CN219987953U - Solid recycled concrete precast pile device - Google Patents

Solid recycled concrete precast pile device Download PDF

Info

Publication number
CN219987953U
CN219987953U CN202321589744.2U CN202321589744U CN219987953U CN 219987953 U CN219987953 U CN 219987953U CN 202321589744 U CN202321589744 U CN 202321589744U CN 219987953 U CN219987953 U CN 219987953U
Authority
CN
China
Prior art keywords
die
mould
bolt
precast pile
recycled concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321589744.2U
Other languages
Chinese (zh)
Inventor
方张平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huainan Union University Huainan Employee University Huainan Branch Of Anhui Open University
Original Assignee
Huainan Union University Huainan Employee University Huainan Branch Of Anhui Open University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huainan Union University Huainan Employee University Huainan Branch Of Anhui Open University filed Critical Huainan Union University Huainan Employee University Huainan Branch Of Anhui Open University
Priority to CN202321589744.2U priority Critical patent/CN219987953U/en
Application granted granted Critical
Publication of CN219987953U publication Critical patent/CN219987953U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Moulds, Cores, Or Mandrels (AREA)

Abstract

The utility model relates to the technical field of constructional engineering and discloses a solid recycled concrete precast pile device which comprises a first die and a second die, wherein a bottom plate is arranged between the first die and the second die, supporting blocks I are arranged on the outer sides of the first die and the second die, fixing blocks I fixed on the first die are hinged to two sides of the top end of the supporting block I positioned on the outer side of the first die, fixing blocks II fixed on the second die are hinged to two sides of the top end of the supporting block I positioned on the outer side of the second die, a containing groove is formed in the bottom end of the supporting block I, and supporting blocks II are inserted in the containing groove in a sliding mode. The utility model has reasonable structure, can rapidly prepare the solid recycled concrete precast pile, can adaptively regulate and control the device, can facilitate the user to store the support component of the idle device, has high working performance and is convenient to use.

Description

Solid recycled concrete precast pile device
Technical Field
The utility model relates to the technical field of constructional engineering, in particular to a solid recycled concrete precast pile device.
Background
The precast concrete pile is prefabricated in a prefabricated part processing factory, the corresponding precast pile device is spliced by using a template in the preparation process of the precast concrete pile, then the steel bars are tied in the precast pile device, then the concrete is injected into the precast pile device, after the concrete in the precast pile device is solidified, the precast pile device is disassembled, the prefabricated part in the precast pile device is taken out, the precast pile device is maintained, and the precast pile device is transported to a construction site after the design strength is reached.
The existing solid recycled concrete precast pile device can be used for preparing the solid recycled concrete precast pile, but most of the solid recycled concrete precast pile device is fixed with corresponding length in the using process, when the length is not matched with the solid recycled concrete precast pile to be prepared, workers are often required to saw out redundant templates on the solid recycled concrete precast pile device, in the process, time and labor are wasted, the solid recycled concrete precast pile device is easy to damage, and the solid recycled concrete precast pile device is inconvenient to use.
Disclosure of Invention
The utility model provides a solid recycled concrete precast pile device, which aims to solve the technical problem that a concrete precast pile device is inconvenient to use.
The utility model is realized by adopting the following technical scheme: the utility model provides a solid recycled concrete precast pile device, includes mould one and mould two, be equipped with the bottom plate between mould one and the mould two, the outside of mould one and mould two all is equipped with supporting shoe one, and the both sides at supporting shoe one top in the mould one outside articulates has the rigid coupling piece one fixed on mould one, and the both sides at supporting shoe one top in the mould two outsides articulates has the rigid coupling piece two fixed on mould two, the holding tank has been seted up to the bottom of supporting shoe one, the inside slip of holding tank is inserted and is equipped with supporting shoe two, adjusts and controls the relevant position of bottom plate, folds mould one and mould two, pulls supporting shoe one, drives supporting shoe one and deflects, pulls supporting shoe two after the supporting shoe one deflects to suitable angle, drives supporting shoe two and shifts, when supporting shoe two contacts with supporting ground, places the reinforcing bar that will make into in the inside of the casing that mould one and mould two formed, later pours into the concrete into the inside the casing of mould one and mould two, after waiting for the inside concrete of casing, mould one and mould two are taken apart, with mould two inside prefabricated part, solid to solidify it again to prepare the precast pile of it and to solidify it again.
As a further improvement of the scheme, a plurality of bearing grooves are formed in the inner walls of the first die and the second die in the vertical direction, a stop block is connected to the inner walls of the bearing grooves in a sliding mode, a plurality of pushing springs are fixed to the inner walls of the end portions of the bearing grooves, the other ends of the pushing springs are fixed to the adjacent stop blocks, two ends of the bottom plate are respectively inserted into the adjacent bearing grooves in a sliding mode and are in contact with the adjacent stop blocks, limiting grooves are formed in the inner walls of the two ends of the bearing grooves, limiting blocks sliding in the adjacent limiting grooves are fixed to the two ends of the stop blocks, the bottom plate can be limited through operation of the components, and unused bearing grooves can be plugged.
As a further improvement of the scheme, a bolt II is connected to the outer side of the bottom end of the supporting block II in a threaded manner, a plurality of first thread grooves are formed in one side, close to the adjacent bolt II, of the supporting block II in the threaded manner, a fixing block III is fixed to the outer side of the supporting block I, a locating plate is hinged to the outer side of the fixing block III, a bolt III is connected to the movable end of the locating plate in a threaded manner, a plurality of second thread grooves are formed in the outer sides of the die I and the die II in a threaded manner in a vertical manner, the bolt III is connected to the inner side of the adjacent thread grooves, when the corresponding position of the supporting block II is required to be adjusted, the bolt II is driven to move, after the bolt II is separated from the inner side of the thread groove I, the supporting block II is pulled, the supporting block II is driven to move, after the supporting block II is slid to a proper position, the bolt II is driven to move, when the bolt II enters the inner side of the adjacent thread groove I, the corresponding position of the supporting block II is hinged to the locating plate, the corresponding position of the locating plate is fixed, when the corresponding position of the supporting block I is adjusted, the bolt II is rotated, the bolt III can be driven to move to the corresponding position of the supporting block II, when the bolt III is driven to move the corresponding position of the supporting block II, and the bolt II is driven to move to the corresponding position of the bolt II, and the bolt II is driven to move the bolt II to the corresponding position of the bolt II.
As a further improvement of the scheme, the bottoms of the first die and the second die are provided with loading grooves, two end parts of the supporting blocks positioned outside the containing grooves slide inside the adjacent loading grooves, and the second supporting blocks can be stored through the loading grooves, so that the stability of the second supporting blocks is improved.
As a further improvement of the scheme, the outer side of the second die is in threaded connection with a plurality of first bolts, the first die is provided with a plurality of through holes, the tail end of each first bolt penetrates through the adjacent through hole and is in threaded sleeve connection with a fixing sleeve, and the second die can be fixed together through threaded matching of the first bolts and the fixing sleeve.
As a further improvement of the scheme, the diameter of the fixing sleeve is larger than the aperture of the perforation, the diameter of the head of the bolt is larger than the aperture of the perforation, and the fixing sleeve with the diameter larger than the aperture of the perforation can avoid sliding in the perforation, so that the stability of the fixing sleeve is improved.
As a further improvement of the scheme, the length of the second supporting block is larger than the depth of the accommodating groove, the length of the second supporting block is larger than the length of the first supporting block, and the second supporting block can be prevented from completely entering the accommodating groove through the second supporting block with the length larger than the depth of the accommodating groove.
As a further improvement of the scheme, the positioning plate is arranged in a staggered mode with the first die and the second die, the lengths of the first die and the second die are larger than those of the positioning plate, and deflection of the positioning plate caused by interference of the first die and the second die with the positioning plate can be avoided.
Compared with the prior art, the utility model has the beneficial effects that:
through mould one, mould two, the bottom plate, supporting shoe one, rigid coupling piece two, the holding tank, supporting shoe two, bolt one, the joint piece three, the locating plate, bolt three, the cooperation work of loading channel, the dog, push spring and rigid coupling piece one, can carry out quick preparation to solid recycled concrete precast pile, and can carry out the adaptability to the device according to the preparation demand, avoid the workman saw cut out unnecessary template on the solid recycled concrete precast pile device, convenient to use, and can facilitate the use person accomodate the supporting component of idle device, thereby facilitate the use person carries the device and moves.
In conclusion, the utility model has reasonable structure, can rapidly prepare the solid recycled concrete precast pile, can adaptively regulate and control the device, can facilitate the user to store the support component of the idle device, and has high working performance and convenient use.
Drawings
FIG. 1 is a schematic structural view of a solid recycled concrete precast pile apparatus;
FIG. 2 is an elevation view of a solid recycled concrete precast pile apparatus;
FIG. 3 is a schematic view of a first support block in a solid recycled concrete precast pile apparatus;
fig. 4 is an enlarged schematic view of the structure at a in fig. 1.
Main symbol description:
1. a first die; 2. a second die; 3. a bottom plate; 4. a first supporting block; 5. a second fixing block; 6. a receiving groove; 7. a second supporting block; 8. a first bolt; 9. a third fixing block; 10. a positioning plate; 11. a third bolt; 12. a carrying groove; 13. a stop block; 14. a pushing spring; 15. and a first fixing block.
Detailed Description
The present utility model will be further described with reference to the accompanying drawings and detailed description, wherein it is to be understood that, on the premise of no conflict, the following embodiments or technical features may be arbitrarily combined to form new embodiments.
Example 1:
referring to fig. 1, a solid recycled concrete precast pile device of the present embodiment includes a first mold 1 and a second mold 2, a bottom plate 3 is disposed between the first mold 1 and the second mold 2, a first support block 4 is disposed on the outer sides of the first mold 1 and the second mold 2, a first fixing block 15 fixed on the first mold 1 is hinged to two sides of the top end of the first support block 4 disposed on the outer side of the first mold 1, a second fixing block 5 fixed on the second mold 2 is hinged to two sides of the top end of the first support block 4 disposed on the outer side of the second mold 2, a receiving groove 6 is provided at the bottom end of the first support block 4, and a second support block 7 is slidably inserted in the receiving groove 6.
The implementation principle of the solid recycled concrete precast pile device in the embodiment of the utility model is as follows: when the solid recycled concrete precast pile is required to be prepared, the corresponding position of the bottom plate 3 can be regulated and controlled according to the preparation requirement, after the corresponding position of the bottom plate 3 is regulated and controlled, the corresponding heights of the first die 1 and the second die 2 can be regulated and controlled, the first supporting block 4 is pulled to drive the first supporting block 4 to deflect, after the first supporting block 4 is deflected to a proper angle, the second supporting block 7 is pulled to drive the second supporting block 7 to displace, when the second supporting block 7 is contacted with the supporting ground, the first die 1 and the second die 2 are firmly fixed on the ground, at this time, the rolled steel bars can be placed in the shell formed by the first die 1 and the second die 2 according to the length of the solid recycled concrete precast pile, then concrete is injected into the shell formed by the first die 1 and the second die 2, after the concrete in the shell is solidified, the first die 1 and the second die are disassembled, the prefabricated members in the first die 1 and the second die are taken out, and the solid recycled concrete precast pile is prepared.
Example 2:
with reference to fig. 4, this embodiment is further improved on the basis of embodiment 1 in that: the inner walls of the first die 1 and the second die 2 are vertically provided with a plurality of bearing grooves 12, the inner walls of the bearing grooves 12 are in sliding connection with a stop block 13, the inner walls of the end parts of the bearing grooves 12 are fixedly provided with a plurality of pushing springs 14, the other ends of the pushing springs 14 are fixedly arranged on the adjacent stop blocks 13, the two ends of the bottom plate 3 are respectively in sliding insertion with the inner parts of the adjacent bearing grooves 12 and are in contact with the adjacent stop blocks 13, limiting grooves are formed in the inner walls of the two ends of the bearing grooves 12, limiting blocks which are in sliding connection with the inner walls of the adjacent limiting grooves are fixedly arranged at the two ends of the stop blocks 13, when the corresponding positions of the bottom plate 3 are required to be adjusted, one end of the bottom plate 3 can be inserted into the corresponding bearing groove 12 of the first die 1, the second die 2 can be folded with the first die 1 after one end of the bottom plate 3 is inserted into the bearing groove 12 of the first die 1, the other end of the bottom plate 3 is inserted into the bearing groove 12 of the second die 2, the corresponding positions of the bottom plate 3 are fixed, the rest bearing grooves 12 are pushed by the elasticity of the pushing springs 14, the stop blocks 13 are pushed to displace, when the outer sides of the stop blocks 13 are flush with the inner walls of the first die 1 and the second die 2, limiting blocks are in parallel and level with the inner walls of the limiting grooves, one end of the limiting blocks 12 can be prevented from being carried out by limiting the limiting grooves 12, and the rest bearing grooves 12.
Example 3:
with reference to fig. 2 and 3, this embodiment is further improved on the basis of embodiment 1 in that: the outside threaded connection of supporting shoe one 4 bottom has the bolt two, a plurality of thread grooves have been seted up to one side that the supporting shoe two 7 is close to adjacent bolt two, bolt two threaded connection is inside adjacent thread groove one, outside fixed connection piece three 9 of supporting shoe one 4, the outside of fixed connection piece three 9 articulates there is locating plate 10, the expansion end threaded connection of locating plate 10 has bolt three 11, a plurality of thread grooves two have been seted up along vertical in the outside of mould one 1 and mould two 2, bolt three 11 threaded connection is inside adjacent thread groove two, when need adjust the relevant position of supporting shoe two 7, rotatable bolt two, drive bolt two and displace, after the bolt two breaks away from the inside of thread groove one, drive supporting shoe two 7 and displace, after supporting shoe two 7 slides to suitable position, rotate bolt two, drive bolt two and displace, after the bolt two gets into adjacent thread groove one inside, the relevant position of this moment supporting shoe two 7 is fixed, when the corresponding angle of adjusting supporting shoe one 4, rotatable bolt three 11, drive three 11 and displace the corresponding bolt 11 and be carried out the corresponding position of three, the bolt 11 is rotated to the corresponding position of supporting shoe 10, can be rotated to the bolt two after the corresponding locating plate 11, the bolt 11 is rotated to the inside the corresponding bolt 11, the bolt is deflected, the bolt is rotated to the corresponding position of the three is rotated to the supporting shoe 10, and the bolt is rotated to displace when the inside the corresponding position of supporting shoe 10.
The loading grooves are formed in the bottoms of the first die 1 and the second die 2, the end parts of the second supporting blocks 7 located outside the containing grooves 6 slide inside the adjacent loading grooves, the second supporting blocks 7 can be stored through the loading grooves, and the stability of the second supporting blocks 7 is improved.
The outside threaded connection of mould two 2 has a plurality of bolts one 8, and mould one 1 has seted up a plurality of perforation, and the tail end of bolt one 8 runs through adjacent perforation to the screw thread has cup jointed fixed cover, through the screw thread cooperation of bolt one 8 and fixed cover, can fix mould two 2 and mould 1 together.
The diameter of the fixed sleeve is larger than the aperture of the perforation, the diameter of the head of the first bolt 8 is larger than the aperture of the perforation, and the fixed sleeve can be prevented from sliding in the perforation through the fixed sleeve with the diameter larger than the aperture of the perforation, so that the stability of the fixed sleeve is improved.
The length of the second supporting block 7 is greater than the depth of the accommodating groove 6, the length of the second supporting block 7 is greater than the length of the first supporting block 4, and the second supporting block 7 can be prevented from completely entering the accommodating groove 6 through the second supporting block 7 with the length greater than the depth of the accommodating groove 6.
The positioning plate 10 is arranged in a staggered mode with the first die 1 and the second die 2, the lengths of the first die 1 and the second die 2 are larger than those of the positioning plate 10, and the first die 1 and the second die 2 which are arranged in a staggered mode with the positioning plate 10 can avoid the deflection of the positioning plate 10 caused by interference of the first die 1 and the second die 2.
Working principle: when the solid recycled concrete precast pile is needed to be prepared, the corresponding position of the bottom plate 3 can be regulated and controlled according to the preparation requirement, one end of the bottom plate 3 is inserted into the corresponding bearing groove 12 of the first die 1, after one end of the bottom plate 3 is inserted into the bearing groove 12 of the first die 1, the second die 2 and the first die 1 can be folded, after the other end of the bottom plate 3 is inserted into the bearing groove 12 of the second die 2, the corresponding position of the bottom plate 3 is fixed, when the first die 1 and the second die 2 are folded, after the first bolt 8 on the second die 2 penetrates through the adjacent perforation of the first die 1, the fixing sleeve can be aligned with the first bolt 8, the fixing sleeve is rotated, when the fixing sleeve is contacted with the first die 1, the first die 1 and the second die 2 can be fixed together, then the corresponding heights of the first die 1 and the second die 2 can be regulated, the third bolt 11 is rotated, and the third bolt 11 is driven to displace, when the third bolt 11 is separated from the inside of the corresponding thread groove II, the first supporting block 4 can be pulled to drive the first supporting block 4 to deflect, when the first supporting block 4 deflects to an adaptive angle, the positioning plate 10 can be pulled to drive the positioning plate 10 to deflect, when the third bolt 11 on the positioning plate 10 corresponds to the adjacent thread groove II, the third bolt 11 can be rotated to drive the third bolt 11 to displace, when the third bolt 11 enters the inside of the corresponding thread groove II, the corresponding angle of the first supporting block 4 is fixed, then the second bolt can be rotated to drive the second bolt to displace, when the second bolt is separated from the inside of the thread groove I, the second supporting block 7 is pulled to drive the second supporting block 7 to displace, when the second supporting block 7 contacts with the supporting ground, the second bolt is rotated to drive the second bolt to displace, when the second bolt enters the inside of the adjacent thread groove I, the corresponding position of the second supporting block 7 is fixed, at this time, through the support of supporting shoe one 4 and supporting shoe two 7, mould one 1 and mould two 2 are firm in ground, can place the reinforcement that the bundle was made at this moment inside the casing that mould one 1 and mould two 2 formed, afterwards pour into the concrete into inside the casing that mould one 1 and mould two 2 formed into, wait for the inside concrete of casing to solidify the back, disassemble mould one 1 and mould two, take out the prefabrication part in mould one and mould two, it is again to maintenance, solid recycled concrete precast pile preparation is accomplished at this moment, and when filling concrete, remaining loading groove 12, through the elasticity of pushing spring 14, promote dog 13 and carry out the displacement, when the outside of dog 13 and the inner wall parallel and level of mould one 1 and mould two 2, limit through limiting block and limiting groove at this moment, limit dog 13 can be prevented from sliding out the inside of loading groove 12, through dog 13, can seal remaining loading groove 12, avoid the concrete of pouring to go into remaining loading groove 12 inside.
The above embodiments are merely preferred embodiments of the present utility model, and the scope of the present utility model is not limited thereto, but any insubstantial changes and substitutions made by those skilled in the art on the basis of the present utility model are intended to be within the scope of the present utility model as claimed.

Claims (8)

1. The utility model provides a solid recycled concrete precast pile device, includes mould one and mould two, its characterized in that, be equipped with the bottom plate between mould one and the mould two, the outside of mould one and mould two all is equipped with supporting shoe one, and the both sides on supporting shoe one top in the mould one outside articulates there is the rigid coupling piece one of fixing on mould one, and the both sides on supporting shoe one top in the mould two outsides articulates there is the rigid coupling piece two of fixing on mould two, the holding tank has been seted up to the bottom of supporting shoe one, the inside slip of holding tank is inserted and is equipped with supporting shoe two.
2. The solid recycled concrete precast pile device as defined in claim 1, wherein a plurality of bearing grooves are vertically formed in the inner walls of the first die and the second die, a stop block is connected in a sliding manner in the bearing grooves, a plurality of pushing springs are fixed on the inner walls of the end parts of the bearing grooves, the other ends of the pushing springs are fixed on the adjacent stop blocks, two ends of the bottom plate are respectively inserted in the adjacent bearing grooves in a sliding manner and are in contact with the adjacent stop blocks, limiting grooves are formed in the inner walls of the two ends of the bearing grooves, and limiting blocks sliding in the adjacent limiting grooves are fixed at the two ends of the stop blocks.
3. The solid recycled concrete precast pile device according to claim 1, wherein a second bolt is connected to the outer side of the bottom end of the first supporting block in a threaded mode, a plurality of first thread grooves are formed in one side, close to the second adjacent bolt, of the second supporting block in a threaded mode, the second bolt is connected to the inner portion of the first adjacent thread groove in a threaded mode, a third fixing block is fixed to the outer side of the first supporting block, a positioning plate is hinged to the outer side of the third fixing block, a third bolt is connected to the movable end of the positioning plate in a threaded mode, a plurality of second thread grooves are formed in the outer sides of the first die and the second die in a threaded mode in a vertical mode, and the third bolt is connected to the inner portion of the second adjacent thread groove in a threaded mode.
4. A solid recycled concrete precast pile apparatus as defined in claim 1, wherein the bottoms of the first and second molds are provided with loading grooves, and the two ends of the supporting block outside the receiving groove slide inside the adjacent loading grooves.
5. A solid recycled concrete precast pile device as defined in claim 1, wherein a plurality of first bolts are connected to the outer side of the second die in a threaded manner, a plurality of through holes are formed in the first die, and the tail ends of the first bolts penetrate through the adjacent through holes and are sleeved with fixing sleeves in a threaded manner.
6. A solid recycled concrete precast pile apparatus as defined in claim 5, in which the diameter of the fixing sleeve is greater than the diameter of the through hole, and the diameter of the bolt-head is greater than the diameter of the through hole.
7. A solid recycled concrete precast pile apparatus as defined in claim 1, wherein the second support block has a length greater than the depth of the receiving groove and a length greater than the first support block.
8. A solid recycled concrete precast pile assembly as defined in claim 3, wherein the locating plate is arranged in a staggered manner with respect to the first and second dies, and the first and second dies are longer than the locating plate.
CN202321589744.2U 2023-06-21 2023-06-21 Solid recycled concrete precast pile device Active CN219987953U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321589744.2U CN219987953U (en) 2023-06-21 2023-06-21 Solid recycled concrete precast pile device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321589744.2U CN219987953U (en) 2023-06-21 2023-06-21 Solid recycled concrete precast pile device

Publications (1)

Publication Number Publication Date
CN219987953U true CN219987953U (en) 2023-11-10

Family

ID=88612544

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321589744.2U Active CN219987953U (en) 2023-06-21 2023-06-21 Solid recycled concrete precast pile device

Country Status (1)

Country Link
CN (1) CN219987953U (en)

Similar Documents

Publication Publication Date Title
CN114991303B (en) Grouting-free sleeve assembly integral beam column structure UHPC connection construction method
CN112942867A (en) Automatic material loading filled type equipment of building a wall
CN219987953U (en) Solid recycled concrete precast pile device
CN216239746U (en) Narrow and small space concrete structure template is propped up and is established device
CN106050271B (en) A kind of tunnel ditch die set device and its construction method
CN115897996B (en) Concrete form for house building construction
CN106089257B (en) A kind of tunnel ditch cable trough construction trolley
CN112609881A (en) Assembled coincide floor
CN210947702U (en) Aluminum formwork device for building
CN217974925U (en) Light partition wall connection structure
CN114654560B (en) Baffle and baffle automatic regulating apparatus for panel mould
CN109025258B (en) Formwork moving device for creeping formwork and construction method thereof
CN217252470U (en) Quick ligature device of steel reinforcement cage
CN206035502U (en) Cable die carrier device and ditch cable duct construction trolley car for tunnel
CN215978489U (en) Constructional column pouring opening feeding device
CN221502007U (en) Quick supporting construction of underground connection wall
CN116044041B (en) Prefabricated shear wall assembly structure and assembly method
CN113550475B (en) Prefabricated floor slab mounting structure
CN112794245B (en) Transport fork truck
CN221027200U (en) Construction reinforcement cage lifting device
CN219034049U (en) Building templates convenient to drawing of patterns
CN213539758U (en) A reinforcement structure for superelevation space
CN221372192U (en) Novel construction equipment of cast-in-place concrete stiff composite pile
CN214832011U (en) Box girder inner cavity diaphragm minimally invasive reinforcement construction equipment
CN221096551U (en) Combined hydraulic steel template for tunnel cable trench

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant