CN219471561U - Aluminum die material conveying port iron box - Google Patents

Aluminum die material conveying port iron box Download PDF

Info

Publication number
CN219471561U
CN219471561U CN202320664507.1U CN202320664507U CN219471561U CN 219471561 U CN219471561 U CN 219471561U CN 202320664507 U CN202320664507 U CN 202320664507U CN 219471561 U CN219471561 U CN 219471561U
Authority
CN
China
Prior art keywords
box body
sleeve pipe
trapezoidal frame
inverted trapezoidal
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320664507.1U
Other languages
Chinese (zh)
Inventor
李永会
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Dongxin Construction Equipment Co ltd
Original Assignee
Shandong Dongxin Construction Equipment Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Dongxin Construction Equipment Co ltd filed Critical Shandong Dongxin Construction Equipment Co ltd
Priority to CN202320664507.1U priority Critical patent/CN219471561U/en
Application granted granted Critical
Publication of CN219471561U publication Critical patent/CN219471561U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P10/00Technologies related to metal processing
    • Y02P10/20Recycling

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

An aluminum mould material transfer port iron box relates to the technical field of building construction, and the technical scheme is as follows: including the box body, be fixed with the limiting plate on the box body, the slip is provided with the sleeve pipe on the limiting plate, and sheathed tube lower extreme extends to the below of box body, and the sleeve pipe lower extreme is provided with two baffles, and two baffles are used for carrying out spacingly with the box body. The beneficial effects of this technical scheme are: through the cooperation between sleeve pipe, baffle, lead screw and the regulating plate, can make the baffle fix in the below of aluminum alloy template, in later stage concrete placement, avoid the box body to come up and run the position condition, sheathed tube setting simultaneously, the convenience is adjusted according to the thickness of aluminum alloy template when using.

Description

Aluminum die material conveying port iron box
Technical Field
The utility model relates to the technical field of building construction, in particular to an aluminum die material conveying port iron box.
Background
The aluminum alloy template is a building template made of aluminum alloy, also called as aluminum template, the aluminum alloy template is manufactured by extruding the aluminum template through special equipment according to the manufacturing design of a module, and in an aluminum alloy template construction system, a material conveying port is an indispensable temporary reserved hole, so that the aluminum alloy template can be conveniently manually and upwards transported to an upper-layer construction floor after a bottom floor template is removed, and vertical transportation equipment is not required to be occupied.
Application number: 202122244846.8A material conveying port iron box for aluminum alloy template construction is disclosed, wherein the lower ends of two rectangular short side plates of the rectangular lower frame are respectively provided with at least one positioning plate, each positioning plate is welded and fixed with the corresponding rectangular short side plate, and each positioning plate is also provided with a plurality of bolt mounting holes for connecting and fixing the aluminum alloy template; during assembly, the rectangular lower frame is arranged on the rectangular bottom plate of the trapezoidal upper frame and is arranged in central alignment with the material conveying opening on the rectangular bottom plate. The utility model has the advantages that: the bolt mounting holes formed in the positioning plate are aligned with the bolt mounting holes in the aluminum alloy template and are connected and fastened together through bolts, so that the discharge hole iron box is limited and fixed.
Set up the bolt mounting hole, fix box body and aluminum alloy template, when earlier stage pouring concrete, the phenomenon of come-up and running the position can not appear in the material transfer mouth iron box, but adopts the bolt to carry out spacingly, after pouring concrete, the concrete can glue on the locating plate, inconvenient dismantlement bolt, and aluminum alloy template model is different simultaneously, and the height of material transfer mouth is also different, and the bolt mounting hole on the locating plate does not correspond with the hole on the aluminum alloy template when the installation.
Disclosure of Invention
The utility model aims to overcome the defects that the prior iron box on a material conveying port is inconvenient to install in the early stage and detach in the later stage and has low efficiency, and the prior iron box on the material conveying port of an aluminum die is limited by bolts and aluminum templates for overcoming the floating and the deviation of the iron box.
In order to achieve the above purpose, the present utility model adopts the following technical scheme:
the utility model provides an aluminium mould passes feed inlet iron box, includes the box body, is fixed with the limiting plate on the box body, and the slip is provided with the sleeve pipe on the limiting plate, and sheathed tube lower extreme extends to the below of box body, and the sleeve pipe lower extreme is provided with two baffles, and two baffles are used for spacing the box body, are provided with adjusting part on the sleeve pipe, and adjusting part adjusts the angle of two baffles.
Adopt baffle butt at the lower surface of aluminium mould, carry out spacingly and fixedly to the box body, avoid the box body come-up and run a situation, control easy to assemble and dismantlement simultaneously to the baffle through adjusting part, the sleeve pipe can slide on the limiting plate simultaneously, adjusts the position of baffle, uses the aluminium mould of co-altitude.
Preferably, the adjusting component comprises a mounting block arranged in the sleeve, a screw rod is mounted on the mounting block, two ends of the screw rod extend to two sides of the sleeve, an adjusting plate is mounted at the lower end thread of the screw rod, push rods are hinged to two ends of the adjusting plate, one end of the baffle is hinged to the side wall of the sleeve, one end of the push rod, far away from the adjusting plate, is hinged to the baffle, and a rotating column is mounted at the upper end of the screw rod.
The adjusting component enables the baffle to be in an inclined state to be adjusted to be in a horizontal state, so that the baffle is convenient to put in the earlier stage and detach in the later stage, and the installation efficiency is improved.
Preferably, the limiting plate is provided with an opening, the outer wall of the sleeve is in sliding connection with the side wall of the opening, the sleeve is provided with a plurality of limiting holes along the vertical direction, the limiting plate is provided with a bolt in a threaded manner, and one end of the bolt extends into one of the limiting holes.
The bolt fixes the sleeve, fixes after adjusting the sleeve, and is convenient for the operation of staff.
Preferably, a limiting block is arranged at the lower part of the screw rod and limits the adjusting plate.
When the screw rod controls the adjusting plate to move downwards, the limiting block can avoid the condition that the adjusting plate falls.
Preferably, the box body comprises a first inverted trapezoidal frame, a second inverted trapezoidal frame is arranged at the lower end of the first inverted trapezoidal frame, a third inverted trapezoidal frame is arranged at the lower end of the second inverted trapezoidal frame, the lower bottom of the first inverted trapezoidal frame is fixed at the upper bottom of the second inverted trapezoidal frame, and the lower bottom of the second inverted trapezoidal frame is fixed at the upper bottom of the third inverted trapezoidal frame.
The arrangement of the three inverted trapezoid frames is beneficial to the blocking of later-stage concrete and the retention problem of plate surface reinforcing steel bars.
Preferably, handles are provided on both sidewalls within the first inverted trapezoidal frame.
Compared with the prior art, the utility model has the beneficial effects that: through the cooperation between sleeve pipe, baffle, lead screw and the regulating plate, can make the baffle fix in the below of aluminum alloy template, in later stage concrete placement, avoid the box body to come up and run the position condition, sheathed tube setting simultaneously, the convenience is adjusted according to the thickness of aluminum alloy template when using.
Drawings
In order to more clearly illustrate the technical solutions of the present utility model, the drawings that are needed in the description will be briefly introduced below, it being obvious that the drawings in the following description are only some embodiments of the present utility model, and that other drawings can be obtained according to these drawings without inventive effort for a person skilled in the art.
Fig. 1 is a schematic structural diagram of an embodiment of the present utility model.
Fig. 2 is a side view of an embodiment of the present utility model.
Fig. 3 is a top view of an embodiment of the present utility model.
Fig. 4 is a schematic view of the structure in the sleeve according to the embodiment of the present utility model.
In the figure: the box comprises a box body 1, a limiting hole 2, a sleeve 3, a screw 4, a limiting plate 5, a bolt 6, a rotating column 7, a baffle 8, an adjusting plate 9, a push rod 10, a mounting block 11, a limiting block 12, a handle 13, a first inverted trapezoidal frame 101, a second inverted trapezoidal frame 102 and a third inverted trapezoidal frame 103.
Detailed Description
In order to make the objects, features and advantages of the present utility model more obvious and understandable, the technical solutions of the present utility model will be clearly and completely described below with reference to the drawings in this specific embodiment, and it is apparent that the embodiments described below are only some embodiments of the present utility model, but not all embodiments of the present utility model. All other embodiments, based on the embodiments in this patent, which would be within the purview of one of ordinary skill in the art without the particular effort to make the utility model are intended to be within the scope of the patent protection.
Referring to fig. 1-4, an aluminum die feed port iron box comprises a box body 1, wherein a limiting plate 5 is fixed on the box body 1, the limiting plate 5 is transversely arranged on two side walls of the box body 1 and plays a role in supporting the upper part of the box body 1, a sleeve 3 is slidably arranged on the limiting plate 5, the lower end of the sleeve 3 extends to the lower part of the box body 1, two baffles 8 are arranged at the lower end of the sleeve 3 and are used for limiting the box body 1, the baffles 8 are abutted to the lower surface of an aluminum alloy template, when concrete is poured, the baffles 8 limit the box body 1 in the process of floating the box body 1 by the concrete, an adjusting component is arranged on the sleeve 3 and adjusts the angle of the two baffles 8, the box body 1 includes first trapezoidal frame 101 that falls, the second trapezoidal frame 102 that falls is installed to the lower extreme of first trapezoidal frame 101, the third trapezoidal frame 103 that falls is installed to the lower extreme of second trapezoidal frame 102, the lower bottom of first trapezoidal frame 101 is fixed at the upper end of second trapezoidal frame 102 that falls, the lower bottom of second trapezoidal frame 102 is fixed at the upper end of third trapezoidal frame 103, the shutoff of later stage concrete is favorable to being provided with of three trapezoidal frames that falls, and the stay problem of face reinforcing bar, all be provided with handle 13 on two lateral walls in the first trapezoidal frame 101, handle 13 makes things convenient for the staff to place and take box body 1.
Referring to fig. 2 and 4, the adjusting assembly includes the installation piece 11 that sets up in sleeve pipe 3, install lead screw 4 on the installation piece 11, lead screw 4 rotates and cup joints on installation piece 11, carry out spacingly to the position of lead screw 4, the both ends of lead screw 4 extend to the both sides of sleeve pipe 3, adjusting plate 9 is installed to the lower extreme screw thread of lead screw 4, drive adjusting plate 9 and reciprocate when lead screw 4 controls, the lower part of lead screw 4 is provided with stopper 12, stopper 12 carries out spacingly to adjusting plate 9, the both ends of adjusting plate 9 all articulate there is push rod 10, the one end of baffle 8 articulates on the lateral wall of sleeve pipe 3, the one end that push rod 10 kept away from adjusting plate 9 articulates on baffle 8, can make two push rods 10 promote two baffles 8 when adjusting plate 9 upwards move, make baffle 8 become horizontal setting, afterwards, whole sleeve pipe 3 drives baffle 8 and lead screw 4 and upwards move together, until baffle 8 butt is at the lower surface of aluminum alloy template, the upper end of lead screw 4 installs rotation post 7, rotation post 7 sets up and conveniently controls the rotation of lead screw 4.
Referring to fig. 1 and 3, be provided with the opening on the limiting plate 5, the outer wall and the open-ended lateral wall sliding connection of sleeve pipe 3, sleeve pipe 3 is provided with a plurality of spacing holes 2 along vertical direction, because aluminum alloy template standard is different, spacing between the spacing holes 2 sets up according to the height that sets up the aluminum alloy in usual, the position of every spacing hole 2 represents the height when an aluminum alloy template is used promptly, bolt 6 is installed to the screw thread on the limiting plate 5, the one end of bolt 6 extends to in one of them spacing hole 2, bolt 6 carries out spacingly to sleeve pipe 3, make things convenient for the position of staff's regulation sleeve pipe 3.
When the box body 1 is used, firstly, the whole box body 1 is placed on a material conveying opening of an aluminum alloy template, then, the height of a sleeve 3 is adjusted according to the thickness of the aluminum alloy template, a screw rod 4 and two baffles 8 are driven to move downwards together when the sleeve 3 is adjusted, after the sleeve 3 is moved to the lower part of the material conveying opening, the sleeve 3 is limited and fixed through a bolt 6, then, a rotating column 7 is rotated to drive an adjusting plate 9 to move upwards, when the sleeve is moved, the angle of the baffles 8 is adjusted through two push rods 10, the baffles 8 are horizontally arranged, the two baffles 8 are abutted to the lower part of the aluminum alloy template, the box body 1 cannot generate the conditions of floating and running in the later concrete pouring process, so that the sleeve is reinforced in place, and meanwhile, three inverted-ladder-shaped frames are favorable for blocking of later concrete after pouring and the problem of retaining plate steel bars.
The previous description of the disclosed embodiments is provided to enable any person skilled in the art to make or use the present utility model. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the utility model. Thus, the present utility model is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (6)

1. The utility model provides an aluminium mould passes feed inlet iron box, includes box body (1), its characterized in that: be fixed with limiting plate (5) on box body (1), sliding is provided with sleeve pipe (3) on limiting plate (5), and the lower extreme of sleeve pipe (3) extends to the below of box body (1), and sleeve pipe (3) lower extreme is provided with two baffles (8), and two baffles (8) are used for spacing box body (1), are provided with adjusting part on sleeve pipe (3), and the angle of two baffles (8) is adjusted to adjusting part.
2. The aluminum die transfer port iron box of claim 1, wherein: the adjusting component comprises an installing block (11) arranged in the sleeve (3), a screw rod (4) is arranged on the installing block (11), two ends of the screw rod (4) extend to two sides of the sleeve (3), an adjusting plate (9) is arranged at the lower end of the screw rod (4) in a threaded mode, push rods (10) are hinged to two ends of the adjusting plate (9), one end of the baffle (8) is hinged to the side wall of the sleeve (3), one end of the push rod (10) away from the adjusting plate (9) is hinged to the baffle (8), and a rotating column (7) is arranged at the upper end of the screw rod (4).
3. The aluminum die transfer port iron box of claim 1, wherein: be provided with the opening on limiting plate (5), the outer wall and the open-ended lateral wall sliding connection of sleeve pipe (3), sleeve pipe (3) are provided with a plurality of spacing holes (2) along vertical direction, and bolt (6) are installed to the screw thread on limiting plate (5), and in one end of bolt (6) extends to one of them spacing hole (2).
4. The aluminum die transfer port iron box of claim 2, wherein: the lower part of the screw rod (4) is provided with a limiting block (12), and the limiting block (12) limits the adjusting plate (9).
5. The aluminum die transfer port iron box of claim 1, wherein: the box body (1) comprises a first inverted trapezoidal frame (101), a second inverted trapezoidal frame (102) is arranged at the lower end of the first inverted trapezoidal frame (101), a third inverted trapezoidal frame (103) is arranged at the lower end of the second inverted trapezoidal frame (102), the lower bottom of the first inverted trapezoidal frame (101) is fixed at the upper bottom of the second inverted trapezoidal frame (102), and the lower bottom of the second inverted trapezoidal frame (102) is fixed at the upper bottom of the third inverted trapezoidal frame (103).
6. The aluminum die transfer port iron box of claim 5, wherein: handles (13) are arranged on two side walls in the first inverted trapezoid frame (101).
CN202320664507.1U 2023-03-27 2023-03-27 Aluminum die material conveying port iron box Active CN219471561U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320664507.1U CN219471561U (en) 2023-03-27 2023-03-27 Aluminum die material conveying port iron box

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320664507.1U CN219471561U (en) 2023-03-27 2023-03-27 Aluminum die material conveying port iron box

Publications (1)

Publication Number Publication Date
CN219471561U true CN219471561U (en) 2023-08-04

Family

ID=87458995

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320664507.1U Active CN219471561U (en) 2023-03-27 2023-03-27 Aluminum die material conveying port iron box

Country Status (1)

Country Link
CN (1) CN219471561U (en)

Similar Documents

Publication Publication Date Title
CN109853946A (en) A kind of structure and its installation method of column template
CN111021712B (en) Damper cantilever wall template reinforcing mechanism and using method thereof
CN211817948U (en) Aluminum template assembly for casting L-shaped node of shear wall
CN207526100U (en) Wall is poured with aluminum alloy pattern plate leveling and ruggedized construction
CN103104090B (en) Silo concrete whole slip template
CN209892231U (en) Full-width template for inverted arch trestle
CN216427858U (en) Linear adjusting template device for post-cast section of curved track beam
CN219471561U (en) Aluminum die material conveying port iron box
CN202831621U (en) Integrated slipform for silo concrete
CN210331780U (en) Full-bridge type center transmission mud scraper
CN106050271A (en) Ditch formwork device for tunnel and construction method of ditch formwork device
CN106089256A (en) Ditch cable trench construction trolley and construction method, tunnel cable die set device
CN211850824U (en) Supporting unit and supporting device
CN215594893U (en) Descending plate formwork device
CN205857710U (en) Air-conditioning formwork support structure
CN214834773U (en) Beam wall fast-assembling early beam structure of tearing open convenient to beam bottom is adjusted and is fixed a position
CN211447781U (en) Aluminum alloy template beam side anti-expansion die device
CN212836697U (en) Shaping support mold for stair forming
CN211682683U (en) Pouring template convenient to enter mold
CN210910493U (en) Integral type assembly stair prefabricated template
CN106089257A (en) A kind of tunnel ditch cable trough construction trolley
CN113787587A (en) Integral stair pouring mold and stair pouring construction method
CN112627570A (en) Repairing tool for repairing large gap of door opening and construction method thereof
CN208380073U (en) Template tie
CN219137703U (en) Height-adjustable crown beam steel support Z-shaped hanging device

Legal Events