CN219528488U - Assembled protection device for construction elevator in hoistway - Google Patents

Assembled protection device for construction elevator in hoistway Download PDF

Info

Publication number
CN219528488U
CN219528488U CN202320446337.XU CN202320446337U CN219528488U CN 219528488 U CN219528488 U CN 219528488U CN 202320446337 U CN202320446337 U CN 202320446337U CN 219528488 U CN219528488 U CN 219528488U
Authority
CN
China
Prior art keywords
protection
protective
middle plate
scaffold
side plates
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320446337.XU
Other languages
Chinese (zh)
Inventor
何骏炜
曹跃军
黄兴
吴坚荣
黄嘉琪
许运盼
潘海峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Construction Group Co Ltd
Original Assignee
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Construction Group Co Ltd filed Critical Zhongtian Construction Group Co Ltd
Priority to CN202320446337.XU priority Critical patent/CN219528488U/en
Application granted granted Critical
Publication of CN219528488U publication Critical patent/CN219528488U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B50/00Energy efficient technologies in elevators, escalators and moving walkways, e.g. energy saving or recuperation technologies

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

The utility model discloses an assembly type protection device for a construction elevator in a hoistway, and belongs to the field of construction equipment. The spliced protective device is arranged on a frame beam of a floor above a construction elevator in a hoistway and comprises a protective side plate, a protective middle plate and a scaffold clamping piece. The protection curb plate is fixed with in frame roof beam top both sides, is provided with the protection medium plate between the protection curb plate for protection curb plate and protection medium plate amalgamation cover frame roof beam top. The splice of the top of the protective side plate and the protective middle plate is provided with a circular hole for the scaffold to pass through, and two scaffold clamping pieces are arranged around the circular hole. The bottom of the scaffold clamping piece is bent, and the bent part of the bottom covers gaps among the scaffold, the protection side plates and the protection middle plate. The gap is blocked by waterproof sealing material. The assembly type protective device is convenient and simple to install and detach, can be matched with elevator shafts of various sizes, can be recycled, and can improve construction efficiency.

Description

Assembled protection device for construction elevator in hoistway
Technical Field
The utility model belongs to the field of construction equipment, and particularly relates to an assembly type protection device for a construction elevator in a hoistway.
Background
The well formula construction elevator sets up in the elevator well, when concrete placement operation is carried out on upper portion, has concrete and raw materials to drop, for the safe handling of protection well formula construction elevator, often need set up one protection in upper portion, adopts mode and waterproofing membrane's form to install generally. The method requires woodworking and waterproof workers to complete the matching, and the installation time is long. In the protection, dismantling, lifting and installing processes, the wood templates are easy to damage, the material loss rate is high, and the turnover capacity is low. In addition, the wood pattern installation of the method is generally directly placed on the structural plate, so that the reliability is low, and safety risks exist.
Therefore, there is a need for a protection device that seals and prevents water for construction elevators in a hoistway, is not easily damaged, can be reused, and has high installation and removal efficiency.
Disclosure of Invention
The utility model aims to solve the defects in the prior art and provides an assembly type protection device for an elevator constructed in a hoistway.
The specific technical scheme adopted by the utility model is as follows:
the utility model provides an assembly type protective device for an elevator in a hoistway, which particularly comprises a protective side plate, a protective middle plate and a scaffold clamping piece. The spliced protective device is arranged on a frame beam of a building above a construction elevator in a hoistway and used for protecting the construction elevator.
The bottom of protection curb plate and protection medium plate is buckled, and the department of buckling has two with the plane laminating protection curb plate of frame roof beam, and every piece bottom department of buckling is provided with a plurality of haplopore gaskets, utilizes first fastener to pass the haplopore gasket is fixed in the top both sides of frame roof beam respectively with two protection curb plates.
One or more protection middle plates with bent bottoms are arranged between the two protection side plates, so that the protection side plates and the protection middle plates are spliced to cover the top of the frame beam. Circular holes for the scaffold to pass through are formed in the spliced positions of the tops of the protective side plates and the protective middle plate. Two scaffold clamping pieces are arranged around the round hole. The two scaffold clamping pieces are fixedly connected through a second fastener. The bottoms of the two scaffold clamping pieces are bent, and the bent parts of the bottoms cover gaps among the scaffold, the protection side plates and the protection middle plate. The bottom of the scaffold penetrates through the protection side plates and the protection middle plate and then is fixed on the main body structure of the elevator shaft.
The bottom bending and splicing parts of the protection side plates and the protection middle plate are provided with double-hole gaskets. The double-hole gasket spans the gap at the joint of the protection side plate and the protection middle plate and is respectively provided with a first fastener in two holes to realize the tight splicing of the protection side plate and the protection middle plate.
The joints of the protective side plates, the protective middle plate and the scaffold clamping pieces are plugged by waterproof sealing materials. The joints of the protective side plates, the protective middle plate and the frame beam are blocked by waterproof sealing materials.
Preferably, the installation floor of the split type protective device is two floors higher than the highest stop floor of the construction elevator in the hoistway.
Preferably, a plurality of single-hole gaskets are arranged at the bending part of the bottom of the protective middle plate, and the protective middle plate is further fixed on the frame beam by penetrating the single-hole gaskets through a first fastener.
Preferably, the waterproof sealing material adopts sealing glue, sealing rubber strips, building sealing paste, foam plugs or rubber gaskets.
Preferably, the materials of the protective side plates, the protective middle plate and the scaffold clamping pieces are steel plates.
Preferably, the first fastener is an expansion bolt.
Preferably, the second fastener is a screw.
Compared with the prior art, the utility model has the following beneficial effects:
(1) The protection device provided by the utility model is assembled by adopting the steel plates, the waterproof sealing material is adopted for plugging at the joint of the joints, so that the tightness of the whole protection device is ensured, and the influence of falling of concrete and raw materials thereof in the upper construction process of a building structure on the safety of a lower construction elevator is prevented;
(2) The protection device provided by the utility model can be upwards transferred along with the increase of floors in the building process; the protection device is convenient to install and dismantle, can be matched with elevator shafts of various sizes, can be used repeatedly, and improves the turnover capacity of materials.
Drawings
Fig. 1 is a schematic installation diagram of a split mounting type protection device provided in the present embodiment;
fig. 2 is an enlarged view of an installation node of the split mounting type protection device provided in the present embodiment;
fig. 3 is a schematic view of a scaffold clip provided in this embodiment;
in the figure: frame beam 1, protection curb plate 2, protection medium plate 3, single hole gasket 4, diplopore gasket 5, first fastener 6, scaffold clamping piece 7, second fastener 8 and scaffold 9.
Detailed Description
In order that the above objects, features and advantages of the utility model will be readily understood, a more particular description of the utility model will be rendered by reference to the appended drawings. In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present utility model. The present utility model may be embodied in many other forms than described herein and similarly modified by those skilled in the art without departing from the spirit of the utility model, whereby the utility model is not limited to the specific embodiments disclosed below. The technical features of the embodiments of the utility model can be combined correspondingly on the premise of no mutual conflict.
In the description of the present utility model, it will be understood that when an element is referred to as being "connected" to another element, it can be directly connected to the other element or be indirectly connected with intervening elements present. In contrast, when an element is referred to as being "directly connected" to another element, there are no intervening elements present.
In the description of the present utility model, it should be understood that the terms "first" and "second" are used solely for the purpose of distinguishing between the descriptions and not necessarily for the purpose of indicating or implying a relative importance or implicitly indicating the number of features indicated. Thus, a feature defining "a first" or "a second" may explicitly or implicitly include at least one such feature.
As the existing high-rise building is built higher, the number of house layers is increased, if a frame structure is selected, the anti-seismic requirement cannot be met, and frame beams are required to be arranged in the shear wall, so that the anti-seismic effect can be achieved. In the building process, the construction elevator is upwards arranged along with the construction progress. In order to avoid the influence of concrete and raw materials falling on the construction elevator when the concrete pouring operation is carried out above the construction elevator, a protection device is required to be arranged on a frame beam above the construction elevator.
As shown in fig. 1 and 2, in a preferred embodiment of the present utility model, there is provided an in-hoistway construction elevator assembly type protector, which mainly includes two protective side plates 2, a protective middle plate 3, and four scaffold clips 7. In this embodiment, the installation floor of the above-described modular guard is two floors higher than the highest stop floor of the construction elevator in the hoistway. The connection relation and the use method of each component are described in detail below.
The two protection side plates 2 are respectively arranged on two sides above the frame beam 1. The bottom of the protection side plate 2 is bent, and the bending part is attached to the plane of the frame beam 1. The bending part at the bottom of the protection side plate 2 is provided with a plurality of single-hole gaskets 4, and the first fastening piece penetrates through the single-hole gaskets 4 to fix the protection side plate 2 on the frame beam 1. A protective middle plate 3 is arranged between the two protective side plates 2. The bottom of the protection middle plate 3 is bent, and the bending part is also attached to the plane of the frame beam 1. The bottom bending and splicing part of the protection side plate 2 and the protection middle plate 3 is provided with a double-hole gasket 5, and the double-hole gasket 5 spans a gap between the protection side plate 2 and the protection middle plate 3. The first fasteners 6 are respectively installed in the two holes to realize the tight splicing of the protective side plates 2 and the protective middle plate 3, so that the protective side plates 2 and the protective middle plate 3 are arranged on the frame beam 1 in a full-spread mode, and a whole protective device main body structure is formed.
In view of the large load that the connections between the protective side plates 2, the protective middle plate 3 and the frame beam 1 need to carry, expansion bolts are selected as the first fasteners in this embodiment. When the device is used, the impact electric drill or the impact hammer is used for drilling holes with corresponding sizes on the fixed body (namely the frame beam), then the bolts and the expansion pipes are arranged in the holes, and the nuts are screwed, so that the bolts, the expansion pipes, the mounting parts (namely the protection side plates and the protection middle plate) and the fixed body (namely the frame beam) are expanded into a whole.
It should be noted that, if the size of the frame beam 1 is smaller, the two protection side plates 2 can be covered on the frame beam 1 in a full-spread mode after being spliced, and then the protection middle plate 3 is not required to be additionally arranged; if the frame beam 1 is large in size or the elevator shaft to be protected is composed of a plurality of continuous protection shafts, a plurality of protection middle plates 3 can be additionally arranged between the two protection side plates 2 to enlarge the protection range.
In order to make the worker more convenient in high-altitude construction and ensure the smooth construction process, a scaffold 9 is required to be arranged in the elevator shaft. The bottom of the scaffold 9 is fixed on the I-steel of one layer on the highest stop floor of the construction elevator. The I-steel both sides are fixed in elevator well body structure.
The splice at the tops of the protective side plates 2 and the protective middle plate 3 is provided with a circular hole for the scaffold 9 to pass through. In order to ensure that the scaffold 9 can be tightly connected with the protection side plates 2 and the protection middle plate 3, materials such as fine crushed concrete and the like are prevented from falling to damage a construction elevator below, two scaffold clamping pieces 7 are arranged around each circular hole at the splicing position of the tops of the protection side plates 2 and the protection middle plate 3. The two scaffold clips 7 are arranged opposite to each other so that they can wrap the passing scaffold 9. The two scaffold clamping piece sides are fixedly connected through screws. In addition, the bottoms of the two scaffold clamping pieces 7 are bent, and the bent parts of the bottoms cover gaps among the scaffold 9, the protective side plates 2 and the protective middle plate 3.
In order to further ensure the tightness of the whole assembly type protective device, the joints of the protective side plates 2, the protective middle plate 3 and the scaffold clamping pieces 7 and the joints of the protective side plates 2, the protective middle plate 3 and the frame beam 1 are plugged by waterproof sealing materials. In this embodiment, the sealant is selected as a waterproof sealing material for sealing. However, the waterproof sealing material is not required in this embodiment, and materials such as a sealing rubber strip, a building sealing paste, a foam plug, and a rubber gasket may be selected.
Under the condition that the main body structure is a frame beam, the assembly type protection device is arranged. If the frame beam 1 structure is replaced by a shear wall structure, the protection effect on the construction elevator can be realized, and only the bottom bending of the protection side plate 2 and the protection middle plate 3 is canceled, and the side edges of the protection side plate 2 and the protection middle plate are directly fixedly connected with the edge of the shear wall through fasteners.
The split mounting type protection device provided by the embodiment is convenient and simple to install and detach, can be matched with elevator shafts of various sizes, can be recycled and reused, and can improve construction efficiency. And the protection device is tightly connected with the main body structure, the gaps are blocked by waterproof materials, the whole engineering is completed by common workers, and the waterproof construction is reduced.
The above embodiment is only a preferred embodiment of the present utility model, but it is not intended to limit the present utility model. Various changes and modifications may be made by one of ordinary skill in the pertinent art without departing from the spirit and scope of the present utility model. Therefore, all the technical schemes obtained by adopting the equivalent substitution or equivalent transformation are within the protection scope of the utility model.

Claims (7)

1. The spliced protective device for the construction elevator in the hoistway is characterized by comprising a protective side plate (2), a protective middle plate (3) and a scaffold clamping piece (7); the spliced protective device is arranged on a frame beam (1) of a floor above a construction elevator in a hoistway and is used for protecting the construction elevator;
the bottoms of the protection side plates (2) and the protection middle plate (3) are bent, and the bent parts are attached to the plane of the frame beam (1); the two protection side plates (2) are provided with a plurality of single-hole gaskets (4) at the bending position of the bottom of each block, and the two protection side plates (2) are respectively fixed on the two sides of the top of the frame beam (1) by penetrating the single-hole gaskets (4) through first fasteners (6);
one or more protection middle plates (3) with bent bottoms are arranged between the two protection side plates (2), so that the protection side plates (2) and the protection middle plates (3) are spliced to cover the top of the frame beam (1); the joint of the tops of the protective side plates (2) and the protective middle plate (3) is provided with a circular hole for a scaffold (9) to pass through; two scaffold clamping pieces (7) are arranged around the round hole; the two scaffold clamping pieces (7) are fixedly connected through a second fastening piece (8); the bottoms of the two scaffold clamping pieces (7) are bent, and gaps among the scaffold (9), the protective side plates (2) and the protective middle plate (3) are covered at the bent parts of the bottoms; the bottom of the scaffold (9) passes through the protective side plate (2) and the protective middle plate (3) and then is fixed on the main structure of the elevator shaft;
the bottom bending and splicing parts of the protective side plates (2) and the protective middle plate (3) are provided with double-hole gaskets (5); the double-hole gasket (5) spans a gap at the joint of the protective side plate (2) and the protective middle plate (3) and is respectively provided with a first fastener (6) in the two holes to realize the tight splicing of the protective side plate (2) and the protective middle plate (3);
the joints of the protective side plates (2), the protective middle plate (3) and the scaffold clamping pieces (7) are plugged by waterproof sealing materials; the joints of the protective side plates (2), the protective middle plate (3) and the frame beam (1) are plugged by waterproof sealing materials.
2. The in-hoistway construction elevator assembly safety device of claim 1, wherein an installation floor of the assembly safety device is two floors higher than a highest stop floor of an in-hoistway construction elevator.
3. The assembly type protection device for the construction elevator in the hoistway according to claim 1, wherein a plurality of single hole gaskets (4) are arranged at the bending position of the bottom of the protection middle plate (3), and the protection middle plate (3) is further fixed on the frame beam (1) by penetrating the single hole gaskets (4) through a first fastener.
4. The in-hoistway construction elevator assembly type protection device according to claim 1, wherein the waterproof sealing material is sealant, sealing rubber strip, building sealing paste, foam plug or rubber gasket.
5. The assembly type protection device for the construction elevator in the hoistway according to claim 1, wherein the materials of the protection side plates (2), the protection middle plate (3) and the scaffold clamping pieces (7) are steel plates.
6. The in-hoistway construction elevator assembly protection device of claim 1, wherein the first fastener (6) is an expansion bolt.
7. The in-hoistway construction elevator assembly guard of claim 1, wherein the second fastener (8) is a screw.
CN202320446337.XU 2023-03-10 2023-03-10 Assembled protection device for construction elevator in hoistway Active CN219528488U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320446337.XU CN219528488U (en) 2023-03-10 2023-03-10 Assembled protection device for construction elevator in hoistway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320446337.XU CN219528488U (en) 2023-03-10 2023-03-10 Assembled protection device for construction elevator in hoistway

Publications (1)

Publication Number Publication Date
CN219528488U true CN219528488U (en) 2023-08-15

Family

ID=87581772

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320446337.XU Active CN219528488U (en) 2023-03-10 2023-03-10 Assembled protection device for construction elevator in hoistway

Country Status (1)

Country Link
CN (1) CN219528488U (en)

Similar Documents

Publication Publication Date Title
US9878187B2 (en) Joist anchor
CN210508327U (en) Scaffold board subplate and turn over board of scaffold
CN215407311U (en) A protective structure for climbing frame group seam department
CN219528488U (en) Assembled protection device for construction elevator in hoistway
CN112112418A (en) Construction method of high-rise building aluminum formwork climbing frame combined system
JP2019173334A (en) Dry floor structure and construction method thereof, and seal dry floor panel and previously laminated dry floor panel forming dry floor structure
CN203160726U (en) Tool type edge protection structure
EP0361039A2 (en) Prefabricated building
CN214034053U (en) Strengthen evaporating and pressing aerated concrete slab building structure system
CN210797579U (en) Detachable soil nailing wall structure
CN209994020U (en) Bridge with firmly fixed cover plate
CN219316410U (en) Aluminum mould construction entrance to a cave safety device
CN214423604U (en) Explosion-proof wall of assembling fast
CN215859205U (en) Protective device for tower crane through structural slab
CN209855992U (en) Detachable sound-proof shield of gas compressor
CN210105730U (en) Portable crane span structure climbing ladder
CN220523474U (en) Structure of pipeline through wall
CN213358560U (en) Novel need not welded lightening hole protection device
CN214615352U (en) Regularization well protection operation platform
CN211010756U (en) Steel grating fixing system
CN213205021U (en) Assembled safe construction passageway
CN217811948U (en) Fireproof roof structure
CN220868777U (en) Scaffold gangway
CN206071025U (en) A kind of attachment support suitable for super-high storied building steel climbing frame
CN219569669U (en) Assembled drawknot protection shed

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant