CN220387359U - Pump pipe cleaning channel and sewage discharging device - Google Patents

Pump pipe cleaning channel and sewage discharging device Download PDF

Info

Publication number
CN220387359U
CN220387359U CN202321828631.3U CN202321828631U CN220387359U CN 220387359 U CN220387359 U CN 220387359U CN 202321828631 U CN202321828631 U CN 202321828631U CN 220387359 U CN220387359 U CN 220387359U
Authority
CN
China
Prior art keywords
pipe
building main
main body
pump line
pump
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321828631.3U
Other languages
Chinese (zh)
Inventor
文鹏
丁德成
宋韶宇
张林伟
符土金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Engineering Group Co Ltd
China Railway Construction Engineering Group South China Co Ltd
Original Assignee
China Railway Construction Engineering Group Co Ltd
China Railway Construction Engineering Group South China Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Engineering Group Co Ltd, China Railway Construction Engineering Group South China Co Ltd filed Critical China Railway Construction Engineering Group Co Ltd
Priority to CN202321828631.3U priority Critical patent/CN220387359U/en
Application granted granted Critical
Publication of CN220387359U publication Critical patent/CN220387359U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model relates to a pump pipe cleaning channel and a sewage disposal device, which comprises a building main body, wherein a material distributor is arranged at the top of the building main body, a pump pipe is arranged in the building main body, the pump pipe is fixedly arranged at the outer side of the material distributor, a guide pipe is arranged in the building main body and positioned at one side of the pump pipe, one end of the pump pipe extends to the inside of the guide pipe, and a sewage disposal mechanism is arranged in the building main body. The utility model has the beneficial effects that the pump washing pipe water and the waste are flushed into the three-stage sedimentation sewage tank through the guide pipe, finally discharged to the outdoor drainage ditch through the three-stage sedimentation sewage tank to enter the municipal water inlet, and the settled sand and the waste are recycled at fixed time, so that the utility model can be used for manufacturing precast concrete blocks, pipeline hanging holes and the like, further can play a secondary use role on construction waste resources, basically eliminates the cross flow of cleaning sewage and the discharge of the waste of the concrete pump pipe, realizes orderly management, and brings benefits to civilized construction in the project main structure construction stage.

Description

Pump pipe cleaning channel and sewage discharging device
Technical Field
The utility model relates to the technical field of engineering construction, in particular to a pump pipe cleaning channel and a sewage discharging device.
Background
In the construction stage process of the main structure, the concrete pump pipe cleaning procedure is easy to neglect to adopt such methods as elevator shaft scattering and the like, and sewage cross flow and stones fly transversely in the pump pipe cleaning process, so that the construction management of the construction site image and civilization is extremely unfavorable, decoration penetration and elevator shaft cleaning work in the construction stage of the main structure are affected, and the construction period progress is correspondingly affected.
The prior main structure has the following two defects in the construction process;
1. when the existing concrete pump pipe is used for pouring a building, the sewage can be directly discharged for convenience, so that the environmental pollution is increased;
2. the existing pump washing pipe usually generates more sand and stone waste after being washed in the operation process, and the existing construction cannot carry out secondary utilization on the sand and stone waste, so that the waste of resources is caused.
Disclosure of Invention
In view of the foregoing problems of the prior art, a primary object of the present utility model is to provide a pump pipe cleaning channel and a sewage draining device.
The technical scheme of the utility model is as follows: the utility model provides a pump line washs passageway and waste fitting discharging, includes the building main part, the top of building main part is provided with the cloth machine, the inside of building main part is provided with the pump line, pump line fixed mounting is in the outside of cloth machine, the inside of building main part just is located one side of pump line and is provided with the pipe, the one end of pump line extends to the inside of pipe, the inside of building main part is provided with waste fitting discharging mechanism, waste fitting discharging mechanism includes tertiary sedimentation effluent water sump and water inlet, the inside of building main part is provided with tertiary sedimentation effluent water sump, the inside fixedly connected with water inlet of tertiary sedimentation effluent water sump, the one end that the pump line was kept away from to the pipe extends to the inside of water inlet.
As a preferred implementation mode, the blowdown mechanism still includes first baffle, second preformed hole, second baffle, first preformed hole and wash port, the inside fixedly connected with first baffle of tertiary sedimentation effluent water sump, the inside of first baffle is provided with the second preformed hole, the inside fixedly connected with second baffle of tertiary sedimentation effluent water sump, the inside of second baffle is provided with first preformed hole, the inside of tertiary sedimentation effluent water sump is provided with the wash port.
As a preferred implementation mode, the inside equidistance of building main part is provided with the elevator shaft, the equal fixedly connected with steel pipe in both sides of elevator shaft inner wall, the pipe sets up the intersection between two steel pipes, all be provided with pipe staple wall bolt around the pipe, the pipe passes through pipe staple wall bolt fixed mounting in the intersection of two steel pipes.
As a preferred embodiment, the interior of the building body is provided with developing rooms at equal intervals, and the interior of the building body is provided with elevator halls at equal intervals on one side of the elevator shaft.
As a preferable implementation mode, stairs are arranged in the building body at equal intervals, and a punching net cover plate is arranged at the top of the three-stage sedimentation sewage tank.
As a preferred embodiment, walkways are arranged inside the building main body and at equal intervals on one side of the stairs.
Compared with the prior art, the utility model has the advantages and positive effects that,
according to the utility model, the pump washing pipe water and the waste are flushed into the three-stage sedimentation sewage tank through the guide pipe, and finally discharged to the outdoor drainage ditch to enter the municipal water inlet through the three-stage sedimentation sewage tank, and the settled sand, the waste and the like are recycled at fixed time, so that the method can be used for manufacturing precast concrete blocks, pipeline hanging holes and the like, further can play a secondary use role on construction waste resources, basically eliminates the cross flow of sewage and the discharge of the waste from the concrete pump pipe, realizes orderly management, and brings benefits to civilized construction in the project main structure construction stage.
Drawings
FIG. 1 is a cross-sectional view of a pump tube cleaning channel and drain assembly according to the present utility model;
FIG. 2 is a schematic diagram of a conduit and elevator shaft structure providing a pump line cleaning channel and a drain assembly in accordance with the present utility model;
FIG. 3 is a top view of a three-stage sedimentation wastewater tank provided with a pump pipe cleaning passage and a sewage disposal device according to the present utility model;
fig. 4 is a front cross-sectional view of a three-stage sedimentation wastewater tank provided with a pump pipe cleaning passage and a sewage disposal device according to the present utility model.
Legend description: 1. a building main body; 2. a pump tube; 3. a cloth machine; 4. a conduit; 5. developing a room; 6. an elevator shaft; 7. an elevator hall; 8. stairs; 9. a walkway; 10. a third-stage sedimentation sewage tank; 11. a drain hole; 12. a steel pipe; 13. pipe clip wall bolts; 14. punching a net cover plate; 15. a first preformed hole; 16. a second preformed hole; 17. a water inlet; 18. a first separator; 19. and a second separator.
Detailed Description
For the purpose of making the objects, technical solutions and advantages of the embodiments of the present utility model more apparent, the technical solutions of the embodiments of the present utility model will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present utility model, and it is apparent that the described embodiments are some embodiments of the present utility model, but not all embodiments of the present utility model. The components of the embodiments of the present utility model generally described and illustrated in the figures herein may be arranged and designed in a wide variety of different configurations. Thus, the following detailed description of the embodiments of the utility model, as presented in the figures, is not intended to limit the scope of the utility model, as claimed, but is merely representative of selected embodiments of the utility model. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
The utility model will be further described with reference to the drawings and the specific embodiments
Example 1
As shown in fig. 1, 2, 3 and 4, the present utility model provides a technical solution: including building main part 1, the top of building main part 1 is provided with cloth machine 3, the inside of building main part 1 is provided with pump line 2, pump line 2 fixed mounting is in the outside of cloth machine 3, the inside of building main part 1 and be located one side of pump line 2 are provided with pipe 4, the one end of pump line 2 extends to the inside of pipe 4, the inside of building main part 1 is provided with sewage disposal mechanism, sewage disposal mechanism includes tertiary sedimentation effluent water sump 10 and water inlet 17, the inside of building main part 1 is provided with tertiary sedimentation effluent water sump 10, the inside fixedly connected with water inlet 17 of tertiary sedimentation effluent water sump 10, the one end that pump line 2 was kept away from to the inside of water inlet 17 is arranged in pipe 4, through the setting up of pump line 2, can wash the residual grit aggregate that the construction was left in pipe 4 and discharge, and be provided with tertiary sedimentation effluent water sump 10 in first floor elevator hall 7, wash pipe 2 water and waste material into tertiary sedimentation effluent water sump 10 through pipe 4 finally discharge to outdoor sewer inlet municipal water inlet, and subsidence waste water drain, and waste material can be used for making and using the concrete pump and the side-by side flow and water inlet 17, the construction waste material is carried out the construction stage and the concrete pump is put forward and the construction is guaranteed to the basic construction and waste material is put forward, the basic construction is put forward, and waste material is well and well removed and has been washed and has been put forward to the construction stage.
Wherein, blowdown mechanism still includes first baffle 18, second preformed hole 16, second baffle 19, first preformed hole 15 and wash port 11, tertiary sedimentation effluent water sump 10's inside fixedly connected with first baffle 18, first baffle 18's inside is provided with second preformed hole 16, tertiary sedimentation effluent water sump 10's inside fixedly connected with second baffle 19, second baffle 19's inside is provided with first preformed hole 15, tertiary sedimentation effluent water sump 10's inside is provided with wash port 11, through setting up first baffle 18 and second baffle 19 in tertiary sedimentation effluent water sump 10, can divide into three parts with tertiary sedimentation effluent water sump 10, and then can carry out the multiple precipitation to sewage, the clear water has basically been accomplished and discharged, environmental pollution has been reduced, and sewage after will precipitating is discharged through wash port 11.
Wherein, the inside equidistance of building main part 1 is provided with elevator shaft 6, the equal fixedly connected with steel pipe 12 in both sides of elevator shaft 6 inner wall, pipe 4 sets up the intersection between two steel pipes 12, pipe 4 all is provided with pipe clamp wall bolt 13 all around, pipe 4 passes through pipe clamp wall bolt 13 fixed mounting in the intersection of two steel pipes 12, cross through two steel pipes 12 to can be with the stable fixed mounting of pipe 4 in elevator shaft 6 bight department through pipe clamp wall bolt 13, and fixed form is fixed layer by layer, so that wash the waste material in the pipe 4.
Wherein, inside equidistance of building main part 1 is provided with research and development and uses room 5, and the inside of building main part 1 just is located the one side equidistance of elevator shaft 6 and is provided with elevator hall 7, through elevator hall 7's setting to bear the weight of the resident.
Wherein, inside equidistance of building main part 1 is provided with stair 8, and the top of tertiary sedimentation effluent water sump 10 is provided with net apron 14 that punches a hole, through the setting of net apron 14 that punches a hole to clear up the impurity in the tertiary sedimentation effluent water sump 10.
Wherein, inside of building main part 1 and be located the one side equidistance of stair 8 and be provided with pavement 9, through the setting of pavement 9 to the resident personnel uses in the convenience.
Working principle:
as shown in fig. 1, fig. 2, fig. 3 and fig. 4, firstly, through the arrangement of the pump pipe 2, the residual sand aggregates left in construction in the guide pipe 4 can be washed and discharged, and the three-level sedimentation sewage tank 10 is arranged in the first-layer elevator hall 7, the pump washing pipe 2 water and waste materials are flushed into the three-level sedimentation sewage tank 10 through the guide pipe 4, the three-level sedimentation sewage tank 10 is finally discharged to an outdoor drainage ditch to enter a municipal water inlet, and the residual sand waste materials are recycled at regular time, so that the method can be used for manufacturing prefabricated concrete blocks, pipeline hanging holes and the like, further, the secondary utilization effect on construction waste materials resources can be achieved, the cross flow of sewage cleaning of the concrete pump pipe 2 and the discharge of waste materials are basically stopped, the orderly management is achieved, and the civilized construction in the construction stage of a project main structure is beneficial, and through the arrangement of the first partition 18 and the second partition 19 in the three-level sedimentation sewage tank 10, the sewage can be divided into three parts, the sewage can be subjected to multiple sedimentation effect on sewage, the discharge is basically achieved, the environmental pollution is reduced, and the sewage is discharged after being uniformly discharged through the drainage hole 11.
Finally, it should be noted that: the embodiments described above are only for illustrating the technical solution of the present utility model, and are not limiting; although the utility model has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art that: the technical scheme described in the foregoing embodiments can be modified or some or all of the technical features thereof can be replaced with equivalents; such modifications and substitutions do not depart from the spirit of the utility model.

Claims (6)

1. The utility model provides a pump line washs passageway and waste fitting discharging, includes building main part (1), its characterized in that: the utility model discloses a sewage treatment device for the sewage treatment of the building, including building main body (1), the top of building main body (1) is provided with cloth machine (3), the inside of building main body (1) is provided with pump line (2), pump line (2) fixed mounting is in the outside of cloth machine (3), the inside of building main body (1) just is located one side of pump line (2) and is provided with pipe (4), the one end of pump line (2) extends to the inside of pipe (4), the inside of building main body (1) is provided with blowdown mechanism, blowdown mechanism includes tertiary sedimentation effluent water sump (10) and water inlet (17), the inside of building main body (1) is provided with tertiary sedimentation effluent water sump (10), the inside fixedly connected with water inlet (17) of tertiary sedimentation effluent water sump (10), the inside of water inlet (17) is kept away from to the one end extension of pump line (2).
2. The pump line cleaning tunnel and drain according to claim 1, wherein: the sewage disposal mechanism further comprises a first partition plate (18), a second preformed hole (16), a second partition plate (19), a first preformed hole (15) and a drain hole (11), the first partition plate (18) is fixedly connected to the inside of the three-stage sedimentation sewage tank (10), the second preformed hole (16) is formed in the inside of the first partition plate (18), the second partition plate (19) is fixedly connected to the inside of the three-stage sedimentation sewage tank (10), the first preformed hole (15) is formed in the inside of the second partition plate (19), and the drain hole (11) is formed in the inside of the three-stage sedimentation sewage tank (10).
3. The pump line cleaning tunnel and drain according to claim 1, wherein: the inside equidistance of building main part (1) is provided with elevator shaft (6), the equal fixedly connected with steel pipe (12) in both sides of elevator shaft (6) inner wall, pipe (4) set up the intersection between two steel pipes (12), all be provided with pipe staple wall bolt (13) around pipe (4), pipe (4) pass through pipe staple wall bolt (13) fixed mounting in the intersection of two steel pipes (12).
4. A pump line cleaning tunnel and drain according to claim 3, wherein: the inside equidistance of building main part (1) is provided with research and development room (5), the inside of building main part (1) just is located one side equidistance of elevator shaft (6) and is provided with elevator hall (7).
5. The pump line cleaning tunnel and drain according to claim 1, wherein: stairs (8) are arranged in the building main body (1) at equal intervals, and a punching net cover plate (14) is arranged at the top of the three-stage sedimentation sewage tank (10).
6. The pump line cleaning tunnel and drain according to claim 5, wherein: the inside of building main part (1) just is located one side equidistance of stair (8) and is provided with pavement (9).
CN202321828631.3U 2023-07-12 2023-07-12 Pump pipe cleaning channel and sewage discharging device Active CN220387359U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321828631.3U CN220387359U (en) 2023-07-12 2023-07-12 Pump pipe cleaning channel and sewage discharging device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321828631.3U CN220387359U (en) 2023-07-12 2023-07-12 Pump pipe cleaning channel and sewage discharging device

Publications (1)

Publication Number Publication Date
CN220387359U true CN220387359U (en) 2024-01-26

Family

ID=89597259

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321828631.3U Active CN220387359U (en) 2023-07-12 2023-07-12 Pump pipe cleaning channel and sewage discharging device

Country Status (1)

Country Link
CN (1) CN220387359U (en)

Similar Documents

Publication Publication Date Title
CN201245519Y (en) Sewage purification processing and recycling system for shield construction
CN103224298A (en) Construction site sewage precipitation purification treatment and recovery utilization method
CN214833159U (en) Anti-blocking device for water supply and drainage based on building
CN208072577U (en) Construction site rainwater recycle utilizes system
CN220387359U (en) Pump pipe cleaning channel and sewage discharging device
CN207277487U (en) Water Sproading utilization system for construction site
CN108625461A (en) A kind of shutoff type shunting well on combined sewerage system
CN104328836B (en) A kind of environment-friendly type prefabricated pair of case deep hole type catch pit and construction method thereof
CN111167214A (en) Energy-saving environment-friendly assembled vehicle desilting and purifying circulation system for construction site
CN216240796U (en) Tunnel construction structure of shunting of decontaminating
CN201644490U (en) Concrete placing waste treatment and recovery system
CN108457340A (en) High-building construction washes pump water discharge recycling system
CN206477382U (en) Rainwater recycle comprehensively utilizes structure
CN109293061A (en) A kind of Discussion about Unconventional Water Resources reuse method for construction site
CN215291501U (en) Novel high-rise building waste treatment system
CN210002198U (en) construction site water collection comprehensive utilization system
CN210133091U (en) Combined automatic car washing device capable of recycling water
CN112609528A (en) Municipal road structure and construction method thereof
CN208545784U (en) A kind of irrigation canals and ditches sewage disposal apparatus
CN111762907A (en) Construction sewage purification treatment recycling system and use method
CN202157406U (en) Washing table of engineering truck for job site
CN105148607A (en) Tunnel construction water recycling system
CN217041683U (en) Concrete pump pipe washes waste water treatment system of recycling
CN114109395B (en) Tunnel dirt-cleaning and flow-dividing construction method and structure
CN216546110U (en) Vehicle flushing system convenient for construction area access and exit inner side arrangement

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant