CN219471712U - Large advertisement cloth fence for construction during operation - Google Patents

Large advertisement cloth fence for construction during operation Download PDF

Info

Publication number
CN219471712U
CN219471712U CN202320493073.3U CN202320493073U CN219471712U CN 219471712 U CN219471712 U CN 219471712U CN 202320493073 U CN202320493073 U CN 202320493073U CN 219471712 U CN219471712 U CN 219471712U
Authority
CN
China
Prior art keywords
advertisement cloth
cloth
disc
fence
scaffold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320493073.3U
Other languages
Chinese (zh)
Inventor
李萌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Santori Shanghai Engineering Consulting Co ltd
Original Assignee
Santori Shanghai Engineering Consulting Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Santori Shanghai Engineering Consulting Co ltd filed Critical Santori Shanghai Engineering Consulting Co ltd
Priority to CN202320493073.3U priority Critical patent/CN219471712U/en
Application granted granted Critical
Publication of CN219471712U publication Critical patent/CN219471712U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A large advertising cloth fence for construction during operation, comprising: the fire-proof wall comprises a plate-buckling scaffold, a surrounding frame, fire-proof advertisement cloth, a wall connecting piece and a binding belt, wherein the surrounding frame is connected with the plate-buckling scaffold, the surrounding frame is arranged on the inner side of the fire-proof advertisement cloth, the fire-proof advertisement cloth is connected with the plate-buckling scaffold through the binding belt, and the wall connecting piece is connected with the plate-buckling scaffold. Wherein, the dish knot formula scaffold includes: upright pole, disc, horizontal pole and bolt. Compared with the prior art, the method solves the limitation of influence of construction time and construction efficiency, ensures the installation quality and apparent effect of each node, adopts sectional erection, can finish the erection work in a limited space and a limited number of people, reduces personnel cost, manages cost and avoids operation loss cost.

Description

Large advertisement cloth fence for construction during operation
Technical Field
The utility model relates to a building construction system, in particular to a large advertisement cloth fence for building construction during operation.
Background
In recent years, the construction of domestic theme parks and foreign theme parks continuously flow into China, and with the construction of large theme parks, the operation is opened, so that a large number of tourists can be attracted to play experiences each year. During the operation of the park, new theme elements are added to reform and newly build the building, and the newly added theme elements are constructed during the operation, so that the operation of the park, safety and the experience of tourists are greatly influenced during the construction. Therefore, temporary construction maintenance is carried out on the building under construction urgently, on one hand, the visual experience of tourists during operation is met, and on the other hand, the safety of the tourists during operation is guaranteed. Due to the specificity of theme parks, there are mainly the following factors: 1. construction is not allowed during operation, which results in a construction time (night time) of only 6 hours per day to the garden clearing opening before the garden closing and opening, and the night construction results in a reduction in construction efficiency. 2. Because of the limitation of theme park sites, materials such as scaffolds for building large-scale advertisement cloth fences are stored, the advertisement cloth frames are far away from the site, secondary transportation is involved, and hard wood boards are required to be paved and protected on all pavements during transportation. 3. All procedures are in a finished state before the large advertising cloth fence is erected, the effect must reach the visual requirement, and the tourist experience cannot be influenced. 4. Workers cannot advance the field, and need to advance the field after closing the garden, so that many preparation works cannot be performed in advance. 5. The large advertisement cloth is accessible to tourists below the fence, and the visitors above the building can see the advertisement cloth.
Aiming at the limitation of the factors, the large advertisement cloth is very stressed in enclosing and blocking time on the premise of ensuring the effect and the safety quality, and the maintenance of the traditional building construction outer wall scaffold encryption mesh network cannot meet the requirements from the aspects of aesthetic degree and safety performance.
To solve the above problems, we have made a series of improvements.
Disclosure of Invention
The utility model aims to provide a large advertisement cloth fence for building construction during operation, which overcomes the defects and the shortcomings of the prior art.
A large advertising cloth fence for construction during operation, comprising: the fire-proof wall comprises a plate-buckle type scaffold, a surrounding frame, a fire-proof advertisement cloth, a wall connecting piece and a binding belt, wherein the surrounding frame is connected with the plate-buckle type scaffold;
wherein, the dish knot formula scaffold includes: the fireproof advertisement comprises a vertical rod, a disc, a cross rod and a bolt, wherein the disc is arranged on the vertical rod, the cross rod is fixedly connected with the disc through the bolt, the cross rod is connected with a surrounding frame, the vertical rod is connected with the left end and the right end of the fireproof advertisement cloth, the upper end and the lower end of the cross rod are connected with the fireproof advertisement cloth, and the vertical rod is connected with a building wall through a wall connecting piece.
Further, be equipped with the claw on enclosing the fender frame, enclose and keep off the frame and be connected with the horizontal pole through the claw, enclose and keep off through self-tapping screw fixed connection between the frame, enclose and keep off the height of frame and be 3m, the width is 1.5m.
Further, the wall connecting member includes: the steel pipe is welded with the steel plate, and the steel plate is connected with the building wall through the expansion bolts.
The utility model has the beneficial effects that:
compared with the prior art, the method solves the limitation of influence of construction time and construction efficiency, ensures the installation quality and apparent effect of each node, adopts sectional erection, can finish the erection work in a limited space and a limited number of people, reduces personnel cost, manages cost and avoids operation loss cost.
Description of the drawings:
fig. 1 is a schematic plan view of the present utility model.
Fig. 2 is a schematic elevation view of the present utility model.
Fig. 3 is a schematic structural view of the disc buckle type scaffold of the present utility model.
Fig. 4 is a cross-sectional view of a wall coupling according to the present utility model.
Fig. 5 is an enlarged view of a node of the wall-connecting member of the present utility model.
Fig. 6 is a fixed structure view of the fireproof advertising cloth of the present utility model.
Reference numerals:
the scaffold comprises a disc buckle type scaffold 100, a vertical rod 110, a disc 120, a cross bar 130 and a bolt 140.
A fence frame 200, claws 210 and a fire-resistant advertising cloth 300.
Wall connector 400, steel tube 410, steel plate 420, expansion bolts 430, tie 500 and building wall 600.
Detailed Description
The utility model will now be further described with reference to specific examples. It should be understood that the following examples are illustrative of the present utility model and are not intended to limit the scope of the present utility model.
Example 1
Fig. 1 is a schematic plan view of the present utility model. Fig. 2 is a schematic elevation view of the present utility model. Fig. 3 is a schematic structural view of the disc buckle type scaffold of the present utility model. Fig. 4 is a cross-sectional view of a wall coupling according to the present utility model. Fig. 5 is an enlarged view of a node of the wall-connecting member of the present utility model. Fig. 6 is a fixed structure view of the fireproof advertising cloth of the present utility model.
As shown in fig. 1 to 6, a large advertisement cloth fence for construction during operation includes: the wall connecting piece 400 is connected with the disc-buckling scaffold 100, the surrounding frame 200 is arranged on the inner side of the fireproof advertising cloth 300, the fireproof advertising cloth 300 is connected with the disc-buckling scaffold 100 through the binding belt 500, and the wall connecting piece 400 is connected with the disc-buckling scaffold 100;
wherein, the disc buckle type scaffold 100 comprises: the fireproof advertisement cloth comprises a vertical rod 110, a disc 120, a cross rod 130 and a bolt 140, wherein the disc 120 is arranged on the vertical rod 110, the cross rod 130 is fixedly connected with the disc 120 through the bolt 140, the cross rod 130 is connected with a surrounding frame 200, the vertical rod 110 is connected with the left end and the right end of the fireproof advertisement cloth 300, the cross rod 130 is connected with the upper end and the lower end of the fireproof advertisement cloth 300, and the vertical rod 110 is connected with a building wall 600 through a wall connecting piece 400.
The fence frame 200 is provided with the claws 210, the fence frame 200 is connected with the cross bars 130 through the claws 210, the fence frames 200 are fixedly connected through self-tapping screws, the height of the fence frame 200 is 3m, and the width is 1.5m.
Wall link 400 includes: steel pipe 410, steel sheet 420 and expansion bolts 430, steel pipe 410 and steel sheet 420 welded connection, steel sheet 420 passes through expansion bolts 430 and is connected with building wall 600.
The principle of the utility model is that the construction of the advertisement cloth enclosure is firstly to position the scaffold construction path according to the drawing. Building a first layer of scaffold: the fireproof cloth is paved in sequence, the channel steel is paved, the long scaffold board, the base, the vertical rod 110, the longitudinal sweeping rod, the transverse horizontal rod and the longitudinal horizontal rod are positioned, the unloading steel wire rope, the throwing support, the scissor support and the wall connecting piece 400 are arranged, the scaffold board is paved, the protective railing is pricked, and the safety net channel is pricked and set up to be synchronous with the frame body. Then, the enclosure frames 200 are fixed on the transverse rods 130 on the outer sides of the disc buckle type scaffold 100, each enclosure comprises 6 claws 210 on the fixed transverse rods 130, each enclosure frame 200 is fixed by self-tapping screws, the frame size is 3m, the width is 1.5m, the construction is simple and convenient, and meanwhile, the overall stability of the enclosure frames is ensured. When the enclosure frame 200 is installed, the planes of the enclosure frames 200 are kept in the same horizontal plane, the bottoms and the tops of the enclosure frames 200 are kept in the same horizontal line, the fireproof advertisement cloth 300 is installed, the fireproof advertisement cloth 300 is fixed on the cross bars 130 of the outer frames of the scaffolds by using the binding belts 500 up and down, the fireproof advertisement cloth 300 is fixed on the upright posts 110 of the two-side scaffolds left and right, and the binding rolling belts 500 are kept in a straightened state. Finally, the steps are repeated for each layer of installation, meanwhile, the length of 500mm is reserved around the fire-proof advertisement cloth 300 is adjusted, the patterns of the fire-proof advertisement cloth 300 are aligned, the upper layer and the lower layer of enclosure frame 200 are abutted together, the integrity of the patterns of the fire-proof advertisement cloth 300 is guaranteed, the fire-proof advertisement cloth 300 adopts two layers of existing grid cloth, one layer of original base color fire-proof grid cloth and one layer of color printing theme fire-proof grid cloth is covered on the original base color fire-proof grid cloth, the permeability of the enclosure of high wind weather is guaranteed, the inner building cannot be seen by tourists below, and meanwhile, the grid cloth is convenient to dismantle and install in typhoon weather.
Compared with the prior art, the method solves the limitation of influence of construction time and construction efficiency, ensures the installation quality and apparent effect of each node, adopts sectional erection, can finish the erection work in a limited space and a limited number of people, reduces personnel cost, manages cost and avoids operation loss cost.
The present utility model has been described in detail with reference to the embodiments, but the present utility model is not limited thereto, and various modifications may be made without departing from the spirit of the present utility model.

Claims (3)

1. The utility model provides a large-scale advertisement cloth of construction encloses fender during operation, its characterized in that includes: the fireproof wall connecting device comprises a disc buckle type scaffold (100), a surrounding frame (200), fireproof advertisement cloth (300), a wall connecting piece (400) and a binding belt (500), wherein the surrounding frame (200) is connected with the disc buckle type scaffold (100), the surrounding frame (200) is arranged on the inner side of the fireproof advertisement cloth (300), the fireproof advertisement cloth (300) is connected with the disc buckle type scaffold (100) through the binding belt (500), and the wall connecting piece (400) is connected with the disc buckle type scaffold (100);
wherein, the disc buckle type scaffold (100) comprises: pole setting (110), disc (120), horizontal pole (130) and bolt (140), on pole setting (110) are located to disc (120), horizontal pole (130) are through bolt (140) and disc (120) fixed connection, horizontal pole (130) are connected with enclosing fender frame (200), pole setting (110) are connected with both ends about fire prevention advertisement cloth (300), both ends are connected about horizontal pole (130) and fire prevention advertisement cloth (300), pole setting (110) are connected with building wall (600) through linking wall spare (400).
2. A construction large scale advertising cloth fence during operation according to claim 1, characterized in that: the fence frame (200) is provided with a claw (210), the fence frame (200) is connected with the cross rod (130) through the claw (210), the fence frames (200) are fixedly connected through self-tapping screws, and the height of the fence frame (200) is 3m and the width is 1.5m.
3. A construction large scale advertising cloth fence during operation according to claim 1, characterized in that: the wall-connecting member (400) includes: the steel pipe (410), steel plate (420) and expansion bolts (430), steel pipe (410) and steel plate (420) welded connection, steel plate (420) are connected with building wall (600) through expansion bolts (430).
CN202320493073.3U 2023-03-15 2023-03-15 Large advertisement cloth fence for construction during operation Active CN219471712U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320493073.3U CN219471712U (en) 2023-03-15 2023-03-15 Large advertisement cloth fence for construction during operation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320493073.3U CN219471712U (en) 2023-03-15 2023-03-15 Large advertisement cloth fence for construction during operation

Publications (1)

Publication Number Publication Date
CN219471712U true CN219471712U (en) 2023-08-04

Family

ID=87467350

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320493073.3U Active CN219471712U (en) 2023-03-15 2023-03-15 Large advertisement cloth fence for construction during operation

Country Status (1)

Country Link
CN (1) CN219471712U (en)

Similar Documents

Publication Publication Date Title
CN212656515U (en) Adjustable movable scaffold
CN101775896B (en) Rigid suspended scaffold for installing pipeline of steel roof equipment
CN206319610U (en) Roof system steel truss slipping and assembling construction platform structure
CN219471712U (en) Large advertisement cloth fence for construction during operation
CN201635377U (en) Rigid suspended type scaffold provided with large-span steel roof equipment pipeline
CN211498507U (en) Whole reassembling type protection rack
CN210066543U (en) Wind-proof sound barrier
CN111236519A (en) Seepage-proof steel structure roof
CN215212255U (en) Suspension type frame combined high-altitude operation platform
CN111236603A (en) Comprehensive construction method for steel plate mesh overhanging scaffold
CN110424762B (en) Cave dwelling reinforcing system
CN212867098U (en) Security fence for building construction management
CN220686824U (en) Large-span temporary-building board house anti-smashing protective shed
CN108412033B (en) External vertical forest overhanging balcony structure of building and construction method thereof
CN209942289U (en) Detachable reinforcement processing canopy of encorbelmenting to one side
CN111636667A (en) High-altitude operation platform construction method and operation platform applied to large-span plant
CN214697029U (en) Steel construction assembled house floor face limit protector
CN214653222U (en) Anti-climbing device for tower crane
CN211666427U (en) Assembled face limit protective apparatus
CN216949193U (en) Novel balcony railing
CN215717474U (en) Assembled escape way protection shed for construction
CN215632066U (en) Self-supporting high-speed rail crossing frame for power transmission line
CN210768095U (en) Railway engineering protection fence
CN214884358U (en) Steel skeleton structure of ecological environmental protection greenhouse for movable assembly type livestock
CN217299742U (en) Construction platform for crossing over aerial swimming pool between super high-rise buildings

Legal Events

Date Code Title Description
GR01 Patent grant