CN219410865U - Pile foundation construction auxiliary assembly - Google Patents

Pile foundation construction auxiliary assembly Download PDF

Info

Publication number
CN219410865U
CN219410865U CN202320971854.9U CN202320971854U CN219410865U CN 219410865 U CN219410865 U CN 219410865U CN 202320971854 U CN202320971854 U CN 202320971854U CN 219410865 U CN219410865 U CN 219410865U
Authority
CN
China
Prior art keywords
fixedly connected
pile foundation
hole
plate
auxiliary equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320971854.9U
Other languages
Chinese (zh)
Inventor
岳立强
张春磊
卢有赢
王骏益
陈龙
王云
赵海峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Communications Construction Group Southeast Construction Co ltd
CCCC Construction Group Co Ltd
Original Assignee
China Communications Construction Group Southeast Construction Co ltd
CCCC Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Communications Construction Group Southeast Construction Co ltd, CCCC Construction Group Co Ltd filed Critical China Communications Construction Group Southeast Construction Co ltd
Priority to CN202320971854.9U priority Critical patent/CN219410865U/en
Application granted granted Critical
Publication of CN219410865U publication Critical patent/CN219410865U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The utility model discloses pile foundation construction auxiliary equipment, which comprises a plate, wherein a central hole is formed in the center of the plate, a plurality of through holes are uniformly formed in the side wall of the plate, a moving mechanism is fixedly connected below the plate, an adjusting mechanism is arranged in the through holes, and a centering mechanism is fixedly connected above the plate; the adjusting mechanism comprises a retaining plate, a sleeve, a screwing screw and a rotating handle; the sleeve is connected in the through hole in a sliding way, one end of the sleeve, which is close to the central hole, extends out of the through hole and is fixedly connected with the retaining plate, one end of the screwing screw rod extends into the sleeve and is abutted against the retaining plate, and the other end of the screwing screw rod penetrates through the through hole and is fixedly connected with the rotating handle; a connecting block is arranged between the screwing screw and one end, far away from the center hole, of the through hole, the outer side of the connecting block is fixedly connected with the through hole, and the inner side of the connecting block is in threaded connection with the screwing screw. The utility model can conveniently position the pile foundation during pile foundation construction and press the pile, can greatly avoid the inclination of the pile foundation and ensure the construction quality of the pile foundation.

Description

桩基施工辅助设备Auxiliary equipment for pile foundation construction

技术领域technical field

本实用新型属于桩基施工技术领域,尤其涉及一种桩基施工辅助设备。The utility model belongs to the technical field of pile foundation construction, in particular to an auxiliary equipment for pile foundation construction.

背景技术Background technique

由桩和连接桩顶的桩承台组成的深基础,或由柱与桩基连接的单桩基础,简称桩基,在桩基施工过程中,多采用静压法沉桩的方式进行桩基固定,一般又分为顶压式和箍压式两种,针对于箍压式沉桩,现有的设备,无法使桩基在下压的过程中始终处于垂直状态,容易使桩基出现偏斜的现象,影响桩基固定的效果。The deep foundation composed of piles and pile caps connected to the top of the pile, or the single pile foundation connected by the column and the pile foundation, referred to as the pile foundation, in the construction process of the pile foundation, the pile foundation is fixed by the method of static pressure pile sinking, which is generally divided into two types: top pressure type and hoop pressure type. For the hoop pressure type pile sinking, the existing equipment cannot keep the pile foundation in a vertical state during the downward pressure process, and it is easy to cause the pile foundation to be deflected and affect the effect of pile foundation fixing.

公开号为CN217460570U的中国专利公开了一种公路施工用桩基辅助垂直装置,包括压桩千斤顶、安装在压桩千斤顶底端的抱箍千斤顶以及安装在抱箍千斤顶内侧的桩基柱,压桩千斤顶顶端还安装有便于对桩基柱进行辅助垂直的垂直组件;所述垂直组件包括有底座、立柱、螺纹轴、第一转动件和顶板。此申请通过水平组件使得左右两侧均处于水平状态,从而便于使桩基处于水平竖直状态,但此技术仅仅只从左右两侧对桩基进行了辅助固定,避免倾斜,但桩基仍有可能从前后方向歪斜。因此,该技术并没有完全解决桩基在压桩过程中保持竖直不歪斜的问题。并且,对于桩基的定位此专利中也没有给出相应的解决方案,即便桩基可以不产生歪斜,如何方便地使桩基在规划好的位置点进行压桩也是需要解决的问题The Chinese patent with the publication number CN217460570U discloses a pile foundation auxiliary vertical device for highway construction, including a pile jack, a hoop jack installed at the bottom of the pile jack, and a pile foundation column installed inside the hoop jack, and a vertical assembly for assisting the vertical of the pile foundation column is installed on the top of the pile jack. This application uses horizontal components to make the left and right sides in a horizontal state, so that the pile foundation is in a horizontal and vertical state. However, this technology only assists in fixing the pile foundation from the left and right sides to avoid tilting, but the pile foundation may still be skewed from the front and rear directions. Therefore, this technology does not fully solve the problem that the pile foundation remains vertical and not skewed during the pile pressing process. Moreover, this patent does not provide a corresponding solution for the positioning of the pile foundation. Even if the pile foundation can not be skewed, how to conveniently make the pile foundation pile at the planned position is also a problem that needs to be solved.

为此,提出一种桩基施工辅助设备。For this reason, an auxiliary equipment for pile foundation construction is proposed.

实用新型内容Utility model content

为解决上述技术问题,本实用新型提出了一种桩基施工辅助设备。In order to solve the above technical problems, the utility model proposes an auxiliary equipment for pile foundation construction.

为实现上述目的,本实用新型提供了一种桩基施工辅助设备,包括:安装板,所述安装板中心开设有中心孔,所述安装板侧壁均匀开设有若干贯通孔,所述安装板下方固接有移动机构,所述贯通孔内设有调整机构,所述安装板上方固接有扶正机构;In order to achieve the above object, the utility model provides a pile foundation construction auxiliary equipment, comprising: a mounting plate, a center hole is opened in the center of the mounting plate, a number of through holes are evenly opened on the side wall of the mounting plate, a moving mechanism is fixedly connected under the mounting plate, an adjustment mechanism is arranged in the through hole, and a centralizing mechanism is fixedly connected above the mounting plate;

所述调整机构包括抵板、套筒、旋拧螺杆和转动把手;所述套筒滑动连接于所述贯通孔内,所述套筒靠近所述中心孔的一端伸出所述贯通孔与所述抵板固接,所述旋拧螺杆一端伸进所述套筒内部与所述抵板抵接,另一端穿过所述贯通孔与所述转动把手固接;所述旋拧螺杆与所述贯通孔远离所述中心孔的一端之间设置有连接块,所述连接块外侧与所述贯通孔固接,内侧与所述旋拧螺杆螺纹连接。The adjustment mechanism includes a backing plate, a sleeve, a screw rod and a rotating handle; the sleeve is slidably connected in the through hole, and one end of the sleeve close to the central hole protrudes out of the through hole to be fixedly connected to the backing plate; one end of the screw rod extends into the interior of the sleeve to abut against the backing plate, and the other end passes through the through hole and is affixed to the turning handle; a connecting block is arranged between the screwing screw and an end of the through hole away from the central hole, and the outside of the connecting block is fixedly connected to the through hole. The inner side is threadedly connected with the screw rod.

优选的,所述抵板上滑动嵌设有若干滚珠。Preferably, a plurality of balls are slidably embedded on the abutment plate.

优选的,所述套筒远离所述中心孔的一端向外凸起,所述贯通孔靠近所述中心孔的一端向内凸起。Preferably, the end of the sleeve away from the central hole protrudes outward, and the end of the through hole close to the central hole protrudes inward.

优选的,所述扶正机构包括支撑柱,所述支撑柱固接于所述安装板顶面左右及后方三侧;左右两侧所述支撑柱顶端固接有液压伸缩杆,所述液压伸缩杆活动端固接有夹具组件。Preferably, the righting mechanism includes a support column, and the support column is fixedly connected to the left, right and rear sides of the top surface of the installation plate; hydraulic telescopic rods are fixedly connected to the tops of the support columns on the left and right sides, and a clamp assembly is fixedly connected to the movable end of the hydraulic telescopic rod.

优选的,所述夹具组件包括与所述液压伸缩杆活动端固接的外壳,所述外壳两侧固接有电机,所述外壳中间固接有安装架,所述电机输出端固接有移动螺杆,所述移动螺杆与所述外壳以及安装架转动连接,所述移动螺杆上套设有滑动块,所述滑动块上固接有连接杆,所述外壳远离所述液压伸缩杆的一侧开设有条形槽,所述连接杆穿过所述条形槽固接有夹板。Preferably, the clamp assembly includes a housing affixed to the movable end of the hydraulic telescopic rod, motors are affixed to both sides of the housing, a mounting bracket is affixed to the middle of the housing, a moving screw is affixed to the output end of the motor, the moving screw is rotatably connected to the housing and the mounting bracket, a sliding block is sleeved on the moving screw, a connecting rod is fixedly connected to the sliding block, a strip groove is opened on the side of the housing away from the hydraulic telescopic rod, and a splint is fixed to the connecting rod passing through the strip groove.

优选的,所述支撑柱上下两端分别设置有测距仪。Preferably, rangefinders are respectively provided at the upper and lower ends of the support column.

优选的,所述移动机构包括固接于所述安装板四角的液压支撑柱,所述液压支撑柱活动端固接有万向轮,所述液压支撑柱内侧固接有固定柱。Preferably, the moving mechanism includes a hydraulic support column fixed to the four corners of the installation plate, a universal wheel is fixed to the movable end of the hydraulic support column, and a fixed column is fixed to the inner side of the hydraulic support column.

优选的,所述固定柱底端固接有支撑盘。Preferably, a support plate is fixedly connected to the bottom end of the fixing column.

与现有技术相比,本实用新型具有如下优点和技术效果:Compared with the prior art, the utility model has the following advantages and technical effects:

在桩基的施工过程中,首先将本桩基施工辅助设备通过移动机构移动至桩基的定位点上方,将中心孔中心轴与桩基定位轴线进行粗略定位,而后启用吊车将桩基吊至本桩基施工辅助设备上方,并将桩基插入中心孔内,转动转动把手,旋拧螺杆转动,旋拧螺杆在连接块作用下向安装板内部旋进,顶着抵板与套筒同步向内部滑动,直至抵板与桩基表面抵接,多个调整机构的抵板与桩基抵接,对桩基从不同方向进行挤压推动,使得桩基可以在任意方向进行细致的位移,方便桩基的位置和角度确定;定好桩基的位置与角度后,扶正机构对桩基进行扶持,进一步保证了桩基的稳定性,避免在压桩过程中桩基的倾斜。本申请桩基施工辅助设备可方便地对桩基施工时进行桩基的定位,并在进行压桩,可极大的避免桩基倾斜,保证桩基施工质量。During the construction of the pile foundation, firstly, the auxiliary equipment for pile foundation construction is moved above the positioning point of the pile foundation through the moving mechanism, and the central axis of the center hole and the positioning axis of the pile foundation are roughly positioned, and then the crane is used to hoist the pile foundation above the auxiliary equipment for pile foundation construction, and the pile foundation is inserted into the center hole, the handle is turned, the screw is rotated, the screw screw is screwed into the installation plate under the action of the connecting block, and slides inward synchronously against the abutment plate and the sleeve until the abutment plate abuts against the surface of the pile foundation, and the abutment of multiple adjustment mechanisms The plate is in contact with the pile foundation, and the pile foundation is squeezed and pushed from different directions, so that the pile foundation can be carefully displaced in any direction, and the position and angle of the pile foundation can be determined conveniently; The pile foundation construction auxiliary equipment of the present application can conveniently locate the pile foundation during pile foundation construction, and carry out pile pressing, which can greatly avoid the inclination of the pile foundation and ensure the construction quality of the pile foundation.

附图说明Description of drawings

构成本申请的一部分的附图用来提供对本申请的进一步理解,本申请的示意性实施例及其说明用于解释本申请,并不构成对本申请的不当限定。在附图中:The drawings constituting a part of the application are used to provide further understanding of the application, and the schematic embodiments and descriptions of the application are used to explain the application, and do not constitute an improper limitation to the application. In the attached picture:

图1为本实用新型桩基施工辅助设备结构示意图;Fig. 1 is the structural representation of auxiliary equipment for pile foundation construction of the utility model;

图2为本实用新型图1中C-C的剖视图;Fig. 2 is the sectional view of C-C in Fig. 1 of the utility model;

图3为本实用新型夹具组件结构示意图;Fig. 3 is a structural schematic diagram of the clamp assembly of the utility model;

图4为本实用新型图2中A的放大图;Fig. 4 is the enlarged view of A in Fig. 2 of the utility model;

图中:1、安装板;2、中心孔;3、贯通孔;4、抵板;5、套筒;6、旋拧螺杆;7、转动把手;8、连接块;9、滚珠;10、支撑柱;11、液压伸缩杆;12、外壳;13、电机;14、安装架;15、固定柱;16、移动螺杆;17、滑动块;18、连接杆;19、条形槽;20、夹板;21、测距仪;22、万向轮;23、液压支撑柱;24、支撑盘。In the figure: 1. Mounting plate; 2. Center hole; 3. Through hole; 4. Arresting plate; 5. Sleeve; 6. Screw screw; 7. Turning handle; 8. Connecting block; 9. Ball; 10. Support column; 22, universal wheel; 23, hydraulic support column; 24, support plate.

具体实施方式Detailed ways

下面将结合本实用新型实施例中的附图,对本实用新型实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本实用新型一部分实施例,而不是全部的实施例。基于本实用新型中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本实用新型保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. Apparently, the described embodiments are only some of the embodiments of the present invention, not all of them. Based on the embodiments of the present utility model, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the scope of protection of the present utility model.

为使本实用新型的上述目的、特征和优点能够更加明显易懂,下面结合附图和具体实施方式对本实用新型作进一步详细的说明。In order to make the above purpose, features and advantages of the utility model more obvious and understandable, the utility model will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

参照图1-4所示,本实施例提供一种桩基施工辅助设备,包括:安装板1,安装板1中心开设有中心孔2,安装板1侧壁均匀开设有若干贯通孔3,安装板1下方固接有移动机构,贯通孔3内设有调整机构,安装板1上方固接有扶正机构;Referring to Figures 1-4, this embodiment provides a pile foundation construction auxiliary equipment, including: a mounting plate 1, a center hole 2 is opened in the center of the mounting plate 1, a number of through holes 3 are uniformly opened on the side wall of the mounting plate 1, a moving mechanism is fixedly connected under the mounting plate 1, an adjustment mechanism is provided in the through hole 3, and a centralizing mechanism is fixedly connected above the mounting plate 1;

调整机构包括抵板4、套筒5、旋拧螺杆6和转动把手7;套筒5滑动连接于贯通孔3内,套筒5靠近中心孔2的一端伸出贯通孔3与抵板4固接,旋拧螺杆6一端伸进套筒5内部与抵板4抵接,另一端穿过贯通孔3与转动把手7固接;旋拧螺杆6与贯通孔3远离中心孔2的一端之间设置有连接块8,连接块8外侧与贯通孔3固接,内侧与旋拧螺杆6螺纹连接。The adjustment mechanism includes a backing plate 4, a sleeve 5, a screw rod 6 and a rotating handle 7; the sleeve 5 is slidably connected in the through hole 3, and one end of the sleeve 5 close to the center hole 2 protrudes out of the through hole 3 to be fixedly connected with the backing plate 4; 3 fixed connections, the inner side is threadedly connected with the screw rod 6 .

在桩基的施工过程中,首先将本桩基施工辅助设备通过移动机构移动至桩基的定位点上方,将中心孔2中心轴与桩基定位轴线进行粗略定位,而后启用吊车将桩基吊至本桩基施工辅助设备上方,并将桩基插入中心孔2内,转动转动把手7,旋拧螺杆6转动,旋拧螺杆6在连接块8作用下向安装板1内部旋进,顶着抵板4与套筒5同步向内部滑动,直至抵板4与桩基表面抵接,多个调整机构的抵板4与桩基抵接,对桩基从不同方向进行挤压推动,使得桩基可以在任意方向进行细致的位移,方便桩基的位置和角度确定;定好桩基的位置与角度后,扶正机构对桩基进行扶持,进一步保证了桩基的稳定性,避免在压桩过程中桩基的倾斜。本申请桩基施工辅助设备可方便地对桩基施工时进行桩基的定位,并在进行压桩,可极大的避免桩基倾斜,保证桩基施工质量。During the construction process of the pile foundation, firstly, the pile foundation construction auxiliary equipment is moved above the positioning point of the pile foundation through the moving mechanism, and the central axis of the center hole 2 is roughly positioned with the pile foundation positioning axis, and then the crane is used to hoist the pile foundation above the pile foundation construction auxiliary equipment, and the pile foundation is inserted into the center hole 2, the turning handle 7 is turned, the screw rod 6 is rotated, and the screw rod 6 is screwed into the inside of the installation plate 1 under the action of the connecting block 8, and slides inward synchronously against the support plate 4 and the sleeve 5 until the support plate 4 and the pile The surface of the foundation abuts, and the abutment plates 4 of multiple adjustment mechanisms abut against the pile foundation to squeeze and push the pile foundation from different directions, so that the pile foundation can be finely displaced in any direction, which facilitates the determination of the position and angle of the pile foundation; The pile foundation construction auxiliary equipment of the present application can conveniently locate the pile foundation during pile foundation construction, and carry out pile pressing, which can greatly avoid the inclination of the pile foundation and ensure the construction quality of the pile foundation.

进一步优化方案,抵板4上滑动嵌设有若干滚珠9。To further optimize the solution, a number of balls 9 are slidably embedded on the counter plate 4 .

滚珠9可在桩基下压过程中将桩基与抵板4的滑动连接变为滚动连接,减小抵板4与桩基之间的摩擦力,减小抵板4的磨损,延长抵板4的使用寿命。The ball 9 can change the sliding connection between the pile foundation and the abutment plate 4 into a rolling connection in the process of pressing down the pile foundation, reduce the friction between the abutment plate 4 and the pile foundation, reduce the wear of the abutment plate 4, and prolong the service life of the abutment plate 4.

进一步优化方案,套筒5远离中心孔2的一端向外凸起,贯通孔3靠近中心孔2的一端向内凸起。In a further optimized solution, the end of the sleeve 5 away from the central hole 2 protrudes outward, and the end of the through hole 3 close to the central hole 2 protrudes inward.

套筒5远离中心孔2处的凸起和贯通孔3靠近中心孔2处的凸起彼此卡接,使得套筒5在贯通孔3内滑动但不会脱出贯通孔3,对贯通孔3进行位置限定。The protrusion of the sleeve 5 away from the center hole 2 and the protrusion of the through hole 3 close to the center hole 2 engage with each other, so that the sleeve 5 slides in the through hole 3 but does not come out of the through hole 3, and the position of the through hole 3 is limited.

进一步优化方案,扶正机构包括支撑柱10,支撑柱10固接于安装板1顶面左右及后方三侧;左右两侧支撑柱10顶端固接有液压伸缩杆11,液压伸缩杆11活动端固接有夹具组件。To further optimize the scheme, the righting mechanism includes a support column 10, and the support column 10 is affixed to the left, right and rear sides of the top surface of the installation plate 1; a hydraulic telescopic rod 11 is affixed to the top of the support column 10 on the left and right sides, and a clamp assembly is affixed to the movable end of the hydraulic telescopic rod 11.

扶正机构位于安装板1上方,对桩基进行扶正,支撑柱10将夹具组件提升一定的高度,有利于桩基倾斜的扶正与测量,液压伸缩杆11在吊车吊起桩基插入中心孔2时收缩,避免影响桩基的进入;在调整机构调整好桩基的位置后伸张,安装板1两侧的夹具组件向内移动对桩基进行夹紧扶正,并可根据桩基的倾斜情况进行一定的伸张量的调整,以矫正桩基的倾斜情况。The straightening mechanism is located above the mounting plate 1 to straighten the pile foundation. The support column 10 lifts the fixture assembly to a certain height, which is beneficial to the straightening and measurement of the pile foundation inclination. The hydraulic telescopic rod 11 shrinks when the pile foundation is lifted by the crane and inserted into the center hole 2, so as to avoid affecting the entry of the pile foundation; after the adjustment mechanism adjusts the position of the pile foundation, it stretches. the inclination situation.

进一步优化方案,夹具组件包括与液压伸缩杆11活动端固接的外壳12,外壳12两侧固接有电机13,外壳12中间固接有安装架14,电机13输出端固接有移动螺杆16,移动螺杆16与外壳12以及安装架14转动连接,移动螺杆16上套设有滑动块17,滑动块17上固接有连接杆18,外壳12远离液压伸缩杆11的一侧开设有条形槽19,连接杆18穿过条形槽19固接有夹板20。In a further optimization scheme, the fixture assembly includes a housing 12 fixedly connected to the movable end of the hydraulic telescopic rod 11, a motor 13 is fixedly connected to both sides of the housing 12, a mounting bracket 14 is fixedly connected to the middle of the housing 12, a moving screw 16 is fixedly connected to the output end of the motor 13, the moving screw 16 is rotationally connected with the housing 12 and the mounting bracket 14, a sliding block 17 is set on the moving screw 16, and a connecting rod 18 is fixedly connected to the sliding block 17. , the connecting rod 18 passes through the bar-shaped groove 19 and is fixedly connected with the splint 20 .

两外壳12内侧面抵接桩基两侧对桩基进行横向的夹紧,为避免桩基竖向的倾斜,两电机13分别带动两移动螺杆16转动,两移动螺杆16上的两滑动块17因此在移动螺杆16上进行竖向的平移,带动与滑动块17通过连接杆18连接的夹板20进行竖向的平移,使得两夹板20对桩基进行竖向的位置调整和夹紧。条形槽19为连接杆18的移动提供了空间。两夹板20对桩基竖向的倾斜进行扶正。The inner sides of the two shells 12 abut against the both sides of the pile foundation to clamp the pile foundation horizontally. In order to avoid the vertical inclination of the pile foundation, the two motors 13 respectively drive the two moving screw rods 16 to rotate. The strip groove 19 provides space for the movement of the connecting rod 18 . Two splints 20 straighten the vertical inclination of the pile foundation.

进一步优化方案,支撑柱10上下两端分别设置有测距仪21。To further optimize the solution, rangefinders 21 are respectively provided at the upper and lower ends of the support column 10 .

上下两个测距仪21可根据桩基不同位置与支撑柱10的距离测量支撑柱10的倾斜情况,施工人员可据此通过液压伸缩杆11进行一定的倾斜调整。The upper and lower rangefinders 21 can measure the inclination of the support column 10 according to the distance between different positions of the pile foundation and the support column 10 , and the construction personnel can adjust the inclination through the hydraulic telescopic rod 11 accordingly.

进一步优化方案,移动机构包括固接于安装板1四角的液压支撑柱23,液压支撑柱23活动端固接有万向轮22,液压支撑柱23内侧固接有固定柱15。In a further optimized solution, the moving mechanism includes a hydraulic support column 23 fixed to the four corners of the mounting plate 1 , the movable end of the hydraulic support column 23 is fixed with a universal wheel 22 , and the inner side of the hydraulic support column 23 is fixed with a fixed column 15 .

万向轮22可方便地移动此桩基施工辅助设备到桩基压桩的定位点上方;在此桩基施工辅助设备定好位后,液压支撑柱23收缩,固定柱15逐渐接触地面,并与地面抵接,使本本申请桩基施工辅助设备位置固定。待桩基压桩完成后,液压支撑柱23伸张,使得固定柱15远离地面,万向轮22与地面接触,同时提升安装板1高度,使本申请桩基施工辅助设备从桩基上方安全移出桩基打桩位置。The universal wheel 22 can easily move the auxiliary equipment for pile foundation construction to above the positioning point of the pile foundation pile; after the auxiliary equipment for pile foundation construction is positioned, the hydraulic support column 23 shrinks, and the fixed column 15 gradually touches the ground and abuts against the ground, so that the position of the auxiliary equipment for pile foundation construction of this application is fixed. After the pile foundation pile is completed, the hydraulic support column 23 is stretched, so that the fixed column 15 is away from the ground, the universal wheel 22 is in contact with the ground, and the height of the installation plate 1 is raised at the same time, so that the pile foundation construction auxiliary equipment of the present application can safely move out of the pile foundation piling position from above the pile foundation.

进一步的,可在安装板1上安装水准仪,观测水准仪,并分别调整液压支撑柱23的伸长量可使安装板1调至水平。可应用于由于地面不平导致的安装板1不水平的情况。Further, a level can be installed on the mounting plate 1 , the level can be observed, and the elongation of the hydraulic support column 23 can be adjusted respectively so that the mounting plate 1 can be adjusted to the level. It can be applied to the situation that the mounting plate 1 is not level due to uneven ground.

进一步优化方案,固定柱15底端固接有支撑盘24。In a further optimized solution, a support plate 24 is fixedly connected to the bottom of the fixing column 15 .

支撑盘24在液压支撑柱23收缩后与地面抵接,支撑盘24可分散固定柱15柱脚的支撑力,使支撑更稳定。The support disc 24 abuts against the ground after the hydraulic support column 23 shrinks, and the support disc 24 can disperse the supporting force of the column feet of the fixed column 15 to make the support more stable.

在本实用新型的描述中,需要理解的是,术语“纵向”、“横向”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本实用新型,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本实用新型的限制。In the description of the present utility model, it should be understood that the orientations or positional relationships indicated by the terms "longitudinal", "transverse", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer" and so on are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the utility model, rather than indicating or implying that the device or element referred to must have a specific orientation or be constructed in a specific orientation and operation, and therefore cannot be construed as a limitation of the present utility model.

以上所述的实施例仅是对本实用新型的优选方式进行描述,并非对本实用新型的范围进行限定,在不脱离本实用新型设计精神的前提下,本领域普通技术人员对本实用新型的技术方案做出的各种变形和改进,均应落入本实用新型权利要求书确定的保护范围内。The embodiments described above are only to describe the preferred mode of the utility model, not to limit the scope of the utility model. Without departing from the design spirit of the utility model, various deformations and improvements made by those skilled in the art to the technical solution of the utility model should fall within the scope of protection determined by the claims of the utility model.

Claims (8)

1.一种桩基施工辅助设备,其特征在于,包括:安装板(1),所述安装板(1)中心开设有中心孔(2),所述安装板(1)侧壁均匀开设有若干贯通孔(3),所述安装板(1)下方固接有移动机构,所述贯通孔(3)内设有调整机构,所述安装板(1)上方固接有扶正机构;1. An auxiliary equipment for pile foundation construction, characterized in that, comprising: a mounting plate (1), the center of the mounting plate (1) is provided with a central hole (2), and the side wall of the mounting plate (1) is uniformly provided with a plurality of through holes (3), the lower part of the mounting plate (1) is fixedly connected with a moving mechanism, the through hole (3) is provided with an adjustment mechanism, and the top of the mounting plate (1) is fixedly connected with a righting mechanism; 所述调整机构包括抵板(4)、套筒(5)、旋拧螺杆(6)和转动把手(7);所述套筒(5)滑动连接于所述贯通孔(3)内,所述套筒(5)靠近所述中心孔(2)的一端伸出所述贯通孔(3)与所述抵板(4)固接,所述旋拧螺杆(6)一端伸进所述套筒(5)内部与所述抵板(4)抵接,另一端穿过所述贯通孔(3)与所述转动把手(7)固接;所述旋拧螺杆(6)与所述贯通孔(3)远离所述中心孔(2)的一端之间设置有连接块(8),所述连接块(8)外侧与所述贯通孔(3)固接,内侧与所述旋拧螺杆(6)螺纹连接。The adjustment mechanism includes a stop plate (4), a sleeve (5), a screw rod (6) and a rotating handle (7); the sleeve (5) is slidably connected in the through hole (3), and one end of the sleeve (5) close to the center hole (2) protrudes from the through hole (3) to be fixedly connected with the stop plate (4); one end of the screw rod (6) extends into the sleeve (5) to abut against the stop plate (4), and the other end passes through the through hole (3) It is affixed to the turning handle (7); a connection block (8) is arranged between the screw rod (6) and the end of the through hole (3) away from the central hole (2), the outside of the connection block (8) is fixedly connected to the through hole (3), and the inside is threadedly connected to the screw rod (6). 2.根据权利要求1所述的桩基施工辅助设备,其特征在于:所述抵板(4)上滑动嵌设有若干滚珠(9)。2. The auxiliary equipment for pile foundation construction according to claim 1, characterized in that: a plurality of balls (9) are slidably embedded on the abutment plate (4). 3.根据权利要求1所述的桩基施工辅助设备,其特征在于:所述套筒(5)远离所述中心孔(2)的一端向外凸起,所述贯通孔(3)靠近所述中心孔(2)的一端向内凸起。3. The auxiliary equipment for pile foundation construction according to claim 1, characterized in that: the end of the sleeve (5) away from the central hole (2) protrudes outward, and the end of the through hole (3) close to the central hole (2) protrudes inward. 4.根据权利要求1所述的桩基施工辅助设备,其特征在于:所述扶正机构包括支撑柱(10),所述支撑柱(10)固接于所述安装板(1)顶面左右及后方三侧;左右两侧所述支撑柱(10)顶端固接有液压伸缩杆(11),所述液压伸缩杆(11)活动端固接有夹具组件。4. Auxiliary equipment for pile foundation construction according to claim 1, characterized in that: the righting mechanism includes a support column (10), and the support column (10) is fixedly connected to the left, right and rear sides of the top surface of the installation plate (1); a hydraulic telescopic rod (11) is fixedly connected to the top of the support column (10) on the left and right sides, and a clamp assembly is fixedly connected to the movable end of the hydraulic telescopic rod (11). 5.根据权利要求4所述的桩基施工辅助设备,其特征在于:所述夹具组件包括与所述液压伸缩杆(11)活动端固接的外壳(12),所述外壳(12)两侧固接有电机(13),所述外壳(12)中间固接有安装架(14),所述电机(13)输出端固接有移动螺杆(16),所述移动螺杆(16)与所述外壳(12)以及安装架(14)转动连接,所述移动螺杆(16)上套设有滑动块(17),所述滑动块(17)上固接有连接杆(18),所述外壳(12)远离所述液压伸缩杆(11)的一侧开设有条形槽(19),所述连接杆(18)穿过所述条形槽(19)固接有夹板(20)。5. Auxiliary equipment for pile foundation construction according to claim 4, characterized in that: the clamp assembly includes a housing (12) fixedly connected to the movable end of the hydraulic telescopic rod (11), motors (13) are fixedly connected to both sides of the housing (12), a mounting frame (14) is fixedly connected to the middle of the housing (12), a moving screw (16) is fixedly connected to the output end of the motor (13), and the moving screw (16) is rotationally connected to the housing (12) and the mounting frame (14). A sliding block (17) is sheathed on the moving screw (16), and a connecting rod (18) is fixedly connected to the sliding block (17). A bar-shaped groove (19) is provided on the side of the housing (12) away from the hydraulic telescopic rod (11), and a splint (20) is fixedly connected to the connecting rod (18) through the bar-shaped groove (19). 6.根据权利要求4所述的桩基施工辅助设备,其特征在于:所述支撑柱(10)上下两端分别设置有测距仪(21)。6. The auxiliary equipment for pile foundation construction according to claim 4, characterized in that: the upper and lower ends of the support column (10) are respectively provided with distance meters (21). 7.根据权利要求1所述的桩基施工辅助设备,其特征在于:所述移动机构包括固接于所述安装板(1)四角的液压支撑柱(23),所述液压支撑柱(23)活动端固接有万向轮(22),所述液压支撑柱(23)内侧固接有固定柱(15)。7. The auxiliary equipment for pile foundation construction according to claim 1, characterized in that: the moving mechanism includes a hydraulic support column (23) fixed to the four corners of the installation plate (1), a universal wheel (22) is fixedly connected to the movable end of the hydraulic support column (23), and a fixed column (15) is fixedly connected to the inner side of the hydraulic support column (23). 8.根据权利要求7所述的桩基施工辅助设备,其特征在于:所述固定柱(15)底端固接有支撑盘(24)。8. The auxiliary equipment for pile foundation construction according to claim 7, characterized in that: a support plate (24) is fixedly connected to the bottom of the fixed column (15).
CN202320971854.9U 2023-04-26 2023-04-26 Pile foundation construction auxiliary assembly Active CN219410865U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320971854.9U CN219410865U (en) 2023-04-26 2023-04-26 Pile foundation construction auxiliary assembly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320971854.9U CN219410865U (en) 2023-04-26 2023-04-26 Pile foundation construction auxiliary assembly

Publications (1)

Publication Number Publication Date
CN219410865U true CN219410865U (en) 2023-07-25

Family

ID=87241009

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320971854.9U Active CN219410865U (en) 2023-04-26 2023-04-26 Pile foundation construction auxiliary assembly

Country Status (1)

Country Link
CN (1) CN219410865U (en)

Similar Documents

Publication Publication Date Title
CN114988324A (en) Pipeline installation damping seat based on hydraulic engineering construction
CN219410865U (en) Pile foundation construction auxiliary assembly
CN117405529A (en) A building structure inspection equipment capable of multi-directional inspection
CN216476364U (en) Building construction structure renovation formwork support device
CN219100764U (en) Supporting device for civil engineering construction convenient to move
CN217734952U (en) Nearly modern building antidetonation reinforcing apparatus based on structural performance optimizes
CN215491646U (en) Bridge load test detection equipment
LU501761B1 (en) Restoration and reinforcement apparatus for stone ancient building walls
CN220080915U (en) Building structure reinforced structure
WO2022161533A2 (en) Conveniently movable mounting stand for electromechanical apparatus
CN217132027U (en) A measuring device for interior design assistance
CN221722398U (en) House building structure beam bottom reinforcing apparatus
CN212153109U (en) A double-pier bridge bridge jacking column
CN223867666U (en) A bottom mounting kit for a steel structure column
CN211736423U (en) Auxiliary wall laying device
CN112027957A (en) Intelligent mobile jack
CN218715136U (en) Building engineering template support frame
CN213972749U (en) Guide buffer device of oil press
CN217602037U (en) Elevator shaft assembly type construction operation platform
CN220167436U (en) Lifting frame for building construction
LU506346B1 (en) Construction platform for gravity pier
CN220808960U (en) Voucher pressing machine
CN219623582U (en) Remote emergency alarm device based on application of Internet of things
CN219532050U (en) High formwork structure monitoring devices
CN221001840U (en) Auxiliary installation device for heavy-load air-floatation terrace armor joint

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant