CN219622231U - Construction hanging basket for engineering construction - Google Patents

Construction hanging basket for engineering construction Download PDF

Info

Publication number
CN219622231U
CN219622231U CN202321372460.8U CN202321372460U CN219622231U CN 219622231 U CN219622231 U CN 219622231U CN 202321372460 U CN202321372460 U CN 202321372460U CN 219622231 U CN219622231 U CN 219622231U
Authority
CN
China
Prior art keywords
steel cable
fixing assembly
basket
basket body
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202321372460.8U
Other languages
Chinese (zh)
Inventor
杨龙
周慧蓉
刘孝军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Xinyiheng Construction Machinery Leasing Co ltd
Original Assignee
Chengdu Xinyiheng Construction Machinery Leasing Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Xinyiheng Construction Machinery Leasing Co ltd filed Critical Chengdu Xinyiheng Construction Machinery Leasing Co ltd
Priority to CN202321372460.8U priority Critical patent/CN219622231U/en
Application granted granted Critical
Publication of CN219622231U publication Critical patent/CN219622231U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to an engineering construction hanging basket, which aims to solve the technical problem that the existing engineering construction hanging basket workers easily shake in the construction process at present, and comprises a basket body and a stabilizing mechanism; the stabilizing mechanism is arranged at one side of the basket body; the stabilizing mechanism comprises a top fixing component, a bottom fixing component, a steel cable and a traction component; the bottom fixing assembly is arranged below the top fixing assembly, and the steel cable is arranged between the top fixing assembly and the bottom fixing assembly; the traction assembly is sleeved with the steel cable; according to the utility model, the steel cable is clamped into the clamping space traction assemblies of the pulleys A and B to drive the basket body to slide up and down on the straightened steel cable, and provide horizontal traction force for the basket body, so that the shaking of the basket body in the horizontal direction in the process that a constructor walks on the basket body is reduced, and the comfort of the constructor taking the hanging basket is improved; the utility model has the advantages of clear structure and strong practicability.

Description

Construction hanging basket for engineering construction
Technical Field
The utility model relates to the technical field of engineering construction equipment, in particular to an engineering construction hanging basket.
Background
The hanging basket is a building tool for high-altitude operation of building engineering, and acts on curtain wall installation and outer wall cleaning. The hanging basket is novel high-place operation equipment which can replace the traditional scaffold, lighten labor intensity, improve working efficiency and be repeatedly used. The use of the building hanging basket is gradually becoming a trend, and is used for the construction of the outer wall of a high-rise multi-layer high building, the installation of a curtain wall, the heat preservation construction, the maintenance and the cleaning of the outer wall and other high-place operations.
When the existing engineering construction building hanging basket is used in high-rise building construction, a hanging basket body needs to be lifted by a crane through steel wires, so that the hanging basket body moves up and down on the periphery of a wall surface, workers need to walk on the hanging basket body in the construction process, the hanging basket body is easy to shake, and constructors are uncomfortable. In view of this, we propose an engineering construction building basket.
Disclosure of Invention
The utility model aims to overcome the defects of the prior art, adapt to the actual needs, and provide an engineering construction hanging basket so as to solve the technical problem that the existing engineering construction hanging basket workers easily shake in the construction process.
In order to achieve the purpose of the utility model, the technical scheme adopted by the utility model is as follows: the engineering construction hanging basket comprises a basket body and a stabilizing mechanism; the stabilizing mechanism is arranged at one side of the basket body;
the stabilizing mechanism comprises a top fixing component, a bottom fixing component, a steel cable and a traction component; the bottom fixing assembly is arranged below the top fixing assembly, and the steel cable is arranged between the top fixing assembly and the bottom fixing assembly; the traction assembly is sleeved with the steel cable;
the traction assembly comprises a mounting box A and a mounting box B; the installation boxes A and B are oppositely arranged, one surface of each installation box A and each installation box B is of an open structure, and the closed surface of each installation box A is fixedly connected with one side surface of the basket body; the excrement on the inner walls of the installation box A and the installation box B is rotationally connected with a pulley A and a pulley B; the pulley A and the pulley B are tangential; one end of the opposite sides of the installation box A and the installation box B are rotationally connected through a hinge, and the other ends of the opposite sides are fixedly connected through a lock catch; the steel cable penetrates through the clamping space between the steel cable and the pulleys A and B.
Preferably, the top fixing assembly comprises a bearing plate A and an L-shaped supporting frame; one end of the L-shaped supporting frame is fixedly connected with the surface of the bearing plate A, and a plurality of fixing rods A are arranged on the bearing plate A; the surface of the fixed rod A is sleeved with a plurality of balancing weights A.
Preferably, the bottom fixing assembly comprises a bearing plate B and an electric winch; the electric winch is arranged on the surface of the bearing plate B; a plurality of fixing rods B are arranged on the bearing plate B; and a plurality of balancing weights B are sleeved on the surface of the fixed rod B.
Preferably, one end of the steel cable is fixedly connected with the other end of the supporting frame.
Preferably, the other end of the steel cable is fixedly connected with the electric winch.
Compared with the prior art, the utility model has the beneficial effects that:
the novel basket body and the stabilizing mechanism are arranged, wherein a top fixing assembly, a bottom fixing assembly, a steel cable and a traction assembly are arranged, the steel cable is tensioned and straightened through the top fixing assembly and the bottom fixing assembly, a lock catch in the traction assembly on the surface of the basket body is opened, a mounting box B is turned over, the steel cable is clamped into clamping spaces of a pulley A and the pulley B, the mounting box B is turned over to be connected with the mounting box A, and the lock catch is closed; the traction assembly drives the basket body to slide up and down on the straightened steel cable, and provides traction force in the horizontal direction for the basket body, so that shaking of the basket body in the horizontal direction in the process that constructors walk on the basket body is reduced, and comfort of the constructors riding the hanging basket is improved.
Drawings
FIG. 1 is a schematic diagram of the overall structure of the present utility model;
FIG. 2 is a schematic view of a top fixture assembly of the present utility model;
FIG. 3 is a schematic view of a bottom fixture assembly of the present utility model;
FIG. 4 is a schematic view of a traction assembly of the present utility model;
FIG. 5 is a schematic view of the assembled structure of the pulling assembly and basket and cable of the present utility model;
in the figure: 1. a basket body; 2. a stabilizing mechanism; 201. a top fixing assembly; 2011. a bearing plate A; 2012. an L-shaped supporting frame; 2013. a fixed rod A; 2014. a balancing weight A; 202. a bottom fixing assembly; 2021. a bearing plate B; 2022. an electric winch; 2023. a fixed rod B; 2024. a balancing weight B; 203. a wire rope; 204. a traction assembly; 2041. a mounting box A; 2042. a mounting box B; 2043. a pulley A; 2044. a pulley B; 2045. a hinge; 2046. and (5) locking.
Detailed Description
The utility model is further illustrated by the following examples in conjunction with the accompanying drawings:
example 1:
the embodiment discloses an engineering construction hanging basket, which is shown in figure 1 and comprises a basket body 1 and a stabilizing mechanism 2; in this embodiment, the basket body 1 is an existing engineering construction hanging basket on the market.
As shown in fig. 1 to 5, the stabilizing mechanism 2 is arranged on one side of the basket body 1; a top fixing assembly 201, a bottom fixing assembly 202, a steel cable 203 and a traction assembly 204 of the stabilizing mechanism 2; in the present embodiment, two steel cables 203 are arranged in parallel on the left and right; the traction assembly 204 is provided with four sets; the bottom fixing assembly 202 is arranged below the top fixing assembly 201, and the steel cable 203 is arranged between the top fixing assembly 201 and the bottom fixing assembly 202; the traction assembly 204 is sleeved with the steel cable 203.
Specifically, as shown in fig. 1 and 2, the top fixing assembly 201 includes a carrier plate a2011 and an L-shaped supporting frame 2012; one end of the L-shaped supporting frame 2012 is fixedly connected with the surface of the bearing plate A2011, and a plurality of fixing rods A2013 are arranged on the bearing plate A2011; a plurality of balancing weights A2014 are sleeved on the surface of the fixed rod A2013; placing the balancing weight a2014 on the roof, inserting the balancing weight a2014 on the fixing rod a2013, increasing the weight of the top fixing assembly 201, and increasing stability; in this embodiment, two L-shaped supporting frames 2012 are provided.
Further, as shown in fig. 1 and 3, the bottom fixing assembly 202 includes a bearing plate B2021 and an electric winch 2022; the electric winch 2022 is arranged on the surface of the bearing plate B2021; the bearing plate B2021 is provided with a plurality of fixing rods B2023; a plurality of balancing weights B2024 are sleeved on the surface of the fixed rod B2023; placing the bearing plate B2021 on the ground, inserting the balancing weight B2024 on the fixing rod B2023, increasing the weight of the bottom fixing component 202, and improving the stability; in this embodiment, two electric winches 2022 are provided.
Still further, as shown in fig. 1, 4, 5, the traction assembly 204 includes a mounting box a2041, a mounting box B2042; the installation boxes A2041 and B2042 are oppositely arranged, the opposite surfaces of the installation boxes A2041 and B2042 are of an open structure, and the closed surfaces of the four installation boxes A2041 are fixedly connected with four corners of one side surface of the basket body 1; the inner wall feces of the installation box A2041 and the installation box B2042 are rotationally connected with a pulley A2043 and a pulley B2044; pulley A2043 and pulley B2044 are tangential; one end of the opposite sides of the installation box A2041 and the installation box B2042 are rotationally connected through a hinge 2045, and the other end is fixedly connected through a lock catch 2046; the two steel cables 203 are respectively penetrated into clamping spaces of the pulleys A2043 and B2044 in the two groups of traction components 204, the lock catch 2046 is opened, the installation box B2042 is turned over, the steel cables 203 are clamped into the clamping spaces of the pulleys A2043 and B2044, the installation box B2042 is turned over to be connected with the installation box A2041, and the lock catch 2046 is closed; the traction assembly 204 carries the basket 1 up and down on the straightened wire rope 203 and provides traction to the basket 1 in the horizontal direction, reducing the shaking of the basket 1 in the horizontal direction during the lifting or descending of the crane.
It should be noted that, as shown in fig. 1 to 5, one end of the steel cable 203 is fixedly connected to the other end of the L-shaped support 2012; the other end of the steel cable 203 is fixedly connected with the electric winch 2022, which is used for improving the stability of the steel cable, and meanwhile, the electric winch 2022 can wind the steel cable 203, so that the steel cable 203 is in a stretched state between the supporting frame 2012 and the electric winch 2022.
Working principle: when the utility model is used, firstly, the balancing weight A2014 is placed on a roof, the balancing weight A2014 is inserted into the fixed rod A2013, the bearing plate B2021 is placed on the ground, and the balancing weight B2024 is inserted into the fixed rod B2023; the upper end of the steel cable 203 is fixedly connected with one end of an L-shaped supporting frame 2012, the lower end of the steel cable 203 is fixedly connected with two electric winches 2022 respectively, and the electric winches 2022 are driven by an external control mechanism to shrink and tighten the steel cable 203; opening the lock catches 2046 in the four traction assemblies 204 on the surface of the basket body 1, overturning the installation box B2042, clamping the steel cable 203 into the clamping spaces of the pulleys A2043 and B2044, overturning the installation box B2042 to be connected with the installation box A2041, and closing the lock catches 2046; the traction assembly 204 drives the basket body 1 to slide up and down on the straightened steel cable 203, and provides traction force for the basket body 1 in the horizontal direction, so that shaking of the basket body 1 in the horizontal direction in the process that a constructor walks on the basket body 1 is reduced, and comfort of the constructor taking the hanging basket is improved.
The embodiments of the present utility model are disclosed as preferred embodiments, but not limited thereto, and those skilled in the art will readily appreciate from the foregoing description that various modifications and variations can be made without departing from the spirit of the present utility model.

Claims (5)

1. The construction hanging basket for engineering construction is characterized by comprising a basket body (1) and a stabilizing mechanism (2); the stabilizing mechanism (2) is arranged at one side of the basket body (1);
the stabilizing mechanism (2) comprises a top fixing component (201), a bottom fixing component (202), a steel cable (203) and a traction component (204); the bottom fixing assembly (202) is arranged below the top fixing assembly (201), and the steel cable (203) is arranged between the top fixing assembly (201) and the bottom fixing assembly (202); the traction component (204) is sleeved with the steel cable (203);
the traction assembly (204) comprises a mounting box A (2041) and a mounting box B (2042); the installation boxes A (2041) and B (2042) are oppositely arranged, the opposite surfaces of the installation boxes A (2041) and B (2042) are of an open structure, and the closed surface of the installation box A (2041) is fixedly connected with one side surface of the basket body (1); the inner walls of the installation box A (2041) and the installation box B (2042) are rotationally connected with a pulley A (2043) and a pulley B (2044); the pulley A (2043) and the pulley B (2044) are tangential; one end of the opposite sides of the installation box A (2041) and the installation box B (2042) are rotationally connected through a hinge (2045), and the other ends are fixedly connected through a lock catch (2046); the steel cable (203) is penetrated in a clamping space with the pulley A (2043) and the pulley B (2044).
2. The construction and construction basket according to claim 1, wherein the top fixing assembly (201) comprises a carrier plate a (2011) and an L-shaped support frame (2012); one end of the L-shaped supporting frame (2012) is fixedly connected with the surface of the bearing plate A (2011), and a plurality of fixing rods A (2013) are arranged on the bearing plate A (2011); a plurality of balancing weights A (2014) are sleeved on the surface of the fixed rod A (2013).
3. An engineering construction building basket according to claim 1, characterized in that the bottom fixing assembly (202) comprises a carrier plate B (2021) and an electric winch (2022); the electric winch (2022) is arranged on the surface of the bearing plate B (2021); a plurality of fixing rods B (2023) are arranged on the bearing plate B (2021); the surface of the fixed rod B (2023) is sleeved with a plurality of balancing weights B (2024).
4. An engineering construction building basket according to claim 2, wherein one end of the steel cable (203) is fixedly connected to the other end of the L-shaped support bracket (2012).
5. A construction and construction basket according to claim 3, characterized in that the other end of the wire rope (203) is fixedly connected to the electric winch (2022).
CN202321372460.8U 2023-06-01 2023-06-01 Construction hanging basket for engineering construction Active CN219622231U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202321372460.8U CN219622231U (en) 2023-06-01 2023-06-01 Construction hanging basket for engineering construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202321372460.8U CN219622231U (en) 2023-06-01 2023-06-01 Construction hanging basket for engineering construction

Publications (1)

Publication Number Publication Date
CN219622231U true CN219622231U (en) 2023-09-01

Family

ID=87776012

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202321372460.8U Active CN219622231U (en) 2023-06-01 2023-06-01 Construction hanging basket for engineering construction

Country Status (1)

Country Link
CN (1) CN219622231U (en)

Similar Documents

Publication Publication Date Title
CN212295596U (en) Combined hanging basket for house construction
CN108149914B (en) Forward and backward rotation simultaneous lifting system and method for all-steel attached lifting scaffold
CN214989776U (en) Bridge crane with anti-swing function
CN219622231U (en) Construction hanging basket for engineering construction
CN219031531U (en) Electromagnetic double-beam bridge crane
CN213085125U (en) Elevator shaft traction rotary telescopic construction elevator
CN115043343A (en) Light partition board installation construction device and construction method thereof
CN209777997U (en) Standard festival anti-drop buffer structure of construction elevator cage
CN2756806Y (en) New vertically mounting and lifting drilling bit derrick
CN214935363U (en) Suspension device for building steel structure frame
CN219950303U (en) Prefabricated component hangs and gets device
CN218465324U (en) Steel construction lifting device
CN220434185U (en) Electric hanging basket with anti-shaking structure
CN218714959U (en) Hanging basket convenient to hoist
CN220393068U (en) Novel empty box lifting appliance
CN214087413U (en) Electromechanical pipeline hoisting structure of large-span steel construction
CN212982187U (en) Building construction is with lift that has high-efficient safety device
CN216105555U (en) Adjustable assembly type building stair component hoisting tool
CN218288070U (en) Scaffold platform for repairing ship convenient to install
CN216215436U (en) Automatic lifter hanger for live working
CN220485058U (en) Lifting appliance for building construction
CN212226858U (en) Lifting type high-pole lamp
CN220487059U (en) Portable suspension cable construction hanging flower basket
CN220811580U (en) Efficient curtain wall lifting device
CN215326552U (en) Hoisting accessory that has protect function based on prefabricated building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant