CN220247339U - Novel steel bar truss floor carrier plate free of form removal and construction structure thereof - Google Patents
Novel steel bar truss floor carrier plate free of form removal and construction structure thereof Download PDFInfo
- Publication number
- CN220247339U CN220247339U CN202321442774.0U CN202321442774U CN220247339U CN 220247339 U CN220247339 U CN 220247339U CN 202321442774 U CN202321442774 U CN 202321442774U CN 220247339 U CN220247339 U CN 220247339U
- Authority
- CN
- China
- Prior art keywords
- steel
- bars
- steel bars
- bottom die
- steel bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
Description
技术领域Technical field
本实用新型属于建筑用楼承板施工技术领域,具体涉及一种免拆模新型钢筋桁架楼承板及其施工结构。The utility model belongs to the technical field of building floor decking construction, and specifically relates to a new formwork-free steel truss floor decking and its construction structure.
背景技术Background technique
钢结构楼房建筑不断发展,传统现场浇板的施工方法很难跟上建筑主体采用钢结构的施工速度,从而影响了总体的施工进度。现场浇板的施工需要搭建模板以及脚手架等辅助设施,导致施工流程总体脱节。Steel structure building construction continues to develop, and the traditional construction method of cast-in-place slabs is difficult to keep up with the construction speed of steel structures for the main body of the building, thus affecting the overall construction progress. The construction of cast-on-site slabs requires the construction of formwork, scaffolding and other auxiliary facilities, resulting in an overall disjointed construction process.
实用新型内容Utility model content
本实用新型的目的在于:本实用新型提供了一种免拆模新型钢筋桁架楼承板及其施工结构,解决了传统现场浇板的施工方法施工效率低的问题。The purpose of this utility model is: this utility model provides a new type of steel truss floor decking and its construction structure that does not require removal of formwork, and solves the problem of low construction efficiency of the traditional on-site cast slab construction method.
本实用新型中桁架楼承板底部镀锌钢板作为模板使用,该楼承板可省去支模、拆模的工序与费用,美观耐用,并且可减少现场钢筋绑扎工作量约70%,能大幅提高施工效率,降低施工成本,此外,钢筋排列均匀,上下两层钢筋间距及混凝土保护层厚度能充分得到保证,为提高楼板施工质量创造了有利条件。The galvanized steel plate at the bottom of the truss floor deck of this utility model is used as a formwork. The floor deck can save the process and cost of formwork support and removal, is beautiful and durable, and can reduce the workload of on-site steel bar binding by about 70%, and can significantly Improve construction efficiency and reduce construction costs. In addition, the steel bars are evenly arranged, the spacing between the upper and lower steel bars and the thickness of the concrete protective layer can be fully guaranteed, creating favorable conditions for improving the quality of floor slab construction.
本实用新型目的通过下述技术方案来实现:The purpose of this utility model is achieved through the following technical solutions:
一种免拆模新型钢筋桁架楼承板,包括底模钢板,底模钢板上设有若干组沿横向并间隔布置的腹杆钢筋,每组腹杆钢筋包括呈八字形对称布置的两个,每组的两个腹杆钢筋的上部之间连接有沿横向布置的上弦钢筋,每组的两个腹杆钢筋的下部均连接有沿横向布置的下弦钢筋。A new formwork-free steel truss floor bearing plate includes a bottom formwork steel plate. The bottom formwork steel plate is provided with several groups of web steel bars arranged transversely and at intervals. Each group of web bar steel bars includes two symmetrically arranged in a figure-eight shape. The upper parts of the two web bar reinforcements in each group are connected with upper chord steel bars arranged transversely, and the lower parts of the two web bar reinforcements in each group are connected with lower chord steel bars arranged transversely.
进一步的,所述的腹杆钢筋包括交替设置的立面三角段和水平U形段,立面三角段的上端角与上弦钢筋连接,立面三角段的下两角与下弦钢筋连接,水平U形段与底模钢板连接。Further, the web steel bars include alternating facade triangular sections and horizontal U-shaped sections. The upper end corners of the facade triangular sections are connected to the upper chord steel bars. The lower two corners of the facade triangular sections are connected to the lower chord steel bars. The horizontal U-shaped sections are connected alternately. The shape section is connected to the bottom formwork steel plate.
进一步的,所述的底模钢板为镀锌钢板。Further, the bottom mold steel plate is a galvanized steel plate.
进一步的,还包括位于上弦钢筋、下弦钢筋端部的端部支座,端部支座包括相互连接的支座竖向钢筋和支座水平钢筋,支座竖向钢筋连接在上弦钢筋与底模钢板之间,支座水平钢筋连接在两个下弦钢筋之间。Further, it also includes end supports located at the ends of the upper and lower chord steel bars. The end supports include interconnected vertical steel bars of the supports and horizontal steel bars of the supports. The vertical steel bars of the supports are connected between the upper chord steel bars and the bottom formwork. Between the steel plates, the horizontal steel bars of the support are connected between the two lower chord steel bars.
进一步的,所述的底模钢板的一端设有扣合部甲,底模钢板的另一端设有与扣合部甲配合的扣合部乙。Further, one end of the bottom mold steel plate is provided with a buckling part A, and the other end of the bottom mold steel plate is provided with a buckling part B that cooperates with the buckling part A.
进一步的,所述的底模钢板上设有凸台部,凸台部与腹杆钢筋连接。Further, the bottom mold steel plate is provided with a boss portion, and the boss portion is connected to the web bar steel bar.
一种免拆模新型钢筋桁架楼承板的施工结构,包括上述的免拆模新型钢筋桁架楼承板,还包括纵向布置的梁模板,所述的梁模板连接在间隔相邻的两底模钢板之间,梁模板的上端与底模钢板连接,梁模板内设有伸至底模钢板上方的梁内钢筋,间隔相邻的两底模钢板上的上弦钢筋、下弦钢筋之间通过过渡钢筋连接,直接相邻的两底模钢板之间通过扣合连接。A construction structure for a new formwork-free steel truss floor deck, which includes the above-mentioned new type steel truss floor deck without demolition, and also includes a beam formwork arranged longitudinally, and the beam formwork is connected to two adjacent bottom formworks. Between the steel plates, the upper end of the beam formwork is connected to the bottom formwork steel plate. The beam formwork is equipped with steel bars in the beam that extend above the bottom formwork steel plate. Transition steel bars are used between the upper chord steel bars and the lower chord steel bars on the two adjacent bottom formwork steel plates. Connection, the two directly adjacent bottom formwork steel plates are connected through buckling.
进一步的,还包括支撑架,支撑架通过木方对梁模板的三个端面进行支撑,梁模板与上端的木方之间通过铁钉连接。Further, it also includes a support frame, which supports the three end faces of the beam formwork through wooden squares, and the beam formwork and the upper wooden squares are connected through iron nails.
进一步的,所述的底模钢板上设有与上弦钢筋同向布置的板面筋。Furthermore, the bottom formwork steel plate is provided with plate reinforcements arranged in the same direction as the upper chord steel bars.
进一步的,所述的间隔相邻的两底模钢板相对梁模板为反向布置,间隔相邻的两底模钢板上的上弦钢筋之间通过横向的上弦连接钢筋连接,间隔相邻的两底模钢板上的下弦钢筋之间通过横向的下弦连接钢筋连接,下弦钢筋之间连接有纵向的分布筋。Further, the two adjacent bottom formwork steel plates are arranged in opposite directions relative to the beam formwork. The upper chord steel bars on the two adjacent bottom formwork steel plates are connected by transverse upper chord connecting steel bars. The two adjacent bottom formwork steel plates are spaced apart. The lower chord steel bars on the formwork steel plate are connected by transverse lower chord connecting steel bars, and the lower chord steel bars are connected by longitudinal distributed bars.
进一步的,所述的间隔相邻的两底模钢板相对梁模板为反向布置,间隔相邻的两底模钢板上的上弦钢筋之间通过横向的支座负筋连接,间隔相邻的两底模钢板上的下弦钢筋之间通过横向的分布筋连接。Further, the two adjacent bottom formwork steel plates are arranged in opposite directions relative to the beam formwork, and the upper chord steel bars on the two adjacent bottom formwork steel plates are connected through transverse support negative reinforcements. The lower chord steel bars on the bottom formwork steel plate are connected by transverse distributed bars.
进一步的,所述的间隔相邻的两底模钢板中其中一个相对梁模板为正向布置、另一个相对梁模板为反向布置,间隔相邻的两底模钢板上的上弦钢筋之间通过横向的支座负筋连接,间隔相邻的两底模钢板上的下弦钢筋之间通过横向的分布筋连接。Further, among the two adjacent bottom formwork steel plates, one of the opposite beam formworks is arranged in a forward direction, and the other opposite beam formwork is arranged in a reverse direction, and the upper chord steel bars on the two adjacent bottom formwork steel plates pass through The horizontal bearings are connected by negative reinforcement, and the lower chord steel bars on the two adjacent bottom formwork steel plates are connected by horizontal distributed reinforcement.
本实用新型的有益效果:Beneficial effects of this utility model:
1、新型钢筋桁架楼承板实现了机械化生产,有利于钢筋排列间距均匀、混凝土保护层厚度一致,保证了混凝土楼板浇筑及成型质量。1. The new steel truss floor deck realizes mechanized production, which is conducive to the uniform spacing of steel bars and the consistent thickness of the concrete protective layer, ensuring the quality of concrete floor pouring and molding.
2、装配式钢筋桁架楼承板可显著减少现场钢筋绑扎工程量,加快施工进度,增加施工安全保证,实现文明施工。2. The prefabricated steel truss floor deck can significantly reduce the amount of on-site steel bar binding work, speed up the construction progress, increase construction safety guarantee, and achieve civilized construction.
3、钢筋桁架楼承板是我们最为常见的一种楼承板类型,并且在钢筋桁架楼承板中采用钢筋的材质也使得它的稳定性更强,而且使用寿命也更长。3. Steel truss floor decking is the most common type of floor decking, and the use of steel bars in the steel truss floor decking also makes it more stable and has a longer service life.
4、与普通压型钢板相比,钢筋桁架楼承板的底板只做模板使用,可以尽可能采用最薄的钢板,其厚度仅需0.5mm即可,在一定程度上降低了其成本,同时使用钢筋桁架楼承板浇筑的楼板比传统混凝土楼板的厚度减少30-50mm,如果要求楼房建筑有相同的净空间,每层建筑可以节约30-50mm空间的建筑成本,对于高层建筑更加具有明显的节省投资优势。4. Compared with ordinary profiled steel plates, the bottom plate of the steel truss floor deck is only used as a formwork. The thinnest steel plate can be used as much as possible, with a thickness of only 0.5mm, which reduces its cost to a certain extent. At the same time Floor slabs cast using steel truss floor decks are 30-50mm thicker than traditional concrete floor slabs. If the building is required to have the same clear space, each floor of the building can save 30-50mm of space in construction costs, which is more obvious for high-rise buildings. Savings investment advantages.
5、施工完成后,钢筋桁架完全被混凝土包裹,而且浇筑的混凝土保护层厚度均匀,而地板采用镀锌钢板,具有良好的防腐性能。5. After the construction is completed, the steel truss is completely wrapped in concrete, and the poured concrete protective layer has a uniform thickness, and the floor is made of galvanized steel plate, which has good anti-corrosion properties.
前述本实用新型主方案及其各进一步选择方案可以自由组合以形成多个方案,均为本实用新型可采用并要求保护的方案;且本实用新型,(各非冲突选择)选择之间以及和其他选择之间也可以自由组合。本领域技术人员在了解本实用新型方案后根据现有技术和公知常识可明了有多种组合,均为本实用新型所要保护的技术方案,在此不做穷举。The aforementioned main scheme of the present utility model and its further options can be freely combined to form multiple schemes, all of which are schemes that can be adopted and claimed for protection by the present utility model; and in the present utility model, (each non-conflicting choice) between choices and Other options can also be combined freely. After understanding the solution of the present utility model, those skilled in the art will understand that there are many combinations according to the existing technology and common sense, all of which are the technical solutions to be protected by the present utility model, and an exhaustive list will not be made here.
附图说明Description of drawings
图1是本实用新型钢筋桁架楼承板的结构立面图。Figure 1 is a structural elevation of the steel truss floor deck of the present utility model.
图2是本实用新型钢筋桁架楼承板的结构侧面图(剖视)。Figure 2 is a structural side view (section) of the steel truss floor deck of the present utility model.
图3是本实用新型钢筋桁架楼承板的端部支座的结构侧面图。Figure 3 is a structural side view of the end support of the steel truss floor deck of the present utility model.
图4是本实用新型施工结构板面筋的排布示意图。Figure 4 is a schematic diagram of the arrangement of gluten in the construction structural plate of the present invention.
图5是本实用新型施工结构节点一结构示意图。Figure 5 is a structural schematic diagram of a node of the construction structure of the present utility model.
图6是本实用新型施工结构节点二结构示意图。Figure 6 is a structural schematic diagram of the second node of the construction structure of the present utility model.
图7是本实用新型施工结构节点三结构示意图。Figure 7 is a schematic structural diagram of the three nodes of the construction structure of the present utility model.
图8是本实用新型施工结构钢筋桁架楼承板扣合结构示意图。Figure 8 is a schematic diagram of the buckling structure of the steel truss floor deck of the construction structure of the present utility model.
图中:1-上弦钢筋,2-下弦钢筋,3-腹杆钢筋,4-底模钢板,5-端部支座,6-支座竖向钢筋,7-支座水平钢筋,8-扣合部甲,9-扣合部乙,10-凸台部,11-板面筋,12-支撑架,13-梁模板,14-木方,15-梁内钢筋,16-上弦连接钢筋,17-下弦连接钢筋,18-铁钉,19-分布筋,20-支座负筋。In the picture: 1-upper chord steel bar, 2-lower chord steel bar, 3-web bar steel bar, 4-bottom form steel plate, 5-end support, 6-support vertical steel bar, 7-support horizontal steel bar, 8-buckle Joint part A, 9-fastening part B, 10-boss part, 11-plate reinforcement, 12-support frame, 13-beam formwork, 14-timber square, 15-beam inner steel bar, 16-upper chord connecting steel bar, 17 -Bottom chord connecting steel bars, 18-iron nails, 19-distribution bars, 20-bearing negative bars.
具体实施方式Detailed ways
下列非限制性实施例用于说明本实用新型。The following non-limiting examples serve to illustrate the invention.
实施例1Example 1
参考图1~图3所示,一种免拆模新型钢筋桁架楼承板,包括上弦钢筋1、下弦钢筋2、腹杆钢筋3、底模钢板4、端部支座5(包括支座竖向钢筋6和支座水平钢筋7)、扣合部甲8、扣合部乙9和凸台部10。Referring to Figures 1 to 3, a new formwork-free steel truss floor bearing plate includes an upper chord steel bar 1, a lower chord steel bar 2, a web steel bar 3, a bottom formwork steel plate 4, and an end support 5 (including the vertical support of the support). The axial steel bar 6 and the support horizontal steel bar 7), the fastening part A 8, the fastening part B 9 and the boss part 10.
参考图1和图2所示,底模钢板4为0.5mm厚镀锌钢板,用于作为底部的模板使用。底模钢板4上设有若干组沿横向并间隔布置的腹杆钢筋3(直径4.5mm),每组腹杆钢筋3包括呈八字形对称布置的两个,每组的两个腹杆钢筋3的上部之间焊接连接有沿横向布置的上弦钢筋1(直径10mm/8mm),每组的两个腹杆钢筋3的下部均焊接连接有沿横向布置的下弦钢筋2(直径10mm/8mm)。Referring to Figures 1 and 2, the bottom formwork steel plate 4 is a 0.5mm thick galvanized steel plate used as the bottom formwork. The bottom formwork steel plate 4 is provided with several groups of web bar steel bars 3 (diameter 4.5mm) arranged transversely and at intervals. Each group of web bar steel bars 3 includes two symmetrically arranged in a figure-eight shape. The two web bar steel bars 3 in each group There are upper chord steel bars 1 (diameter 10mm/8mm) arranged laterally, welded and connected between the upper parts of each group, and lower chord steel bars 2 (diameter 10mm/8mm) arranged laterally are welded and connected to the lower parts of the two web steel bars 3 of each group.
每根腹杆钢筋3包括交替设置的立面三角段和水平U形段,立面三角段的上端角与上弦钢筋1焊接连接,立面三角段的下两角与下弦钢筋2焊接连接,水平U形段与底模钢板4上的凸台部10焊接连接,从而形成上部的钢筋桁架结构。Each web rod steel bar 3 includes alternating facade triangular sections and horizontal U-shaped sections. The upper end corners of the facade triangular section are welded and connected to the upper chord steel bar 1, and the lower two corners of the facade triangular section are welded and connected to the lower chord steel bars 2. The horizontal The U-shaped section is welded to the boss portion 10 on the bottom formwork steel plate 4 to form an upper steel truss structure.
参考图3所示,还包括位于上弦钢筋1、下弦钢筋2端部的端部支座5,端部支座5包括相互焊接连接的支座竖向钢筋6和支座水平钢筋7,支座竖向钢筋6焊接连接在上弦钢筋1与底模钢板4之间,支座水平钢筋7焊接连接在两个下弦钢筋2之间,利用端部支座5对上弦钢筋1、下弦钢筋2的端部进行支撑固定。Referring to Figure 3, it also includes an end support 5 located at the ends of the upper chord steel bar 1 and the lower chord steel bar 2. The end support 5 includes a support vertical steel bar 6 and a support horizontal steel bar 7 that are welded to each other. The vertical steel bar 6 is welded and connected between the upper chord steel bar 1 and the bottom form steel plate 4. The horizontal steel bar 7 of the support is welded and connected between the two lower chord steel bars 2. The end supports 5 are used to pair the ends of the upper chord steel bar 1 and the lower chord steel bar 2. The base is supported and fixed.
底模钢板4的一端设有扣合部甲8,底模钢板4的另一端设有与扣合部甲8配合的扣合部乙9,利用扣合部甲8与扣合部乙9之间的扣合连接,实现直接相邻的两个底模钢板4之间的连接,避免连接缝隙发生漏浆。底模钢板4上还设有凸台部10,凸台部10与腹杆钢筋3焊接连接。One end of the bottom mold steel plate 4 is provided with a buckle part A 8, and the other end of the bottom mold steel plate 4 is provided with a buckle part B 9 that cooperates with the buckle part A 8. The connection between the buckle part A 8 and the buckle part B 9 is used. The fastening connection between the two directly adjacent bottom formwork steel plates 4 is realized to avoid slurry leakage in the connection gap. The bottom mold steel plate 4 is also provided with a boss portion 10, and the boss portion 10 is welded to the web bar steel bar 3.
实施例2Example 2
参考图4~图8所示,一种免拆模新型钢筋桁架楼承板的施工结构,包括实施例1的免拆模新型钢筋桁架楼承板,还包括板面筋11、支撑架12、梁模板13、木方14、梁内钢筋15、上弦连接钢筋16、下弦连接钢筋17、铁钉18、分布筋19和支座负筋20。Referring to Figures 4 to 8, a construction structure of a new formwork-free steel truss floor deck includes the formwork-free new steel truss floor deck of Embodiment 1, and also includes slab reinforcements 11, support frames 12, and beams. Formwork 13, wooden squares 14, beam internal steel bars 15, upper chord connecting steel bars 16, lower chord connecting steel bars 17, iron nails 18, distribution bars 19 and bearing negative bars 20.
支撑架12采用盘扣式钢管支撑架,利用支撑架12对梁模板13进行支撑,从而实现梁模板13的固定安装。梁模板13为纵向布置,同时梁模板13连接在间隔相邻的两底模钢板4之间(即存在间隔的两底模钢板4),梁模板13的上端与底模钢板4连接,利用梁模板13对底模钢板4进行支撑,实现钢筋桁架楼承板的固定安装。梁模板13内设有伸至底模钢板4上方的梁内钢筋15,梁内钢筋15为梁结构浇筑后内部的钢筋骨架。The support frame 12 adopts a buckle-type steel pipe support frame, and the support frame 12 is used to support the beam formwork 13, thereby realizing the fixed installation of the beam formwork 13. The beam formwork 13 is arranged longitudinally. At the same time, the beam formwork 13 is connected between two adjacent bottom formwork steel plates 4 (that is, there are two bottom formwork steel plates 4 that are spaced apart). The upper end of the beam formwork 13 is connected to the bottom formwork steel plate 4. By using the beam The formwork 13 supports the bottom formwork steel plate 4 to realize the fixed installation of the steel truss floor bearing plate. The beam formwork 13 is provided with internal beam reinforcement bars 15 extending above the bottom formwork steel plate 4. The internal beam reinforcement bars 15 are the internal steel reinforcement skeleton of the beam structure after it is poured.
间隔相邻的两底模钢板4上的上弦钢筋1、下弦钢筋2之间通过过渡钢筋连接,利用过渡钢筋将间隔相邻的两底模钢板4上的钢筋桁架连接为一体,保证整体的结构更加牢固,也可以将过渡钢筋连接在梁内钢筋15,进一步加强连接强度。The upper chord steel bars 1 and the lower chord steel bars 2 on the two adjacent bottom formwork steel plates 4 are connected by transition steel bars. The transition steel bars are used to connect the steel bar trusses on the two adjacent bottom formwork steel plates 4 into one body to ensure the overall structure. To make it stronger, the transition steel bars can also be connected to the steel bars 15 inside the beam to further enhance the connection strength.
参考图8所示,直接相邻的两底模钢板4(即连接处重合的两底模钢板4)之间通过扣合连接,即一个底模钢板4的扣合部甲8扣合连接在另一个底模钢板4的扣合部乙9上,利用该种弯折扣合的结构,既可以将两个底模钢板4的端部连接,也可以利用多道的弯折结构实现连接处的密封作用。Referring to Figure 8, two directly adjacent bottom formwork steel plates 4 (i.e., two bottom formwork steel plates 4 with overlapping joints) are connected by snapping, that is, the snapping portion A 8 of one bottom formwork steel plate 4 is snappingly connected. On the fastening portion B 9 of the other bottom form steel plate 4, this kind of bending and folding structure can be used to connect the ends of the two bottom form steel plates 4, or to use multiple bending structures to realize the connection. Sealing effect.
参考图4所示,底模钢板4上设有与上弦钢筋1同向布置的板面筋11,当存在板面筋11间距a受桁架上弦筋影响时,靠近上弦筋的面筋可直接与其绑扎一起,此时间距为b,此后的面筋间距则继续保持为a。Referring to Figure 4, the bottom formwork steel plate 4 is provided with plate reinforcements 11 arranged in the same direction as the upper chord reinforcement 1. When there is a spacing a between the plate reinforcements 11 that is affected by the upper chord reinforcement of the truss, the gluten close to the upper chord reinforcement can be directly tied with it. At this time, the spacing is b, and the subsequent gluten spacing will continue to be a.
梁模板13为U形截面结构,梁模板13的外侧设有木方14,支撑架12通过木方14对梁模板13的三个端面进行支撑,并底模钢板4与上端的木方14之间通过铁钉18连接,实现梁模板13对底模钢板4的支撑。The beam formwork 13 has a U-shaped cross-section structure. There are wooden squares 14 on the outside of the beam formwork 13. The support frame 12 supports the three end faces of the beam formwork 13 through the wooden squares 14, and connects the bottom formwork steel plate 4 and the upper wooden square 14. are connected through iron nails 18 to realize the support of the beam formwork 13 to the bottom formwork steel plate 4.
间隔相邻的两底模钢板4相对梁模板13的位置关系有三种,每种位置关系对应不同种的连接节点,并以梁模板13为纵向布置进行说明。There are three positional relationships between the two adjacent bottom formwork steel plates 4 relative to the beam formwork 13. Each positional relationship corresponds to a different type of connection node, and the description is made with the beam formwork 13 as the longitudinal arrangement.
参考图5所示,第一种,间隔相邻的两底模钢板4相对梁模板13为反向布置,间隔相邻的两底模钢板4上的上弦钢筋1之间通过横向的上弦连接钢筋16绑扎连接,上弦连接钢筋16为倒扣的U形结构,间隔相邻的两底模钢板4上的下弦钢筋2之间通过横向的下弦连接钢筋17绑扎连接,下弦连接钢筋17为正扣的U形结构,下弦钢筋2之间绑扎连接有纵向的分布筋19。Referring to Figure 5, in the first type, two adjacent bottom formwork steel plates 4 are arranged in opposite directions relative to the beam formwork 13, and the upper chord steel bars 1 on the two adjacent bottom formwork steel plates 4 are connected by transverse upper chords. 16 is tied and connected, and the upper chord connecting steel bar 16 is an inverted U-shaped structure. The lower chord steel bars 2 on the two adjacent bottom formwork steel plates 4 are tied and connected by a transverse lower chord connecting steel bar 17, and the lower chord connecting steel bar 17 is a positive buckle. U-shaped structure, the lower chord steel bars 2 are tied and connected with longitudinal distribution bars 19.
参考图6所示,第二种,间隔相邻的两底模钢板4相对梁模板13为反向布置,间隔相邻的两底模钢板4上的上弦钢筋1之间通过横向的支座负筋20连接,支座负筋20为倒扣的U形结构,间隔相邻的两底模钢板4上的下弦钢筋2之间通过横向的分布筋19连接,并该节点的分布筋19为通长布置。Referring to Figure 6, in the second type, two adjacent bottom formwork steel plates 4 are arranged in opposite directions relative to the beam formwork 13, and the upper chord steel bars 1 on the two adjacently spaced bottom formwork steel plates 4 are connected by transverse bearings. The steel bars 20 are connected, and the support negative reinforcement 20 is an inverted U-shaped structure. The lower chord steel bars 2 on the two adjacent bottom formwork steel plates 4 are connected by transverse distribution bars 19, and the distribution bars 19 of this node are through Long arrangement.
参考图7所示,第三种,间隔相邻的两底模钢板4中其中一个相对梁模板13为正向布置、另一个相对梁模板13为反向布置,间隔相邻的两底模钢板4上的上弦钢筋1之间通过横向的支座负筋20连接,支座负筋20为倒扣的U形结构,间隔相邻的两底模钢板4上的下弦钢筋2之间通过横向的分布筋19连接,并该节点的分布筋19仅伸至反向布置的底模钢板4内的端部位置。Referring to Figure 7, in the third type, among the two adjacent bottom formwork steel plates 4, one of the opposite beam formwork 13 is arranged in a forward direction, and the other opposite beam formwork 13 is arranged in a reverse direction. The two adjacent bottom formwork steel plates are spaced apart. The upper chord steel bars 1 on the two adjacent bottom formwork steel plates 4 are connected by transverse support negative reinforcements 20. The support negative reinforcements 20 are inverted U-shaped structures. The distribution bars 19 are connected, and the distribution bars 19 of this node only extend to the end position in the reversely arranged bottom formwork steel plate 4.
一种免拆模新型钢筋桁架楼承板的施工方法,针对该免拆模新型钢筋桁架楼承板的施工结构,包括如下步骤。A construction method for a new formwork-free steel truss floor deck. The construction structure of the formwork-free new steel truss floor deck includes the following steps.
步骤1,支撑架搭设:钢筋桁架楼承板安装前搭设满堂支撑架,立杆纵横间距1200mm,步距1500mm,立杆扫地杆距底板面≤550mm,模板支架可调托座伸出顶层水平杆长度≤650mm,且丝杆外露长度≤400mm,可调托座插入立杆长度不得小于150mm。立杆顶部采用可调托撑,托撑内钢管根数为两根。Step 1, support frame erection: Before installing the steel truss floor deck, set up the entire hall support frame. The vertical and horizontal spacing of the vertical poles is 1200mm, and the step distance is 1500mm. The distance between the vertical sweeping pole and the floor surface is ≤550mm. The adjustable bracket of the formwork bracket extends out of the top horizontal pole. The length is ≤650mm, and the exposed length of the screw rod is ≤400mm. The length of the adjustable bracket inserted into the vertical pole shall not be less than 150mm. The top of the vertical pole adopts an adjustable support, and the number of steel pipes in the support is two.
步骤2,在支撑架上安装梁模板:利用支撑架为支撑基础,对梁模板进行安装固定,并通过木方对梁模板的外侧进行支撑,避免梁模板在浇筑后发生涨模。Step 2, install the beam formwork on the support frame: Use the support frame as the support base to install and fix the beam formwork, and support the outside of the beam formwork with wooden squares to prevent the beam formwork from expanding after pouring.
步骤3,安装钢筋桁架楼承板:梁模板安装完成后,钢筋桁架楼承板铺设前,按图纸所示的起始位置放设铺板时的基准线,对准基准线,安装第一块板,并依次安装其它板,采用非标准板收尾。Step 3, install the steel truss floor decking: After the beam formwork is installed and before the steel truss floor decking is laid, place the base line when laying the slab according to the starting position shown in the drawing, align it with the base line, and install the first slab. , and install other boards in sequence, finishing with non-standard boards.
将间隔相邻的钢筋桁架楼承板固定在梁模板上,钢筋桁架楼承板与梁模板连接处,镀锌底模钢板在梁模板边模上与梁边齐平,钢筋桁架楼承板就位之后,将其端部的底模钢板与梁或柱的侧模用铁钉固定牢固,铁钉间距≤200mm,利用梁模板对钢筋桁架楼承板进行支撑安装。Fix the adjacent reinforced truss floor decking plates on the beam formwork. At the connection point between the reinforced truss floor decking plate and the beam formwork, the galvanized bottom formwork steel plate is flush with the beam edge on the side formwork of the beam formwork. The reinforced truss floor decking plate is then After positioning, the bottom formwork steel plate at its end and the side formwork of the beam or column are firmly fixed with iron nails. The distance between the iron nails is ≤200mm. The beam formwork is used to support and install the steel truss floor deck.
直接相邻的两钢筋桁架楼承板之间扣合连接,楼承板之间连接采用扣合方式,板与板之间的拉钩紧密连接,保证浇筑混凝土时不漏浆,同时注意排板方向要一致。The two directly adjacent steel truss floor decks are connected by buckles. The connection between the floor decks is buckled. The hooks between the boards are tightly connected to ensure that there is no leakage of slurry when pouring concrete. At the same time, pay attention to the direction of arranging the boards. Be consistent.
步骤4,线管敷设:电气接线盒的预留预埋,可先将其在镀锌板上固定,允许钻Φ30㎜及以下的小孔,钻孔应小心,避免钢筋桁架楼承板变形以及桁架与镀锌底模钢板底模脱焊,影响外观或导致漏浆。管线敷设时,禁止随意扳动、切断钢筋桁架任何钢筋。Step 4. Wire pipe laying: The electrical junction box can be pre-embedded. It can be fixed on the galvanized plate first. Small holes of Φ30mm and below are allowed to be drilled. Drilling should be done carefully to avoid deformation of the steel truss floor deck and The bottom form of the truss and the galvanized bottom form steel plate is desoldered, which affects the appearance or causes slurry leakage. When laying pipelines, it is prohibited to pull or cut any steel bars of the steel trusses at will.
步骤5,绑扎钢筋:放置梁内钢筋,绑扎平行于钢筋桁架楼承板方向的板面筋、垂直钢筋桁架楼承板方向的分布筋(板底筋)。Step 5, tie the steel bars: place the steel bars in the beam, tie the slab reinforcements parallel to the direction of the steel truss floor deck, and the distribution bars (slab bottom bars) perpendicular to the direction of the steel truss floor deck.
步骤6,检查验收并浇筑混凝土:在混凝土浇筑前,钢筋桁架楼承板安装及其它工程应完成并验收合格,必须清除楼承板上的杂物(包括栓钉上的瓷环)及灰尘、油脂等,最后浇筑混凝土并进行养护。Step 6, check and accept and pour concrete: Before concrete is poured, the installation of the steel truss floor deck and other projects should be completed and accepted. Debris on the floor deck (including porcelain rings on the studs) and dust, must be removed. Grease, etc., and finally the concrete is poured and cured.
前述本实用新型基本例及其各进一步选择例可以自由组合以形成多个实施例,均为本实用新型可采用并要求保护的实施例。本实用新型方案中,各选择例,与其他任何基本例和选择例都可以进行任意组合。The above-mentioned basic examples of the present invention and its further optional examples can be freely combined to form multiple embodiments, and they are all applicable and claimed embodiments of the present invention. In the scheme of the present utility model, each optional example can be arbitrarily combined with any other basic example and optional example.
以上所述仅为本实用新型的较佳实施例而已,并不用以限制本实用新型,凡在本实用新型的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本实用新型的保护范围之内。The above descriptions are only preferred embodiments of the present utility model and are not intended to limit the present utility model. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present utility model shall be included in the present utility model. Within the protection scope of utility model.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202321442774.0U CN220247339U (en) | 2023-06-07 | 2023-06-07 | Novel steel bar truss floor carrier plate free of form removal and construction structure thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202321442774.0U CN220247339U (en) | 2023-06-07 | 2023-06-07 | Novel steel bar truss floor carrier plate free of form removal and construction structure thereof |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN220247339U true CN220247339U (en) | 2023-12-26 |
Family
ID=89267891
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202321442774.0U Active CN220247339U (en) | 2023-06-07 | 2023-06-07 | Novel steel bar truss floor carrier plate free of form removal and construction structure thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN220247339U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116556568A (en) * | 2023-06-07 | 2023-08-08 | 中国五冶集团有限公司 | Novel steel bar truss floor support plate free of form removal, construction structure and construction method thereof |
-
2023
- 2023-06-07 CN CN202321442774.0U patent/CN220247339U/en active Active
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116556568A (en) * | 2023-06-07 | 2023-08-08 | 中国五冶集团有限公司 | Novel steel bar truss floor support plate free of form removal, construction structure and construction method thereof |
| CN116556568B (en) * | 2023-06-07 | 2025-07-11 | 中国五冶集团有限公司 | Novel steel bar truss floor support plate free of form removal, construction structure and construction method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN113202219B (en) | Fully prefabricated assembled steel-concrete composite floor system and design calculation method | |
| CN105297887A (en) | Three-dimensional light steel frame composed of two-way continuous double beams | |
| CN105220808A (en) | Large-span prestressed arch bar site prefabrication construction method of installation | |
| CN206428968U (en) | A kind of steel bar girder formula is without supporting template system | |
| CN110005109A (en) | A kind of open flume type prestressed concrete overlapped slab | |
| CN204940522U (en) | Three-dimensional light steel frame composed of two-way continuous double beams | |
| CN204098313U (en) | Two-way mixing cross wise reinforcement truss self-supporting hollowcore slab | |
| CN111794423A (en) | A steel-concrete composite beam structure, building and construction method | |
| CN113738007A (en) | Truss floor plate | |
| CN116480133A (en) | Formwork support system and method for fair-faced concrete construction with Gaussian curved surfaces in the coastal environment | |
| CN220247339U (en) | Novel steel bar truss floor carrier plate free of form removal and construction structure thereof | |
| CN116427587B (en) | A prefabricated edge-type steel column-composite wall structure system | |
| CN108691382A (en) | Pin-connected panel precast floor slab and its construction method | |
| CN109972512B (en) | Cast-in-place construction method of profiled steel sheet-concrete combined bridge deck slab | |
| CN115369918B (en) | Variable-section thick arc-shaped arch plate formwork system and construction method thereof | |
| CN204940652U (en) | Large-span prestressed site prefabrication arch bar | |
| CN114263275B (en) | Construction method for same-layer construction of high-rise assembled steel structure-core tube | |
| CN209114299U (en) | A single box multi-chamber box girder bridge | |
| CN116556568B (en) | Novel steel bar truss floor support plate free of form removal, construction structure and construction method thereof | |
| CN208039577U (en) | Half prefabricated prestressed concrete floor slab of figure of eight steel bar girder | |
| CN220565527U (en) | Assembled rib plate structure | |
| CN101245642A (en) | A two-way laminated concrete slab with strip-shaped block bottom slab | |
| CN118375253A (en) | A floor structure using ultra-high toughness concrete combined with permanent formwork | |
| CN109518861A (en) | A kind of steel bar truss floor support plate being applied in combination with cast-in-situ wall | |
| CN116950302A (en) | Construction method of floor slab with industrial factory building steel-concrete combined structure and floor slab |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant |