CN219386022U - Bridge support pad stone template assembly - Google Patents

Bridge support pad stone template assembly Download PDF

Info

Publication number
CN219386022U
CN219386022U CN202320235546.XU CN202320235546U CN219386022U CN 219386022 U CN219386022 U CN 219386022U CN 202320235546 U CN202320235546 U CN 202320235546U CN 219386022 U CN219386022 U CN 219386022U
Authority
CN
China
Prior art keywords
positioning
location
template
filler
filler stone
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320235546.XU
Other languages
Chinese (zh)
Inventor
张冲
张秋险
杨俊�
刘庆灵
龙舟
王允
李孝龙
代辉祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN202320235546.XU priority Critical patent/CN219386022U/en
Application granted granted Critical
Publication of CN219386022U publication Critical patent/CN219386022U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Moulds, Cores, Or Mandrels (AREA)

Abstract

The utility model discloses a bridge support filler stone template component, which comprises a filler stone side template structure formed by a composite material template, and also comprises at least one group of positioning hole tools, wherein each group of positioning hole tools comprises a plurality of positioning Kong Xinmo and a positioning structure thereof, a positioning Kong Xinmo is provided with a jack, the positioning structure is provided with a horizontal fixing frame and a plurality of positioning steel pipes which are arranged according to the design positions of positioning holes and are matched with the jacks of a core mold of the positioning holes, the positioning steel pipes are vertically arranged, the upper ends of the positioning steel pipes are connected with the horizontal fixing frame, and the horizontal fixing frame is arranged at the top of the filler stone side template structure and fixedly connected with the top of the filler stone side template structure. The positioning hole fixture disclosed by the utility model has the advantages that the position precision of the positioning hole is ensured by utilizing the position precision of the positioning steel pipe in the positioning hole fixture, the size precision of the positioning hole is ensured by utilizing the size precision of the positioning Kong Xinmo, the quality is ensured, the later maintenance and repair of the filler stone can be avoided, the structure is simple, the mounting and dismounting are convenient, the technical level requirements on constructors are low, and the safety risk is small.

Description

Bridge support pad stone template assembly
Technical Field
The utility model relates to a template assembly, in particular to a bridge support cushion stone template assembly.
Background
At present, the composite material template has the advantages of light weight, convenient installation, easy operation, no need of special personnel for installation, flexible size customization and the like, and is widely applied to the construction of railway and highway bridge engineering filler concrete. In the filler concrete structure, the bridge locating hole is designed, the position precision and the size precision of the bridge locating hole are higher, the current filler pouring template component is difficult to meet the position precision and the size precision requirements of the bridge locating hole due to the lack of a locating hole accurate locating structure, later maintenance and repair treatment are needed, resource waste and construction cost are further caused, the technical level requirements on constructors are higher, the manual and mechanical inputs are more, and the safety risk is larger.
Disclosure of Invention
The utility model provides a bridge support cushion stone template component for solving the technical problems in the prior art, and the component can ensure the precision of a positioning hole.
The utility model adopts the technical proposal for solving the technical problems in the prior art that: the utility model provides a bridge beam supports filler stone template subassembly, includes the filler stone side form structure that constitutes by combined material template, still includes at least a set of locating hole frock, every group locating hole frock includes a plurality of location Kong Xinmo and location structure thereof, location Kong Xinmo is equipped with the jack, location structure is equipped with a horizontal fixed frame and a plurality of according to the locating hole design position arrange, with the identical location steel pipe of locating hole core form jack, the vertical setting of location steel pipe, upper end with horizontal fixed frame is connected, horizontal fixed frame sets up the top of filler stone side form structure, both rigid couplings.
The side mould structure of the filler is formed by combining a peripheral flat mould plate and a corner connecting mould plate, and the horizontal fixing frame is connected with the side mould structure of the filler by adopting connecting bolts.
The horizontal fixing frame is formed by welding angle steel.
The locating hole mandrel is made of PVC plastic pipe.
The utility model has the advantages and positive effects that: in the pouring process, the position accuracy of the positioning holes is guaranteed by utilizing the position accuracy of the positioning steel pipes in the positioning hole tool, the size accuracy of the positioning holes is guaranteed by utilizing the size accuracy of the positioning Kong Xinmo, the quality is guaranteed, the later maintenance and repair of the filler stone can be avoided, the labor and mechanical investment are further saved, and the construction cost is reduced. The utility model has simple structure, adopts the composite material template, is convenient to assemble and disassemble, has low requirements on the technical level of constructors, has small safety risk and has strong applicability.
Drawings
FIG. 1 is a schematic diagram of the structure of the present utility model;
FIG. 2 is a cross-sectional view A-A of FIG. 1;
fig. 3 is a sectional view of B-B of fig. 1.
In the figure: 1-1, a flat template; 1-2, connecting a corner with a template; 2-1, a horizontal fixing frame; 2-2, positioning the steel pipe; 3. positioning Kong Xinmo; 4. and (5) a bolt.
Detailed Description
For a further understanding of the utility model, its features and advantages, reference is now made to the following examples, which are illustrated in the accompanying drawings in which:
referring to fig. 1-3, a bridge support bolster template assembly comprises a bolster side mold structure formed by a composite material template, and further comprises at least one group of positioning hole tools, wherein each group of positioning hole tools comprises a plurality of positioning hole core molds 3 and positioning structures thereof, each positioning hole core mold 3 is provided with a positioning jack, each positioning structure is provided with a horizontal fixing frame 2-1 and a plurality of positioning steel pipes 2-2 which are arranged according to the design positions of the positioning holes and are matched with the positioning jacks of the positioning hole core mold, each positioning steel pipe 2-2 is vertically arranged, the upper end of each positioning steel pipe is connected with the corresponding horizontal fixing frame 2-1, and each horizontal fixing frame 2-1 is arranged at the top of the bolster side mold structure and fixedly connected with the corresponding positioning steel pipe 2-2.
In the embodiment, the side mould structure of the filler is formed by combining the peripheral flat mould plates 1-1 and the corner connecting mould plates 1-2, and the horizontal fixing frame 2-1 is connected with the side mould structure of the filler by bolts 4, so that the side mould structure of the filler is convenient to install and detach. The horizontal fixing frame 2-1 is formed by welding angle steel, and is light in weight and high in strength. The positioning hole core mould 3 is made of PVC plastic pipe, and is convenient to manufacture.
The application of the utility model:
1) The positioning hole core mold positioning structure is manufactured, 2 sets of positioning holes are arranged in the figure 1, and the horizontal fixing frame 2-1 is formed by welding angle steel. Because the positioning structure is prefabricated on the ground, the positioning precision is convenient to guarantee.
2) After the binding of the filler steel bars is completed, fixing the filler steel bar cushion block, and then installing the filler side die structure.
3) After the detection of the side mould structure of the sizing block is qualified, the core mould 3 of the positioning hole is arranged at the position of the reserved hole of the sizing block steel bar, then the positioning structure manufactured in the step 1) is arranged on the side mould structure of the sizing block, positioning Kong Xinmo is inserted into the positioning steel pipes 2-2 in a one-to-one correspondence mode, the position precision of the positioning hole is ensured by utilizing the position precision of the positioning steel pipes, and the size precision of the positioning hole is ensured by utilizing the size precision of the positioning Kong Xinmo.
4) The horizontal fixing frame 2-1 and the side mould structure of the filler stone are connected together by adopting a connecting bolt 4.
5) After the steps are adopted to finish the installation work of the composite material template and the locating hole tool, accurate measurement and rechecking are carried out, and concrete pouring and maintenance work are carried out after the composite material template and the locating hole tool are qualified.
6) When the filler concrete reaches initial setting and meets the demolding condition, the mold can be disassembled, the positioning structure is disassembled integrally, then the positioning Kong Xinmo 3 is disassembled, and finally the filler side mold structure is disassembled. When the concrete is dismantled, the damage of the concrete corners is avoided, the finished product is protected, and the concrete is maintained for a plurality of times until the next working procedure is constructed.
Although the preferred embodiments of the present utility model have been described above with reference to the accompanying drawings, the present utility model is not limited to the above-described embodiments, which are merely illustrative and not restrictive, and many forms may be made by those having ordinary skill in the art without departing from the spirit of the present utility model and the scope of the appended claims, which are within the scope of the present utility model.

Claims (4)

1. The utility model provides a bridge beam supports filler stone template subassembly, includes the filler stone side form structure that constitutes by combined material template, its characterized in that, this template subassembly still includes at least a set of locating hole frock, every group locating hole frock includes a plurality of location Kong Xinmo and location structure thereof, the locating hole mandrel is equipped with the location jack, location structure is equipped with a horizontal fixed frame and a plurality of according to the location hole design position arrangement, with the identical location steel pipe of locating hole core die location jack, the vertical setting of location steel pipe, upper end with horizontal fixed frame is connected, horizontal fixed frame sets up the top of filler stone side form structure, both rigid couplings.
2. The bridge support bolster template assembly of claim 1, wherein the bolster side form structure is formed by combining a peripheral flat form and a corner connection form, and the horizontal fixing frame is connected with the bolster side form structure by adopting a connecting bolt.
3. The bridge support bolster template assembly of claim 1 wherein the horizontal fixed frame is welded with angle steel.
4. The bridge abutment bolster die plate assembly as defined in claim 1 wherein said pilot hole mandrel is made of PVC plastic tubing.
CN202320235546.XU 2023-02-16 2023-02-16 Bridge support pad stone template assembly Active CN219386022U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320235546.XU CN219386022U (en) 2023-02-16 2023-02-16 Bridge support pad stone template assembly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320235546.XU CN219386022U (en) 2023-02-16 2023-02-16 Bridge support pad stone template assembly

Publications (1)

Publication Number Publication Date
CN219386022U true CN219386022U (en) 2023-07-21

Family

ID=87197857

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320235546.XU Active CN219386022U (en) 2023-02-16 2023-02-16 Bridge support pad stone template assembly

Country Status (1)

Country Link
CN (1) CN219386022U (en)

Similar Documents

Publication Publication Date Title
CN105365042A (en) Manufacturing method of small prefabricated box girder
CN110206144B (en) Construction method of steel reinforced column beam column joint
CN109571720A (en) A kind of high-accuracy multifunctional concrete slab prefabricated mould and its working method
CN111098396A (en) Hydraulic adjustable multi-cabin prefabricated pipe gallery die and manufacturing method of multi-cabin prefabricated pipe gallery
CN112282360A (en) Device for fixing shear wall and column and construction method thereof
CN219386022U (en) Bridge support pad stone template assembly
CN112302209B (en) Steel and concrete shear wall mixed structure and manufacturing method thereof
CN111042188A (en) Supporting-free template for reserved bolt holes of roughing mill body and construction method
CN104533035A (en) Glass guardrail system for high-rise buildings and construction method
CN111042549A (en) Method for building aluminum frame plastic formwork room
CN112627570A (en) Repairing tool for repairing large gap of door opening and construction method thereof
CN112921807A (en) Bridge supporting structure machining method
CN113293793A (en) Assembly for connecting prefabricated short column under subway vehicle base cover with foundation and construction method
CN111636678A (en) Manufacturing method of detachable toilet hanging mold supporting tool
CN221436756U (en) Assembled case roof beam ligature mould
CN214293627U (en) Superimposed sheet production mould
CN218969793U (en) Template device with wet joint for PC prefabricated bridge deck of overspan expressway
CN110565529A (en) Sound barrier basis and case roof beam integration template of pouring
CN220285321U (en) Detachable building body mould of marking time
CN220661246U (en) Bottom die and side die combined system of prefabricated box girder and forming system comprising same
CN219486062U (en) Wallboard assembling die
CN211143737U (en) Column formwork bottom reinforcing device
CN211682709U (en) Hydraulic adjustable multi-cabin prefabricated pipe gallery die
CN215319420U (en) Removable prefabricated coincide board mould
CN219450474U (en) Hollow mound construction mould

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant