CN219327298U CN202320553067.2U CN202320553067U CN219327298U CN 219327298 U CN219327298 U CN 219327298U CN 202320553067 U CN202320553067 U CN 202320553067U CN 219327298 U CN219327298 U CN 219327298U
Authority
CN
China
Prior art keywords
rod
rod body
hanging basket
guide rod
corresponding floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202320553067.2U
Other languages
Chinese (zh)
Inventor
田为永
李贤�
韩栋
周品
石志辉
陈宇轩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Investment Building Industrialization Investment Construction Development Co ltd
Original Assignee
Beijing Investment Building Industrialization Investment Construction Development Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Investment Building Industrialization Investment Construction Development Co ltd filed Critical Beijing Investment Building Industrialization Investment Construction Development Co ltd
Priority to CN202320553067.2U priority Critical patent/CN219327298U/en
Application granted granted Critical
Publication of CN219327298U publication Critical patent/CN219327298U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The application relates to a segmentation internal pulling formula hanging flower basket construction equipment belongs to the construction field, and its technical scheme main points include: the hanging basket assembly outside the corresponding floor is arranged, and the hanging basket assembly outside the corresponding floor is arranged and used for hanging the hanging basket assembly, the hanging basket assembly comprises a guide rod arranged outside the corresponding floor and a pulley block arranged at the end part of the guide rod, when the hanging basket assembly is used, the hanging basket assembly is hung on the corresponding floor by installing the guide rod and the pulley block according to construction requirements, so that the hanging basket assembly always keeps the same horizontal distance with each floor, different heights can be met, and the hanging basket assembly is convenient to operate, low in cost and high in safety.

Description

Sectional internal pulling type hanging basket construction device
Technical Field
The application relates to the field of building construction, in particular to a sectional internal pulling type hanging basket construction device.
Background
The curtain wall is a light wall body with decorative effect, which is commonly used in modern large-scale and high-rise buildings, and consists of a panel and a supporting structure system. With the development of the building industry, the large-angle camber curtain wall engineering with attractive appearance is more and more.
During construction, supporting structures such as keels are built, then the panel is hoisted to a preset position on the keels for installation, and a hoisting tool is usually provided with a hanging basket, a scaffold and a climbing vehicle: the conventional hanging basket can only vertically move up and down and cannot meet the construction requirement of the camber curtain wall; the scaffold is built, so that a full scaffold is required to be built, the construction is complicated, the cost is high, the quality of the built scaffold is greatly influenced by personal technology of staff, the safety cannot be ensured, in addition, the closing-up of curtain walls at the dismantling positions is considered after the scaffold is dismantled, and the workload is increased; the operation point of the climbing vehicle is single, the requirement of simultaneous construction at multiple points cannot be met, the construction period is prolonged, meanwhile, the climbing vehicle belongs to large equipment, the renting cost is high, and the construction cost is increased.
Aiming at the related technology, the inventor provides a sectional internal pulling type hanging basket construction device to solve the defects in the prior art.
Disclosure of Invention
In order to solve the problem that a panel is installed in the construction of the camber curtain wall only by means of a scaffold and a climbing vehicle, the application provides a sectional internal pulling type hanging basket construction device.
The application provides a segmentation internal pulling formula hanging flower basket construction equipment adopts following technical scheme:
a segmented pull-in basket construction device, comprising: the lifting assembly comprises a guide rod arranged on the outer side of the corresponding floor and a pulley block arranged at the end part of the guide rod.
Through adopting above-mentioned technical scheme, according to the construction demand, install guide bar and assembly pulley on corresponding floor and hoist and mount hanging flower basket subassembly, make hanging flower basket subassembly all remain the same horizontal spacing with every layer of floor all throughout, can satisfy the installation of the camber curtain wall of different height, different inclination, the simple operation, with low costs, the security is high.
The application further sets up: the pulley block is detachably connected to the end part of the guide rod.
Through adopting above-mentioned technical scheme, can install the guide bar of corresponding floor with the assembly pulley according to the construction demand on, realize the turnover use of assembly pulley, reduce the cost input, reduced construction cost.
The application further sets up: the pulley block is provided with a positioning block, the end part of the guide rod is provided with a positioning groove for accommodating the positioning block, the guide rod is connected with a bolt in a threaded manner, and the bolt penetrates through the positioning block.
Through adopting above-mentioned technical scheme, when installing the assembly pulley, align locating piece and constant head tank on the assembly pulley and slide into along the constant head tank, realize the prepositioning of assembly pulley, the simple operation, the rethread bolt is fixed the assembly pulley, and is fixed firm.
The application further sets up: the anti-loosening toothed ring is sleeved on the nut of the bolt, and an anti-loosening toothed block meshed with the anti-loosening toothed ring is arranged on the guide rod.
Through adopting above-mentioned technical scheme, when hanging flower basket subassembly goes up and down, guide bar and assembly pulley can produce certain rocking, under the cooperation of locking ring gear and locking tooth piece, reduced the possibility that the bolt pine takes off, it is fixed more firm, the security is higher.
The application further sets up: the guide rod comprises a first rod body arranged on the outer side of the corresponding floor and a second rod body which is connected to the end of the first rod body in a sliding mode along the length direction of the first rod body, and a fixing assembly used for fixing the second rod body is arranged on the first rod body.
Through adopting above-mentioned technical scheme, be fixed in the floor outside with the first body of rod after, according to the position of the first body of rod to the length that the second body of rod stretches out the floor is adjusted to hoist and mount hanging flower basket subassembly, need not select the guide bar of suitable length repeatedly, simple operation, labour saving and time saving.
The application further sets up: the fixed assembly comprises a first jack arranged on a first rod body, an inserting rod is arranged in the first jack in a penetrating mode, and second jacks which are arranged in an array mode and correspond to the first jacks are arranged on a second rod body in the length direction of the second rod body.
Through adopting above-mentioned technical scheme, slide the second body of rod to the preset position after, one of them second jack aligns with first jack, passes first jack and second jack with the inserted bar simultaneously, and the second body of rod is fixed, simple operation, labour saving and time saving.
The application further sets up: the outside of the inserted link is sleeved with a spring, one end of the spring is connected to the inserted link, the other end of the spring is connected to the first rod body, and the spring enables the inserted link to slide towards the second rod body.
Through adopting above-mentioned technical scheme, under the effect of spring restoring force, the inserted bar supports tightly in first jack and second jack, and the inserted bar is difficult for the pine to take off, and is fixed more firm, and the security is higher.
The application further sets up: the first rod body is provided with a reinforcing rod, and the other end of the reinforcing rod is connected to a corresponding floor.
Through adopting above-mentioned technical scheme, strengthened the bulk strength of guide bar, reduced the cracked possibility of guide bar in the hoist and mount process, the security is higher.
In summary, the present application has the following beneficial effects:
according to construction demand, install guide bar and assembly pulley on corresponding floor and hoist and mount hanging flower basket subassembly, make hanging flower basket subassembly all remain the same horizontal interval with every layer of floor all throughout, the simple operation, with low costs, the security is high.
Drawings
FIG. 1 is a schematic overall structure of an embodiment of the present application;
fig. 2 is an enlarged view at a in fig. 1 of an embodiment of the present application.
Reference numerals illustrate:
1. a floor; 2. a guide rod; 21. a first rod body; 22. a second rod body; 23. a first jack; 24. a rod; 25. a second jack; 26. a spring; 27. a reinforcing rod; 3. pulley block; 31. a positioning block; 32. a positioning groove; 33. a bolt; 34. an anti-loosening toothed ring; 35. locking tooth blocks; 41. a main body structure steel beam; 42. a floor slab; 43. embedding a steel beam; 51. a hanging basket; 52. a wire rope; 53. a safety rope; 61. a support; 62. a rotating wheel; 63. a groove.
Detailed Description
The present application is described in further detail below with reference to the accompanying drawings.
This embodiment: a segmented pull-in basket construction apparatus, referring to fig. 1 and 2, comprising: the hanging basket assembly arranged on the outer side of the corresponding floor 1 and the hanging assembly arranged on the outer side of the corresponding floor 1 and used for hanging the hanging basket assembly, the floor 1 comprises a main body structure steel beam 41 and a floor slab 42 erected on the main body structure steel beam 41, and an embedded steel beam 43 is embedded at the edge of the floor slab 42.
The hoisting assembly comprises guide rods 2 horizontally welded on the embedded steel beams 43 of the corresponding floor 1 and pulley blocks 3 detachably connected to the end parts of the guide rods 2, the guide rods 2 extend to the outside of the floor 1, reinforcing rods 27 are welded at the bottoms of the guide rods 2, forty-five degrees are formed between the reinforcing rods 27 and the guide rods 2, and the other ends of the reinforcing rods 27 are welded on the main structure steel beams 41. The basket assembly comprises a basket 51, a steel wire rope 52 and a safety rope 53 which are fixedly connected to the top of the basket 51, and the steel wire rope 52 and the safety rope 53 pass through the pulley block 3.
During construction, all floors 1 to be installed are welded with guide rods 2 at the edges, then the pulley block 3 is installed on one guide rod 2 from low to high or from high to low, the steel wire rope 52 and the safety rope 53 penetrate through the pulley block 3, the panel is hoisted to the corresponding floor 1 through the hanging basket 51, the pulley block 3 is installed on the next guide rod 2 after the installation is completed, and the like until the construction is completed, the installation of camber curtain walls with different heights and different inclination angles can be met, the operation is convenient, the cost is low, and the safety is high.
Before welding the guide rod 2, the guide rod 2 with a proper length needs to be selected according to the position of the embedded steel beam 43, which is time-consuming and labor-consuming, therefore, the guide rod 2 comprises a first rod body 21 welded on the outer side of the corresponding floor 1 and a second rod body 22 slidably connected to the end part of the first rod body 21 along the length direction of the first rod body 21, and a fixing assembly for fixing the second rod body 22 is arranged on the first rod body 21.
The fixed assembly comprises a first jack 23 arranged on the first rod body 21, a plug rod 24 is arranged in the first jack 23 in a sliding mode, the extending direction of the plug rod 24 is perpendicular to the extending direction of the first rod body 21, and five second jacks 25 which are arranged in an array mode and correspond to the first jack 23 are arranged on the second rod body 22 along the length direction of the second rod body 22. In addition, the insert rod 24 is sleeved with a spring 26, one end of the spring 26 is connected to the insert rod 24, the other end of the spring 26 is connected to the first rod body 21, and the spring 26 enables the insert rod 24 to slide towards the second rod body 22.
After the first rod body 21 is welded on the embedded steel beam 43, the inserting rod 24 is pulled up, at the moment, the spring 26 is in a stretched state, after the second rod body 22 slides to a preset position, one second inserting hole 25 is aligned with the first inserting hole 23, the inserting rod 24 is loosened, under the action of restoring force of the spring 26, the inserting rod 24 rebounds into the first inserting hole 23 and the second inserting hole 25, the second rod body 22 is fixed, and the operation is convenient, time-saving and labor-saving.
The pulley block comprises a support 61 and a rotating wheel 62 rotatably connected to the support 61, a positioning block 31 is welded on the support 61, a positioning groove 32 for accommodating the positioning block 31 is formed in the end portion of the guide rod 2, four bolts 33 are vertically connected to the end portion of the guide rod 2 in a threaded mode, and the bolts 33 penetrate through the positioning block 31. The nut of the bolt 33 is welded with a locking gear ring 34, the guide rod 2 is provided with four grooves 63, and each groove 63 is internally clamped with a locking gear block 35 meshed with the locking gear ring 34.
When the pulley block 3 is installed, the positioning block 31 on the support 61 is aligned with the positioning groove 32 on the guide rod 2 and slides in along the positioning groove 32, after the pulley block 3 is installed in place, the four bolts 33 are screwed into the guide rod 2 and the positioning block 31, the pulley block 3 is fixed, the pulley block 3 is convenient to assemble and disassemble, the turnover use of the pulley block 3 is realized, the cost input is reduced, the construction cost is reduced, finally, the anti-loosening tooth block 35 is clamped into the groove 63, the anti-loosening tooth block 35 is meshed with the anti-loosening tooth ring 34, the possibility of loosening the bolts 33 is reduced, the fixing is more stable, and the safety is higher.
The implementation principle of the sectional internal pulling type hanging basket construction device provided by the embodiment of the application is as follows: during construction, the guide rods 2 are welded on all floors 1 to be constructed, the second rod body 22 is slid to a preset position, the second rod body 22 is fixed by the inserted rods 24, the pulley blocks 3 are sequentially installed on each guide rod 2 from high to low or from low to high, the pulley blocks 3 are fixed by the bolts 33, the rotation of the bolts 33 is limited by the anti-loosening toothed rings 34 and the anti-loosening toothed blocks 35, and finally the panel is hoisted to the corresponding floor 1, so that turnover of the pulley blocks 3 is realized, cost investment is reduced, construction cost is reduced, and meanwhile, installation of camber curtain walls with different heights and different inclination angles can be met, and the installation method is convenient and quick to operate, low in cost and high in safety.
The foregoing are all preferred embodiments of the present application, and are not intended to limit the scope of the present application in any way, therefore: all equivalent changes in structure, shape and principle of this application should be covered in the protection scope of this application.

Claims (5)

1. The utility model provides a segmentation internal pulling formula hanging flower basket construction equipment which characterized in that includes: the lifting device comprises a hanging basket assembly arranged on the outer side of a corresponding floor (1) and a lifting assembly arranged on the outer side of the corresponding floor (1) and used for lifting the hanging basket assembly, wherein the lifting assembly comprises a guide rod (2) arranged on the outer side of the corresponding floor (1) and a pulley block (3) arranged at the end part of the guide rod (2);
the pulley block (3) is detachably connected to the end part of the guide rod (2);
the pulley block (3) is provided with a positioning block (31), the end part of the guide rod (2) is provided with a positioning groove (32) for accommodating the positioning block (31), the guide rod (2) is connected with a bolt (33) in a threaded manner, and the bolt (33) penetrates through the positioning block (31);
the anti-loosening toothed ring (34) is sleeved on the nut of the bolt (33), and the anti-loosening toothed block (35) meshed with the anti-loosening toothed ring (34) is arranged on the guide rod (2).
2. The segmented pull-in basket construction device of claim 1, wherein: the guide rod (2) comprises a first rod body (21) arranged on the outer side of the corresponding floor (1) and a second rod body (22) which is connected to the end portion of the first rod body (21) in a sliding manner along the length direction of the first rod body (21), and a fixing assembly used for fixing the second rod body (22) is arranged on the first rod body (21).
3. A segmented pull-in basket construction apparatus according to claim 2, wherein: the fixing assembly comprises a first jack (23) arranged on a first rod body (21), a plug rod (24) is arranged in the first jack (23) in a penetrating mode, and second jacks (25) which are arranged in an array mode and correspond to the first jack (23) are arranged on a second rod body (22) in the length direction of the second rod body (22).
4. A segmented pull-in basket construction apparatus according to claim 3, wherein: the novel sliding rod is characterized in that a spring (26) is sleeved outside the inserted rod (24), one end of the spring (26) is connected to the inserted rod (24), the other end of the spring (26) is connected to the first rod body (21), and the spring (26) enables the inserted rod (24) to slide towards the second rod body (22).
5. A segmented pull-in basket construction apparatus according to claim 2, wherein: the first rod body (21) is provided with a reinforcing rod (27), and the other end of the reinforcing rod (27) is connected to the corresponding floor (1).
CN202320553067.2U 2023-03-18 2023-03-18 Sectional internal pulling type hanging basket construction device Active CN219327298U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202320553067.2U CN219327298U (en) 2023-03-18 2023-03-18 Sectional internal pulling type hanging basket construction device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202320553067.2U CN219327298U (en) 2023-03-18 2023-03-18 Sectional internal pulling type hanging basket construction device

Publications (1)

Publication Number Publication Date
CN219327298U true CN219327298U (en) 2023-07-11

Family

ID=87063235

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202320553067.2U Active CN219327298U (en) 2023-03-18 2023-03-18 Sectional internal pulling type hanging basket construction device

Country Status (1)

Country Link
CN (1) CN219327298U (en)

Similar Documents

Publication Publication Date Title
CN213329955U (en) Flower basket diagonal rod type overhanging scaffold
CN213897480U (en) Multi-story high-rise frame steel structure
CN219327298U (en) Sectional internal pulling type hanging basket construction device
CN111236616A (en) Horizontal guide rail walking hanging basket for high-rise construction
CN113175089A (en) Construction method of large-span heavy cantilever truss
CN109879179B (en) Assembled steel construction tower crane platform
CN114412192B (en) Interlayer complex special-shaped aluminum veneer curtain wall and construction method thereof
CN111762690B (en) Device and method for vertically hanging and horizontally moving multiple metal net curtains in place in large space
CN114873431A (en) Movable lifting appliance convenient for adjusting position of lifting hook
CN111962851A (en) Concrete building overhanging part decoration operation platform
CN111305433A (en) Construction structure and construction method of inclined glass curtain wall of roof steel structure platform
CN205777422U (en) Encorbelment combined type support system based on intelligent monitoring oblique pull
CN217759925U (en) BIM-based steel operating platform for light production well
CN220167426U (en) High-safety building construction frame
CN218149654U (en) Overhanging type scaffold
CN114856213B (en) High-altitude butt joint construction method for round pipe column
CN204456585U (en) A kind of furred ceiling angle bar frame counter support structure
CN109577632B (en) Suspended scaffold and construction method thereof
CN220621124U (en) Unit curtain wall hoisting and hanging basket installing guide rail system
CN217557747U (en) Green steel construction hoisting device that decorates
CN219387183U (en) Construction hole hanging die device
CN217106264U (en) Balcony edge protection system
CN114086660B (en) Green energy-saving assembled building and construction method
CN217924767U (en) Hanging basket mounting structure
CN220907022U (en) Lifting crawling ladder for building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant