CN219157341U - Curb erection equipment - Google Patents
Curb erection equipment Download PDFInfo
- Publication number
- CN219157341U CN219157341U CN202223006761.7U CN202223006761U CN219157341U CN 219157341 U CN219157341 U CN 219157341U CN 202223006761 U CN202223006761 U CN 202223006761U CN 219157341 U CN219157341 U CN 219157341U
- Authority
- CN
- China
- Prior art keywords
- curb
- mounting apparatus
- winch
- wire rope
- pulleys
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/60—Planning or developing urban green infrastructure
Abstract
The utility model discloses a curb mounting device which comprises a device shell, wherein a winch and a plurality of pulleys are arranged in the device shell, a supporting rod is arranged on the device shell, the pulleys are arranged below the supporting rod and connected with the winch through a steel wire rope, one end of the steel wire rope is connected with the winch, and the pulleys extending out of the other end of the steel wire rope and below the supporting rod are connected with a clamp. The installation equipment is internally provided with the winch, the winch passes through the pulley to be connected with the clamp, and the kerbstone clamped on the clamp can be pulled through the operation of the winch so as to install the kerbstone, so that compared with manual operation, the load is larger, and the efficiency is higher; the installation equipment has moderate overall size, occupies smaller construction space and is suitable for construction operation in narrow space.
Description
Technical Field
The utility model relates to the field of road construction, in particular to a curb stone installation device.
Background
The kerbs are the curbs provided between the road surface and other structures, and are generally required to be provided between the separation zones of urban roads and the road surface, and between the sidewalk and the road surface. The road curb comprises a leveling stone and a vertical stone, wherein the vertical stone is arranged on two sides of a road surface or around a separation belt and a safety island, a pavement is separated from structures such as a pavement, a green belt, the separation belt and the safety island, the pavement range is calibrated to maintain traffic safety and longitudinally guide and remove road surface rainwater, and the leveling stone is a plane scaling stone arranged between the pavement and the vertical stone.
At present, the municipal road engineering curb installation mainly takes manpower as a main part and takes a rack truck as an auxiliary part to install the curb.
However, the existing municipal road engineering curb installation mode has the following defects: the weight of the common concrete curb is about 150kg, and the weight of the granite high curb is about 270kg, so that the common artificial shoulder is difficult to pick; the lever section of the trolley used for the crane is lengthened due to the heavy weight, so that the requirement on the spaciousness of a construction site is met, and more manual assistance is needed.
Disclosure of Invention
Aiming at the defects in the prior art, the utility model solves the technical problems as follows: how to design the installation equipment aiming at municipal road engineering curb installation, the manpower resources required by construction are saved, and the equipment can be applicable to narrow construction space.
In order to achieve the technical purpose, the utility model adopts the following technical scheme:
the utility model provides a curb erection equipment, includes the equipment shell, is provided with hoist engine and a plurality of pulley in the equipment shell, is provided with the bracing piece on the equipment shell, is provided with the pulley under the bracing piece, and the pulley is all connected with the hoist engine through wire rope, and wire rope one end is connected with the hoist engine, and the other end epitaxy pulley under the bracing piece is connected with anchor clamps.
Preferably, a power supply is arranged in the equipment shell, and the power supply adopts a lead storage battery.
Preferably, a plurality of rollers are arranged under the equipment shell.
Preferably, the rollers are provided with at least 2 pairs under the device housing.
Preferably, the tyre of the roller is a rubber tyre or a nylon tyre.
Preferably, the pulleys are arranged at least 2 in the equipment shell, and at least 1 pulley is arranged below the supporting rod.
Preferably, the winch is a reversible winch.
Preferably, the clamp is a clamp or an angle clamp.
Preferably, the pulleys are fixed pulleys.
Preferably, the steel of the steel wire rope is carbon structural steel or stainless steel.
Compared with the prior art, the utility model has the beneficial effects that:
1. this novel curb erection equipment is provided with the hoist engine, is connected with the pulley through wire rope to at wire rope one end fixedly connected with anchor clamps, can stimulate the curb of centre gripping on anchor clamps through the hoist engine operation, with the installation of carrying out the curb, compare in the mode of current manual handling, the curb weight that this equipment can transport is bigger, and can practice thrift manpower resources, efficiency is higher.
2. The equipment shell of this novel curb erection equipment and the bracing piece of setting on equipment shell, its overall dimension is relatively moderate, need set up longer lever for current jack-up shelf car, and the construction space that this equipment occupy is littleer, can use the construction operation with narrow space.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings that are needed in the description of the embodiments will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present application, and that other drawings may be obtained according to these drawings without inventive effort for a person skilled in the art.
Fig. 1 is a schematic diagram of the overall structure of a reinforced connection structure of a steel sleeve according to an embodiment of the present utility model.
In the figure: 1-installing equipment; 11-a roller; 12-an equipment housing; 13-a winch; 14-a power supply; 15-a steel wire rope; 16-pulleys; 17-supporting rods; 18-clamping; 2-kerbstone.
Detailed Description
For the purposes of making the objects, technical solutions and advantages of the embodiments of the present application more clear, the technical solutions of the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application, and it is apparent that the described embodiments are some embodiments of the present application, but not all embodiments. All other embodiments, which can be made by one of ordinary skill in the art without undue burden from the present disclosure, are within the scope of the present application based on the embodiments herein.
As shown in fig. 1, the kerbstone installation apparatus provided in this embodiment includes an apparatus housing 12, a hoist 13 and a plurality of pulleys 16 disposed inside the apparatus housing 12, and a supporting rod 17 fixedly connected to the apparatus housing 12, wherein the pulleys 16 are fixedly connected to the bottom of the supporting rod 17, the pulleys 16 are connected to the hoist 13 through a wire rope 15, one end of the wire rope 15 is connected to the hoist 13, the other end extends out of the pulleys 16 disposed on the supporting rod 17 and is connected to a fixture 18, and the fixture 18 is used for clamping the kerbstone 2.
The effect that above-mentioned structural design brought is:
1. this novel curb erection equipment is provided with hoist engine 13, is connected with pulley 16 through wire rope 15 to at wire rope 15 one end fixedly connected with anchor clamps 18, can pull the curb 2 of centre gripping on anchor clamps 18 through hoist engine 13 function, with carry out the installation of curb 2, compare in the mode of current manual handling, the curb 2 weight that this equipment can transport is bigger, and can practice thrift manpower resources, efficiency is higher.
2. The equipment shell 12 of this novel curb erection equipment and the bracing piece 17 of setting on equipment shell 12, its overall dimension is relatively moderate, need set up longer lever for current jack-up shelf car, and the construction space that this equipment occupy is littleer, can use the construction operation with narrow space.
Further, the power supply 14 is further disposed inside the equipment housing 12, and specifically, in this embodiment, a lead storage battery is selected as the power supply equipment of the hoist 13, and the lead storage battery has the advantage of being capable of being disposed as the movable power supply 14, so that wiring on a construction site is avoided.
Further, a plurality of rollers 11 are further arranged at the bottom of the equipment shell 12, and the rollers 11 are arranged, so that the equipment can be moved on a road surface or a base layer, and construction staff can conveniently install the continuous curbstone 2 at different positions without repeatedly transferring lifting equipment before construction.
Further, the rollers 11 are provided with at least 2 pairs at the bottom of the equipment housing 12, the number of pairs of rollers 11 being selected according to the weight of the desired installed kerb 2 of the installation equipment 1.
Further, the tire of the roller 11 may be a rubber tire or a nylon tire, but is not limited to the above tire, and the tire capable of bearing the curb 2 having a certain weight may be selected.
Further, at least 2 pulleys 16 are arranged inside the equipment shell 12, at least 1 pulley 16 is arranged at the bottom of the supporting rod 17, and the number of the pulleys 16 is selected according to the overall structural design of the equipment shell 12, so that the power of the winch 13 can be transmitted to the outside of the equipment shell 12 in a reasonable direction.
Further, in this embodiment, the hoist 13 is a reversible hoist 13, so as to realize reversible pulling and descending prevention of the wire rope 15, and facilitate moving and installing the curb 2.
Further, in the present embodiment, the clamp 18 may be a clamp or an angle clamp, but the clamp 18 is not limited to the clamp 18, and the clamp 18 capable of clamping the curb 2 with a certain weight may be selected.
Further, the pulleys 16 are fixed pulleys 16, the fixed pulleys 16 are arranged in the equipment shell 12 and at the bottom of the supporting rod 17, the steel wire ropes 15 penetrate through the fixed pulleys 16 to be connected with the windlass 13 and the clamp 18, the direction of the power generated by the windlass 13 is changed, and the power can be transmitted to the clamp 18 for clamping and transporting the curb 2.
Further, the steel material of the steel wire rope 15 is carbon structural steel or stainless steel, specifically, in this embodiment, the carbon structural steel model is Q235 or Q295, the stainless steel model is 304 or 316, the carbon structural steel wire rope 15 has the advantages of larger carrying capacity, certain shaping, and the stainless steel wire rope 15 has the advantage of being capable of prolonging the service life of the rope.
Specifically, according to the structural design points, the use flow of the novel installation device is as follows:
before construction, the curb 2 to be installed is transported to a construction site for placement and inspection, an installation control pile is arranged on the site, after lofting measurement is carried out according to a design elevation, the installation work of the curb 2 can be carried out, the curb 2 blocks of each section of designed intersection are calculated in advance, the novel installation equipment 1 is used for lifting to a designated position for installation, after the installation is finished, the installation of the next block can be carried out through the roller 11 moving equipment to the next designated position until the complete installation of the curb 2 required for construction is finished, specifically, during lifting, the power supply 14 in the equipment is used for providing power for the winch 13 to produce power for pulling or lowering the lifting appliance connected to the steel wire rope 15, the effect of saving manpower resources is achieved, the installation efficiency is improved, and the construction work of a relatively narrow construction environment can be adapted.
In the description of the present application, it should be noted that the azimuth or positional relationship indicated by the terms "upper", "lower", etc. are based on the azimuth or positional relationship shown in the drawings, and are merely for convenience of description of the present application and simplification of the description, and are not indicative or implying that the apparatus or element in question must have a specific azimuth, be configured and operated in a specific azimuth, and thus should not be construed as limiting the present application. Unless specifically stated or limited otherwise, the terms "mounted," "connected," and "coupled" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; can be directly connected or indirectly connected through an intermediate medium, and can be communication between two elements. The specific meaning of the terms in this application will be understood by those of ordinary skill in the art as the case may be.
It should be noted that in this application, relational terms such as "first" and "second" and the like are used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Moreover, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising one … …" does not exclude the presence of other like elements in a process, method, article, or apparatus that comprises an element.
The foregoing is merely a specific embodiment of the application to enable one skilled in the art to understand or practice the application. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the application. Thus, the present application is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.
Claims (10)
1. A curb mounting apparatus, characterized by: including equipment shell (12), be provided with hoist engine (13) and a plurality of pulley (16) in equipment shell (12), be provided with bracing piece (17) on equipment shell (12), be provided with pulley (16) under bracing piece (17), pulley (16) all are connected with hoist engine (13) through wire rope (15), wire rope (15) one end is connected with hoist engine (13), pulley (16) under the other end epitaxy bracing piece (17) are connected with anchor clamps (18).
2. A curb mounting apparatus as claimed in claim 1, wherein: a power supply (14) is arranged in the equipment shell (12), and a lead storage battery is selected as the power supply (14).
3. A curb mounting apparatus as claimed in claim 1, wherein: a plurality of rollers (11) are arranged below the equipment shell (12).
4. A curb mounting apparatus as claimed in claim 3, wherein: the rollers (11) are provided with at least 2 pairs under the device housing (12).
5. A curb mounting apparatus as claimed in claim 3, wherein: the tire of the roller (11) is a rubber tire or a nylon tire.
6. A curb mounting apparatus as claimed in claim 1, wherein: at least 2 pulleys (16) are arranged in the equipment shell (12), and at least 1 pulley is arranged below the supporting rod (17).
7. A curb mounting apparatus as claimed in claim 1, wherein: the winch (13) is a reversible winch.
8. A curb mounting apparatus as claimed in claim 1, wherein: the clamp (18) is a clamp or an angle clamp.
9. A curb mounting apparatus as claimed in claim 1, wherein: the pulleys (16) are fixed pulleys.
10. A curb mounting apparatus as claimed in claim 1, wherein: the steel of the steel wire rope (15) is carbon structural steel or stainless steel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202223006761.7U CN219157341U (en) | 2022-11-11 | 2022-11-11 | Curb erection equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202223006761.7U CN219157341U (en) | 2022-11-11 | 2022-11-11 | Curb erection equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN219157341U true CN219157341U (en) | 2023-06-09 |
Family
ID=86616823
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202223006761.7U Active CN219157341U (en) | 2022-11-11 | 2022-11-11 | Curb erection equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN219157341U (en) |
-
2022
- 2022-11-11 CN CN202223006761.7U patent/CN219157341U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110562840B (en) | Construction method for turning large-scale equipment by using crane and pulley block | |
CN114105005B (en) | Curb mounting trolley | |
CN111828730B (en) | Construction process for installing inner sleeve steel pipe in jacking pipe | |
KR101964633B1 (en) | Apparatus for Installing Underground Cable Using Vehicle | |
WO2022001169A1 (en) | Highway-railway dual-purpose track-laying machine for urban rail transit engineering | |
CN219157341U (en) | Curb erection equipment | |
CN206188298U (en) | Transformer lifting device | |
CN208345620U (en) | Light grade penstock mounting operation platform | |
CN214573175U (en) | A distributing device for town road engineering curb | |
CN110904861A (en) | Cable-stayed bridge girder erection crane and construction method thereof | |
CN208345621U (en) | High pressure abrupt slope diversion steel pipe lifting operation system | |
CN213923950U (en) | Civil engineering elevating gear | |
CN205500636U (en) | Water conservancy project component handling device | |
CN210480668U (en) | Device for integrally transporting tensioning equipment in box chamber | |
CN204633186U (en) | A kind of current conversion station converter transformer stable turning device | |
CN202595602U (en) | Large-scale kerb displacement clamp | |
CN214993215U (en) | Culvert wall body support and whole sideslip device of template | |
CN110510526A (en) | A kind of cable conveyer for Traffic Emergency Safeguards | |
CN217400285U (en) | Be used for reinforced (rfd) device of hydraulic engineering overflow weir | |
CN112854296B (en) | Vertical wall sliding installation supporting device and construction method thereof | |
CN214662461U (en) | Pipeline moving device for laying large-diameter pipeline | |
CN114673035B (en) | Track slab replacement operation method | |
CN218152683U (en) | Pipeline laying hoisting frame | |
CN215249058U (en) | A simple and easy gallows for prefabricated tube coupling hoist and mount | |
CN215629770U (en) | Scalable secondary platform device of rock-fill dam panel slipform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |