CN219793671U - Bridge floor construction hanging fence operation platform - Google Patents

Bridge floor construction hanging fence operation platform Download PDF

Info

Publication number
CN219793671U
CN219793671U CN202321204831.1U CN202321204831U CN219793671U CN 219793671 U CN219793671 U CN 219793671U CN 202321204831 U CN202321204831 U CN 202321204831U CN 219793671 U CN219793671 U CN 219793671U
Authority
CN
China
Prior art keywords
frame
operation platform
hanging
sides
deck construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321204831.1U
Other languages
Chinese (zh)
Inventor
张妍
郭德群
丛晓亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinan Construction Equipment Installation Co ltd
Original Assignee
Jinan Construction Equipment Installation Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinan Construction Equipment Installation Co ltd filed Critical Jinan Construction Equipment Installation Co ltd
Priority to CN202321204831.1U priority Critical patent/CN219793671U/en
Application granted granted Critical
Publication of CN219793671U publication Critical patent/CN219793671U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a bridge deck construction hanging fence operation platform, and belongs to the field of building construction. The technical proposal is as follows: including shearing fork lift, the support frame of setting on shearing fork lift, be provided with transverse adjustment mechanism on the support frame, be provided with lift hanging flower basket subassembly on the transverse adjustment mechanism, the support frame is including setting up the perpendicular vaulting pole in shearing fork lift mesa four corners department, and perpendicular vaulting pole tip is provided with the top frame, and the top frame side is provided with side frame, is provided with transverse adjustment mechanism on the side frame. The beneficial effects of the utility model are as follows: simple structure, convenient to use are applicable to construction such as bridge guardrail outside, are applicable to the guardrail of co-altitude simultaneously, and it is convenient to remove to but both sides construction simultaneously has reduced engineering time, when having improved work efficiency greatly, has higher security.

Description

Bridge floor construction hanging fence operation platform
Technical Field
The utility model relates to the field of building construction, in particular to a bridge deck construction hanging fence operation platform.
Background
When bridge deck guardrail is under construction, need operate in the guardrail outside at the in-process such as reinforcement ligature machine template installation, to most bridges, the clearance is great under the bridge, and guardrail outside operation just belongs to high altitude construction, exists very big danger.
Disclosure of Invention
The utility model aims to provide the bridge deck construction hanging rail operation platform which has the advantages of simple structure, convenience in use, suitability for construction of the outer sides of bridge guardrails and the like, convenience in movement, capability of simultaneously constructing on two sides, reduction in construction time, great improvement in working efficiency and higher safety.
The utility model is realized by the following measures:
the bridge deck construction hanging rail operation platform is characterized by comprising a scissor type lifter and a supporting frame arranged on the scissor type lifter, wherein a transverse adjusting mechanism is arranged on the supporting frame, and a lifting hanging basket assembly is arranged on the transverse adjusting mechanism;
the supporting frame comprises vertical supporting rods arranged at four corners of the table top of the scissor fork type lifter, top frames are arranged at the end parts of the vertical supporting rods, side frames are arranged on the side faces of the top frames, and the lateral adjusting mechanisms are arranged on the side frames;
the transverse adjusting mechanism comprises a pair of sliding rails arranged on two sides of the top of the side frame in the length direction, sliding blocks are arranged on the sliding rails on two sides, and adjusting frames are arranged on the sliding blocks on two sides;
the adjusting frame is provided with an inverted U-shaped mounting frame, and the inverted U-shaped mounting frame is provided with a lifting basket assembly.
The utility model has the specific characteristics that:
the side frame with be provided with the lead screw on the top frame, the lead screw is followed side frame width direction sets up, be provided with driving motor on the top frame, driving motor's motor shaft with lead screw end connection, adjust frame width direction both sides frame intermediate position all is provided with the lead screw slider, the lead screw slider sets up the lead screw is peripheral.
The lifting basket assembly comprises a pair of windlass arranged at the bottom of the inverted U-shaped mounting frame, and a basket is arranged at the end part of a steel wire rope of the pair of windlass.
The adjusting frame is internally provided with a plurality of third reinforcing beams along the width direction of the adjusting frame, through holes are formed in the positions, corresponding to the steel wire ropes of the windlass, of the third reinforcing beams on two sides, the end parts of the steel wire ropes penetrate through the through holes to form hooks, hanging rings are arranged at the tops of the hanging baskets, and the hooks are arranged on the hanging rings.
The steel wire rope is characterized in that a limiting sleeve is arranged on the periphery of the steel wire rope between the third reinforcing beam and the hook, the bottom end of the limiting sleeve is propped against the hook, a limiting insertion barrel is arranged on the bottom surface of the third reinforcing beam and on the periphery of the through hole, and the top end of the limiting sleeve is inserted into the limiting sleeve and propped against the bottom of the third reinforcing beam.
The lifting basket is characterized in that a limiting inserting plate is arranged at one side, close to the scissor type lifter, of the bottom of the hanging basket, a limiting inserting groove is formed in the side face of the table top of the scissor type lifter, and the limiting inserting plate is arranged in the limiting inserting groove.
The inside a plurality of first entablature that falls that is provided with of top frame, the side frame is inside to be provided with a plurality of second entablature, both sides first entablature with be provided with the reinforcing plate on the second entablature.
When the operation platform is in a normal state, the winch is tightened, the limiting sleeve is inserted into the limiting inserting cylinder, meanwhile, the limiting inserting plate is inserted into the limiting inserting groove, and at the moment, the hanging basket is not easy to shake;
during construction, constructors enter the hanging bar and the scissor fork lifter by means of the crawling ladder, the scissor fork lifter is lifted to enable the hanging basket to be higher than the bridge guardrail, the scissor fork lifter is moved to be close to the bridge guardrail, the hanging basket is pushed to the outer side of the bridge guardrail by the transverse adjusting mechanism, the scissor fork lifter is lowered to a construction position, the inner side construction position is guaranteed, the hanging basket is moved to the side close to the bridge guardrail by the transverse adjusting mechanism, the height of the hanging basket is adjusted by the winch, construction is guaranteed at the outer side construction position, and the scissor fork lifter moves forwards stably and can keep continuous construction.
The beneficial effects of the utility model are as follows: simple structure, convenient to use are applicable to construction such as bridge guardrail outside, are applicable to the guardrail of co-altitude simultaneously, and it is convenient to remove to but both sides construction simultaneously has reduced engineering time, when having improved work efficiency greatly, has higher security.
Drawings
Fig. 1 is a schematic structural diagram of an embodiment of the present utility model.
Fig. 2 is a schematic diagram of a side view of an embodiment of the present utility model.
Fig. 3 is a schematic top view of an embodiment of the present utility model.
Fig. 4 is a schematic structural diagram of a front view of an embodiment of the present utility model.
Fig. 5 is a schematic structural view of a lifting basket assembly according to an embodiment of the present utility model.
Fig. 6 is a schematic structural diagram of a lifting basket assembly according to an embodiment of the present utility model.
Fig. 7 is a partial enlarged view of a portion a in fig. 6.
Wherein, the reference numerals are as follows: 1. a scissor lift; 2. a vertical stay bar; 3. a top frame; 301. a first reinforcing beam; 4. a side frame; 401. a second reinforcing beam; 5. a lateral adjustment mechanism; 6. lifting the hanging basket assembly; 7. a hanging basket; 701. a hanging ring; 8. a slide rail; 9. a slide block; 12. a screw rod; 13. a driving motor; 14. an adjusting frame; 1401. a third reinforcing beam; 15. an inverted U-shaped mounting rack; 18. a screw rod sliding block; 19. a hoist; 20. a wire rope; 21. a limit sleeve; 22. a hook; 23. and limiting the inserting cylinder.
Detailed Description
In order to clearly illustrate the technical characteristics of the scheme, the scheme is explained below through a specific embodiment.
Referring to fig. 1-7, a bridge deck construction hanging rail operation platform comprises a scissor lift 1 and a support frame arranged on the scissor lift 1, wherein a transverse adjusting mechanism 5 is arranged on the support frame, and a lifting basket component 6 is arranged on the transverse adjusting mechanism 5;
the support frame comprises vertical supporting rods 2 arranged at four corners of the table top of the scissor lift 1, top frames 3 are arranged at the end parts of the vertical supporting rods 2, side frames 4 are arranged on the side surfaces of the top frames 3, and transverse adjusting mechanisms 5 are arranged on the side frames 4;
the transverse adjusting mechanism 5 comprises a pair of sliding rails 8 arranged at two sides of the top of the side frame 4 in the length direction, sliding blocks 9 are arranged on the sliding rails 8 at two sides, and an adjusting frame 14 is arranged on the sliding blocks 9 at two sides;
the adjusting frame 14 is provided with an inverted U-shaped mounting frame 15, and the inverted U-shaped mounting frame 15 is provided with a lifting basket assembly 6.
The side frames 4 and the top frame 3 are provided with screw rods 12, the screw rods 12 are arranged along the width direction of the side frames 4, the top frame 3 is provided with a driving motor 13, a motor shaft of the driving motor 13 is connected with the end parts of the screw rods 12, the middle positions of the frames 4 on the two sides of the width direction of the adjusting frame 14 are provided with screw rod sliding blocks 18, and the screw rod sliding blocks 18 are arranged on the periphery of the screw rods 12.
The lifting basket assembly 6 comprises a pair of winches 19 arranged at the bottom of the inverted U-shaped mounting frame 15, and the ends of the wire ropes 20 of the pair of winches 19 are provided with a basket 7.
A plurality of third reinforcing cross beams 1401 are arranged in the adjusting frame 14 along the width direction of the adjusting frame 14, through holes are formed in the third reinforcing cross beams 1401 on the two sides, corresponding to the positions of the steel wire ropes 20 of the windlass 19, of the steel wire ropes 20, hooks 22 are arranged at the ends of the steel wire ropes 20, penetrating through the through holes, hanging rings 701 are arranged at the top of the hanging basket 7, and the hooks 22 are arranged on the hanging rings 701.
The periphery of the steel wire rope 20 between the third reinforcing beam 1401 and the hook 22 is provided with a limit sleeve 21, the bottom end of the limit sleeve 21 is propped against the hook 22, the periphery of the bottom surface and the through hole of the third reinforcing beam 1401 is provided with a limit plug cylinder 23, and the top end of the limit sleeve 21 is plugged into the limit sleeve 21 and propped against the bottom of the third reinforcing beam 1401.
A limiting inserting plate is arranged at one side, close to the scissor lift 1, of the bottom of the hanging basket 7, a limiting inserting groove is arranged on the side face of the table top of the scissor lift 1, and the limiting inserting plate is arranged in the limiting inserting groove.
The top frame 3 is internally provided with a plurality of inverted first reinforcing beams 301, the side frames 4 are internally provided with a plurality of second reinforcing beams 401, and reinforcing plates are arranged on the first reinforcing beams 301 and the second reinforcing beams 401 on two sides.
When the operation platform is in a normal state, the winch 19 is tightened, the limiting sleeve 21 is inserted into the limiting insertion barrel 23, and meanwhile, the limiting insertion plate is inserted into the limiting insertion slot, so that the hanging basket 7 is not easy to shake;
during construction, constructors enter the hanging bar and the scissor type lifter 1 by means of the crawling ladder, the scissor type lifter 1 is lifted to enable the hanging basket 7 to be higher than the bridge guardrail, the scissor type lifter 1 is moved to be close to the bridge guardrail, the hanging basket 7 is pushed to the outer side of the bridge guardrail by the transverse adjusting mechanism 5, the scissor type lifter 1 is lowered to a construction position, the inner side construction position is guaranteed, the hanging basket 7 is moved to the side close to the bridge guardrail by the transverse adjusting mechanism 5, the height of the hanging basket 7 is adjusted by the winch 19, construction is guaranteed at the outer side construction position, and the scissor type lifter 1 can be moved forwards stably and can keep continuous construction.
The technical features of the present utility model that are not described in the present utility model may be implemented by or using the prior art, and are not described in detail herein, but the above description is not intended to limit the present utility model, and the present utility model is not limited to the above examples, but is also intended to be within the scope of the present utility model by those skilled in the art.

Claims (7)

1. The bridge deck construction hanging rail operation platform is characterized by comprising a scissor type lifter and a supporting frame arranged on the scissor type lifter, wherein a transverse adjusting mechanism is arranged on the supporting frame, and a lifting hanging basket assembly is arranged on the transverse adjusting mechanism;
the supporting frame comprises vertical supporting rods arranged at four corners of the table top of the scissor fork type lifter, top frames are arranged at the end parts of the vertical supporting rods, side frames are arranged on the side faces of the top frames, and the lateral adjusting mechanisms are arranged on the side frames;
the transverse adjusting mechanism comprises a pair of sliding rails arranged on two sides of the top of the side frame in the length direction, sliding blocks are arranged on the sliding rails on two sides, and adjusting frames are arranged on the sliding blocks on two sides;
the adjusting frame is provided with an inverted U-shaped mounting frame, and the inverted U-shaped mounting frame is provided with a lifting basket assembly.
2. The deck construction boom operation platform according to claim 1, wherein a screw is provided on the side frame and the top frame, the screw is provided along the width direction of the side frame, a driving motor is provided on the top frame, a motor shaft of the driving motor is connected with the end of the screw, screw sliders are provided at intermediate positions of the two side frames in the width direction of the adjusting frame, and the screw sliders are provided at the periphery of the screw.
3. The deck construction boom operating platform of claim 2, wherein the lifting basket assembly comprises a pair of hoists disposed at the bottom of the inverted U-shaped mounting frame, and a pair of baskets are disposed at the ends of the wire ropes of the hoists.
4. The deck construction boom operation platform according to claim 3, wherein a plurality of third reinforcing cross beams are arranged in the adjusting frame along the width direction of the adjusting frame, through holes are formed in the third reinforcing cross beams on two sides corresponding to the positions of steel wire ropes of the hoist, hooks are arranged at the ends of the steel wire ropes, penetrating through the through holes, hanging rings are arranged at the tops of the hanging baskets, and the hooks are arranged on the hanging rings.
5. The deck construction boom operation platform of claim 4, wherein a limiting sleeve is arranged on the periphery of the steel wire rope between the third reinforcing beam and the hook, the bottom end of the limiting sleeve is propped against the hook, a limiting insertion barrel is arranged on the periphery of the through hole and on the bottom surface of the third reinforcing beam, and the top end of the limiting sleeve is inserted into the limiting sleeve and propped against the bottom of the third reinforcing beam.
6. The deck construction boom operation platform of claim 5, wherein a limiting insertion plate is arranged at one side of the bottom of the hanging basket, which is close to the scissor lift, and a limiting insertion groove is arranged at the side surface of the table top of the scissor lift, and the limiting insertion plate is arranged in the limiting insertion groove.
7. The deck construction boom operation platform of claim 6, wherein a plurality of inverted first reinforcement beams are arranged inside the top frame, a plurality of second reinforcement beams are arranged inside the side frame, and reinforcement plates are arranged on the first reinforcement beams and the second reinforcement beams on both sides.
CN202321204831.1U 2023-05-18 2023-05-18 Bridge floor construction hanging fence operation platform Active CN219793671U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321204831.1U CN219793671U (en) 2023-05-18 2023-05-18 Bridge floor construction hanging fence operation platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321204831.1U CN219793671U (en) 2023-05-18 2023-05-18 Bridge floor construction hanging fence operation platform

Publications (1)

Publication Number Publication Date
CN219793671U true CN219793671U (en) 2023-10-03

Family

ID=88178678

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321204831.1U Active CN219793671U (en) 2023-05-18 2023-05-18 Bridge floor construction hanging fence operation platform

Country Status (1)

Country Link
CN (1) CN219793671U (en)

Similar Documents

Publication Publication Date Title
CN219793671U (en) Bridge floor construction hanging fence operation platform
CN113638312A (en) Multi-functional bridge railing construction trolley
CN210620052U (en) Assembled building hoisting accessory
JPS59158794A (en) Crane for assembling steel tower
CN215925636U (en) Multi-functional bridge railing construction trolley
CN112299283A (en) Hydraulic lifting platform applied to gantry crane
CN113636467A (en) Rolling mill frame hoisting device
CN202088198U (en) Lifting device for disassembling monorail crane
CN109879165A (en) A kind of steel hanger and the construction method using steel hanger manpower hoisting steel beam
CN215666814U (en) Light reactor hoisting device
CN218988618U (en) Bridge crane convenient to change electric block
CN216071811U (en) Wedge lifting walking beam structure
CN220245368U (en) Electric hoist gantry crane
CN218403281U (en) Hoist for prefabricated guardrail
CN219653547U (en) Auxiliary device for bridge anti-collision guardrail construction
CN211548700U (en) Prestressed construction platform for inner factory building
CN220117149U (en) Hydraulic engineering trash rack convenient to clearance
CN217756513U (en) Large-span lifting appliance for crane
CN212682383U (en) Anti-falling self-locking device for dummy bar
CN217516554U (en) Adjustable simple and easy hoisting apparatus is pushed away to walking formula
CN219363024U (en) Electric single-beam crane capable of reducing shaking
CN210341680U (en) Door type corrugated steel web plate installation and overhanging type hanging bracket structure
CN215558492U (en) Electric single-beam suspension crane
CN210682975U (en) Hoisting walking frame of low-altitude crane
CN214652985U (en) Steel bar framework lifting and leveling device for building construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant