CN220523474U - Structure of pipeline through wall - Google Patents

Structure of pipeline through wall Download PDF

Info

Publication number
CN220523474U
CN220523474U CN202322189212.6U CN202322189212U CN220523474U CN 220523474 U CN220523474 U CN 220523474U CN 202322189212 U CN202322189212 U CN 202322189212U CN 220523474 U CN220523474 U CN 220523474U
Authority
CN
China
Prior art keywords
equipment pipeline
wall
steel
hoop
flat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202322189212.6U
Other languages
Chinese (zh)
Inventor
贺光
贺子珺
李宗奇
杨树香
安晓楠
刘佳琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Haiwan Chemical Engineering Design & Research Institute Co ltd
Original Assignee
Qingdao Haiwan Chemical Engineering Design & Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Haiwan Chemical Engineering Design & Research Institute Co ltd filed Critical Qingdao Haiwan Chemical Engineering Design & Research Institute Co ltd
Priority to CN202322189212.6U priority Critical patent/CN220523474U/en
Application granted granted Critical
Publication of CN220523474U publication Critical patent/CN220523474U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

The utility model discloses a pipeline wall penetrating structure which comprises a wall body, a steel sleeve, an equipment pipeline and a fixing mechanism, wherein the equipment pipeline is arranged in the steel sleeve, a sealing adhesive layer and a filling foaming layer are respectively arranged between the equipment pipeline and a port of the steel sleeve, a rubber water stop belt is fixedly connected to the outer sides of the ports of the equipment pipeline and the steel sleeve, an aluminum alloy folded plate is arranged on the outer sides of the rubber water stop belt, two fixing mechanisms are symmetrically sleeved on the outer sides of the equipment pipeline, the steel sleeve and the aluminum alloy folded plate, the problem that cracks occur to the wall body due to deformation and expansion of the equipment pipeline can be avoided by arranging the steel sleeve, the problem of heat preservation of gaps between the steel sleeve and the equipment pipeline can be solved by arranging the sealing adhesive layer and the filling foaming layer, and rainwater can be prevented from entering a room through the gaps between the sleeve and the equipment pipeline by arranging the rubber water stop belt and the aluminum alloy folded plate, and therefore the wall body cracking prevention and waterproof heat preservation effects can be achieved.

Description

Structure of pipeline through wall
Technical Field
The utility model relates to the technical field of pipeline construction, in particular to a pipeline wall penetrating structure.
Background
Along with the requirement of social green economic development, a large number of pollution chemical enterprises in cities need to be transformed, upgraded and moved outside, each large city sequentially builds an economic development area and a chemical industry park, and many enterprises are transformed, upgraded and changed into fine chemical or petrochemical enterprises, and the fine chemical or petrochemical enterprises are provided with holes on building walls, through which the connection of a plurality of containers and towers is required to pass, to enter and exit the connection. Because many pipelines have vibration or deformation expansion caused by higher temperature, the pipelines must be separated from the building wall, so that gaps between the building wall and the pipelines are cracked, and the problems of heat preservation and rain prevention of the wall cannot be solved.
The common building method is that a hole is reserved on the wall surface, and the residual gap is plugged by adopting cement mortar after the pipeline is installed. The construction method is very easy to cause that mortar in the gap is pulled away when the pipeline stretches and contracts, and is also unfavorable for overhauling, installing and disassembling the pipeline in the future. A structure of a conduit through wall is therefore proposed to optimise and solve the above problems.
Disclosure of Invention
The present utility model is directed to a structure of a conduit through wall, so as to solve the problems set forth in the background art.
In order to achieve the above purpose, the present utility model provides the following technical solutions:
the utility model provides a pipeline wall structure, includes the wall body, the opening has been seted up to wall body central point department, opening inner wall fixedly connected with reinforced concrete bolt layer be provided with the steel bushing in the wall body opening, steel bushing outside fixedly connected with fixed ring board, fixed ring board is fixed to be inlayed and is established in reinforced concrete bolt layer, steel bushing inside is provided with the equipment pipeline, be provided with the sealant layer between equipment pipeline and the steel bushing port respectively and fill the foaming layer, equipment pipeline and steel bushing port outside fixedly connected with rubber waterstop, the rubber waterstop outside is provided with the aluminum alloy folded plate, equipment pipeline, steel bushing and aluminum alloy folded plate outside symmetry cover are equipped with two fixed establishment, fixed establishment includes first flat steel hoop, second flat steel hoop and fixing bolt, the inboard and the aluminum alloy closely laminate of first flat steel hoop and second flat steel hoop, be connected through fixing bolt between first flat steel hoop and the second folded plate.
As a further scheme of the utility model: the outer wall of the steel sleeve is attached to and fixedly connected with the inner wall of the reinforced cement bolt layer.
As still further aspects of the utility model: and the reinforced cement bolt layer is provided with a groove for fixing the ring plate.
As still further aspects of the utility model: the aluminum alloy folded plate is sleeved outside the equipment pipeline and the steel sleeve port.
As still further aspects of the utility model: the first flat steel hoop and the second flat steel hoop are symmetrically arranged.
As still further aspects of the utility model: threaded through holes for fixing the threaded connection of the bolts are respectively formed in the first flat steel hoop and the second flat steel hoop.
Compared with the prior art, the utility model has the beneficial effects that:
can avoid the wall body to appear cracked problem because of equipment pipeline warp flexible through setting up the steel bushing, can be to solving the heat preservation problem in gap between steel bushing and the equipment pipeline through setting up the sealant layer and filling the foaming layer, can prevent through setting up rubber waterstop and aluminum alloy folded plate that the rainwater from getting into indoor through the gap between bushing and the equipment pipeline to make above structure can reach and prevent wall body fracture and waterproof heat retaining effect.
Drawings
Fig. 1 is a schematic structural view of a structure of a pipe through wall.
Fig. 2 is a schematic view of a part of the structure of a conduit through wall.
Fig. 3 is a schematic view of a partial structure in the structure of a conduit through wall.
The figure shows: the wall body 1, the reinforced cement bolt layer 2, the steel sleeve 3, the fixed annular plate 4, the equipment pipeline 5, the sealant layer 6, the filling foaming layer 7, the rubber water stop belt 8, the aluminum alloy folded plate 9, the fixing mechanism 10, the first flat steel hoop 11, the second flat steel hoop 12 and the fixing bolt 13.
Detailed Description
The following description of the embodiments of the present utility model will be made clearly and completely with reference to the accompanying drawings, in which it is apparent that the embodiments described are only some embodiments of the present utility model, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the utility model without making any inventive effort, are intended to be within the scope of the utility model.
Referring to fig. 1 to 3, in the embodiment of the utility model, a structure of a pipeline through wall comprises a wall body 1, a reinforced cement bolt layer 2, a steel sleeve 3, a fixed annular plate 4, an equipment pipeline 5, a sealing glue layer 6, a filling foaming layer 7, a rubber water stop belt 8, an aluminum alloy folded plate 9, a fixing mechanism 10, a first flat steel hoop 11, a second flat steel hoop 12 and a fixing bolt 13, wherein an opening is formed in the central position of the wall body 1, the reinforced cement bolt layer 2 is fixedly connected to the inner wall of the opening, the steel sleeve 3 is arranged in the opening of the wall body 1, and the outer wall of the steel sleeve 3 is attached to and fixedly connected with the inner wall of the reinforced cement bolt layer 2.
The steel sleeve 3 outside fixedly connected with fixed ring plate 4, fixed ring plate 4 is fixed to be inlayed and is established in reinforced cement bolt layer 2, set up the recess that is used for fixed ring plate 4 to fixedly inlay on the reinforced cement bolt layer 2, the inside equipment pipeline 5 that is provided with of steel sleeve 3, be provided with sealing gel layer 6 and packing foaming layer 7 between equipment pipeline 5 and the 3 ports of steel sleeve respectively, equipment pipeline 5 and 3 ports outside fixedly connected with rubber waterstop 8 of steel sleeve, the 8 outsides of rubber waterstop are provided with aluminum alloy folded plate 9, aluminum alloy folded plate 9 cover is established in the equipment pipeline 5 and 3 ports outsides of steel sleeve.
The equipment pipeline 5, steel bushing 3 and aluminum alloy folded plate 9 outside symmetry cover is equipped with two fixed establishment 10, fixed establishment 10 includes first flat steel hoop 11, second flat steel hoop 12 and fixing bolt 13, first flat steel hoop 11 and second flat steel hoop 12 are the symmetry setting, the inboard and the aluminum alloy folded plate 9 of first flat steel hoop 11 and second flat steel hoop 12 are closely laminated, connect through fixing bolt 13 between first flat steel hoop 11 and the second flat steel hoop 12, set up the screw thread through-hole that is used for fixing bolt 13 threaded connection on first flat steel hoop 11 and the second flat steel hoop 12 respectively.
The working principle of the utility model is as follows:
when the structure of the pipeline through wall is needed, a person firstly fixedly installs the steel sleeve 3 at a reserved opening on the wall body, then further plugs the equipment pipeline 5 through the steel sleeve 3 and adopts the sealant layer 6 and the filling foaming layer 7, and then the telescopic rubber water stop strip 8 and the aluminum alloy folded plate 9 are used between the steel sleeve 3 and the equipment pipeline 5 on the outer side of the wall body 1, and the first flat steel hoop 11 and the second flat steel hoop 12 in the fixing mechanism 10 are clamped on the aluminum alloy folded plate 9 and are connected through the fixing bolts 13, so that secondary plugging between the steel sleeve 3 and the equipment pipeline 5 is completed, and the through wall installation operation of the equipment pipeline 5 is completed.
Although the present utility model has been described with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described, or equivalents may be substituted for elements thereof, and any modifications, equivalents, improvements and changes may be made without departing from the spirit and principles of the present utility model.

Claims (6)

1. The utility model provides a pipeline wall structure, includes wall body (1), its characterized in that: the wall body (1) central point puts and has been seted up the opening, opening inner wall fixedly connected with reinforcing bar cement bolt layer (2) be provided with steel casing (3) in wall body (1) opening, steel casing (3) outside fixedly connected with fixed link plate (4), fixed link plate (4) are fixed to be inlayed and are established in reinforcing bar cement bolt layer (2), steel casing (3) inside is provided with equipment pipeline (5), be provided with sealant layer (6) and packing foaming layer (7) between equipment pipeline (5) and steel casing (3) port respectively, equipment pipeline (5) and steel casing (3) port outside fixedly connected with rubber waterstop (8), rubber waterstop (8) outside is provided with aluminum alloy folded plate (9), equipment pipeline (5), steel casing (3) and aluminum alloy folded plate (9) outside symmetry cover are equipped with two fixed establishment (10), fixed establishment (10) include first flat steel hoop (11), second flat hoop (12) and fixing bolt (13), first flat hoop (11) and second flat hoop (12) are closely laminated with steel alloy folded plate (9) outside through fixed flat hoop (13).
2. The structure of a conduit wall feed-through according to claim 1, wherein: the outer wall of the steel sleeve (3) is attached to and fixedly connected with the inner wall of the reinforced cement bolt layer (2).
3. The structure of a conduit wall feed-through according to claim 1, wherein: the reinforced cement bolt layer (2) is provided with a groove for fixing the ring plate (4) in a fixed embedded mode.
4. The structure of a conduit wall feed-through according to claim 1, wherein: the aluminum alloy folded plate (9) is sleeved outside the ports of the equipment pipeline (5) and the steel sleeve (3).
5. The structure of a conduit wall feed-through according to claim 1, wherein: the first flat steel hoop (11) and the second flat steel hoop (12) are symmetrically arranged.
6. The structure of a conduit wall feed-through according to claim 1, wherein: threaded through holes for threaded connection of the fixing bolts (13) are respectively formed in the first flat steel hoop (11) and the second flat steel hoop (12).
CN202322189212.6U 2023-08-15 2023-08-15 Structure of pipeline through wall Active CN220523474U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202322189212.6U CN220523474U (en) 2023-08-15 2023-08-15 Structure of pipeline through wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202322189212.6U CN220523474U (en) 2023-08-15 2023-08-15 Structure of pipeline through wall

Publications (1)

Publication Number Publication Date
CN220523474U true CN220523474U (en) 2024-02-23

Family

ID=89924059

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202322189212.6U Active CN220523474U (en) 2023-08-15 2023-08-15 Structure of pipeline through wall

Country Status (1)

Country Link
CN (1) CN220523474U (en)

Similar Documents

Publication Publication Date Title
CN201245909Y (en) Back hanging anchor bolt type stone curtain wall structure with waterproof layer
CN107313455B (en) Cast-in-place and prefabricated combined single-bin comprehensive pipe gallery node and construction method
CN110424458A (en) Tunneling boring PC piping lane piece construction and its closed-water test method
CN103615047B (en) The method that lighting roof steel truss and curtain wall are installed high up in the air
CN211286074U (en) Self-heat-insulation system for prefabricated light high-strength foam concrete filled wallboard outer wall
CN110612373A (en) Prefabricated pre-decorated volume construction of buildings
CN207018649U (en) A kind of Novel fireproof pipeline crossing cabin part for marine rig module
CN220523474U (en) Structure of pipeline through wall
CN105781329A (en) Technology for connection between aluminum alloy door window frame and wall body
CN106149922A (en) A kind of dismantled and assembled stealthy partition wall system and assembly and disassembly methods thereof
CN209873861U (en) Sealing device for lap joint of steel corrugated plate pipe gallery plates
CN211172078U (en) Assembled waterproof lifting hook
CN207878523U (en) Concrete pipe gallery mid-board waterproof structure for deformation seams
CN212002086U (en) Decorative moulding connecting device for outer vertical surface of fabricated building
CN220620503U (en) Waterproof structure for connecting prefabricated embedded outer wall of assembled steel structure with steel column
CN104975686A (en) Waterproof node structure of air pipe concrete discharge structure cave entrance and construction method of waterproof node structure
CN216476583U (en) Quick-mounting modular water tank water inlet and outlet pipe connecting structure
CN216108651U (en) Piping lane movement joint bottom plate waterproof construction
CN220666276U (en) Water supply and drainage pipeline pipe gallery
CN219367021U (en) High-air-tightness wall-penetrating pipeline structure suitable for concrete structure pressurization building
CN219912062U (en) Waterproof structure of wall penetrating pipe
CN213836546U (en) Pre-embedding device for fixing end nut of rear-assembling rubber waterstop
CN209670702U (en) A kind of building doors and windows stuff up a crack water proof structure
CN218597559U (en) Structure of outdoor platform poling of ultralow energy consumption assembly type structure
CN217580823U (en) Assembled steel column combination fire prevention structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant