CN219343189U CN202320855641.XU CN202320855641U CN219343189U CN 219343189 U CN219343189 U CN 219343189U CN 202320855641 U CN202320855641 U CN 202320855641U CN 219343189 U CN219343189 U CN 219343189U
Authority
CN
China
Prior art keywords
foundation pile
fixing clip
rod
base
slider
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320855641.XU
Other languages
Chinese (zh)
Inventor
戴剑
戴兴宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Zilong Construction Engineering Co ltd
Original Assignee
Anhui Zilong Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Zilong Construction Engineering Co ltd filed Critical Anhui Zilong Construction Engineering Co ltd
Priority to CN202320855641.XU priority Critical patent/CN219343189U/en
Application granted granted Critical
Publication of CN219343189U publication Critical patent/CN219343189U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/50Photovoltaic [PV] energy

Landscapes

  • Foundations (AREA)

Abstract

The application relates to foundation pile mount technical field, and discloses a pre-buried reinforcing apparatus of foundation pile, including the fixing clip, the fixing clip is two settings, two the center department fixedly connected with foundation pile of fixing clip, the both sides of fixing clip are all rotated and are connected with the bracing piece, two the equal swing joint of lower extreme of bracing piece has the base, the spout has been seted up to the upper end of base, the inside rotation of spout is connected with the threaded rod, the pole wall threaded connection of threaded rod has the slider, the upper end of slider is rotated with the lower extreme of bracing piece and is connected, the upper end of base is the front and back position with the spout, has evenly seted up rectangular channel. This scheme is when installing the foundation pile on ground, carries out fixed stay to the foundation pile through the fixing clip, makes the supporting rod have certain upward holding in the palm the lifting force to the foundation pile through removing the slider, avoids the foundation pile to move down, can finely tune through the two-way lead screw that sets up simultaneously, has further improved the supporting effect to the foundation pile.

Description

Foundation pile pre-buried reinforcing apparatus
Technical Field
The application relates to the technical field of foundation pile fixing frames, in particular to a foundation pile pre-embedding reinforcing device.
Background
Foundation piles are generally cast integrally from steel bar frames and concrete, and are mostly used as effective supporting bodies for highways or bridges. Foundation pile is when pre-buried use, generally need dig the foundation ditch in advance, then put into foundation ditch with foundation pile one end, pour concrete in the foundation ditch at last, because concrete rigid coupling needs certain time, then need some reinforcing apparatus to realize fixed action to the foundation pile like this, current fixing device, generally only be equipped with single support frame, when resulting in the in-service use like this, can not adjust at will, result in when fixed to the foundation pile, the operation is comparatively loaded down with trivial details, the condition of connecting can appear simultaneously, in sum, single support frame, when acting on the foundation pile, can not adjust the change according to the environment of work, the limitation is great.
Disclosure of Invention
In order to solve the problem that proposes in the background art, this application provides a foundation pile pre-buried reinforcing apparatus.
The utility model provides a pre-buried reinforcing apparatus of foundation pile, includes the fixing clip, the fixing clip is two settings, two the center department fixedly connected with foundation pile of fixing clip, the both sides of fixing clip all rotate and are connected with the bracing piece, two the equal swing joint of lower extreme of bracing piece has the base, the spout has been seted up to the upper end of base, the inside rotation of spout is connected with the threaded rod, the wall threaded connection of threaded rod has the slider, the upper end of slider rotates with the lower extreme of bracing piece to be connected, the upper end of base is the front and back position with the spout, rectangular channel has evenly been seted up to the inside joint in rectangular channel has the stopper, one side and the slider joint of stopper.
Preferably, the inside front and back position of spout all fixedly connected with gag lever post, the pole wall of gag lever post and the inside sliding connection of slider.
Preferably, the center of the support rod is fixedly connected with an inner screw rod, the number of the inner screw rods is two, and the inner walls of the two inner screw rods are connected with two-way screw rods in a threaded mode.
Preferably, the lower end of the base is uniformly and fixedly connected with a fixing rod.
Preferably, a hexagonal block is fixed at the center of the rod wall of the bidirectional screw rod.
In summary, the present application includes the following beneficial technical effects:
when installing the foundation pile on ground, carry out fixed stay to the foundation pile through the fixing clip, make the bracing piece have certain upward holding power to the foundation pile through removing the slider, avoid the foundation pile to move down, can finely tune through the two-way lead screw that sets up simultaneously, further improved the supporting effect to the foundation pile.
Drawings
Fig. 1 is a schematic diagram of the front structure of an embodiment of the application.
Fig. 2 is a schematic view of a support rod structure according to an embodiment of the present application.
Fig. 3 is an enlarged schematic view of the structure at a in fig. 2.
Reference numerals illustrate: 1. a base; 2. a support rod; 3. a foundation pile; 4. a two-way screw rod; 5. an inner screw rod; 6. a fixing clip; 7. a fixed rod; 8. rectangular grooves; 9. a limiting block; 10. a chute; 11. a slide block; 12. a threaded rod; 13. and a limit rod.
Detailed Description
The present application is described in further detail below in conjunction with figures 1-3.
The embodiment of the application discloses pre-buried reinforcing apparatus of foundation pile, refer to fig. 1-3, including fixing clip 6, fixing clip 6 is two settings, the center department fixedly connected with foundation pile 3 of two fixing clips 6, install foundation pile 3 inside the bottom surface, fix two fixing clips 6 at foundation pile 3 suitable position this moment, the both sides of fixing clip 6 are all rotated and are connected with bracing piece 2, the equal swing joint of lower extreme of two bracing pieces 2 has base 1, spout 10 has been seted up to the upper end of base 1, the inside rotation of spout 10 is connected with threaded rod 12, the pole wall threaded connection of threaded rod 12 has slider 11, the upper end of slider 11 is rotated with the lower extreme of bracing piece 2 and is connected, rotate threaded rod 12, make slider 11 to be close to foundation pile 3's direction and remove, slider 11 drives bracing piece 2's lower extreme and remove, make foundation pile 3 have certain ascending prestressing force, and then can avoid foundation pile 3 to sink effectively, the upper end of base 1 is the front and back position with spout 10, evenly set up rectangular slot 8, rectangular slot 8's inside joint has stopper 9, one side and slider 11 of stopper 11 are gone into corresponding stopper 11 after the slider 11 moves into, thereby inside the stopper 8 is gone into to the slider 11 simultaneously very well.
As shown in fig. 3, the front and rear positions of the inside of the chute 10 are fixedly connected with a limit rod 13, the rod wall of the limit rod 13 is in sliding connection with the inside of the slide block 11, and the slide block 11 moves more stably through the limit rod 13.
As shown in fig. 2, the center of the supporting rod 2 is fixedly connected with two inner screw rods 5, the inner wall of each inner screw rod 5 is connected with two bidirectional screw rods 4 in a threaded manner, and the two inner screw rods 5 are far away from or close to each other through rotation of the two bidirectional screw rods 4, so that fine adjustment is further realized, and the supporting effect of the multi-foundation pile 3 is further improved.
As shown in fig. 2, the lower end of the base 1 is uniformly and fixedly connected with a fixing rod 7, and the base 1 can be fixed on the ground through the fixing rod 7, so that the stability of the base 1 is improved.
As shown in fig. 2, a hexagonal block is fixed at the center of the rod wall of the bidirectional screw rod 4, and by means of the arrangement of the hexagonal block, a worker can conveniently rotate the bidirectional screw rod 4 by using tools.
The implementation principle of the foundation pile pre-buried reinforcing device in the embodiment of the application is as follows: the foundation pile 3 is arranged in the bottom surface, at the moment, two fixing clamps 6 are fixed at proper positions of the foundation pile 3, then the fixing rods 7 are inserted into the bottom surface to fix the base 1, at the moment, the threaded rods 12 are rotated to enable the sliding blocks 11 to move towards the direction close to the foundation pile 3, the sliding blocks 11 drive the lower ends of the supporting rods 2 to move, the foundation pile 3 is enabled to have a certain upward prestress, sinking of the foundation pile 3 can be effectively avoided, after the sliding blocks 11 move well, corresponding limiting blocks 9 are clamped into corresponding rectangular grooves 8 at the moment, meanwhile, parts of the limiting blocks 9 enter the sliding blocks 11, and therefore good limiting is carried out on the sliding blocks 11;
further, according to the specific situation, at the later stage, the two inner screw rods 5 are far away from each other or close to each other through the rotation of the two-way screw rods 4, so that fine adjustment is further realized, and the supporting effect of the multi-foundation pile 3 is further improved.
It is noted that relational terms such as first and second, and the like are used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Moreover, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Although embodiments of the present utility model have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the utility model, the scope of which is defined in the appended claims and their equivalents.

Claims (5)

1. The utility model provides a pre-buried reinforcing apparatus of foundation pile, includes fixing clip (6), its characterized in that: fixing clip (6) are two settings, two the center department fixedly connected with foundation pile (3) of fixing clip (6), the both sides of fixing clip (6) all rotate and are connected with bracing piece (2), two equal swing joint of lower extreme of bracing piece (2) has base (1), spout (10) have been seted up to the upper end of base (1), the inside rotation of spout (10) is connected with threaded rod (12), the pole wall threaded connection of threaded rod (12) has slider (11), the upper end of slider (11) is connected with the lower extreme rotation of bracing piece (2), rectangular channel (8) have evenly been seted up for the upper end with the front and back position of spout (10) in the upper end of base (1), the inside joint of rectangular channel (8) has stopper (9), one side and slider (11) joint of stopper (9).
2. A foundation pile pre-buried reinforcing apparatus according to claim 1, wherein: the inner front and rear positions of the sliding groove (10) are fixedly connected with limiting rods (13), and the rod walls of the limiting rods (13) are in sliding connection with the inner parts of the sliding blocks (11).
3. A foundation pile pre-buried reinforcing apparatus according to claim 1, wherein: an inner screw rod (5) is fixedly connected to the center of the supporting rod (2), two inner screw rods (5) are arranged, and two bidirectional screw rods (4) are connected with the inner walls of the inner screw rods (5) in a threaded mode.
4. A foundation pile pre-buried reinforcing apparatus according to claim 1, wherein: the lower end of the base (1) is uniformly and fixedly connected with a fixing rod (7).
5. A foundation pile pre-buried reinforcing apparatus according to claim 3, wherein: a hexagonal block is fixed at the center of the rod wall of the bidirectional screw rod (4).
CN202320855641.XU 2023-04-18 2023-04-18 Foundation pile pre-buried reinforcing apparatus Active CN219343189U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320855641.XU CN219343189U (en) 2023-04-18 2023-04-18 Foundation pile pre-buried reinforcing apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320855641.XU CN219343189U (en) 2023-04-18 2023-04-18 Foundation pile pre-buried reinforcing apparatus

Publications (1)

Publication Number Publication Date
CN219343189U true CN219343189U (en) 2023-07-14

Family

ID=87075140

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320855641.XU Active CN219343189U (en) 2023-04-18 2023-04-18 Foundation pile pre-buried reinforcing apparatus

Country Status (1)

Country Link
CN (1) CN219343189U (en)

Similar Documents

Publication Publication Date Title
CN211396737U (en) Template strutting arrangement for building engineering
CN219343189U (en) Foundation pile pre-buried reinforcing apparatus
CN208473298U (en) Square cross section column type mould reinforcing member
CN114799333A (en) Full-automatic cutting production line of corrugated metal pipe based on prestressed bridge
CN213710355U (en) Construction pouring plate structure
CN210508408U (en) Concrete pouring workbench for house construction
CN210659280U (en) Concrete placement fixing device for building
CN220282035U (en) Firm support is used in precast pile transportation
CN218234468U (en) Vertical building prefab consolidates adjustment facility
CN220226244U (en) Building engineering frame post reinforcing apparatus
CN218523154U (en) Pipeline supporting structure for municipal engineering construction
CN213682448U (en) Municipal transportation sewer well desilting equipment based on environment is administered
CN220807903U (en) Concrete slab pouring device for civil engineering construction
CN217537858U (en) Quick reinforcing tool for ground beam template
CN217326439U (en) Anti-bank formwork reinforcing steel bar clamp
CN219734422U (en) Pipeline laying support fixing device
CN220847715U (en) Water-stopping steel plate fixed mounting structure convenient to install and adjust
CN221186924U (en) Material compacting uniform vibration platform
CN219826187U (en) Compaction system for concrete pouring
CN218292168U (en) Position limiter
CN218667049U (en) Concrete placement is with maintaining patching device
CN220847382U (en) Water conservancy protection slope structure
CN218932911U (en) Template connecting device for bridge construction
CN217079706U (en) Building templates link for civil engineering
CN219522459U (en) Slurry blocking device for assembled building laminated slab mold