CN220133441U - Building ceramic tile gap glue supplementing structure - Google Patents

Building ceramic tile gap glue supplementing structure Download PDF

Info

Publication number
CN220133441U
CN220133441U CN202320877730.4U CN202320877730U CN220133441U CN 220133441 U CN220133441 U CN 220133441U CN 202320877730 U CN202320877730 U CN 202320877730U CN 220133441 U CN220133441 U CN 220133441U
Authority
CN
China
Prior art keywords
frame
spring
tile gap
utility
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320877730.4U
Other languages
Chinese (zh)
Inventor
宋宗伟
夏昌滔
宋绍华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha Junge Building Materials Technology Co ltd
Original Assignee
Changsha Junge Building Materials Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha Junge Building Materials Technology Co ltd filed Critical Changsha Junge Building Materials Technology Co ltd
Priority to CN202320877730.4U priority Critical patent/CN220133441U/en
Application granted granted Critical
Publication of CN220133441U publication Critical patent/CN220133441U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Finishing Walls (AREA)

Abstract

The utility model relates to the technical field of gap glue filling, in particular to a gap glue filling structure of a building ceramic tile. The utility model provides a building tile gap repairing structure capable of aligning gap gluing and conducting uniform speed in the gluing process.

Description

Building ceramic tile gap glue supplementing structure
Technical Field
The utility model relates to the technical field of gap glue filling, in particular to a gap glue filling structure of a building ceramic tile.
Background
The ceramic tile is made of refractory metal oxide and semi-metal oxide, and through grinding, mixing, pressing, glazing and sintering, and is one kind of ceramic, stone, etc. with acid and alkali resistance. The raw materials are formed by mixing clay and quartz sand at high temperature in a compression mode and the like, the ceramic tile has high hardness, the gap between the ceramic tiles needs to be repaired in the installation and paving process, and the common repairing structure has the following defects:
the existing glue supplementing structure can control glue spraying manually, so that the situation of glue spraying errors caused by inaccurate gaps can occur, the glue spraying speed can also influence the effect of gap glue supplementing,
disclosure of Invention
The utility model aims to solve the technical problem of providing a building tile gap glue repairing structure which can be used for glue spraying aiming at gaps and can perform uniform speed in the glue spraying process.
The technical scheme adopted by the utility model is as follows: the utility model provides a building ceramic tile gap glue filling structure, includes the installing frame, its characterized in that: the two sides of the installation frame are respectively provided with a movable frame body, one side of the movable frame body is fixedly provided with a plurality of limit rods, one end of each limit rod, which is far away from the movable frame body, is connected with a fixed frame, a limit block is arranged in the fixed frame, the limit block is fixedly connected with the fixed frame through a first spring, a movable plate is arranged in the movable frame body, the movable plate is fixedly connected with the movable frame body through a second spring, the movable plate is connected with a gap limiting block through a plurality of connecting rods, a motor is fixed in the installation frame, a unidirectional screw rod is connected to an output shaft of the motor, a limiting column is fixed in the installation frame, a movable block is arranged on the unidirectional screw rod and the limiting column in a sleeved mode, a limiting sleeve is arranged in the movable block, a plurality of suckers are fixed on the lower surface of the installation frame, and a handle is connected to the installation frame through the screw rod.
As a further scheme of the utility model: the first spring is positioned in the fixed frame and is in a natural extension state.
As a further scheme of the utility model: the fixing frame is internally provided with a first groove matched with the movement of the limiting block, the mounting frame is internally provided with a groove matched with the movement of the limiting rod and the fixing frame, and the mounting frame is internally provided with a plurality of limiting grooves matched with the movement of one end of the limiting block.
As a further scheme of the utility model: the second spring is positioned in the mounting frame, and the second spring is in a natural extension state.
As a further scheme of the utility model: and a groove III which is matched with the gap limiting block to enter is formed in the movable frame body.
As a further scheme of the utility model: bearings are sleeved at the two ends of the unidirectional screw rod, and the two ends of the unidirectional screw rod are fixedly connected with the mounting frame through the bearings.
As a further scheme of the utility model: the handle sleeve is provided with an anti-skid sleeve.
Compared with the prior art, the utility model has the beneficial effects that:
the device has complete functions, and the gap limiting blocks are clamped in the gaps, so that the device can be accurately aligned with the gaps between the ceramic tiles through the arrangement of the two gap limiting blocks;
the utility model has complete functions, and the movable limit sleeve can move at a constant speed by starting the motor to work, so that the glue beating process can be uniform;
in the whole, the utility model can be used for aligning the gap to perform glue spraying, and the glue spraying process is performed at uniform speed.
Drawings
The accompanying drawings are included to provide a further understanding of the utility model and are incorporated in and constitute a part of this specification, illustrate the utility model and together with the embodiments of the utility model, serve to explain the utility model. In the drawings:
fig. 1 is an overall cross-sectional view of a construction tile gap repair structure according to the present utility model.
Fig. 2 is a schematic diagram of a gap limiting block structure of a gap glue filling structure of a building tile.
Fig. 3 is a sectional view of a stop lever and a fixing frame of a construction tile gap glue filling structure according to the present utility model.
In the accompanying drawings:
( 1. A mounting frame; 2. moving the frame; 3. a limit rod; 4. a fixed frame; 5. a limiting block; 6. a first spring; 7. a moving plate; 8. a second spring; 9. a connecting rod; 10. a gap limiting block; 11. a motor; 12. a unidirectional screw rod; 13. a movable block; 14. a limit sleeve; 15. a suction cup; 16. a rotating rod; 17. a handle; 18. spacing post )
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1-3, the present utility model provides a technical solution:
in order to align the gap glue filling structure of the building ceramic tile and perform glue filling in the gap, and the glue filling process is performed at uniform speed, the utility model provides the building ceramic tile gap glue filling structure as shown in the figure, which has the functions that: including installing frame 1, its characterized in that: the utility model discloses a lifting device is characterized in that the both sides of installation frame 1 all are equipped with removal framework 2, removal framework 2 one side is fixed with a plurality of gag lever posts 3, the one end that removes framework 2 was kept away from to gag lever post 3 is connected with fixed frame 4, be equipped with the recess that cooperation gag lever post 3 and fixed frame 4 removed in the installation frame 1, be equipped with stopper 5 in the fixed frame 4, be equipped with the recess one that cooperation stopper 5 removed in the installation frame 1, be equipped with the spacing recess that a plurality of cooperation stopper 5 one ends got into in the installation frame 1, be connected fixedly through spring one 6 between stopper 5 and the fixed frame 4, spring one 6 is located fixed frame 4, spring one 6 is in the nature extension state, be equipped with movable plate 7 in the removal framework 2, through spring two 8 fixed connection between movable plate 7 and the movable frame 2, spring two 8 are in the installation frame 1, spring two 8 are in the nature extension state, be connected with gap stopper 10 through a plurality of connecting rods 9, be equipped with the recess three motor that cooperate gap 10 gets into in the installation frame 2, be equipped with the three motor that cooperates gap 10 gets into, install the output shaft 1 in the fixed frame 12, be equipped with the fixed connection spiral sleeve 12 with the fixed connection 12, 13, the fixed connection has 12 is equipped with the one-way shaft 12, 13, and the fixed connection has a fixed connection is equipped with the one-way spiral sleeve 13 between the fixed shaft 12, and the fixed connection is equipped with the fixed connection between the fixed frame 1, and the fixed connection has two ends through the fixed connection, and the fixed connection has 13.
The working principle of the utility model is as follows:
the gap limiting block 10 is clamped in the gap, so that the device can be accurately aligned with the gap between the tiles through the arrangement of the two gap limiting blocks 10, the sucker 15 is pressed to suck the tiles, the device can be limited and fixed on one side of the tiles, then the tile glue container is installed and placed in the limiting sleeve 14, the starting motor 11 works to drive the unidirectional screw rod 12 to rotate through the output shaft of the starting motor, the movable block 13 transversely moves to drive the limiting sleeve 14 to move under the limiting effect of the limiting post 18, the tile glue container is manually controlled to squeeze glue, and the limiting sleeve 14 moves at a uniform speed to enable the glue beating process to perform uniform speed.
The utility model and its embodiments have been described above with no limitation, and the actual construction is not limited to the embodiments of the utility model as shown in the drawings. In summary, if one of ordinary skill in the art is informed by this disclosure, a structural manner and an embodiment similar to the technical solution should not be creatively devised without departing from the gist of the present utility model.

Claims (7)

1. The utility model provides a building ceramic tile gap glue filling structure, includes installing frame (1), its characterized in that: the utility model discloses a lifting handle, including installation frame (1), fixed frame (4) are connected through spring one (6), be equipped with movable plate (7) in removal frame (2), through spring two (8) fixed connection between movable plate (7) and the removal frame (2), movable plate (7) are connected with gap stopper (10) through a plurality of connecting rods (9), fixed frame (1) internal fixation has motor (11), the output shaft of motor (11) is connected with unidirectional screw (12), fixed frame (1) internal fixation has spacing post (18), unidirectional screw (12) and spacing post (18) cover are equipped with movable block (13), be equipped with spacing sleeve (14) in the movable block (13), install under fixed frame (1) handle (16) through a plurality of fixed connection handles (17).
2. A construction tile gap repair structure according to claim 1, wherein: the first spring (6) is positioned in the fixed frame (4), and the first spring (6) is in a natural extension state.
3. A construction tile gap repair structure according to claim 1, wherein: the fixing frame is characterized in that a first groove for matching with the movement of the limiting block (5) is formed in the fixing frame (4), a groove for matching with the movement of the limiting rod (3) and the fixing frame (4) is formed in the mounting frame (1), and a plurality of limiting grooves for matching with the movement of one end of the limiting block (5) are formed in the mounting frame (1).
4. A construction tile gap repair structure according to claim 1, wherein: the second spring (8) is positioned in the mounting frame (1), and the second spring (8) is in a natural extension state.
5. A construction tile gap repair structure according to claim 1, wherein: and a groove III which is matched with the gap limiting block (10) to enter is formed in the movable frame body (2).
6. A construction tile gap repair structure according to claim 1, wherein: bearings are sleeved at two ends of the unidirectional screw rod (12), and two ends of the unidirectional screw rod (12) are fixedly connected with the mounting frame (1) through the bearings.
7. A construction tile gap repair structure according to claim 1, wherein: the handle (17) is sleeved with an anti-skid sleeve.
CN202320877730.4U 2023-04-19 2023-04-19 Building ceramic tile gap glue supplementing structure Active CN220133441U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320877730.4U CN220133441U (en) 2023-04-19 2023-04-19 Building ceramic tile gap glue supplementing structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320877730.4U CN220133441U (en) 2023-04-19 2023-04-19 Building ceramic tile gap glue supplementing structure

Publications (1)

Publication Number Publication Date
CN220133441U true CN220133441U (en) 2023-12-05

Family

ID=88954163

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320877730.4U Active CN220133441U (en) 2023-04-19 2023-04-19 Building ceramic tile gap glue supplementing structure

Country Status (1)

Country Link
CN (1) CN220133441U (en)

Similar Documents

Publication Publication Date Title
CN209755595U (en) Lifting adjustment type concrete troweling machine
CN108247821B (en) A kind of automatic liquid supply smears glaze device
CN112123584B (en) Mixing and proportioning device for plastering wall slurry
CN210651178U (en) Ceramic appliance greenware manufacturing device
CN109138386A (en) Clamping device with a holding multiple pieces ceramic tile function
CN220133441U (en) Building ceramic tile gap glue supplementing structure
CN114986336A (en) Processing equipment for toughened building ceramic products
CN208483673U (en) A kind of ceramic tile sander
CN111852057B (en) Broken ceramic tile is changed and is used brick device based on indoor construction of building
CN211136646U (en) Brick grinding device for building engineering
CN216340731U (en) Tile auxiliary device
CN216265172U (en) A grind glaze structure for ceramic tile processing
CN214494872U (en) Feeding and discharging device for glass panel production
CN103101761B (en) Ceramic hollow grouting model clamping transferring device
CN113374231B (en) Construction method for laying ceramic tiles for house decoration engineering
CN219727639U (en) Automatic marking device for green bricks in ceramic production
CN215881218U (en) Automatic grinding device of crystal bar sample wafer
CN218904867U (en) Polishing equipment convenient to it is fixed
CN219946227U (en) Mechanical arm
CN111673587B (en) Production and processing technology of toughened glass
CN219887430U (en) Ground rock board thin-sticking structure
CN220814769U (en) Ceramic tile joint ware
CN215919988U (en) Novel glass edge grinding machine
CN211221499U (en) Inorganic quartzite plate thickness setting device
CN114182927B (en) Wall surface ceramic tile attaching device based on building construction