CN219739889U CN202321248672.5U CN202321248672U CN219739889U CN 219739889 U CN219739889 U CN 219739889U CN 202321248672 U CN202321248672 U CN 202321248672U CN 219739889 U CN219739889 U CN 219739889U
Authority
CN
China
Prior art keywords
mounting
bus duct
double
mounting bracket
threaded rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321248672.5U
Other languages
Chinese (zh)
Inventor
张仁相
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing Fengbaoben Electrical Equipment Co ltd
Original Assignee
Chongqing Fengbaoben Electrical Equipment Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing Fengbaoben Electrical Equipment Co ltd filed Critical Chongqing Fengbaoben Electrical Equipment Co ltd
Priority to CN202321248672.5U priority Critical patent/CN219739889U/en
Application granted granted Critical
Publication of CN219739889U publication Critical patent/CN219739889U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Installation Of Bus-Bars (AREA)

Abstract

The utility model discloses a mounting bracket of a bus duct, which is characterized by comprising two mounting beams which are arranged in parallel and two studs which are arranged in parallel, wherein the two mounting beams are arranged up and down, the two ends of the mounting beam on the upper side along the length direction are provided with first threaded holes which are arranged vertically, the two ends of the mounting beam on the lower side along the length direction are provided with through holes which are arranged vertically, the studs are arranged in the threaded holes and the through holes, and the upper ends of the studs are connected with mounting seats; the installation Liang Nazhuai moves installs the double-end threaded rod, is provided with on the installation roof beam and is used for adjusting the adjusting part of double-end threaded rod, two the opposite one side of installation roof beam is provided with clamping assembly, clamping assembly slidable mounting in the installation roof beam and with double-end threaded rod screw thread fit. The utility model has the advantages of convenient adjustment and installation, suitability for various bus ducts and the like.

Description

Mounting bracket of bus duct
Technical Field
The utility model relates to the technical field of bus duct auxiliary fixtures, in particular to a mounting bracket of a bus duct.
Background
With the continuous development of society, the wide use of various electrified devices in construction projects makes power supply lines in the projects more and more complex. In order to cope with this situation, the bus duct is becoming more and more important in every aspect as a carrier for high-current power supply. At present, the bus duct installation method mainly adopts hanging brackets to support, the hanging brackets and the bus duct are mutually fixed, but when in installation, clamping grooves on some hanging brackets are of fixed width, the clamping grooves are inconvenient to adjust, and are difficult to be suitable for bus ducts with various sizes, so that the bus duct cannot be adaptively clamped on an installation bracket and fixed on facilities such as ceilings. For this reason, some installation occasions adopt the mode of laying the backing plate outside the bus duct to fill the clearance between bus duct and the draw-in groove, but this kind of installation mode makes the installation stability of bus duct relatively poor, takes place the safety problem easily. For example, chinese patent literature discloses a bus duct hanger convenient to install, publication number is: CN218124226U, this scheme is through mounting bracket connection backup pad, backup pad and bus duct sliding connection to accomplish hoist and mount bus duct.
Disclosure of Invention
Aiming at the defects in the prior art, the utility model aims to solve the technical problems that: how to provide a bus duct mounting bracket which is convenient to adjust and can fixedly mount the bus duct.
In order to solve the technical problems, the utility model adopts the following technical scheme: the mounting bracket for the bus duct is characterized by comprising two mounting beams which are arranged in parallel and two studs which are arranged in parallel, wherein the two mounting beams are arranged up and down, first threaded holes which are vertically arranged are formed in the two ends of the mounting beam on the upper side along the length direction, through holes which are vertically arranged are formed in the two ends of the mounting beam on the lower side along the length direction, the studs are arranged in the threaded holes and the through holes, and the upper ends of the studs are connected with mounting seats; the installation Liang Nazhuai moves installs the double-end threaded rod, is provided with on the installation roof beam and is used for adjusting the adjusting part of double-end threaded rod, two the opposite one side of installation roof beam is provided with clamping assembly, clamping assembly slidable mounting in the installation roof beam and with double-end threaded rod screw thread fit.
Through setting up double-end threaded rod and clamping assembly, can conveniently fix and centre gripping bus duct, rotate the double-end threaded rod, thereby by the rotation of adjusting part control double-end threaded rod for clamping assembly can be along the screw thread that sets up relatively on the double-end threaded rod relatively be close to and deviate from the removal, with the size of adaptation bus duct, on bus duct fixed centre gripping and mounting bracket, install double-screw bolt and mount pad at first threaded hole, and control the distance between two mounting beams and fix the bus duct, make the installation firm more and reliable, improved installation effectiveness and adaptability.
Further, the clamping assembly comprises two clamping plates which are in an L shape and can be arranged in a sliding manner, a clamping part used for clamping the bus duct is formed between the two clamping plates, a moving block is fixed on one side, close to the mounting beam, of the clamping plates, a guide hole is formed in one side, opposite to the mounting beam, of the clamping plates, and the moving block penetrates through the guide hole and is in threaded connection with the double-head threaded rod.
The clamping assembly is provided with the slidable L-shaped clamping plate, so that the position of the clamping plate can be flexibly adjusted to adapt to bus ducts of different types and sizes; simultaneously, the movable blocks are respectively in threaded connection with the two sides of the double-head threaded rod, so that the position and the clamping force of the clamping assembly can be conveniently adjusted, and the adaptability and the flexibility are improved.
Further, the inner side of the clamping plate far away from the mounting beam is provided with an insulating layer.
Further, the insulating layer is a ceramic layer.
The insulating layer arranged on the clamping plate is made of ceramic materials, so that the heat resistance and corrosion resistance of the mounting bracket can be improved, an insulating effect is achieved, and the safety and stability of equipment are guaranteed.
Still further, the regulation subassembly including install in the knob of installation roof beam one side, the knob is connected with the regulation pole, the regulation pole keep away from between one end and the double-end threaded rod of knob is connected through bevel gear transmission.
The guide holes are formed in the mounting beam, the adjusting rods are arranged on the knob and are in transmission connection with the bevel gears, so that the positions and angles of the clamping plates can be conveniently adjusted, and the adaptability and the flexibility of the mounting bracket are improved.
Furthermore, two sides of the end parts of the two clamping plates, which are close to each other, are provided with fixing blocks formed by protruding, and bolts are arranged between the two adjacent fixing blocks.
Set up fixed block and mounting bolt on the cardboard, can improve fastness and stability between two cardboard, guaranteed the security and the stability of equipment further, be provided with the nut on the installation roof beam, nut and double-screw bolt lower extreme threaded connection.
Further, the side surface of the mounting beam is provided with a strip-shaped through hole.
The mounting beam is hollow and provided with the strip-shaped through holes, so that the ventilation property and the heat dissipation property of the mounting bracket can be improved.
Further, the mount pad includes rectangle hollow stand, four sides of stand have rectangular opening, the lower extreme of stand has the second screw hole of vertical setting, the upper end threaded connection of double-screw bolt in the second screw hole, the upper end of stand is provided with the mounting panel that is used for fixed mounting.
In conclusion, the utility model has the advantages of convenient adjustment and installation, suitability for various bus ducts and the like.
Drawings
Fig. 1 is a front view of a mounting bracket for a bus duct.
Fig. 2 is a schematic view of a mounting bracket structure of a bus duct.
Fig. 3 is a top view of the mounting beam.
Fig. 4 is an enlarged view of a portion of the block of fig. 1.
Detailed Description
The present utility model will be described in further detail with reference to examples.
The specific implementation method comprises the following steps: as shown in fig. 1 to 4, a mounting bracket for a bus duct comprises two mounting beams 1 arranged in parallel and two studs 2 arranged in parallel, wherein the two mounting beams 1 are arranged up and down, the two ends of the mounting beam 1 on the upper side along the length direction are provided with first threaded holes 11 arranged vertically, the two ends of the mounting beam 1 on the lower side along the length direction are provided with through holes arranged vertically, the studs 2 are arranged in the threaded holes 11 and the through holes, the upper ends of the studs 2 are connected with mounting seats 3, nuts 15 are arranged on the mounting beam 1, and the nuts 15 are in threaded connection with the lower ends of the studs 2. The double-end threaded rod 12 is rotatably mounted on the mounting beam 1, the adjusting assemblies 5 used for adjusting the double-end threaded rod 12 are arranged on the mounting beam 1, the clamping assemblies 4 are arranged on the opposite sides of the mounting beam 1, and the clamping assemblies 4 are slidably mounted on the mounting beam 1 and are in threaded fit with the double-end threaded rod 12. The clamping assembly 4 comprises two clamping plates 41 which are in an L shape and can be arranged in a sliding manner, a clamping part for clamping the bus duct is formed between the two clamping plates 41, a moving block 411 is fixed on one side, close to the mounting beam 1, of each clamping plate 41, a guide hole 13 is formed on the opposite side of each mounting beam 1, and the moving block 411 penetrates through the guide hole 13 and is in threaded connection with the double-end threaded rod 12. The opposite sides of the two mounting beams 1 are provided with guide holes 13; the adjusting assembly 5 comprises a knob 51 arranged on one side of the mounting beam 1, the knob 51 is connected with an adjusting rod 511, and one end, far away from the knob 51, of the adjusting rod 511 is in transmission connection with the double-end threaded rod 12 through a bevel gear 512.
Before installation, the installation beam 1 is fixed at a required position, and two L-shaped clamping plates 41 are adjusted to a proper position so that the clamping plates can accommodate the bus duct, and the bus duct is placed at the clamping part of the clamping assembly 4 to fix the bus duct. The stud 2 is inserted into the first threaded hole 11, the nut is screwed, when the stud is rotated, the position of the mounting beam 1 on the stud 2 can be adjusted, the distance between the two mounting beams 1 is controlled, and then the mounting height of the bus duct is adjusted; next, the mount 3 is attached to the upper end of the stud 2. The bus duct position and the clamping bus duct can be conveniently adjusted, and the mounting bracket can be suitable for various bus duct sizes, and the distance between the clamping plates 41 can be adjusted according to the requirements. That is, the knob 51 of the adjusting component 5 is rotated to drive the double-headed threaded rod 12 to rotate, so that the clamping component 4 slides along the double-headed threaded rod 12, and the clamping force between the clamping component 4 and the bus duct is adjusted, so that the purpose of stably fixing the bus duct is achieved.
In operation, the inner side of the clamping plate 41 remote from the mounting beam 1 has an insulating layer 412. The insulating layer 412 is a ceramic layer, and in addition, the insulating layer can improve safety. Two sides of the end portions, close to the clamping plates 41, are provided with fixing blocks 413 formed in a protruding mode, and bolts are installed between the two adjacent fixing blocks 413.
In practice, the mounting beam 1 is hollow, two ends of the double-ended threaded rod 12 are respectively abutted between two baffles in the mounting beam 1 to limit the position of the double-ended threaded rod 12, and the double-ended threaded rod can rotate, and the side surface is provided with a strip-shaped through hole 14.
When the installation seat 3 is implemented, the installation seat comprises a rectangular hollow upright column 31, rectangular openings 311 are formed in four sides of the upright column 31, a second threaded hole is formed in the lower end of the upright column 31 and is vertically arranged, the upper end of the stud 2 is in threaded connection with the second threaded hole, an installation plate 32 used for fixed installation is arranged at the upper end of the upright column 31, and the distance of the stud 2 extending into the upright column 31 can be adjusted through threaded connection of the stud 2 and the second threaded hole, so that the height is convenient to adjust.
The foregoing description of the preferred embodiments of the utility model is not intended to be limiting, but rather is intended to cover all modifications, equivalents, and alternatives falling within the spirit and principles of the utility model.

Claims (9)

1. The mounting bracket for the bus duct is characterized by comprising two mounting beams which are arranged in parallel and two studs which are arranged in parallel, wherein the two mounting beams are arranged up and down, first threaded holes which are vertically arranged are formed in the two ends of the mounting beam on the upper side along the length direction, through holes which are vertically arranged are formed in the two ends of the mounting beam on the lower side along the length direction, the studs are arranged in the threaded holes and the through holes, and the upper ends of the studs are connected with mounting seats; the installation Liang Nazhuai moves installs the double-end threaded rod, is provided with on the installation roof beam and is used for adjusting the adjusting part of double-end threaded rod, two the opposite one side of installation roof beam is provided with clamping assembly, clamping assembly slidable mounting in the installation roof beam and with double-end threaded rod screw thread fit.
2. The bus duct mounting bracket of claim 1, wherein the clamping assembly comprises two clamping plates which are in an L shape and can be arranged in a sliding manner, a clamping part for clamping the bus duct is formed between the two clamping plates, a moving block is fixed on one side, close to the mounting beam, of the clamping plates, a guide hole is formed on the opposite side of the mounting beam, and the moving block penetrates through the guide hole and is in threaded connection with the double-head threaded rod.
3. The mounting bracket for a busway of claim 2, wherein an inner side of the clip remote from the mounting beam has an insulating layer.
4. A mounting bracket for a bus duct as defined in claim 3, wherein the insulating layer is a ceramic layer.
5. The bus duct mounting bracket of claim 2, wherein the adjustment assembly comprises a knob mounted on one side of the mounting beam, the knob is connected with an adjustment rod, and one end of the adjustment rod away from the knob is in transmission connection with the double-ended threaded rod through a bevel gear.
6. The bus duct mounting bracket of claim 5, wherein two sides of the end of each of the two adjacent clamping plates are provided with a protruding fixing block, and a bolt is arranged between two adjacent fixing blocks.
7. The bus duct mounting bracket of claim 1, wherein the mounting beam is provided with a nut that is threadably coupled to the lower end of the stud.
8. The mounting bracket for a busway of claim 1, wherein the mounting beam sides have bar-shaped through holes.
9. The mounting bracket for a bus duct of claim 1, wherein the mounting base comprises a rectangular hollow upright, four sides of the upright are provided with rectangular openings, the lower end of the upright is provided with a second threaded hole arranged vertically, the upper end of the stud is in threaded connection with the second threaded hole, and the upper end of the upright is provided with a mounting plate for fixed mounting.
CN202321248672.5U 2023-05-22 2023-05-22 Mounting bracket of bus duct Active CN219739889U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321248672.5U CN219739889U (en) 2023-05-22 2023-05-22 Mounting bracket of bus duct

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321248672.5U CN219739889U (en) 2023-05-22 2023-05-22 Mounting bracket of bus duct

Publications (1)

Publication Number Publication Date
CN219739889U true CN219739889U (en) 2023-09-22

Family

ID=88027204

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321248672.5U Active CN219739889U (en) 2023-05-22 2023-05-22 Mounting bracket of bus duct

Country Status (1)

Country Link
CN (1) CN219739889U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117134279A (en) * 2023-10-26 2023-11-28 江苏浩威新材料有限公司 Adjustable fixing frame for mounting casting bus

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117134279A (en) * 2023-10-26 2023-11-28 江苏浩威新材料有限公司 Adjustable fixing frame for mounting casting bus
CN117134279B (en) * 2023-10-26 2024-01-30 江苏浩威新材料有限公司 Adjustable fixing frame for mounting casting bus

Similar Documents

Publication Publication Date Title
CN219739889U (en) Mounting bracket of bus duct
CN115986652B (en) Bus duct clamping device
CN219322050U (en) Cable trench cross arm assembly
CN208643172U (en) A kind of cable positioning tool
CN210597779U (en) Fixed lockset for curtain wall
CN209692302U (en) A kind of suspension type bus structure
CN212427758U (en) Adjustable top-hanging structure of bearing steel pipe
CN113659517A (en) Cable distribution box with high temperature resistant structure and convenient to butt joint
CN221075540U (en) Heating and ventilation pipeline mounting bracket
CN221353866U (en) Intensive bus duct convenient to hang installation
CN219591902U (en) Intelligent power distribution cabinet line monitoring device
CN112031254A (en) Adjustable top hanging structure of bearing steel pipe and mounting method
CN219086752U (en) Cable bridge fastening device
CN217159218U (en) Waterproof type bus duct is fixed with a gallows
CN221126299U (en) Binding post arranges installing support
CN219717811U (en) Cable support of top formula installation walks
CN216045862U (en) Energy-saving air pipe mounting bracket
CN215829287U (en) Environmental protection engineering is with noise prevention and cure equipment of combination formula
CN217362280U (en) Prefabricated 110 kilovolt intelligent substation cabinet
CN219067753U (en) Cable mounting rack with adjustability
CN221177183U (en) Cable bridge rack support
CN219371842U (en) Special device for overhauling conductive arm of isolating switch
CN220857572U (en) Bus duct hoisting and installing structure
CN219420179U (en) Supporting pencil fixed knot of electric motor car constructs
CN219611289U (en) Tee joint connecting piece

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant