CN219240525U - Maintenance and stability system for bored pile construction - Google Patents

Maintenance and stability system for bored pile construction Download PDF

Info

Publication number
CN219240525U
CN219240525U CN202223599448.9U CN202223599448U CN219240525U CN 219240525 U CN219240525 U CN 219240525U CN 202223599448 U CN202223599448 U CN 202223599448U CN 219240525 U CN219240525 U CN 219240525U
Authority
CN
China
Prior art keywords
soil layer
reinforcing
casing
bored pile
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202223599448.9U
Other languages
Chinese (zh)
Inventor
卜德双
杨新民
莫蜀湘
张启军
汤海军
樊小峰
符蓓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 19th Bureau Group Co Ltd
Guangzhou Engineering Co Ltd of China Railway 19 Bureau Group Co Ltd
Original Assignee
China Railway 19th Bureau Group Co Ltd
Guangzhou Engineering Co Ltd of China Railway 19 Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 19th Bureau Group Co Ltd, Guangzhou Engineering Co Ltd of China Railway 19 Bureau Group Co Ltd filed Critical China Railway 19th Bureau Group Co Ltd
Priority to CN202223599448.9U priority Critical patent/CN219240525U/en
Application granted granted Critical
Publication of CN219240525U publication Critical patent/CN219240525U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model provides a maintenance and stabilization system for bored pile construction. The maintenance and stabilization system for the construction of the bored pile comprises a pile casing and a soil layer reinforcing component; the pile casing and the soil layer reinforcing component extend along the vertical direction, and the soil layer reinforcing component surrounds the radial outer side of the pile casing and forms a limiting space with the pile casing; the soil layer reinforcing assembly comprises a plurality of reinforcing members arranged along the circumference of the casing, and each reinforcing member extends along the vertical direction. The maintenance and stability system for the bored pile construction can improve usability, improve construction efficiency, reduce construction cost, and can reduce the waste of concrete when the steel pile casing is pulled out without specially making a thickened steel pile casing.

Description

Maintenance and stability system for bored pile construction
Technical Field
The utility model relates to the technical field of bored pile construction, in particular to a maintenance and stability system for bored pile construction.
Background
The bored pile is a pile formed by forming pile holes in foundation soil by means of mechanical boring, steel pipe soil squeezing, manual excavation or the like on an engineering site, placing a reinforcement cage therein and pouring concrete, and can be divided into a sinking pipe bored pile, a boring bored pile, a hole digging bored pile and the like according to different pore-forming methods. Bored piles generally comprise the following construction processes: firstly positioning a pile position of a cast-in-place pile, burying a steel pile casing, retesting and correcting deviation between the pile position of the cast-in-place pile and the pile casing center, drilling a hole by using a drilling machine, putting a manufactured steel reinforcement cage into the hole, fixing the steel reinforcement cage, pouring a guide pipe downwards, secondarily clearing the hole, pouring concrete, and dispatching a special person to measure the burying depth of the guide pipe, thereby completing pouring of the cast-in-place pile.
The bored pile is used as a non-soil-squeezing pile for improving the foundation, has the advantages of convenience in construction, high engineering progress, strong earthquake resistance and the like, and does not need large mechanical equipment, thereby being widely applied to foundation treatment construction. Generally, the hole digging pile is suitable for clay layers with less groundwater, powdery clay layers or clay layers with a small amount of sand gravel. When the hole digging pile penetrates through a backfill layer, a soft soil layer and a silt layer of the sand-containing gravel, on one hand, the water permeability of the stratum is high, the wall protection is easy to cause water seepage, and on the other hand, the stratum is mainly poor in self-stability due to the stratum, and holes collapse easily occurs in construction.
For this reason, when bored piles are drilled, steel casings are usually arranged at the openings to support weak strata, and are used for guaranteeing the verticality of the drilled holes. Because the soil layer is weak, the steel casing is easy to deform under the self-weight extrusion of the soil layer, and the weight of the steel casing is increased sharply due to the simple increase of the thickness of the steel casing, so that the extraction force of the steel casing when being taken out is greatly increased. Even if the reinforced steel pile casing can be pulled out, the concrete with high fluidity and high density can form an outward extrusion effect on a weak soil layer along with the pulling out of the steel pile casing, so that the diameter of a pile hole is increased, additional concrete is required to be used for casting, and the construction cost is additionally increased.
As another solution, it is generally simple to use clay compaction or to reinforce the soil layer around the steel casing by means of an adhesive modification. The method is simple and easy to operate, but has larger engineering quantity and higher cost. The scheme comprises the steps of using a first limiting rod, a second limiting rod, a third die, a fastening bolt, a first hoop, a second hoop, reinforced soil, grouting pipes and a steel plate. The related accessories can only be suitable for drilling with fixed aperture, different apertures need different three-petal molds and different steel plates, and the structure is complex, the cost is high, and the use is inconvenient.
Disclosure of Invention
The utility model aims to provide a maintenance and stability system for the bored pile construction, which has the advantages of improving usability, improving construction efficiency, reducing construction cost, and reducing the waste of concrete when the steel casing is pulled out without specially making a thickened steel casing.
In order to achieve the above purpose, the utility model provides a maintenance and stabilization system for bored pile construction, which comprises a pile casing and a soil layer reinforcing component; the pile casing and the soil layer reinforcing component extend along the vertical direction, and the soil layer reinforcing component surrounds the radial outer side of the pile casing and forms a limiting space with the pile casing; the soil layer reinforcing assembly comprises a plurality of reinforcing members arranged along the circumference of the casing, and each reinforcing member extends along the vertical direction.
According to the scheme, the soil layer reinforcing component is arranged outside the pile casing, so that the soil layer around the steel pile casing is divided into the inner soil layer and the outer soil layer, a curved path communicated with the inner soil layer and the outer soil layer is formed between two adjacent reinforcing members, and the flow resistance of the soil layer can be increased by the curved path. Because the internal diameter of soil layer reinforcement subassembly is greater than the external diameter of a casing, the compression that the soil layer in the limited spacing space can receive and the deflection that takes place is very little, therefore when extracting a casing, the concrete is difficult to expand along the radial of drilling, avoids additionally using the concrete to pour to save the concrete. In addition, the reinforcement enclosure such as I-steel has better pressure maintaining effect on the concrete poured in the reinforcement enclosure, and is beneficial to improving the structural strength of the poured concrete. Therefore, the pile casing is not required to be thickened, the soil layer around the pile casing is not required to be hardened and improved, and only the national standard I-steel or channel steel is required to be used as the reinforcing member of the soil layer reinforcing tool, so that the reinforcing member can be repeatedly used and can be suitable for different drilling apertures. Soil layer reinforcement can be completed only by inserting and pulling reinforcing members such as I-steel, and the method is simple and easy to operate, high in construction efficiency and low in cost. In addition, as the I-steel and the drill hole are separated by a barreled soil layer, even if the I-steel is pulled out after the cast concrete is solidified, the adhesion phenomenon of the concrete and the I-steel can not occur. Moreover, the contact surface of the single I-steel and the soil layer is far smaller than the contact surface of the protective cylinder and the soil layer, so that the extraction resistance of the I-steel is far smaller than the extraction resistance of the protective cylinder, the I-steel can be easily pressed into the weak soil layer by using a common static pressing machine, and the weak soil layer can also be easily driven into the weak soil layer by using a simple pile driver.
In one preferred embodiment, the maintenance system further comprises a reinforcing inner ring, wherein the reinforcing inner ring is arranged on the radial inner side of the soil layer reinforcing component and is close to the top end of the soil layer reinforcing component, and the reinforcing inner ring supports the soil layer reinforcing component in the radial direction.
Therefore, the supporting strength of the I-steel can be increased by reinforcing the inner ring, and the resistance strength of the soil layer reinforcing component for resisting the horizontal inward extrusion of the soil layer is increased.
Further, the height of the reinforced inner ring is in the range of 50 mm to 100 mm; and/or the wall thickness of the reinforcing inner ring is in the range of 20 mm to 40 mm.
It follows that since the axial height of the reinforcing inner ring is not high, it is easy to install even if the reinforcing inner ring is a little thick.
In one preferred embodiment, the dimensional stability system further comprises a reinforcing outer ring disposed radially outwardly of the soil layer reinforcing assembly and disposed proximate a top end of the soil layer reinforcing assembly, the reinforcing outer ring supporting the reinforcement in a radial direction.
Therefore, the supporting strength of the I-steel can be increased by reinforcing the outer ring, and the resistance strength of the soil layer reinforcing component for resisting the outward expansion of the soil layer is increased.
In a preferred embodiment, the reinforcement is an i-steel or a channel steel.
In a preferred embodiment, a curved path is formed between two adjacent reinforcement members; and/or the width of the meander is in the range of 10 millimeters to 80 millimeters.
Thus, the width of the curved road can be selected according to the softness of the soil layer, and the softer the soil layer, the smaller the width.
Preferably, the length of the reinforcement is equal to the length of the casing; or the length of the reinforcement is greater than the length of the casing, and the bottom wall of the reinforcement is lower than the bottom wall of the casing.
It can be seen that the casing penetrates through the weak soil layer, and the length of the reinforcing member is equal to that of the steel casing. Or the length of the reinforcement member is greater than the length of the casing so that the lower end of the reinforcement member may be inserted into a deeper, relatively stiffer formation to increase the overall horizontal slip resistance of the reinforcement member.
In a preferred embodiment, the number of soil layer reinforcing members is two or more, and the plurality of soil layer reinforcing members are arranged along the radial direction of the casing and coaxially arranged. In the soil layer reinforcing component at the innermost layer, two adjacent reinforcing members are mutually overlapped, and in other soil layer reinforcing components, the two adjacent reinforcing members are arranged at intervals.
Therefore, the mutually overlapped reinforcing members can provide supporting force mutually, strengthen bearing capacity mutually, and can also improve tensile strength in a mutually buckling mode, so that the bearing strength of the soil layer in the whole ring is increased. The upper ends of the I-steel between the two adjacent soil layer reinforcing components can be subjected to lap welding through steel bars or I-steel, so that the adjacent soil layer reinforcing components are mutually supported, and the overall strength of the soil layer reinforcing components is greatly improved. In the soil layer reinforcing component of the innermost layer, two adjacent reinforcing members are mutually overlapped, in other soil layer reinforcing components, two adjacent reinforcing members are arranged at intervals and are not required to be mutually overlapped to form a whole circle, so that the I-steel consumption and the construction workload are saved.
The further scheme is that the height of the pile casing is H, and the radius difference value of two adjacent soil layer reinforcing components is in the range of 0.1H to 0.5H.
Drawings
Fig. 1 is a perspective view of a first embodiment of a stabilization system for bored pile construction according to the present utility model.
Fig. 2 is a top view and a partial enlarged view of a first embodiment of a stabilization system for bored pile construction according to the present utility model.
Fig. 3 is a perspective view of a second embodiment of the stabilization system for bored pile construction of the present utility model.
Fig. 4 is a top view of a second embodiment of the stabilization system for bored pile construction of the present utility model.
Fig. 5 is a top view of a third embodiment of a stabilization system for bored pile construction according to the present utility model.
Fig. 6 is a top view of a fourth embodiment of the stabilization system for bored pile construction of the present utility model.
Fig. 7 is a top view of a fifth embodiment of a stabilization system for bored pile construction according to the present utility model.
Fig. 8 is a top view of a sixth embodiment of the stabilization system for bored pile construction of the present utility model.
Fig. 9 is a top view of a seventh embodiment of the stabilization system for bored pile construction of the present utility model.
Fig. 10 is a top view of an eighth embodiment of the stabilization system for bored pile construction of the present utility model.
Fig. 11 is a top view of a ninth embodiment of the stabilization system for bored pile construction of the present utility model.
The utility model is further described below with reference to the drawings and examples.
Detailed Description
First embodiment of a maintenance and stabilization System for bored pile construction
Referring to fig. 1 and 2, the maintenance system for bored pile construction of the present embodiment includes a casing 11 and a soil reinforcing assembly 12. The pile casing 11 and the soil reinforcing component 12 extend along the vertical direction, the pile casing 11 and the soil reinforcing component 12 are coaxially arranged, and the soil reinforcing component 12 surrounds the radial outer side of the pile casing 11 and forms a limiting space 13 with the pile casing 11. Preferably, the casing 11 is a steel casing.
Soil layer reinforcement assembly 12 includes a plurality of reinforcement members 14 arranged along the circumference of casing 11, each reinforcement member 14 extending in a vertical direction. In this embodiment, the fastener 14 is a i-steel 14. A curved path 15 is formed between two adjacent I-beams 14, and the width of the curved path 15 is in the range of 10 mm to 80 mm. The width of the curved path 15 may be selected according to the degree of weakness of the soil layer, the softer the soil layer the smaller the width.
The length of the i-steel 14 is equal to the length of the casing 11. Alternatively, in other embodiments, the length of the i-beam 14 may be greater than the length of the casing 11, and the bottom wall of the i-beam 14 may be lower than the bottom wall of the casing 11, so that the horizontal sliding resistance of the i-beam 14 as a whole may be increased when the lower end of the i-beam 14 is inserted into a deeper, relatively harder formation.
Each of the i-beams 14 of the soil reinforcing assembly 12 includes a first reinforcement and a second reinforcement, the first reinforcement is a first i-beam 16, the second reinforcement is a second i-beam 17, the first i-beam 16 and the second i-beam 17 are alternately arranged along the circumferential direction of the soil reinforcing assembly 12, the first i-beams 16 are arranged at intervals and in a common circle, the second i-beams 17 are arranged at intervals and in a common circle, and the second i-beam 17 is closer to the radial outer side of the soil reinforcing assembly 12 than the first i-beam 16. The first i-beam 16 includes a first steel plate main body 161, a first extension 162 and a second extension 163 each connected perpendicularly to the first steel plate main body 161, and both ends of the first steel plate main body 161 in the width direction are connected to midpoints of the first extension 162 and the second extension 163 in the width direction, respectively. The second i-steel 17 includes a second steel plate body 171, and a third extension 172 and a fourth extension 173 each connected perpendicularly to the second steel plate body 171, and both ends of the second steel plate body 171 in the width direction are connected to midpoints of the third extension 172 and the fourth extension 173 in the width direction, respectively. Each second i-beam 17 is overlapped on two adjacent first i-beams 16, specifically, two adjacent first i-beams 16, wherein a first extension 162 of one first i-beam 16 is abutted near a connection position of a second steel plate body 171 and a third extension 172 in the corresponding second i-beam 17, and a second extension 163 of the other first i-beam 16 is abutted near a connection position of the second steel plate body 171 and a fourth extension 173 in the second i-beam 17.
The top ends of two adjacent I-beams 14 are fixed through steel bar overlap welding, when the I-beams 14 are removed through concrete curing, the I-beams 14 can be pulled out only by cutting the overlap welded steel bars, and meanwhile, the welding is carried out at the top end positions of the I-beams 14, so that a curved road 15 under a soft soil layer is not influenced. In this embodiment, the reinforcing inner ring and the reinforcing outer ring are not required, and the reinforcing steel bars are used to carry out lap welding on the upper ends of the i-beams 14. Alternatively, the upper end of the i-steel 14 may be lapped with rigid materials at different heights, so as to realize double-layer lapping, and effectively improve the supporting strength of the inner and outer arrays.
In addition, four hanging holes 111 are formed in the upper end portion of the casing 11, the hanging holes 111 penetrate through the casing 11 in the thickness direction, the four hanging holes 111 are uniformly distributed along the circumferential direction of the casing, one hanging hole 141 is formed in the upper end portion of the I-steel 14, the hanging hole 141 penetrates through the I-steel 14 in the thickness direction, and a crane can pull out the casing 11 and the I-steel 14 through the steel rope, the hanging holes 111 and the hanging holes 141.
The construction method of the maintenance system for the bored pile construction comprises the following steps: firstly, positioning, then, drilling, then, inserting the protective cylinder 11 into a soft soil layer along the vertical direction, then, respectively inserting a plurality of I-steel 14 into the soft soil layer along the circumferential direction of the protective cylinder 11 at the outer side of the protective cylinder 11, dividing the soil layer around the protective cylinder 11 into an inner soil layer and an outer soil layer by each I-steel 14, and forming a curved path 15 which is communicated with the inner soil layer and the outer soil layer between two adjacent I-steel 14. Next, concrete is poured into the borehole. Next, the casing 11 is pulled out. Finally, after the concrete reaches the predetermined curing strength, the I-steel 14 is removed and pulled out.
From the above, through the peripheral soil layer reinforcement subassembly of protecting the section of thick bamboo outward to divide into the soil layer in the circle and the outer soil layer of circle with the peripheral soil layer of steel protection section of thick bamboo, be formed with the curved road that communicates the inner soil layer of circle and the outer soil layer of circle between two adjacent reinforcement, the curved road can increase the flow resistance of soil layer. Because the internal diameter of soil layer reinforcement subassembly is greater than the external diameter of a casing, the compression that the soil layer in the limited spacing space can receive and the deflection that takes place is very little, therefore when extracting a casing, the concrete is difficult to expand along the radial of drilling, avoids additionally using the concrete to pour to save the concrete. In addition, the reinforcement enclosure such as I-steel has better pressure maintaining effect on the concrete poured in the reinforcement enclosure, and is beneficial to improving the structural strength of the poured concrete. Therefore, the pile casing is not required to be thickened, the soil layer around the pile casing is not required to be hardened and improved, and only the national standard I-steel or channel steel is required to be used as the reinforcing member of the soil layer reinforcing tool, so that the reinforcing member can be repeatedly used and can be suitable for different drilling apertures. The soil layer reinforcement work can be completed only by inserting and pulling the reinforcing members such as the I-steel, the operation is simple and easy to use, the construction efficiency is high, the cost is low, the I-steel can be used repeatedly, the soil characteristics are not changed, and the soil reinforcement work is very environment-friendly.
In addition, as the I-steel and the drill hole are separated by a barreled soil layer, even if the I-steel is pulled out after the cast concrete is solidified, the adhesion phenomenon of the concrete and the I-steel can not occur. Moreover, the contact surface of the single I-steel and the soil layer is far smaller than the contact surface of the protective cylinder and the soil layer, so that the extraction resistance of the I-steel is far smaller than the extraction resistance of the protective cylinder, the I-steel can be easily pressed into the weak soil layer by using a common static pressing machine, and the weak soil layer can also be easily driven into the weak soil layer by using a simple pile driver. In addition, the I-steel can be welded and lengthened, and the welding fixture is applicable to different thicknesses of weak soil layers.
Second embodiment of a maintenance System for bored pile construction
As a description of the second embodiment of the maintenance system for bored pile construction of the present utility model, only the differences from the first embodiment of the maintenance system for bored pile construction described above will be described below.
Referring to fig. 3 and 4, the dimensional stability system further includes a reinforcing inner ring 28, the reinforcing inner ring 28 being disposed radially inward of the soil layer reinforcing assembly 22 and disposed proximate a top end of the soil layer reinforcing assembly 22, the reinforcing inner ring 28 supporting the soil layer reinforcing assembly 22 in a radial direction. The first extension 262 and the second extension 263 of each first i-beam 26 are in contact with the outer peripheral wall of the reinforcing inner ring 28. The height of the reinforcing inner race 28 is in the range of 50 mm to 100 mm and the wall thickness of the reinforcing inner race 28 is in the range of 20 mm to 40 mm. Reinforcing inner race 28 may increase the support strength of soil layer reinforcement assembly 22, increasing the resistance of soil layer reinforcement assembly 22 to horizontal inward compression of the soil layer.
The upper end of the reinforcing inner ring 28 is also provided with a lifting hole 281, the lifting hole 281 penetrates the reinforcing inner ring 28 in the thickness direction, and the lifting holes 281 on the reinforcing inner ring 28 and the lifting holes 211 of the protective cylinder 21 are arranged in one-to-one correspondence along the radial direction of the protective cylinder 21.
Third embodiment of a maintenance System for bored pile construction
As a description of the third embodiment of the maintenance system for bored pile construction of the present utility model, only the differences from the second embodiment of the maintenance system for bored pile construction described above will be described below.
Referring to fig. 5, the dimensional stability system further includes a reinforcement collar 38, the reinforcement collar 38 being disposed radially outward of the soil layer reinforcement assembly 32 and proximate a top end of the soil layer reinforcement assembly 32, the reinforcement collar 38 supporting the soil layer reinforcement assembly 32 in a radial direction. The third extension 372 and the fourth extension 373 of each second i-beam 37 are in contact with the inner peripheral wall of the reinforcing outer ring 38.
The upper end portion of the reinforcing outer ring 38 is also provided with a lifting hole (not shown) penetrating the reinforcing outer ring 38 in the thickness direction, and the lifting holes in the reinforcing outer ring 38 and the lifting holes 311 of the casing 31 are arranged in one-to-one correspondence in the radial direction of the casing 31.
Fourth embodiment of a stability maintenance System for bored pile construction
As a description of the fourth embodiment of the maintenance system for bored pile construction of the present utility model, only the differences from the first embodiment of the maintenance system for bored pile construction described above will be described below.
Referring to fig. 6, in the present embodiment, in two adjacent first i-beams 46, the first extension 462 of one first i-beam 46 and the second extension 463 of the other first i-beam 46 are located near the middle of the second steel plate body 471. The width of such a curve 45 is wider than in the first embodiment.
Fifth embodiment of a maintenance System for bored pile construction
As a description of the fifth embodiment of the maintenance system for bored pile construction of the present utility model, only the differences from the first embodiment of the maintenance system for bored pile construction described above will be described below.
Referring to fig. 7, in the present embodiment, each of the second i-steels 57 is disposed at two adjacent first i-steels 56, the third extension 572 and the fourth extension 573 of the second i-steel 57 are disposed along the radial direction of the soil reinforcing assembly 52, and the width direction of the second steel plate main body 571 is along the radial direction of the soil reinforcing assembly 52. In the radial direction of the soil reinforcing assembly 52, the first i-steel 56 is disposed near the widthwise middle of the second steel plate main body 571.
Sixth embodiment of a stability maintenance System for bored pile construction
As a description of the sixth embodiment of the maintenance system for bored pile construction of the present utility model, only the differences from the fifth embodiment of the maintenance system for bored pile construction described above will be described below.
Referring to fig. 8, in the present embodiment, in the radial direction of the soil reinforcing assembly 62, the first i-steel 66 is disposed near the first end of the second steel plate body 671 in the width direction. The fourth extension 673 is located at a first end of the second steel plate body 671, and the fourth extension 673 is disposed close to the central axis of the soil reinforcing assembly 62 with respect to the third extension 672. The width of the meander 65 in this embodiment is narrower than the width of the meander 55 in embodiment five.
Seventh embodiment of a stability maintenance System for bored pile construction
As a description of a seventh embodiment of the maintenance system for bored pile construction of the present utility model, only the differences from the fourth embodiment of the maintenance system for bored pile construction described above will be described below.
Referring to fig. 9, in this embodiment, the first reinforcing members 76 are all channel steel, the second reinforcing members 77 are all i-steel, and the notch 761 of the channel steel 76 faces away from the central axis of the casing 71.
Eighth embodiment of a maintenance system for bored pile construction
As a description of the eighth embodiment of the maintenance system for bored pile construction of the present utility model, only the differences from the first embodiment of the maintenance system for bored pile construction described above will be described below.
Referring to fig. 10, in the present embodiment, the first reinforcement is a first channel 86, the second reinforcement is a second channel 87, the notch 861 of the first channel 86 faces away from the central axis of the casing 81, and the notch 871 of the second channel 87 faces toward the central axis of the casing 81.
Ninth embodiment of maintenance system for bored pile construction
As a description of a ninth embodiment of the maintenance system for bored pile construction of the present utility model, only the differences from the first embodiment of the maintenance system for bored pile construction described above will be described below.
Referring to fig. 11, the number of soil reinforcing members 92 is two, and the two soil reinforcing members 92 are arranged in a radial direction of the casing 91 and coaxially disposed. In the soil layer reinforcing component 92 of the innermost layer, two adjacent reinforcing members 94 are mutually overlapped, in the soil layer reinforcing component 92 of the outer side, two adjacent reinforcing members 90 are arranged at intervals, the two adjacent reinforcing members do not need to be mutually overlapped to form a whole circle, and the I-steel consumption and the construction workload are saved. The overlapping reinforcing members 94 can provide supporting force to each other, strengthen bearing capacity to each other, and can also improve tensile strength by buckling each other, so that the bearing strength of soil layers in the whole ring is increased. The upper ends of the I-steel between the two adjacent soil layer reinforcing components 92 can be subjected to lap welding through steel bars or I-steel, so that the adjacent soil layer reinforcing components 92 mutually support each other, the integral strength of the soil layer reinforcing components 92 is greatly improved, and the top ends of the two soil layer reinforcing components 92 can be welded and fixed through rigid materials. The pile casing 91 has a height H, and the radius difference between adjacent soil reinforcing members 92 is in the range of 0.1H to 0.5H.
In the construction method of the maintenance system for bored pile construction of this embodiment, after each i-steel of the inner layer soil layer reinforcing component 92 is inserted into a weak soil layer, each i-steel of the outer layer soil layer reinforcing component 92 is inserted into a weak soil layer, then, the upper ends of the inner layer soil layer reinforcing component 92 and the outer layer soil layer reinforcing component 92 are lapped and fixed by rigid materials, and after part of steel materials can be lapped in a cross manner, concrete is poured.
The number of soil reinforcing members 92 may be two or more. The number and arrangement of fasteners in each soil reinforcement assembly 92 may be varied as desired. The above-described modifications can also achieve the object of the present utility model.
Finally, it should be emphasized that the foregoing is merely a preferred embodiment of the present utility model, and is not intended to limit the utility model, but rather that various changes and modifications can be made by those skilled in the art without departing from the spirit and principles of the utility model, and any modifications, equivalent substitutions, improvements, etc. are intended to be included within the scope of the present utility model.

Claims (9)

1. The maintenance and stabilization system for the construction of the bored pile is characterized by comprising a pile casing and a soil layer reinforcing component;
the pile casing and the soil layer reinforcing component extend along the vertical direction, and the soil layer reinforcing component surrounds the radial outer side of the pile casing and forms a limiting space with the pile casing;
the soil layer reinforcing assembly comprises a plurality of reinforcing members arranged along the circumferential direction of the casing, and each reinforcing member extends along the vertical direction.
2. A stabilization system for bored pile construction according to claim 1, wherein:
the maintenance system further comprises a reinforcing inner ring, wherein the reinforcing inner ring is arranged on the radial inner side of the soil layer reinforcing component and close to the top end of the soil layer reinforcing component, and the reinforcing inner ring radially supports the soil layer reinforcing component.
3. A stabilization system for bored pile construction according to claim 2, wherein:
the height of the reinforcing inner ring is in the range of 50 mm to 100 mm; and/or
The wall thickness of the reinforcing inner ring is in the range of 20 mm to 40 mm.
4. A dimensional stability system for bored pile construction according to any one of claims 1 to 3, wherein:
the maintenance system further comprises a reinforcing outer ring, wherein the reinforcing outer ring is arranged on the radial outer side of the soil layer reinforcing component and close to the top end of the soil layer reinforcing component, and the reinforcing outer ring supports the reinforcing member in the radial direction.
5. A dimensional stability system for bored pile construction according to any one of claims 1 to 3, wherein:
the reinforcement is I-steel or channel steel.
6. A dimensional stability system for bored pile construction according to any one of claims 1 to 3, wherein:
a curved path is formed between two adjacent reinforcement members; and/or
The width of the meander is in the range of 10 mm to 80 mm.
7. A dimensional stability system for bored pile construction according to any one of claims 1 to 3, wherein:
the length of the reinforcement is equal to the length of the casing; or alternatively
The length of the reinforcement is greater than the length of the casing, and the bottom wall of the reinforcement is lower than the bottom wall of the casing.
8. A dimensional stability system for bored pile construction according to any one of claims 1 to 3, wherein:
the number of the soil layer reinforcing components is more than two, and a plurality of the soil layer reinforcing components are arranged along the radial direction of the pile casing and coaxially arranged;
in the soil layer reinforcing component at the innermost layer, two adjacent reinforcing members are mutually overlapped, and in other soil layer reinforcing components, two adjacent reinforcing members are arranged at intervals.
9. The maintenance system for bored pile construction according to claim 8, wherein:
the height of the pile casing is H, and the radius difference value of two adjacent soil layer reinforcing components is in the range of 0.1H to 0.5H.
CN202223599448.9U 2022-12-29 2022-12-29 Maintenance and stability system for bored pile construction Active CN219240525U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202223599448.9U CN219240525U (en) 2022-12-29 2022-12-29 Maintenance and stability system for bored pile construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202223599448.9U CN219240525U (en) 2022-12-29 2022-12-29 Maintenance and stability system for bored pile construction

Publications (1)

Publication Number Publication Date
CN219240525U true CN219240525U (en) 2023-06-23

Family

ID=86806779

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202223599448.9U Active CN219240525U (en) 2022-12-29 2022-12-29 Maintenance and stability system for bored pile construction

Country Status (1)

Country Link
CN (1) CN219240525U (en)

Similar Documents

Publication Publication Date Title
CN103835284B (en) A kind of Pile In Drill In Karst Terrain structure and construction method
CN104264688A (en) Manual hole digging non-uniform pile support construction technology
CN101519880A (en) Method of using rotational multiaxial borehole pouring concrete occluding pile wall for enclosing deep foundation pit and slope protection project
JP2018024982A (en) Reinforcement method and reinforcement structure of existing pile foundation
CN101255691B (en) Construction method for complete casing tube thin wall filling pile and movable internal mold
CN103437348A (en) Construction device and method of pile peripheral cemented soil cast-in-place stiffness core pile
CN211421112U (en) Double-casing pore-forming structure of karst geological pile foundation
CN111764404A (en) Partially recyclable secant pile supporting structure and construction method
KR100618597B1 (en) Cast in place concrete pile using vibro magnetic shovel hammer, and the construction method of this
CN108086307B (en) Steel pipe concrete hole digging and pouring composite miniature pile
KR102173079B1 (en) Composite phc pile for soil retaining wall
CN101899831B (en) Active variable-stiffness leveling pile and construction method thereof
CN104074197A (en) Large-diameter thin-walled tubular pile composite anchor rod type foundation pit support structure and construction method thereof
CN108179759A (en) The underwater drill core slotting of driftway is without bottom sealing method
CN111042121B (en) Construction method of bored backfill end pile foundation
CN219240525U (en) Maintenance and stability system for bored pile construction
CN217870505U (en) Excavation supporting construction of tunnel top foundation ditch excavation
CN206368375U (en) A kind of electric power pylon basis
CN116220023A (en) Maintenance and stability system for bored pile construction and construction method thereof
CN212656218U (en) Heavy pile machine load underpinning structure
CN107476293A (en) A kind of quick spreading structure of soft soil foundation bored concrete pile configures and its spreading method
CN110820734B (en) High-performance combined friction pile structure and construction method
CN112144522A (en) Construction method of prestressed pipe pile and special prestressed pipe pile thereof
CN201172826Y (en) Deep base pit enclosure wall earth-blocking reinforced structure
CN110984244A (en) Method for eliminating pile foundation soil squeezing effect through flexible energy absorption belt

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant