CN220028759U - Vertical lifting device for punching roof of building engineering - Google Patents

Vertical lifting device for punching roof of building engineering Download PDF

Info

Publication number
CN220028759U
CN220028759U CN202220844994.5U CN202220844994U CN220028759U CN 220028759 U CN220028759 U CN 220028759U CN 202220844994 U CN202220844994 U CN 202220844994U CN 220028759 U CN220028759 U CN 220028759U
Authority
CN
China
Prior art keywords
vertical lifting
lifting device
square tube
connecting pipe
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202220844994.5U
Other languages
Chinese (zh)
Inventor
彭光熹
王春成
张明玉
刘伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway 18th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd, Fourth Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CN202220844994.5U priority Critical patent/CN220028759U/en
Application granted granted Critical
Publication of CN220028759U publication Critical patent/CN220028759U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A vertical lifting device for room is built engineering roof and is punched comprises adjustable support base, vertical lifting device and equipment fixing device, the base is installed on adjustable support base top, vertical lifting device installs on the base, equipment fixing device installs on the vertical lifting device. The utility model has the advantages of simple structure, high construction efficiency, good safety, effective protection of constructors and high positioning precision.

Description

Vertical lifting device for punching roof of building engineering
Technical Field
The utility model belongs to auxiliary equipment for building construction, and particularly relates to a vertical lifting device for punching a roof of a building engineering.
Background
In order to ensure the engineering progress and the engineering quality in the construction of the main structure of the building engineering, the technology of drilling and planting ribs at the bottom of a beam or a plate structure is mostly adopted in the construction of a general secondary structure, and a large number of holes are also required to be drilled in a top plate of a suspended ceiling in the decoration and fitment engineering. The roof drilling is a time-consuming and labor-consuming work, and at present, the roof drilling is carried out by manually standing on a high ladder or a scaffold, and the construction method has the following defects: 1. the operator needs to punch holes upwards on the scaffold by holding the electric drill by hand, works at high altitude, climbs up the position of the scaffold or the high ladder that can not be moved down by a few holes, then climbs up the position of the scaffold or the high ladder, and in order to ensure the safety of the constructor in the moving process, the constructor is required to move after leaving the high ladder or the scaffold, so that the construction efficiency is greatly influenced. 2. In the drilling process, a constructor holds an electric drill to drill holes upwards, dust generated during drilling directly endangers the health of constructors, and the risk of operation on a frame is high. 3. Because of the influence of human factors, the depth and verticality of the drilling are not easy to control, and the quality controllability is not high.
Disclosure of Invention
The utility model aims to overcome the defects in the prior art, and provides the vertical lifting device for punching the roof of the building engineering, which has the advantages of simple structure, high construction efficiency, good safety, effective protection of constructors and high positioning precision.
The technical scheme of the utility model is as follows: a vertical lifting device for room is built engineering roof and is punched, its characterized in that: the device comprises an adjustable support base, a vertical lifting device and an equipment fixing device, wherein a base is arranged at the top end of the adjustable support base, the vertical lifting device is arranged on the base, and the equipment fixing device is arranged on the vertical lifting device.
Preferably, the adjustable support base adopts an adjustable tripod, and the bottom ends of the support legs of the adjustable tripod are conical.
Preferably, the adjustable support base is connected with the base by a transverse shaft.
Preferably, the base is made of alloy materials, the connecting mechanism is arranged at the middle part and is a hollow alloy square tube, the wall thickness of the alloy square tube is 1.5mm, and the inner dimension of the alloy square tube is 30 x 60mm.
Preferably, the vertical lifting device comprises a first connecting pipe which can be inserted into the base, a second connecting pipe which is connected with the equipment fixing device, and a connecting piece which is connected between the first connecting pipe and the second connecting pipe, and an operating rod is arranged between the first connecting pipe and the second connecting pipe.
Preferably, the first bottom of the connecting pipe is connected with the tripod base through two pin shafts, and the second top of the connecting pipe is connected with the equipment fixing device through three pin shafts.
Preferably, the first connecting pipe and the second connecting pipe are hollow square pipes with wall thickness of 1.5mm and external dimension of 30 x 60mm, and the wall thickness of the connecting piece is 2mm and the width of the connecting piece is 6mm.
Preferably, the device fixing device consists of an upper square tube and a lower square tube, the lower square tube is arranged in the upper square tube, the top of the upper square tube is provided with an opening, the wall thickness of the upper square tube is 1.5mm, the internal dimension is 100mm, the bottom of the lower square tube is sleeved at the top of the vertical lifting device, the wall thickness of the lower square tube is 1.5mm, and the internal dimension is 30 mm and 60mm.
The utility model has the following advantages and positive effects:
1. according to the utility model, the adjustable support base capable of moving up and down and the vertical lifting device are utilized, so that the multi-layer scaffold can be replaced to be built for carrying out punching construction on floor top plates with different layer heights, and the construction efficiency and the safety are improved.
2. The adjustable support base adopts the adjustable tripod which is of an A-shaped truss structure when in use, has firm structure and good stability, and can well support the vertical lifting device and the equipment fixing device, so that an operator cannot vibrate when carrying out roof punching operation, and the construction safety is further improved.
3. The utility model can accurately control the drilling depth and verticality, improve the positioning precision, effectively absorb dust in the processing process, improve the working environment and ensure the health of operators.
4. The utility model has simple structure, various parts can be folded and disassembled, and the utility model is convenient to move and carry, and saves time and labor.
Drawings
FIG. 1 is a schematic diagram of the structure of the present utility model;
FIG. 2 is a schematic view of the structure of an adjustable support base;
FIG. 3 is a schematic view of a vertical lift device;
FIG. 4 is a schematic structural view of the device fixture;
fig. 5 is a top view of the present utility model.
Detailed Description
In order to describe the technical content, the constructional features, the achieved objects and effects of the present utility model in detail, the following description is made in connection with the embodiments and the accompanying drawings.
Referring to fig. 1, the utility model provides a vertical lifting device for punching a roof of a building engineering, which consists of an adjustable supporting base 3, a vertical lifting device 2 and an equipment fixing device 1, wherein the top end of the adjustable supporting base is provided with a base 4, the vertical lifting device is arranged on the base, and the equipment fixing device is arranged on the vertical lifting device.
Referring to fig. 2, the adjustable support base 3 is an adjustable tripod, the bottom ends of the supporting legs of the adjustable tripod are conical, the adjustable tripod is connected with the base through a transverse shaft, and the height and the opening and closing angle of the supporting legs of the tripod can be adjusted according to requirements. The base is made of alloy materials, the connecting mechanism 5 is arranged at the middle part and is a hollow alloy square tube, the wall thickness of the alloy square tube is 1.5mm, and the inner dimension is 30 mm or 60mm.
Referring to fig. 3, the vertical lift device 2 includes a first connection pipe 11 which can be inserted into the base, a second connection pipe 6 which is connected to the device fixing device, and a connection member 7 which is connected between the first connection pipe and the second connection pipe, between which an operation lever 8 is installed. The first bottom of the connecting pipe is connected with the tripod base through two pin shafts, and the second top of the connecting pipe is connected with the equipment fixing device through three pin shafts. The first connecting pipe and the second connecting pipe are hollow square pipes with the wall thickness of 1.5mm and the external dimension of 30 x 60mm, and the wall thickness of the connecting piece is 2mm and the width of the connecting piece is 6mm.
Referring to fig. 4, the device fixing apparatus 1 is composed of an upper square tube 9 and a lower square tube 10, the lower square tube 10 is installed in the upper square tube 9, the top of the upper square tube is open, the wall thickness of the upper square tube is 1.5mm, the internal dimension is 100mm, the bottom of the lower square tube is sleeved on the top of the vertical lifting apparatus, the wall thickness of the lower square tube is 1.5mm, and the internal dimension is 30 mm.
The working process of the utility model is as follows:
1. the adjustable support base is adjusted to a proper length, the support legs are erected on the ground after being opened to a proper angle, and the top surface of the base is kept horizontal;
2. the punching equipment is installed in the equipment fixing device and is firmly connected with the vertical lifting device;
3. and finally, inserting the bottom of the vertical lifting mechanism of the installed equipment into the tripod top connecting mechanism, and adopting a pin shaft for firm connection. Starting the punching equipment, vertically pulling the operating rod, and starting the operation.
4. And (3) reversely operating after the operation is finished.
The utility model has simple structure, light weight, easy storage, convenient carrying and simple operation, can improve the working efficiency of operators and avoid the overhead operation of operators.
Although the utility model has been described above with reference to the drawings, the utility model is not limited to the above-described embodiments, which are merely illustrative and not restrictive, and many modifications may be made by those of ordinary skill in the art without departing from the spirit of the utility model, which fall within the protection of the utility model.

Claims (8)

1. A vertical lifting device for room is built engineering roof and is punched, its characterized in that: the device comprises an adjustable support base, a vertical lifting device and an equipment fixing device, wherein a base is arranged at the top end of the adjustable support base, the vertical lifting device is arranged on the base, and the equipment fixing device is arranged on the vertical lifting device.
2. The vertical lifting device for roof punching in building engineering according to claim 1, wherein: the adjustable support base adopts adjustable tripod, and its landing leg bottom is the toper.
3. The vertical lifting device for roof punching in building engineering according to claim 1, wherein: the adjustable support base is connected with the base through a transverse shaft.
4. The vertical lifting device for roof punching in building engineering according to claim 1, wherein: the base is made of alloy materials, a connecting mechanism is arranged at the middle part and is a hollow alloy square tube, the wall thickness of the alloy square tube is 1.5mm, and the inner dimension is 30 mm or 60mm.
5. The vertical lifting device for roof punching in building engineering according to claim 1, wherein: the vertical lifting device comprises a first connecting pipe which can be inserted into the base, a second connecting pipe which is connected with the equipment fixing device and a connecting piece which is connected between the first connecting pipe and the second connecting pipe, and an operating rod is arranged between the first connecting pipe and the second connecting pipe.
6. The vertical lifting device for roof perforation of a building project according to claim 5, wherein: the first bottom of the connecting pipe is connected with the tripod base through two pin shafts, and the second top of the connecting pipe is connected with the equipment fixing device through three pin shafts.
7. The vertical lifting device for roof perforation of a building project according to claim 5, wherein: the first connecting pipe and the second connecting pipe are hollow square pipes with the wall thickness of 1.5mm and the external dimension of 30 x 60mm, and the wall thickness of the connecting piece is 2mm and the width of the connecting piece is 6mm.
8. The vertical lifting device for roof punching in building engineering according to claim 1, wherein: the equipment fixing device consists of an upper square tube and a lower square tube, the lower square tube is arranged in the upper square tube, the top opening of the upper square tube has a wall thickness of 1.5mm and an internal dimension of 100mm, the bottom of the lower square tube is sleeved at the top of the vertical lifting device, the wall thickness of the lower square tube is 1.5mm, and the internal dimension of the lower square tube is 30 mm and 60mm.
CN202220844994.5U 2022-04-13 2022-04-13 Vertical lifting device for punching roof of building engineering Active CN220028759U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202220844994.5U CN220028759U (en) 2022-04-13 2022-04-13 Vertical lifting device for punching roof of building engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202220844994.5U CN220028759U (en) 2022-04-13 2022-04-13 Vertical lifting device for punching roof of building engineering

Publications (1)

Publication Number Publication Date
CN220028759U true CN220028759U (en) 2023-11-17

Family

ID=88723323

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202220844994.5U Active CN220028759U (en) 2022-04-13 2022-04-13 Vertical lifting device for punching roof of building engineering

Country Status (1)

Country Link
CN (1) CN220028759U (en)

Similar Documents

Publication Publication Date Title
CN103521807B (en) A kind of liftable laser positioning high spatial suspension rod punching erecting device and method of operating
CN105298148B (en) Installing machine for light partition wallboard
CN110306776B (en) Lifting platform for high-rise building elevator shaft construction
CN103611967B (en) A kind of elevation type percussion drill auxiliary support apparatus
CN206899527U (en) A kind of perforating device for being easy to heighten
CN220028759U (en) Vertical lifting device for punching roof of building engineering
CN110586985A (en) Top plate drilling lifting frame
CN104439403A (en) Portable drilling equipment
CN106825682A (en) High-altitude drilling automatic pilot
CN203541623U (en) Novel punching frame
CN107538046A (en) A kind of portable beam bottom laser positioning bar planting is bored
CN203185299U (en) Composite lever-type electric hammer lifting auxiliary support
CN213827159U (en) Simple punching device for top plate hanging hole
CN203526628U (en) Lifting-type auxiliary support device of percussion drill
CN211078316U (en) Adjustable pipeline installation crane
CN211891503U (en) Drilling support for building engineering
CN219818117U (en) Top plate punching device
CN210877698U (en) Fixing platform for installing top plate drilling support
CN215943375U (en) Positioning and drilling device on ceiling of concrete structure
CN204262411U (en) A kind of portable perforating equipment
CN218110689U (en) Lever lifting formula high altitude drilling tool
CN218365715U (en) Quick drilling device
CN202073501U (en) Floor type drilling mechanism for bottom of concrete slab of indoor ceiling
CN205400600U (en) Ceiling pore -forming construction equipment
CN211640556U (en) Water changes mount equipment suitable for multiple layer height

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant