Quick erection device of building pile foundation detection benchmark stake Download PDFInfo
- Publication number
- CN219909097U CN219909097U CN202321156467.6U CN202321156467U CN219909097U CN 219909097 U CN219909097 U CN 219909097U CN 202321156467 U CN202321156467 U CN 202321156467U CN 219909097 U CN219909097 U CN 219909097U
- Authority
- CN
- China
- Prior art keywords
- drill
- pile foundation
- assembly
- support rod
- erection device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000001514 detection method Methods 0.000 title claims abstract description 22
- 238000005553 drilling Methods 0.000 claims abstract description 19
- 230000002093 peripheral effect Effects 0.000 claims abstract description 8
- 239000004568 cement Substances 0.000 claims abstract description 5
- 238000009434 installation Methods 0.000 claims description 6
- 238000000034 method Methods 0.000 abstract description 7
- 238000012544 monitoring process Methods 0.000 abstract description 2
- 230000000712 assembly Effects 0.000 abstract 1
- 238000000429 assembly Methods 0.000 abstract 1
- 235000017166 Bambusa arundinacea Nutrition 0.000 description 5
- 235000017491 Bambusa tulda Nutrition 0.000 description 5
- 241001330002 Bambuseae Species 0.000 description 5
- 235000015334 Phyllostachys viridis Nutrition 0.000 description 5
- 239000011425 bamboo Substances 0.000 description 5
- 230000007547 defect Effects 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 230000003750 conditioning effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000013011 mating Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
The utility model discloses a rapid erection device for a building pile foundation detection reference pile, which comprises the following components: the drilling device comprises an assembly seat and a plurality of adjusting assemblies arranged on the peripheral side surface of the assembly seat, wherein an assembly groove is formed in the top surface of the assembly seat, a through hole is formed in the bottom surface of the assembly groove, a drilling device is placed in the assembly groove, the output end of the drilling device is movably connected with a rotating shaft barrel, the bottom end of the rotating shaft barrel is slidably connected with a drill rod, and a drill bit is arranged at the bottom end of the drill rod; the adjusting assembly includes: the first support rod is hinged to the outer peripheral side face of the assembly seat, the first support rod is connected with the upper end of the rotating frame in a threaded mode, the lower end of the rotating frame is connected with the second support rod in a threaded mode, the second support rod is hinged to the fixing plate through a pin, and cement nails are arranged on the bottom face of the fixing plate. The drill bit is quickly buried into the pile foundation through the drill, so that the efficiency is higher and the deviation angle is lower compared with the traditional hammering burying method. And through rotating the swivel mount, supplementary adjustment assembly seat and the deviation angle of horizontal plane effectively ensure detection device monitoring data's reliability.
Description
Technical Field
The utility model relates to the technical field of building pile foundation detection, in particular to a device for quickly erecting a building pile foundation detection reference pile.
Background
Pile foundation is the foundation of building construction, obtains extensive application in all kinds of building engineering, and the quality and the stability of pile foundation need utilize detection device to detect it, makes it can be applied to the high-rise of building. The patent number is: the patent name of CN213062005U is: the utility model relates to a rapid erection device for a pile foundation detection reference pile, which comprises a bracket, wherein a fixing pipe in the vertical direction is fixedly arranged on the bracket, a screw rod is connected with the inner thread of the fixing pipe, the free end of the screw rod extends out of the fixing pipe and is fixedly provided with a supporting plate, a motor is fixedly arranged on the bracket, an output shaft of the motor is arranged in parallel with the screw rod, an output shaft of the motor is coaxially connected with a spiral gear meshed with the screw rod, a control switch is electrically connected with the motor, and a clamping mechanism capable of clamping the reference pile is detachably connected to the lower surface of the supporting plate. Through the rotation of motor control screw rod, bury the reference pile underground, replaced the working process of artificial hammering reference pile among the prior art, the installation is more accurate moreover, has reduced intensity of labour, and the practicality is strong.
However, the above-mentioned erection device still has certain use drawbacks for certain use cases: on the one hand, the whole structural design of the erection device is unreasonable, the screw gear drives the screw to rotate, the screw is easy to form self-locking with the screw gear after contacting the pile foundation, further downward movement of the screw is difficult to realize, and the depth of the drill bit buried in the pile foundation cannot be adjusted according to requirements. The erection device cannot assist in adjusting the deviation angle in the erection process of the reference pile, and the precision of the installation of the reference pile is poor. Therefore, a more specialized quick-install device is needed to solve the above-mentioned drawbacks.
Disclosure of Invention
The utility model overcomes the defects of the prior art and provides a device for quickly erecting a building pile foundation detection reference pile.
In order to achieve the above purpose, the utility model adopts the following technical scheme: quick erection device of building pile foundation detection benchmark stake includes: the assembly seat and set up a plurality of adjusting part of assembly seat periphery side, the assembly seat top surface sets up the assembly groove, the assembly groove bottom surface sets up the through-hole, place the perforator in the assembly groove, perforator output swing joint axis of rotation section of thick bamboo, axis of rotation section of thick bamboo bottom sliding connection drilling rod, the drilling rod bottom sets up the drill bit.
The adjustment assembly includes: the first support rod is hinged to the outer peripheral side face of the assembly seat, the first support rod is connected with the upper end of the rotating frame in a threaded mode, the lower end of the rotating frame is connected with the second support rod in a threaded mode, the second support rod is hinged to the fixing plate through a pin, and cement nails are arranged on the bottom face of the fixing plate.
In a preferred embodiment of the utility model, the bottom end of the rotating shaft cylinder is integrally provided with a mounting block, the side surface of the mounting block is provided with a mounting groove, and a clamping column is arranged in the mounting groove.
In a preferred embodiment of the utility model, a connecting part is integrally arranged at the middle position of the clamping column, and the connecting part is connected with the side surface of the mounting groove through a traction spring.
In a preferred embodiment of the present utility model, the side surface of the drill rod is provided with a plurality of clamping grooves in a linear array, and the clamping grooves can be mutually clamped with the clamping columns.
In a preferred embodiment of the utility model, the top surface of the assembly seat is rotatably connected with a locking disc, and a matching hole is arranged in the center of the locking disc, and can be placed into the drill in the matching hole.
In a preferred embodiment of the utility model, a plurality of guiding and limiting strips are arranged on the peripheral side surface of the drill, a plurality of guiding and limiting grooves are arranged on the inner side surface of the assembly groove, and the guiding and limiting strips are in sliding connection with the guiding and limiting grooves.
The utility model solves the defects existing in the background technology, and has the following beneficial effects:
(1) Compared with the traditional hammering embedding method, the drilling machine has the advantages that the efficiency is higher, the deviation angle is lower, the clamping column is matched with the clamping groove on the drill rod, and the clamping column is pulled to adjust the total length of the rotating shaft barrel and the drill rod according to the requirement, so that the depth of the drilling machine embedded into the pile foundation is properly changed, and the practicability is higher.
(2) In the process that the drill bit enters the pile foundation, the total length of the first support rod and the second support rod is finely adjusted by rotating the rotating frame, so that the whole assembly seat is in a horizontal state, further, the detection device on the assembly seat can be ensured to be kept in the horizontal state as much as possible, and the reliability of the detection device for monitoring data is effectively ensured.
(3) According to the utility model, the guide limit strips and the guide limit grooves are matched with each other, so that the stability of the drill during operation can be ensured, and the accuracy of the drill bit entering the pile foundation is further ensured, on the other hand, the drill is locked through the locking disc, and the stability of the whole reference pile is further facilitated.
Drawings
The utility model is further described below with reference to the drawings and examples;
FIG. 1 is a perspective view of a preferred embodiment of the present utility model;
FIG. 2 is a schematic cross-sectional view of a preferred embodiment of the present utility model;
FIG. 3 is an exploded view of the preferred embodiment of the present utility model after concealing the conditioning assembly;
fig. 4 is an enlarged schematic view at a in fig. 2.
Concretely, 1, an assembling seat; 2. an assembly groove; 3. a through hole; 4. a drill; 5. a rotating shaft cylinder; 6. a drill rod; 7. a drill bit; 8. a first support bar; 9. a rotating frame; 10. a second support bar; 11. a fixing plate; 12. a cement nail; 13. a mounting block; 14. a clamping column; 15. a connection part; 16. a pulling spring; 17. a clamping groove; 18. a locking plate; 19. a mating hole; 20. guiding limit strips; 21. a guide limit groove; 22. a hand grip; 23. and (5) a level gauge.
Detailed Description
The utility model will now be described in further detail with reference to the drawings and examples, which are simplified schematic illustrations of the basic structure of the utility model, which are presented only by way of illustration, and thus show only the structures that are relevant to the utility model.
As shown in fig. 1, a device for quickly erecting a building pile foundation detection reference pile comprises: the assembly seat 1 and set up a plurality of adjusting part at assembly seat 1 periphery side, assembly seat 1 top surface sets up assembly groove 2, assembly groove 2 bottom surface sets up through-hole 3, place the drilling equipment 4 in the assembly groove 2, drilling equipment 4 top surface symmetry sets up two handheld handles 22, drilling equipment 4 output swing joint axis of rotation section of thick bamboo 5, axis of rotation section of thick bamboo 5 bottom sliding connection drilling rod 6, drilling rod 6 bottom sets up drill bit 7, buries drill bit 7 fast in the pile foundation through drilling equipment 4, compare in traditional hammering buries, efficiency is higher, the deviation angle is lower.
As shown in fig. 2, the adjustment assembly includes: the first support rod 8 is hinged to the outer peripheral side face of the assembly seat 1, the first support rod 8 is connected with the upper end of the rotating frame 9 in a threaded mode, the lower end of the rotating frame 9 is connected with the second support rod 10 in a threaded mode, the second support rod 10 is hinged to the fixing plate 11 through a pin, and cement nails 12 are arranged on the bottom face of the fixing plate 11.
In a preferred embodiment of the utility model, the top surface of the assembly seat 1 is rotatably connected with the locking disc 18, the top surface of the locking disc 18 is embedded into the level meter 23, the center of the locking disc 18 is provided with the matching hole 19, the matching hole 19 can be placed into the drill 4, and when the locking disc 18 is rotated for a certain angle, the bottom surface of the locking disc 18 is attached to the top surface of the drill 4 to lock the drill 4, so that the stability of the whole foundation pile is facilitated.
In a preferred embodiment of the present utility model, during the process of entering the pile foundation by the drill bit 7, the total length of the first support bar 8 and the second support bar 10 is finely adjusted by rotating the rotating frame 9, and the deviation angle between the assembly seat 1 and the horizontal plane is adjusted in an auxiliary manner according to the state of the level gauge 23, so that the assembly seat 1 is in a horizontal state as a whole, further, the detection device on the assembly seat 1 can be ensured to maintain the horizontal state as much as possible, and the reliability of the data monitored by the detection device is effectively ensured.
As shown in fig. 4, the bottom end of the rotating shaft barrel 5 is integrally provided with a mounting block 13, the side surface of the mounting block 13 is provided with a mounting groove, the mounting groove is internally provided with a clamping column 14, the side surface of the drill rod 6 is provided with a plurality of clamping grooves 17 in a linear array mode, the clamping grooves 17 can be mutually clamped with the clamping columns 14, the middle position of the clamping columns 14 is integrally provided with a connecting part 15, and the connecting part 15 is connected with the side surface of the mounting groove through a traction spring 16. Through the cooperation of draw-in groove 17 on draw-in column 14 and the drilling rod 6, pulling draw-in column 14, can adjust the total length of axis of rotation section of thick bamboo 5 and drilling rod 6 as required to the suitable degree of depth that buries into the pile foundation of drill bit 7, the practicality is stronger.
As shown in fig. 3, a plurality of guiding and limiting strips 20 are arranged on the peripheral side surface of the drill 4, a plurality of guiding and limiting grooves 21 are arranged on the inner side surface of the assembly groove 2, and the guiding and limiting strips 20 are in sliding connection with the guiding and limiting grooves 21. Through mutually supporting between direction spacing 20 and the direction spacing groove 21, can ensure the stability of drilling ware 4 when the operation, and then ensure the drill bit 7 accuracy when getting into the pile foundation.
The working principle of the utility model is as follows: gradually placing the driller 4 into the assembly groove 2, opening the driller 4, holding the hand grip 22 by two hands, drilling the pile foundation by the drill bit 7, quickly entering the pile foundation by pressing the driller 4 in the drilling process, attaching the bottom surface of the driller 4 to the bottom surface of the assembly groove 2, rotating the locking disc 18 to lock the driller 4, and finally rotating each rotating frame 9 until the level gauge 23 on the assembly seat 1 is completely in a horizontal state, thereby completing erection of the reference pile, and accurately fixing the detection equipment on the assembly seat 1.
The above-described preferred embodiments according to the present utility model are intended to suggest that, from the above description, various changes and modifications can be made by the person skilled in the art without departing from the scope of the technical idea of the present utility model. The technical scope of the present utility model is not limited to the description, but must be determined according to the scope of claims.
Claims (6)
1. Quick erection device of building pile foundation detection benchmark stake includes: the drilling machine is characterized in that an assembly groove (2) is formed in the top surface of the assembly seat (1), a through hole (3) is formed in the bottom surface of the assembly groove (2), a drill (4) is placed in the assembly groove (2), the output end of the drill (4) is movably connected with a rotating shaft barrel (5), the bottom end of the rotating shaft barrel (5) is slidably connected with a drill rod (6), and a drill bit (7) is arranged at the bottom end of the drill rod (6);
the adjustment assembly includes: the first support rod (8) is hinged to the outer peripheral side face of the assembly seat (1), the first support rod (8) is connected with the upper end of the rotating frame (9) in a threaded mode, the lower end of the rotating frame (9) is connected with the second support rod (10) in a threaded mode, the second support rod (10) is connected with the fixing plate (11) in a hinged mode through a pin, and cement nails (12) are arranged on the bottom face of the fixing plate (11).
2. The rapid erection device for building pile foundation detection reference piles according to claim 1, wherein: the installation block (13) is integrally arranged at the bottom end of the rotating shaft barrel (5), an installation groove is formed in the side face of the installation block (13), and a clamping column (14) is arranged in the installation groove.
3. The rapid erection device for building pile foundation detection reference piles according to claim 2, wherein: the connecting part (15) is integrally arranged at the middle position of the clamping column (14), and the connecting part (15) is connected with the side surface of the mounting groove through the traction spring (16).
4. A rapid erection device for building pile foundation detection reference piles according to claim 3, wherein: the side surface of the drill rod (6) is provided with a plurality of clamping grooves (17) in a linear array mode, and the clamping grooves (17) can be mutually clamped with the clamping columns (14).
5. The rapid erection device for building pile foundation detection reference piles according to claim 1, wherein: the top surface of the assembly seat (1) is rotationally connected with a locking disc (18), a matching hole (19) is formed in the center of the locking disc (18), and the matching hole (19) can be placed into the drill (4).
6. The rapid erection device for building pile foundation detection reference piles according to claim 1, wherein: the outer peripheral side face of the drill (4) is provided with a plurality of guiding limit strips (20), the inner side face of the assembly groove (2) is provided with a plurality of guiding limit grooves (21), and the guiding limit strips (20) are in sliding connection with the guiding limit grooves (21).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202321156467.6U CN219909097U (en) | 2023-05-15 | 2023-05-15 | Quick erection device of building pile foundation detection benchmark stake |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202321156467.6U CN219909097U (en) | 2023-05-15 | 2023-05-15 | Quick erection device of building pile foundation detection benchmark stake |
Publications (1)
Publication Number | Publication Date |
---|---|
CN219909097U true CN219909097U (en) | 2023-10-27 |
Family
ID=88440825
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202321156467.6U Active CN219909097U (en) | 2023-05-15 | 2023-05-15 | Quick erection device of building pile foundation detection benchmark stake |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN219909097U (en) |
-
2023
- 2023-05-15 CN CN202321156467.6U patent/CN219909097U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN113049298B (en) | Adjust nimble exploration development sampling device | |
CN110005343A (en) | A kind of geotechnical engineering investigation drilling rig | |
CN213336860U (en) | Geotechnical sampling mechanical equipment for civil engineering | |
CN116929924A (en) | Concrete bonding strength testing device and testing method thereof | |
CN109487774B (en) | Pre-drilling type lateral pressure test drilling equipment and hole forming method thereof | |
CN219909097U (en) | Quick erection device of building pile foundation detection benchmark stake | |
CN219387804U (en) | Drilling position stake marking device | |
CN113295451A (en) | Exploration sampling device suitable for under-consolidated soft land | |
CN219638767U (en) | Directional deviation preventing device for geological drilling | |
CN217206300U (en) | Drilling rig for geotechnical engineering investigation | |
CN214462770U (en) | A environmental protection reinforcing apparatus for supporting wall body | |
CN212427092U (en) | Ground anchor of assembled steel construction elevator | |
CN215718470U (en) | Drilling device for geotechnical engineering construction | |
CN210442132U (en) | Highway construction quality sampling device | |
CN210033485U (en) | Underground factory building rock anchor beam drilling positioning device | |
CN218912795U (en) | Foundation pit construction soil perforating device | |
CN217380446U (en) | Mine is drill bit for rig convenient to quick assembly disassembly | |
CN220977969U (en) | Bored pile top elevation control equipment | |
CN221442514U (en) | Geological survey bores probe | |
CN221169555U (en) | Ground stress testing device | |
CN220474116U (en) | Be applied to fixed establishment on geological disaster early warning equipment | |
CN219137672U (en) | Ground anchor device for building construction | |
CN217875222U (en) | Hydraulic engineering water flow velocity measuring device | |
CN215830437U (en) | Exploration equipment used in ore mining | |
CN221255746U (en) | Civil engineering pre-buried component |
Legal Events
Date | Code | Title | Description |
---|---|---|---|