular structure, has improved the structural strength of picture peg, has reduced the picture peg and has taken place bending deformation's phenomenon in the use, has improved the stability in use of picture peg.
Optionally, the main frame includes upper junction plate and lower connecting plate, the upper junction plate orientation one side of lower connecting plate is provided with the inserted block, be provided with on the lower connecting plate and supply the slot that the inserted block was inserted.
Through adopting above-mentioned technical scheme, the main frame is formed by upper junction plate and lower connecting plate combination, and upper junction plate and lower connecting plate pass through inserted block and slot interconnect, convenient operation is swift, the installation of being convenient for.
Optionally, the side wall of the slot is connected with a fixing bolt in a threaded manner, and the fixing bolt penetrates through the insert block.
Through adopting above-mentioned technical scheme, fixing bolt's setting can realize improving the joint strength between inserted block and the slot, reduces to the phenomenon that takes place the pine takes place between upper connecting plate and the lower connecting plate in the use, has improved the fixed stability of water and electricity pipeline.
In summary, the present application includes at least one of the following beneficial technical effects:
1. position adjustment of clamping jaw is realized through adjustment mechanism to this distance adjustment between realization clamping jaw and the butt seat, and the water and electricity pipeline is pressed from both sides tightly by clamping jaw and butt seat, realizes the water and electricity pipeline of the different thickness specifications of adaptation through the distance between change clamping jaw and the butt seat, when realizing fixed water and electricity pipeline, convenient operation is swift.
2. Through set up the slipmat on jack catch and butt seat so that be difficult for appearing slipping the phenomenon that loosens when jack catch and butt seat clamp water and electricity pipeline, stability when having improved water and electricity pipeline and fixed.
3. The arrangement of the inserting plates and the reinforcing rib plates improves the structural strength of the main frame, improves the stability of embedding the main frame and the building, and reduces the phenomenon of loosening and deviation after embedding the main frame.
Drawings
Fig. 1 is an exploded schematic view of the overall structure of the hydropower line pre-buried fixing device according to the embodiment of the application.
Reference numerals illustrate: 1. a main frame; 101. an upper connecting plate; 102. a lower connecting plate; 2. a butt joint seat; 3. an adjusting mechanism; 301. an adjusting bolt; 302. a connecting block; 4. a claw; 5. positioning a nut; 6. an anti-slip pad; 7. inserting plate; 8. reinforcing rib plates; 9. inserting blocks; 10. a slot; 11. and (5) fixing bolts.
Detailed Description
The present application is described in further detail below in conjunction with fig. 1.
The embodiment of the application discloses a pre-buried fixing device of water and electricity pipeline. Referring to fig. 1, the hydropower line pre-buried fixing device comprises a main frame 1, the main frame 1 comprises an upper connecting plate 101 and a lower connecting plate 102, an inserting block 9 is integrally formed on one side, facing the lower connecting plate 102, of the upper connecting plate 101, an inserting groove 10 for inserting the inserting block 9 is formed in the lower connecting plate 102, interference fit is formed between the inserting block 9 and the inserting groove 10, a fixing bolt 11 is connected with the side wall of the inserting groove 10 in a threaded manner, when the inserting block 9 is inserted into the inserting groove 10, the fixing bolt 11 penetrates through the inserting block 9, inserting plates 7 are welded on the outer side walls of the upper connecting plate 101 and the lower connecting plate 102, reinforcing rib plates 8 at the position of the upper connecting plate 101 are welded with the upper connecting plate 101, and reinforcing rib plates 8 at the position of the lower connecting plate 102 are welded with the lower connecting plate 102.
Referring to fig. 1, the inner side wall of the lower connecting plate 102 is welded with a supporting seat 2, an adjusting mechanism 3 is arranged on the upper connecting plate 101, the adjusting mechanism 3 comprises an adjusting bolt 301 and a connecting block 302, the adjusting bolt 301 is in threaded connection with the upper connecting plate 101, the end part of the adjusting bolt 301 faces the supporting seat 2, the connecting block 302 is in rotary connection with the end part of the adjusting bolt 301, the connecting block 302 faces the supporting seat 2, a positioning nut 5 is in threaded connection with the adjusting bolt 301, the positioning nut 5 is located between the upper connecting plate 101 and the connecting block 302, a claw 4 is welded on one side of the connecting block, facing the supporting block, of the connecting block 302, the claw 4 is used for mutually matching with the supporting seat 2 to limit a hydropower pipeline, one side, used for clamping the hydropower pipeline, of the claw 4 and the supporting seat 2 are both adhered with a slipmat 6, the material of the slipmat 6 in this embodiment can be rubber, and one side, facing the hydropower pipeline, of the slipmat 6 is integrally formed with a slipmat.
The implementation principle of the hydropower pipeline embedded fixing device in the embodiment of the application is as follows: in practical use, the lower connecting plate 102 is placed at a designated position, the hydropower pipeline to be fixed is placed on the abutting seat 2, then the upper connecting plate 101 is connected to the lower connecting plate 102 through the inserting block 9 and the inserting groove 10, the fixing bolt 11 is rotatably inserted through the inserting block 9, then the adjusting bolt 301 is rotated to enable the claw 4 to gradually approach and abut against the hydropower pipeline, the claw 4 and the abutting seat 2 are ensured to clamp the fixed support, the positioning nut 5 is rotated to enable the positioning nut 5 to abut against the upper connecting plate 101 to achieve the position fixing of the adjusting bolt 301, the structural strength of the main frame 1 is improved due to the arrangement of the inserting plate 7 and the reinforcing rib plate 8, the connection strength between the main frame 1 and a building can be improved, the hydropower pipeline with various different thickness and size specifications can be adaptively fixed, and the operation is convenient and fast, and the construction speed is improved.
The foregoing are all preferred embodiments of the present application, and are not intended to limit the scope of the present application in any way, therefore: all equivalent changes in structure, shape and principle of this application should be covered in the protection scope of this application.

Claims (8)

1. An embedded fixing device of water and electricity pipeline, its characterized in that: including main frame (1), one side inner wall of main frame (1) is provided with butt seat (2), and the opposite side is provided with adjustment mechanism (3), adjustment mechanism (3) orientation one side of butt seat (2) is provided with jack catch (4), and the hydropower pipeline sets up between butt seat (2) and jack catch (4), adjustment mechanism (3) are used for realizing adjusting the position of jack catch (4).
2. The hydropower line pre-buried fixing device according to claim 1, wherein: the adjusting mechanism (3) comprises an adjusting bolt (301) and a connecting block (302), the adjusting bolt (301) is in threaded connection with the main frame (1), the connecting block (302) is rotationally connected to one side of the adjusting bolt (301) facing the abutting seat (2), and the clamping jaw (4) is connected to one side of the connecting block facing away from the adjusting bolt (301).
3. The hydropower line pre-buried fixing device according to claim 2, wherein: the adjusting bolt (301) is connected with a positioning nut (5) in a threaded mode, and the positioning nut (5) is located between the main frame (1) and the connecting block (302).
4. The hydropower line pre-buried fixing device according to claim 1, wherein: the anti-slip mat (6) is arranged on one side, facing the hydropower line, of the abutting seat (2) and the clamping jaw (4), and the anti-slip mat (6) is provided with an anti-slip protruding strip on one side, facing the hydropower line, of the anti-slip mat.
5. The hydropower line pre-buried fixing device according to claim 1, wherein: the outer side wall of the main frame (1) is provided with a plugboard (7).
6. The hydropower line pre-buried fixing device according to claim 5, wherein: the side wall of the inserting plate (7) is provided with a reinforcing rib plate (8), and the reinforcing rib plate (8) is connected with the outer side wall of the main frame (1).
7. The hydropower line pre-buried fixing device according to claim 1, wherein: the main frame (1) comprises an upper connecting plate (101) and a lower connecting plate (102), wherein an inserting block (9) is arranged on one side, facing the lower connecting plate (102), of the upper connecting plate (101), and a slot (10) for inserting the inserting block (9) is arranged on the lower connecting plate (102).
8. The hydropower line pre-buried fixing device according to claim 7, wherein: the side wall of the slot (10) is connected with a fixing bolt (11) in a threaded mode, and the fixing bolt (11) penetrates through the insert block (9).
CN202322156608.0U 2023-08-10 2023-08-10 Hydropower pipeline pre-buried fixing device Active CN220435630U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322156608.0U CN220435630U (en) 2023-08-10 2023-08-10 Hydropower pipeline pre-buried fixing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322156608.0U CN220435630U (en) 2023-08-10 2023-08-10 Hydropower pipeline pre-buried fixing device

Publications (1)

Publication Number Publication Date
CN220435630U true CN220435630U (en) 2024-02-02

Family

ID=89689949

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322156608.0U Active CN220435630U (en) 2023-08-10 2023-08-10 Hydropower pipeline pre-buried fixing device

Country Status (1)

Country Link
CN (1) CN220435630U (en)

Similar Documents

Publication Publication Date Title
CN220435630U (en) Hydropower pipeline pre-buried fixing device
CN204913698U (en) A fixture attachment for installing socket joint formula nodular cast -iron pipe
CN213745217U (en) Pipeline socket installation tool
JP2011012742A (en) Method for laying pipe body
JP2019155659A (en) Drilling machine
CN210849937U (en) Water and electricity pipeline strutting arrangement
CN210976098U (en) Underground pipe gallery pre-buried support
CN2312393Y (en) Multi-functional apparatus for jointing pipeline
CN216344296U (en) Aligning device for nodular cast iron pipe fitting
CN214889361U (en) Be used for drainage pipe hoist and mount construction equipment
CN213979221U (en) Construction auxiliary assembly based on sewage pipeline
CN213809206U (en) Convenient fixed clamp of pipeline construction usefulness
CN220467285U (en) Portable lifting appliance suitable for reinforced concrete steel bellmouth pipe
CN216576327U (en) Clamping device for welding construction steel bars
CN216938152U (en) Bend-straight adjusting device for embedded steel bar
CN214644842U (en) Device for positioning and grooving building blocks
CN216975994U (en) Pipeline rack for municipal construction
CN212376296U (en) Stirrup spanner tool
JPH0630222U (en) Reaction force stand for steel pipe pile punching machine
CN217726742U (en) Steel pipe cold bending spanner
CN218460525U (en) Pipe bending device for pipe bending machine
CN218523130U (en) Pipe replacing mechanism of pipe pushing jack convenient to operate
CN216666672U (en) Municipal works auxiliary device
CN218437408U (en) Embedded pipeline positioning fixture with spherical nut
CN213622895U (en) Major diameter reinforced concrete pipe hoist

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant