CN220152035U - Bracket for installing comprehensive pipeline - Google Patents

Bracket for installing comprehensive pipeline Download PDF

Info

Publication number
CN220152035U
CN220152035U CN202321700800.5U CN202321700800U CN220152035U CN 220152035 U CN220152035 U CN 220152035U CN 202321700800 U CN202321700800 U CN 202321700800U CN 220152035 U CN220152035 U CN 220152035U
Authority
CN
China
Prior art keywords
frame body
bracket
pipeline
auxiliary frame
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321700800.5U
Other languages
Chinese (zh)
Inventor
吴琦
高旭
潘阳
丁宝川
张剑宇
边拓繁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cscec Xinyuan Construction Co ltd
Xinjiang Construction Engineering Group Co Ltd
Original Assignee
Cscec Xinyuan Construction Co ltd
Xinjiang Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cscec Xinyuan Construction Co ltd, Xinjiang Construction Engineering Group Co Ltd filed Critical Cscec Xinyuan Construction Co ltd
Priority to CN202321700800.5U priority Critical patent/CN220152035U/en
Application granted granted Critical
Publication of CN220152035U publication Critical patent/CN220152035U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a bracket for installing a comprehensive pipeline, which comprises a main bracket body, wherein the main bracket body is fixedly connected with a cross beam through a connecting piece, and a sub-bracket body is arranged below the main bracket body; the main frame body comprises a vertical support and a transverse support, the vertical support and the transverse support are integrally arranged, a chute is arranged on the transverse support, an inverted U-shaped hook is arranged at the upper end of the auxiliary frame body, first fixing holes are formed in two arms of the inverted U-shaped hook, and the auxiliary frame body is fixedly connected with the transverse support through connecting screws; the bracket for installing the comprehensive pipeline has the characteristics of high construction speed, high stability and high safety, various lead partitions of the lead auxiliary frame are used for fixing, and the water supply pipeline and the fire fighting pipeline are connected with the lead partitions through the auxiliary frame body, so that the safety of the lead, the water supply pipeline and the fire fighting pipeline is ensured; the installation is nimble, and overall structure is simple clear, and the construction of being convenient for is pleasing to the eye, can satisfy each specialty pipeline and synthesize the user demand of arranging, more economical and practical.

Description

Bracket for installing comprehensive pipeline
Technical Field
The utility model belongs to the technical field of building construction, and particularly relates to a bracket for installing a comprehensive pipeline.
Background
Along with the requirements of China on the aspects of green construction, saving, safety, function, attractive appearance and the like, the number of professional pipelines in the underground garage of the building is increased, the pipeline arrangement is complicated, and the effective comprehensive arrangement of the pipelines is difficult. The traditional support is more, construction is loaded down with trivial details, construction speed is slow and whole overall arrangement is not pleasing to the eye because of the specialty is different to be under construction. The comprehensive support has the advantages of small construction quantity, convenient construction, greatly improved construction efficiency and attractive overall layout.
Disclosure of Invention
The utility model aims to provide a bracket for installing a comprehensive pipeline, which aims to solve the problems that the traditional bracket is more in construction, complex in construction, slow in construction speed and poor in overall layout due to different professions in the prior art.
The utility model provides a bracket for installing a comprehensive pipeline, which comprises a main bracket body, wherein the main bracket body is fixedly connected with a cross beam through a connecting piece, and a sub-bracket body is arranged below the main bracket body; the main frame body comprises a vertical support and a transverse support, the vertical support and the transverse support are integrally arranged, a sliding groove is formed in the transverse support, an inverted U-shaped hook is arranged at the upper end of the auxiliary frame body, first fixing holes are formed in two arms of the inverted U-shaped hook, and the auxiliary frame body is fixedly connected with the transverse support through connecting screws.
Further, the wire auxiliary frame is further provided with a second fixing hole, and the wire auxiliary frame is fixedly connected with the main frame body through a connecting screw.
Further, a wire clamping groove is formed in the wire auxiliary frame.
Further, the wire auxiliary frame is fixedly connected with the two ends of the transverse support, and the height of one end close to the middle is higher than that of one end close to the outer side.
Further, the connecting piece comprises a fixing piece and an expansion anchor bolt, the fixing piece and the main frame body are welded into a whole, a third mounting hole is formed in the fixing piece, and the fixing piece is fixedly connected with the cross beam through the expansion anchor bolt.
The utility model has the beneficial effects that: the bracket for installing the comprehensive pipeline is simple and convenient to install through bolt connection and high in construction speed; the three vertical support connections enhance the overall stability of the support, improve the safety of the support, fix various wire partitions through the wire auxiliary frame, and install and connect the water supply and fire-fighting pipelines with the wire partitions through the auxiliary frame body, thereby ensuring the respective safety of the wire, the water supply pipeline and the fire-fighting pipeline; in addition, the support for installing the comprehensive pipeline is flexible in installation, simple and clear in overall structure, convenient to construct, attractive, capable of meeting comprehensive arrangement and use requirements of various professional pipelines, and more economical and practical.
The present utility model will be described in further detail with reference to examples.
Drawings
FIG. 1 is a front view of a bracket for integrated pipeline installation.
Fig. 2 is a schematic diagram of the connection structure of the inverted U-shaped hook and the transverse bracket of the sub-frame body.
FIG. 3 is a front view II of a bracket for integrated pipeline installation.
Fig. 4 is a front view III of a bracket for integrated pipeline installation.
Fig. 5 is a front view of a bracket for integrated pipeline installation.
In the figure: 1. a main frame body; 1-1, a vertical bracket; 1-2, a transverse bracket; 2. a connecting piece; 2-1, expanding anchor bolts; 2-2, fixing sheets; 3. a chute; 4. a sub-frame body; 5. a connecting screw; 6. an inverted U-shaped hook; 7. a wire auxiliary frame; 8. a wire clamping groove; 9. and a cross beam.
Detailed Description
The following detailed description, structural features and functions of the present utility model are provided with reference to the accompanying drawings and examples in order to further illustrate the technical means and effects of the present utility model to achieve the predetermined objects.
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
In the description of the present utility model, it should be understood that the terms "center," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "aligned," "overlapping," "bottom," "inner," "outer," and the like indicate orientations or positional relationships based on the orientation or positional relationships shown in the drawings, merely to facilitate description of the present utility model and simplify the description, and do not indicate or imply that the devices or elements referred to must have a specific orientation, be configured and operate in a specific orientation, and therefore should not be construed as limiting the present utility model.
The terms "first," "second," and the like, are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defining "a first", "a second" may include one or more such features, either explicitly or implicitly; in the description of the present utility model, unless otherwise indicated, the meaning of "a plurality" is two or more.
Example 1
The embodiment provides a bracket for installing a comprehensive pipeline as shown in fig. 1 to 5, and the bracket for installing the comprehensive pipeline is mainly used for installing pipelines in buildings such as garages, workshops and the like. The pipeline mainly comprises a water supply pipeline 5, a fire control pipeline 6, a fire hydrant pipeline, a power line, a signal line and the like.
The support for installing the comprehensive pipeline comprises a main support body 1, wherein the main support body 1 is fixedly connected with a cross beam 9 through a connecting piece 2, and preferably, the connecting piece 2 comprises a fixing piece 2-2 and an expansion anchor bolt 2-1, the fixing piece 2-2 and the main support body 1 are welded into a whole, a third installation hole is formed in the fixing piece 2-2, at least four third installation holes are formed in the fixing piece 2-2, the fixing piece 2-2 is fixedly connected with the cross beam 9 through the expansion anchor bolt 2-1, and therefore the connection reliability of the main support body 1 and the cross beam 9 can be ensured. A sub-frame 4 is arranged below the main frame 1; the main frame body 1 comprises a vertical support 1-1 and a transverse support 1-2, wherein the vertical support 1-1 and the transverse support 1-2 are vertically welded into a whole, the vertical support 1-1 is at least provided with three, and the number and the weight of pipelines installed according to actual needs are set according to the requirements: the length of the vertical support 1-1 is 900mm, and the length of the transverse support 1-2 is 2200mm. The transverse bracket 1-2 is provided with a chute 3, the upper end of the auxiliary frame body 4 is provided with an inverted U-shaped hook 6, two arms of the inverted U-shaped hook 6 are provided with first fixing holes, the auxiliary frame body 4 is fixedly connected with the transverse bracket 1-2 through a connecting screw 5, and therefore the auxiliary frame body 4 is doubly fixed with the connecting screw 5 through the inverted U-shaped hook 6, and the safety of an installation pipeline is ensured; on the other hand, the sliding groove 3 and the inverted U-shaped hook 6 can adapt to the connection of the auxiliary frame body 4 with different specifications and the main frame body 1, so that the universality is stronger, and the auxiliary frame body 4 with different specifications is shown in fig. 1 and 3 to be connected with the main frame body 1.
Further, the horizontal distance between the two supports for installing the comprehensive pipeline is not more than 4000mm, the layout is reasonable, the stability and the reliability are realized, and the quality and the safety after the pipeline construction can be ensured.
Further, the connecting screw 5 is an M10 expansion bolt, the expansion bolt is fixed at the distance of 25 mm from the square edge of the fixing piece 2-2, 200 x 5mm, and the connecting screw is in line with the scientific design principle, is convenient for construction, maintenance and disassembly.
Furthermore, the bracket for installing the comprehensive pipeline further comprises a wire auxiliary frame 7, wherein the wire auxiliary frame 7 mainly has the effects of classifying wires to be installed and installing the wires in a partitioned manner, realizing the partition management of strong current and weak current, avoiding the mutual mixed installation and the influence of the mutual mixed installation, and is particularly important for weak wires of signals; the main frame body 1 is also provided with a second fixing hole, and the wire auxiliary frame 7 is fixedly connected with the main frame body 1 through a connecting screw.
Furthermore, the wire auxiliary frame 7 is provided with a plurality of wire clamping grooves 8, the wire clamping grooves 8 are spaced from each other, and the sizes of the wire clamping grooves 8 are different, so that the wire auxiliary frame is suitable for regular integration and installation of wires of different types; in addition, the wire auxiliary frame 7 can be arranged in multiple layers according to the number of wires to be constructed, as shown in fig. 3, the wire auxiliary frame 7 is provided with two layers, so that more wires can be laid, and the wires can be laid in different areas and categories, and the later maintenance and replacement are very convenient.
Further, the two ends of the wire auxiliary frame 7 fixedly connected with the transverse support 1-2 are higher than the end close to the middle; therefore, the balance of the whole comprehensive support for installing the comprehensive pipeline is better, the comprehensive support is more attractive, and the laid pipeline cannot feel extrusion congestion.
Besides, the bracket for installing the comprehensive pipeline is very flexible to use, the auxiliary frame body 4 can be selectively connected or not connected according to actual needs, the bracket for installing the comprehensive pipeline is divided into two areas, the left area is a wire setting area, the right area is a pipeline setting area, and the two areas are all supported by the transverse bracket 1-2, so that the structure is simpler.
When the novel anti-corrosion support is specifically used, the main support body 1 is taken out, then the used vertical support 1-1 is fixed with the structural beam 9 through the expansion anchor bolts 2-1 after being welded and connected with the connecting piece 2, construction is facilitated, stability is high, the wire auxiliary frame 7 is fixedly connected with the vertical support 1-1 and the transverse support 1-2 through the connecting screws, the inverted U-shaped hooks 6 of the auxiliary support body 4 and the connecting screws 5 are connected with the transverse support 1-2, pipeline areas are divided, pipelines are reasonably arranged, silver anti-corrosion paint is coated outside the main support body 1 and the auxiliary support body 4 for two times, and the anti-corrosion capability of the support body is improved, so that the service life of the support body is prolonged, the novel anti-corrosion support is more economical and practical, the distance between the support and the support is not more than 4000mm, and the safety of a construction site is improved.
In summary, the bracket for installing the comprehensive pipeline is simple and convenient to install through bolt connection and high in construction speed; the three vertical support connections enhance the overall stability of the support, improve the safety of the support, fix various wire partitions through the wire auxiliary frame, and install and connect the water supply and fire-fighting pipelines with the wire partitions through the auxiliary frame body, thereby ensuring the respective safety of the wire, the water supply pipeline and the fire-fighting pipeline; in addition, the support for installing the comprehensive pipeline is flexible in installation, simple and clear in overall structure, convenient to construct, attractive, capable of meeting comprehensive arrangement and use requirements of various professional pipelines, and more economical and practical.
The foregoing is a further detailed description of the utility model in connection with the preferred embodiments, and it is not intended that the utility model be limited to the specific embodiments described. It will be apparent to those skilled in the art that several simple deductions or substitutions may be made without departing from the spirit of the utility model, and these should be considered to be within the scope of the utility model.

Claims (5)

1. A bracket for integrated pipeline installation, characterized by: the novel lifting device comprises a main frame body (1), wherein the main frame body (1) is fixedly connected with a cross beam (9) through a connecting piece (2), and a sub-frame body (4) is arranged below the main frame body (1); the main frame body (1) comprises a vertical support (1-1) and a transverse support (1-2), the vertical support (1-1) and the transverse support (1-2) are integrally arranged, a sliding groove (3) is formed in the transverse support (1-2), an inverted U-shaped hook (6) is arranged at the upper end of the auxiliary frame body (4), first fixing holes are formed in two arms of the inverted U-shaped hook (6), and the auxiliary frame body (4) is fixedly connected with the transverse support (1-2) through connecting screws (5).
2. A bracket for integrated pipeline installation as claimed in claim 1, wherein: the novel wire fixing device is characterized by further comprising a wire auxiliary frame (7), wherein a second fixing hole is further formed in the main frame body (1), and the wire auxiliary frame (7) is fixedly connected with the main frame body (1) through a connecting screw.
3. A bracket for integrated pipeline installation as claimed in claim 2, wherein: and a wire clamping groove (8) is formed in the wire auxiliary frame (7).
4. A bracket for integrated pipeline installation as claimed in claim 2 or 3, wherein: the two ends of the wire auxiliary frame (7) fixedly connected with the transverse support (1-2) are higher than the outer side end near the middle.
5. A bracket for integrated pipeline installation as claimed in claim 1, wherein: the connecting piece (2) comprises a fixing piece (2-2) and an expansion anchor bolt (2-1), the fixing piece (2-2) and the main frame body (1) are welded into a whole, a third mounting hole is formed in the fixing piece (2-2), and the fixing piece (2-2) is fixedly connected with the cross beam (9) through the expansion anchor bolt (2-1).
CN202321700800.5U 2023-06-30 2023-06-30 Bracket for installing comprehensive pipeline Active CN220152035U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321700800.5U CN220152035U (en) 2023-06-30 2023-06-30 Bracket for installing comprehensive pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321700800.5U CN220152035U (en) 2023-06-30 2023-06-30 Bracket for installing comprehensive pipeline

Publications (1)

Publication Number Publication Date
CN220152035U true CN220152035U (en) 2023-12-08

Family

ID=89020219

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321700800.5U Active CN220152035U (en) 2023-06-30 2023-06-30 Bracket for installing comprehensive pipeline

Country Status (1)

Country Link
CN (1) CN220152035U (en)

Similar Documents

Publication Publication Date Title
CN213021460U (en) High formwork intelligent security monitoring device
CN202559773U (en) Adjustable support frame for prefabricated column
CN220152035U (en) Bracket for installing comprehensive pipeline
CN111202373A (en) Hanging structure of cabinet side plate
CN110670786A (en) Curvature suspended ceiling large-span hoisting structure system and hoisting method thereof
CN209324062U (en) A kind of easy-to-dismount steel-structure factory building
CN209196687U (en) A kind of vertical type mounting bracket aviation obstruction beacon
CN109140049B (en) Antidetonation suspension and support and building
CN212248809U (en) Prefabricated formula side fascia of assembly type structure
CN209725454U (en) A kind of pepe bridge
CN201771243U (en) Multi-loop common-tower common-frame iron tower
CN215630890U (en) Groove type dry hanging piece for glass composite board
CN211821075U (en) Electromechanical engineering screw jib synthesizes support
CN211313070U (en) ALC board assembled composite floor
CN210669385U (en) Auxiliary positioning structure for cable bridge
CN218386812U (en) Novel power supply system topological structure for ground depot
CN211286236U (en) Curvature suspended ceiling large-span hoisting structure system
CN219627283U (en) High-strength horizontal cable bridge convenient to construct
CN217811755U (en) Partition wall structure of prefabricated building
CN215759952U (en) Suspended ceiling modeling and hanging device
CN210264147U (en) Novel protection network of highway engineering construction usefulness
CN212295216U (en) Pull rod type steel frame structure point type glass curtain wall
CN220395071U (en) Assembled dry-hanging composite aluminum plate wall surface
CN216159165U (en) Assembled air conditioner installation component
CN220523437U (en) Comprehensive bearing bracket for station hall layer of subway station

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant