CN218933612U - Vertical steel bar connection structure of prefabricated shear wall - Google Patents
Vertical steel bar connection structure of prefabricated shear wall Download PDFInfo
- Publication number
- CN218933612U CN218933612U CN202222939295.1U CN202222939295U CN218933612U CN 218933612 U CN218933612 U CN 218933612U CN 202222939295 U CN202222939295 U CN 202222939295U CN 218933612 U CN218933612 U CN 218933612U
- Authority
- CN
- China
- Prior art keywords
- shear wall
- prefabricated shear
- wall
- prefabricated
- cast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 229910000831 Steel Inorganic materials 0.000 title claims description 36
- 239000010959 steel Substances 0.000 title claims description 36
- 230000002787 reinforcement Effects 0.000 claims abstract description 28
- 230000003014 reinforcing effect Effects 0.000 claims description 12
- 125000006850 spacer group Chemical group 0.000 claims description 4
- 238000010276 construction Methods 0.000 abstract description 9
- 238000000034 method Methods 0.000 abstract description 5
- 230000008520 organization Effects 0.000 abstract description 3
- 238000011065 in-situ storage Methods 0.000 abstract description 2
- 238000010586 diagram Methods 0.000 description 5
- 230000000694 effects Effects 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
Images
Landscapes
- Sewage (AREA)
Abstract
本实用新型涉及建筑结构技术领域,公开了一种预制剪力墙的竖向钢筋连接构造,包括下层预制剪力墙、上层预制剪力墙、竖向钢筋连接套筒、可调垫块、长斜支撑和现浇混凝土楼面,所述现浇混凝土楼面设置在下层预制剪力墙顶部一侧,所述可调垫块安装在现浇混凝土楼面顶部,且可调垫块与上层预制剪力墙底部相接触,所述现浇混凝土楼面顶部外壁固定连接有两个第一固定座,所述长斜支撑底端转动安装在右侧的第一固定座上。本实用新型浇筑上层预制剪力墙底部可调垫块高度范围内混凝土,使下层预制剪力墙和上层预制剪力墙形成整体、可靠的连接结构,施工质量可靠,连接整体性好,不影响后序工序穿插和施工组织,较为实用,适合广泛推广和使用。
The utility model relates to the technical field of building structures, and discloses a vertical reinforcement connection structure of a prefabricated shear wall, which comprises a lower prefabricated shear wall, an upper prefabricated shear wall, a vertical reinforcement connection sleeve, an adjustable pad, a long Diagonal support and cast-in-place concrete floor, the cast-in-place concrete floor is arranged on the top side of the prefabricated shear wall of the lower floor, the adjustable pad is installed on the top of the cast-in-place concrete floor, and the adjustable pad The bottom of the shear wall is in contact with each other, and the outer wall of the top of the cast-in-situ concrete floor is fixedly connected with two first fixing seats, and the bottom end of the long oblique support is rotatably mounted on the first fixing seat on the right side. The utility model pours concrete within the height range of the adjustable cushion block at the bottom of the upper prefabricated shear wall, so that the lower prefabricated shear wall and the upper prefabricated shear wall form an integral and reliable connection structure, the construction quality is reliable, the connection integrity is good, and it does not affect Subsequent process interspersion and construction organization are more practical and suitable for widespread promotion and use.
Description
技术领域technical field
本实用新型属于建筑结构技术领域,具体地说,涉及一种预制剪力墙的竖向钢筋连接构造。The utility model belongs to the technical field of building structures, in particular to a vertical reinforcement connection structure of a prefabricated shear wall.
背景技术Background technique
装配整体式混凝土剪力墙结构在工程中的应用越来越广泛,其预制剪力墙的竖向连接大多采用灌浆套筒连接,其施工工艺复杂,不仅灌浆质量难以保证,而且封仓和灌浆的施工工艺影响其后续工序穿插及施工组织,对施工质量和施工工期都造成较大的影响。Assembled integral concrete shear wall structures are more and more widely used in engineering. Most of the vertical connections of prefabricated shear walls are connected by grouting sleeves. The construction technology affects its follow-up process interspersion and construction organization, which has a great impact on the construction quality and construction period.
有鉴于此特提出本实用新型。In view of this, the utility model is proposed.
实用新型内容Utility model content
为解决上述技术问题,本实用新型采用技术方案的基本构思是:In order to solve the problems of the technologies described above, the basic idea of the technical solution adopted by the utility model is:
一种预制剪力墙的竖向钢筋连接构造,包括下层预制剪力墙、上层预制剪力墙、竖向钢筋连接套筒、可调垫块、长斜支撑和现浇混凝土楼面,所述现浇混凝土楼面设置在下层预制剪力墙顶部一侧,所述可调垫块安装在现浇混凝土楼面顶部,且可调垫块与上层预制剪力墙底部相接触,所述现浇混凝土楼面顶部外壁固定连接有两个第一固定座,所述长斜支撑底端转动安装在右侧的第一固定座上,所述上层预制剪力墙一侧开设有调节槽,所述调节槽内壁滑动连接有连接块,所述连接块一侧固定连接有移动座,所述长斜支撑顶端转动安装在移动座上;A vertical reinforcement connection structure of a prefabricated shear wall, comprising a lower prefabricated shear wall, an upper prefabricated shear wall, a vertical reinforcement connection sleeve, an adjustable spacer, a long diagonal support and a cast-in-place concrete floor, the The cast-in-place concrete floor is set on the top side of the lower prefabricated shear wall, the adjustable pad is installed on the top of the cast-in-place concrete floor, and the adjustable pad is in contact with the bottom of the upper prefabricated shear wall, and the cast-in-place There are two first fixed seats fixedly connected to the outer wall of the top of the concrete floor, the bottom end of the long oblique support is rotatably installed on the first fixed seat on the right side, and an adjustment groove is opened on one side of the upper prefabricated shear wall. The inner wall of the adjustment groove is slidably connected with a connecting block, one side of the connecting block is fixedly connected with a moving seat, and the top end of the long oblique support is rotatably mounted on the moving seat;
所述下层预制剪力墙顶部设置有预制墙顶部预留向上外伸钢筋,所述竖向钢筋连接套筒安装在预制墙顶部预留向上外伸钢筋上。The top of the lower prefabricated shear wall is provided with reserved upwardly extending steel bars at the top of the prefabricated wall, and the vertical steel bar connecting sleeve is installed on the reserved upwardly extending steel bars at the top of the prefabricated wall.
作为本实用新型的一种优选实施方式,所述上层预制剪力墙底部设置有预制墙底部预留向下外伸钢筋,所述预制墙顶部预留向上外伸钢筋伸出现浇混凝土楼面的长度不小于竖向钢筋连接套筒的长度。As a preferred embodiment of the present utility model, the bottom of the upper prefabricated shear wall is provided with downwardly extending steel bars reserved at the bottom of the prefabricated wall, and upwardly extending steel bars are reserved at the top of the prefabricated wall to protrude from the cast-in-place concrete floor. The length is not less than the length of the vertical reinforcement connecting sleeve.
作为本实用新型的一种优选实施方式,所述预制墙底部预留向下外伸钢筋的外伸长度须满足竖向钢筋连接套筒连接的所需长度。As a preferred embodiment of the present invention, the extension length of the downwardly extending steel bars reserved at the bottom of the prefabricated wall must meet the required length of the vertical steel bar connection sleeve connection.
作为本实用新型的一种优选实施方式,所述预制墙顶部预留向上外伸钢筋和预制墙底部预留向下外伸钢筋均与竖向钢筋连接套筒相匹配。As a preferred embodiment of the present invention, the upwardly extending steel bars reserved at the top of the prefabricated wall and the downwardly extending steel bars reserved at the bottom of the prefabricated wall are matched with the vertical steel bar connecting sleeves.
作为本实用新型的一种优选实施方式,左侧的所述第一固定座上固定安装有短斜支撑,所述上层预制剪力墙一侧固定连接有第二固定座,所述短斜支撑顶端固定安装在第二固定座上。As a preferred embodiment of the present invention, a short oblique support is fixedly installed on the first fixed seat on the left side, and a second fixed seat is fixedly connected to one side of the upper prefabricated shear wall, and the short oblique support The top end is fixedly installed on the second fixing seat.
作为本实用新型的一种优选实施方式,所述移动座上开设有对称设置的螺纹孔,且两个螺纹孔内壁均螺接有定位螺杆。As a preferred embodiment of the present invention, symmetrically arranged threaded holes are opened on the moving seat, and positioning screws are screwed on the inner walls of the two threaded holes.
作为本实用新型的一种优选实施方式,所述调节槽内壁开设有等距分布的定位孔,两个所述定位螺杆之间的距离与相邻的两个定位孔之间的距离相同,两个所述定位螺杆均与定位孔相适配。As a preferred embodiment of the present utility model, the inner wall of the adjusting groove is provided with positioning holes equidistantly distributed, and the distance between the two positioning screws is the same as the distance between the two adjacent positioning holes. Each of the positioning screws is compatible with the positioning holes.
本实用新型与现有技术相比具有以下有益效果:Compared with the prior art, the utility model has the following beneficial effects:
本实用新型,先浇筑下层混凝土楼面至结构标高,将竖向钢筋连接套筒向下旋拧至下层预制剪力墙上的预制墙顶部预留向上外伸钢筋底部,吊装上层预制剪力墙,通过可调垫块使下层预制剪力墙和上层预制剪力墙相对一侧的预制墙顶部预留向上外伸钢筋和预制墙底部预留向下外伸钢筋满足钢筋连接所需条件,上层预制剪力墙通过第一固定座、短斜支撑和第二固定座与现浇混凝土楼面稳定连接,通过在上层预制剪力墙上设置的调节槽、连接块和移动座,可以对长斜支撑的支撑角度进行调节,便于根据上层预制剪力墙的高度将长斜支撑的顶端固定在上层预制剪力墙一侧适当的位置,当长斜支撑的角度调节完成之后,将两个定位螺杆螺接在两个定位孔内,实现对移动座的定位效果,使得长斜支撑配合短斜支撑的作用加强了现浇混凝土楼面与上层预制剪力墙之间连接的稳定性,然后将竖向钢筋连接套筒向上旋拧,使上层预制剪力墙底部预制墙底部预留向下外伸钢筋和下层预制剪力墙顶部预制墙顶部预留向上外伸钢筋通过竖向钢筋连接套筒形成有效连接,浇筑上层预制剪力墙底部可调垫块高度范围内混凝土,使下层预制剪力墙和上层预制剪力墙形成整体、可靠的连接结构,施工质量可靠,连接整体性好,而且施工工艺简单,不影响后序工序穿插和施工组织。In the utility model, the concrete floor of the lower floor is first poured to the structural elevation, and the vertical reinforcement connecting sleeve is screwed downward to the top of the prefabricated wall on the lower prefabricated shear wall, and the bottom of the upwardly extending steel bar is reserved, and the upper prefabricated shear wall is hoisted. , the prefabricated shear wall on the lower floor and the prefabricated shear wall on the upper floor on the opposite side make the upwardly extending steel bars reserved at the top of the precast wall and the downwardly extending steel bars at the bottom of the prefabricated wall meet the required conditions for reinforcement connection, and the upper layer The prefabricated shear wall is stably connected with the cast-in-place concrete floor through the first fixed seat, short oblique support and second fixed seat, and the long oblique Adjust the support angle of the support so that the top of the long oblique support can be fixed at an appropriate position on one side of the upper prefabricated shear wall according to the height of the upper prefabricated shear wall. After the adjustment of the angle of the long oblique support is completed, the two positioning screws Screwed in the two positioning holes to realize the positioning effect of the mobile seat, so that the function of the long oblique support and the short oblique support strengthens the stability of the connection between the cast-in-place concrete floor and the upper prefabricated shear wall, and then the vertical Screw the connecting sleeve upwards, so that the downwardly extending steel bars reserved at the bottom of the prefabricated wall at the bottom of the upper prefabricated shear wall and the upwardly extending steel bars reserved at the top of the prefabricated wall at the top of the lower prefabricated shear wall are formed through the vertical steel bar connecting sleeve Effective connection, pouring concrete within the height range of the adjustable pad at the bottom of the upper prefabricated shear wall, so that the lower prefabricated shear wall and the upper prefabricated shear wall form an integral and reliable connection structure, the construction quality is reliable, the connection integrity is good, and the construction The process is simple and does not affect the subsequent process interspersed and construction organization.
下面结合附图对本实用新型的具体实施方式作进一步详细的描述。Below in conjunction with accompanying drawing, the specific embodiment of the present utility model is described in further detail.
附图说明Description of drawings
在附图中:In the attached picture:
图1为本实用新型上层预制剪力墙通过调节垫块和斜支撑精准落位、并与现浇混凝土楼板形成稳定连接的结构示意图;Fig. 1 is a schematic diagram of the structure of the upper prefabricated shear wall of the present invention, which is accurately placed by adjusting the cushion block and the oblique support, and forms a stable connection with the cast-in-place concrete floor;
图2为本实用新型竖向钢筋连接套筒向上旋拧,使上、下层竖向钢筋通过连接套筒形成有效连接的结构示意图;Fig. 2 is a schematic diagram of the structure of the utility model where the vertical reinforcing bar connecting sleeve is screwed upwards so that the upper and lower vertical reinforcing bars are effectively connected through the connecting sleeve;
图3为本实用新型竖向钢筋连接套筒安装在下层竖向钢筋的结构示意图;Fig. 3 is the structure schematic diagram that the utility model vertical reinforcing bar connecting sleeve is installed in the vertical reinforcing bar of lower floor;
图4为本实用新型下层剪力墙及下层楼面混凝土浇筑完成后的结构示意图;Fig. 4 is the structural representation of the lower shear wall of the utility model and the concrete pouring of the lower floor;
图5为本实用新型上层预制剪力墙落位后连接区域的平面结构示意图;Fig. 5 is a schematic diagram of the planar structure of the connection area after the upper prefabricated shear wall of the utility model is placed;
图6为本实用新型上层预制剪力墙落位后局部剖视结构示意图。Fig. 6 is a schematic diagram of a partial cross-sectional structure of the upper prefabricated shear wall of the utility model after it is placed in place.
图中:1-下层预制剪力墙;2-上层预制剪力墙;3-竖向钢筋连接套筒;4-可调垫块;5-长斜支撑;6-预制墙顶部预留向上外伸钢筋;7-预制墙底部预留向下外伸钢筋;8-现浇混凝土楼面;9-第一固定座;10-移动座;11-第二固定座;12-短斜支撑;13-调节槽;14-连接块;15-定位孔;16-定位螺杆。In the figure: 1- prefabricated shear wall on the lower floor; 2- prefabricated shear wall on the upper floor; 3- vertical reinforcement connecting sleeve; 4- adjustable spacer; Stretching steel bars; 7-reserved downward extending steel bars at the bottom of the prefabricated wall; 8-cast-in-place concrete floor; 9-first fixed seat; 10-mobile seat; 11-second fixed seat; 12-short oblique support; -Adjustment slot; 14-connection block; 15-positioning hole; 16-positioning screw.
具体实施方式Detailed ways
为使本实用新型实施例的目的、技术方案和优点更加清楚,下面将结合本实用新型实施例中的附图,对实施例中的技术方案进行清楚、完整地描述,以下实施例用于说明本实用新型。In order to make the purpose, technical solutions and advantages of the embodiments of the present invention more clear, the technical solutions in the embodiments will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention. The following embodiments are used for illustration The utility model.
如图1至图6所示As shown in Figure 1 to Figure 6
一种预制剪力墙的竖向钢筋连接构造,包括下层预制剪力墙1、上层预制剪力墙2、竖向钢筋连接套筒3、可调垫块4、长斜支撑5和现浇混凝土楼面8,现浇混凝土楼面8设置在下层预制剪力墙1顶部一侧,可调垫块4安装在现浇混凝土楼面8顶部,且可调垫块4与上层预制剪力墙2底部相接触,现浇混凝土楼面8顶部外壁固定连接有两个第一固定座9,长斜支撑5底端转动安装在右侧的第一固定座9上,上层预制剪力墙2一侧开设有调节槽13,调节槽13内壁滑动连接有连接块14,连接块14一侧固定连接有移动座10,长斜支撑5顶端转动安装在移动座10上,可以对长斜支撑5的支撑角度进行调节,便于根据上层预制剪力墙2的高度将长斜支撑5的顶端固定在上层预制剪力墙2一侧适当的位置;A vertical reinforcement connection structure of a prefabricated shear wall, comprising a lower prefabricated
下层预制剪力墙1顶部设置有预制墙顶部预留向上外伸钢筋6,竖向钢筋连接套筒3安装在预制墙顶部预留向上外伸钢筋6上,并且竖向钢筋连接套筒3向下旋拧至底部。The top of the
在具体实施方式中,上层预制剪力墙2底部设置有预制墙底部预留向下外伸钢筋7,预制墙顶部预留向上外伸钢筋6伸出现浇混凝土楼面8的长度不小于竖向钢筋连接套筒3的长度,预制墙底部预留向下外伸钢筋7的外伸长度须满足竖向钢筋连接套筒3连接的所需长度,预制墙顶部预留向上外伸钢筋6和预制墙底部预留向下外伸钢筋7需要提前在外伸长度范围内车丝,使之与竖向钢筋连接套筒3相匹配,将竖向钢筋连接套筒3向上旋拧,使上层预制剪力墙2底部预制墙底部预留向下外伸钢筋7和下层预制剪力墙1顶部预制墙顶部预留向上外伸钢筋6通过竖向钢筋连接套筒3形成有效连接,浇筑上层预制剪力墙2底部可调垫块4高度范围内混凝土,使下层预制剪力墙1和上层预制剪力墙2形成整体、可靠的连接结构。In a specific embodiment, the bottom of the upper
进一步的,左侧的第一固定座9上固定安装有短斜支撑12,上层预制剪力墙2一侧固定连接有第二固定座11,短斜支撑12顶端固定安装在第二固定座11上,移动座10上开设有对称设置的螺纹孔,且两个螺纹孔内壁均螺接有定位螺杆16,调节槽13内壁开设有等距分布的定位孔15,两个定位螺杆16之间的距离与相邻的两个定位孔15之间的距离相同,两个定位螺杆16均与定位孔15相适配,当长斜支撑5的角度调节完成之后,将两个定位螺杆16螺接在两个定位孔15内,实现对移动座10的定位效果,使得长斜支撑5配合短斜支撑12的作用加强了现浇混凝土楼面8与上层预制剪力墙2之间连接的稳定性。Further, a short
本实施例的一种预制剪力墙的竖向钢筋连接构造的实施原理如下:先浇筑下层混凝土楼面至结构标高,将竖向钢筋连接套筒3向下旋拧至下层预制剪力墙1上的预制墙顶部预留向上外伸钢筋6底部,吊装上层预制剪力墙2,通过可调垫块4使下层预制剪力墙1和上层预制剪力墙2相对一侧的预制墙顶部预留向上外伸钢筋6和预制墙底部预留向下外伸钢筋7满足钢筋连接所需条件,上层预制剪力墙2通过第一固定座9、短斜支撑12和第二固定座11与现浇混凝土楼面8稳定连接,通过在上层预制剪力墙2上设置的调节槽13、连接块14和移动座10,可以对长斜支撑5的支撑角度进行调节,便于根据上层预制剪力墙2的高度将长斜支撑5的顶端固定在上层预制剪力墙2一侧适当的位置,当长斜支撑5的角度调节完成之后,将两个定位螺杆16螺接在两个定位孔15内,实现对移动座10的定位效果,使得长斜支撑5配合短斜支撑12的作用加强了现浇混凝土楼面8与上层预制剪力墙2之间连接的稳定性,然后将竖向钢筋连接套筒3向上旋拧,使上层预制剪力墙2底部预制墙底部预留向下外伸钢筋7和下层预制剪力墙1顶部预制墙顶部预留向上外伸钢筋6通过竖向钢筋连接套筒3形成有效连接,浇筑上层预制剪力墙2底部可调垫块4高度范围内混凝土,使下层预制剪力墙1和上层预制剪力墙2形成整体、可靠的连接结构。The implementation principle of the vertical reinforcement connection structure of a prefabricated shear wall in this embodiment is as follows: first pour the lower concrete floor to the structural elevation, and screw the vertical reinforcement connection sleeve 3 downward to the lower
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222939295.1U CN218933612U (en) | 2022-11-04 | 2022-11-04 | Vertical steel bar connection structure of prefabricated shear wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202222939295.1U CN218933612U (en) | 2022-11-04 | 2022-11-04 | Vertical steel bar connection structure of prefabricated shear wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN218933612U true CN218933612U (en) | 2023-04-28 |
Family
ID=86060635
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202222939295.1U Active CN218933612U (en) | 2022-11-04 | 2022-11-04 | Vertical steel bar connection structure of prefabricated shear wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN218933612U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117386003A (en) * | 2023-10-26 | 2024-01-12 | 淮安市建筑设计研究院有限公司 | Design and construction method of precast concrete shear wall joints with mechanical sleeve connections |
CN118793234A (en) * | 2024-08-15 | 2024-10-18 | 中国十七冶集团有限公司 | A kind of steel bar positioning construction structure and method for prefabricated structure transfer layer |
-
2022
- 2022-11-04 CN CN202222939295.1U patent/CN218933612U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117386003A (en) * | 2023-10-26 | 2024-01-12 | 淮安市建筑设计研究院有限公司 | Design and construction method of precast concrete shear wall joints with mechanical sleeve connections |
CN118793234A (en) * | 2024-08-15 | 2024-10-18 | 中国十七冶集团有限公司 | A kind of steel bar positioning construction structure and method for prefabricated structure transfer layer |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN218933612U (en) | Vertical steel bar connection structure of prefabricated shear wall | |
CN204151701U (en) | Single column pier bridge adds steel structure support overturning or slip resistance analysis bracing means | |
CN209443766U (en) | Pouring model for building | |
CN106499093B (en) | A kind of exterior wall attachment structure and its construction method | |
CN207003997U (en) | A kind of construction template | |
CN206123903U (en) | Prefabricated assembled concrete stairway mould | |
CN218952796U (en) | Adjustable kitchen and bathroom hanging die positioning and fixing device | |
CN220247388U (en) | Floor reinforcing steel bar fixing and plate thickness control device | |
CN213711106U (en) | A pouring formwork for tunnel center drainage ditch | |
CN114370007A (en) | Steel diaphragm beam small-radius curve beam bridge assembling construction template and construction method | |
CN208815889U (en) | A kind of deformation joint integrally can turnover type template system | |
CN208803700U (en) | Precast concrete cushion block between sinking | |
CN207794409U (en) | GBF thin-walled square chest hollow floor structures | |
CN209584870U (en) | Pedestal structure for the prefabricated a variety of line style free cantilever erections segment of long line method | |
CN206752761U (en) | A kind of exterior wall attachment structure | |
CN214272930U (en) | Anti-bank reinforcing apparatus of aluminium mould kitchen bathroom | |
CN212897204U (en) | Adjustable fixing and reinforcing device | |
CN207415622U (en) | The prefabricated anti-bank support device for hanging mould | |
CN206279654U (en) | A kind of interior wall attachment structure | |
CN218323492U (en) | Pre-buried web node of short column | |
CN220644202U (en) | A kind of steel sheet pile for foundation reinforcement | |
CN205421645U (en) | Floor with honeycomb core | |
CN216740680U (en) | An upside-down wall formwork device | |
CN220226274U (en) | Plate thickness control device for assembled floor | |
CN217923132U (en) | Prefabricated pier site assembly construction auxiliary device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20241231 Address after: Room 1603, Building 6, Block B3, Haichao Hui Plaza, 1677 Xingyuan Street, Tangzhi Street, Licheng District, Jinan City, Shandong Province, China 250109 Patentee after: China Construction Third Engineering Group Shandong Investment Construction Co.,Ltd. Country or region after: China Address before: 430000, No. 552, Guanshan Road, Hongshan District, Wuhan City, Hubei Province Patentee before: CHINA CONSTRUCTION THIRD CONSTRUCTION ENGINEERING Co.,Ltd. Country or region before: China |