CN218990189U - Force transfer beam structure - Google Patents

Force transfer beam structure Download PDF

Info

Publication number
CN218990189U
CN218990189U CN202222661130.2U CN202222661130U CN218990189U CN 218990189 U CN218990189 U CN 218990189U CN 202222661130 U CN202222661130 U CN 202222661130U CN 218990189 U CN218990189 U CN 218990189U
Authority
CN
China
Prior art keywords
structure according
plate
beam structure
fixing plate
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202222661130.2U
Other languages
Chinese (zh)
Inventor
张生
王森林
孙浩
满旋
范春宇
郑夕军
任陕新
董小风
杜春达
张辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Technology Construction Co Ltd
Original Assignee
China Construction Eighth Engineering Division Technology Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Technology Construction Co Ltd filed Critical China Construction Eighth Engineering Division Technology Construction Co Ltd
Priority to CN202222661130.2U priority Critical patent/CN218990189U/en
Application granted granted Critical
Publication of CN218990189U publication Critical patent/CN218990189U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model relates to a transfer beam structure, comprising: the foundation pit is characterized by comprising a plurality of fender posts vertically arranged along the inner wall of the foundation pit, a structural beam for supporting between two opposite fender posts and a connecting piece connected between the end part of the structural beam and the corresponding fender post.

Description

Force transfer beam structure
Technical Field
The utility model relates to the technical field of building construction, in particular to a force transfer beam structure.
Background
At present, the deep foundation pit engineering inner support is mainly made of concrete, so that the construction is complex, the progress is slow, a large amount of construction waste is generated in the dismantling process, and great pollution is brought to the surrounding environment. The steel support is high in construction efficiency, and the components can be recycled after being removed, so that the steel support meets the concept of green development. The steel support is connected with the peripheral enclosing structure by welding, and quality defects such as slag inclusion and cracks often occur due to different technical levels of welders in the actual operation process, so that the safety risk of the foundation pit is greatly increased.
Disclosure of Invention
The utility model aims to overcome the defects of the prior art and provides a force transfer beam structure, wherein the connecting beam is detachably arranged on a force transfer piece fixed on a fender post, so that the whole structure can be used for multiple times, and the structure is simple and the operation is convenient.
The technical scheme for achieving the purpose is as follows: a transfer beam structure comprising:
the foundation pit is characterized by comprising a plurality of fender posts vertically arranged along the inner wall of the foundation pit, a structural beam for supporting between two opposite fender posts and a connecting piece connected between the end part of the structural beam and the corresponding fender post.
Further, the connector includes: the first fixing plate is fixed to the fender post in a fitting mode, the second fixing plate is fixed to the end portion of the structural beam in a fitting mode, and the connecting plate is horizontally connected between the first fixing surface and the second fixing surface.
Further, the connector further comprises:
the first reinforcing plate is vertically arranged at the end part of the connecting plate and is fixedly connected with the first fixing plate and the second fixing plate; and
the second reinforcing plate is vertically arranged at the other end part of the connecting plate and is fixedly connected with the first fixing plate and the second fixing plate.
Further, the method further comprises the following steps: and the enclosing purlin is connected with the second fixing plate and the end part of the structural beam.
Further, the enclosing purlin is fixedly connected with the second fixing plate and the structural beam through bolts.
Further, the method further comprises the following steps: and the connecting beam is horizontally fixed on the side part of the fender post, and the structural beam is arranged on the top of the connecting beam.
Further, the method further comprises the following steps: one end of the inclined strut is arranged on the side wall of the fender post, and the other end of the inclined strut props against the bottom surface of the connecting beam.
Further, the inclined strut and the connecting beam form an included angle of 45 degrees.
Further, the method further comprises the following steps: and the capping beams are arranged at the tops of the guard piles.
Further, the connecting piece is fixed to the fender post in a welding mode. Compared with the prior art, the utility model has the following beneficial effects:
the utility model provides a dowel structure will the connecting beam detachable installs in the biography power spare that is fixed in the fender post makes overall structure repeatedly usable, and simple structure, convenient operation.
Drawings
Fig. 1 is a schematic structural view of a transfer beam structure according to the present utility model.
Legend description: 1. a fender post; 2. a structural beam; 3. a connecting beam; 4. enclosing purlin; 5. a connecting piece; 6. a capping beam; 7. and (5) diagonal bracing.
Detailed Description
The utility model will be further described with reference to the drawings and the specific examples.
As shown in fig. 1, a transfer beam structure includes:
the foundation pit comprises a plurality of fender posts 1 vertically arranged along the inner wall of the foundation pit, a structural beam 2 for supporting between the two opposite fender posts 1 and a connecting piece 5 connected between the end part of the structural beam 2 and the corresponding fender post 1.
Further, the connector 5 includes: the first fixing plate fixed on the fender post 1, the second fixing plate fixed on the end part of the structural beam 2 and the connecting plate horizontally connected between the first fixing surface and the second fixing surface are laminated.
Further, the connecting piece 5 further includes: the first reinforcing plate is vertically arranged at the end part of the connecting plate and is fixedly connected with the first fixing plate and the second fixing plate; and a second reinforcing plate vertically arranged at the other end part of the connecting plate, wherein the second reinforcing plate is fixedly connected with the first fixing plate and the second fixing plate.
Further, the method further comprises the following steps: and an enclosing purlin 4 connected to the second fixing plate and the end of the structural beam 2.
Further, the enclosing purlin 4 is fixedly connected with the second fixing plate and the structural beam 2 through bolts. The structural beam 2 can be conveniently removed by the bolts.
Further, the method further comprises the following steps: and the structural beam 2 is arranged on the top of the connecting beam, and is horizontally fixed on the connecting beam at the side part of the fender post 1. The connection beams provide support points for the structural beams 2.
Further, the method further comprises the following steps: and one end of the inclined strut 7 is arranged on the side wall of the fender post 1, and the other end of the inclined strut abuts against the bottom surface of the connecting beam 3. The diagonal brace 7 can better support the connecting beam to prevent the connecting beam from displacing.
Further, the included angle between the diagonal brace 7 and the connecting beam 3 is 45 °.
Further, the method further comprises the following steps: and the capping beams 6 are arranged at the tops of the guard piles 1.
Further, the connecting piece 5 is welded and fixed to the fender post 1.
The following describes the use of a transfer beam structure according to the utility model.
The edge of foundation ditch sets up fender post 1 the connecting beam 3 is all installed to two opposite lateral walls of fender post 1, in order to guarantee the holistic stability of connecting beam 3 the bottom of connecting beam 3 with fender post 1's lateral wall diagonal bracing 7 will pass power piece 5 weld in fender post 1, will pass power piece 5 keep away from fender post 1's one end with enclose purlin 4 fixed connection, will structural beam 2 fixed mounting is in two relatively enclose between purlin 4 and through bolt fixed connection.
The present utility model has been described in detail with reference to the embodiments of the drawings, and those skilled in the art can make various modifications to the utility model based on the above description. Accordingly, certain details of the illustrated embodiments are not to be taken as limiting the utility model, which is defined by the appended claims.

Claims (10)

1. A force transfer beam structure is characterized in that: comprising the following steps:
the foundation pit is characterized by comprising a plurality of fender posts vertically arranged along the inner wall of the foundation pit, a structural beam for supporting between two opposite fender posts and a connecting piece connected between the end part of the structural beam and the corresponding fender post.
2. A transfer beam structure according to claim 1, characterized in that: the connector includes: the first fixed plate of laminating be fixed in the fender post, laminating be fixed in the second fixed plate of the tip of structure roof beam and horizontal connection in first fixed plate with the connecting plate between the second fixed plate.
3. A transfer beam structure according to claim 2, characterized in that: the connector further comprises:
the first reinforcing plate is vertically arranged at the end part of the connecting plate and is fixedly connected with the first fixing plate and the second fixing plate; and
the second reinforcing plate is vertically arranged at the other end part of the connecting plate and is fixedly connected with the first fixing plate and the second fixing plate.
4. A transfer beam structure according to claim 2, characterized in that: further comprises: and the enclosing purlin is connected with the second fixing plate and the end part of the structural beam.
5. A transfer beam structure according to claim 4, wherein: the enclosing purlin is fixedly connected with the second fixing plate and the structural beam through bolts.
6. A transfer beam structure according to claim 1, characterized in that: further comprises: and the connecting beam is horizontally fixed on the side part of the fender post, and the structural beam is arranged on the top of the connecting beam.
7. A transfer beam structure according to claim 6, wherein: further comprises: one end of the inclined strut is arranged on the side wall of the fender post, and the other end of the inclined strut props against the bottom surface of the connecting beam.
8. A transfer beam structure according to claim 7, wherein: the inclined strut and the connecting beam form an included angle of 45 degrees.
9. A transfer beam structure according to claim 1, characterized in that: further comprises: and the capping beams are arranged at the tops of the guard piles.
10. A transfer beam structure according to claim 1, characterized in that: the connecting piece is fixed in the fender post in a welding way.
CN202222661130.2U 2022-10-10 2022-10-10 Force transfer beam structure Active CN218990189U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202222661130.2U CN218990189U (en) 2022-10-10 2022-10-10 Force transfer beam structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202222661130.2U CN218990189U (en) 2022-10-10 2022-10-10 Force transfer beam structure

Publications (1)

Publication Number Publication Date
CN218990189U true CN218990189U (en) 2023-05-09

Family

ID=86218027

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202222661130.2U Active CN218990189U (en) 2022-10-10 2022-10-10 Force transfer beam structure

Country Status (1)

Country Link
CN (1) CN218990189U (en)

Similar Documents

Publication Publication Date Title
CN218990189U (en) Force transfer beam structure
CN211285624U (en) Can have enough to meet need formula structure and trade and prop system
CN212832436U (en) Gantry crane foundation with box girder replacing Bailey girder
CN211420889U (en) Temporary limiting device for linear adjustment of PC track beam
CN211547741U (en) Height-adjustable internal support cutting split heads
CN210482242U (en) Cylindrical tail water surge chamber impedance plate concrete pouring combined supporting system
CN209816666U (en) Assembled bracing connection structure between steel-pipe piles
CN113699961A (en) Pile-beam connecting structure and method for offshore independent fixed concrete mixing station
CN111501565A (en) Detachable hoop type bridge support steel pipe connecting device and method
CN218028932U (en) Outer overhanging tool type turnover unloading inclined supporting base
CN219175295U (en) Bailey beam combined deepwater cofferdam
CN212803242U (en) Shield constructs construction slag bath steel construction device
CN220768799U (en) Mountain region photovoltaic support assembly installation operation platform
CN220747273U (en) Lattice column supports quick splicing device
CN218540401U (en) Assembled integrated temporary buttress
CN216740010U (en) Steel frame structure
CN218880881U (en) Steel supporting structure
CN211973861U (en) Connecting component for assembled steel structure building
CN217517340U (en) Tie beam bracket structure
CN214658680U (en) Stiffness type steel reinforced concrete beam lower hanging operation platform
CN110733975B (en) Gantry crane combined beam device and installation method
CN213572371U (en) Prefabricated cabin transformer substation pin-connected panel steel construction foundation butt-joint structural
CN215331607U (en) Section stand concatenation straightness controlling means that hangs down
CN216807810U (en) Assembled can have enough to meet need many sizes composite beam support steel corbel
CN212926140U (en) Support upright post pile

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant